Block individual planned orders from CIF

Hello All,
I would like to know if there is a way to exclude individual planned orders from CIF transfer from R/3 to APO?
Thanks and Regards

Hi Gabriella,
It would not make sense to modify the standard way of working of SAP APO only for 2 months.
If you use any kind of enhancements, etc, you would need to later on remove it or deactivate it.
Best option would be to make adjustments in your forecast so that SNP could plan additionally for this temporary demand. Otherwise create dummy sales orders in R/3 which would inflate the demand. But this would be feasible, only if you DON'T automatically confirm the Sales orders for delivery in some way, or if you could think of some way in which these Sales Orders do not get processed further in some way.
Or, as you yourself mentioned, increase the safety stock temporarily, and later on (may be after 2 months), reduce it to the normal value. But especially closer to end of 2 month period, someone would need to manually adjust planned or production orders in R/3 to have data sanity. Similarly, action would be needed in APO also to have data in sync with R/3.
You could have created the planned orders directly in R/3 and sent them across to APO, but this would increase the receipt situation, so SNP would then start planning for lower "net demand".
PS: In such scenarios where business needs something temporarily and which can't fit in the standard process, it is best that we  convince them to have some workarounds which might not really sound like businesswise wise (in this case creating additional forecast).
Thanks - Pawan

Similar Messages

  • What are the ways to Copy Firm Planned Order from one ASCP Plan to another?

    We run two EDD Plans with very similar options, but with different plan horizons.
    To have the suggestions synchronized, we need to copy the "Firm Planned Orders" from one plan to another.
    We tried inserting the records in MSC_ST_SUPPLIES with Order type 5 and firm planned type 1 with appropriate plan id, but Planning ODS Load is not considering those inserted records.
    We don't want to insert directly into MSC_SUPPLIES.
    Any inputs is appreciated.
    Thanks
    Sundar

    You can also call a custom DTSX package in SSIS via the datamanager.
    there are at least 5 ways of transfering data in BPC between apps.
    1. Through the front end (excel etc) via evdre/evsnds
    2. Through Script logic using *Dest App
    3. Using BPC's standard export dtsx package via DM
    4. Using SSIS using BPC's custom SSIS tasks
    5. Through Script logic using stored procs.
    i am sure people will come up with more.
    remember if you use ssis and move data into any table but the wb, you need to process the cube afterwards.

  • Locating Planned order from a  purchase requisition

    Hi Gurus ,
    A purchase requisition has been created manually , by converting a planned order . Is it possible to find out the planned order , from a purchase requisition   Pls advise.

    Hi
    Once planned order converted in to Production order or Purchase requisition, we can't see any details of the planned order.Planned orders are stored dynamically in tables.once it is  coverted,Details can not be seen even in PLAF-Plan order table.
    In production order, you can see the planned order number but for PR , it is difficult to get the reference Plan order number.
    Regards
    Ramakrishna

  • Migration of Planned Orders from one SAP system to another one

    Hi,
    A quick help needed.
    We are migrating SAP data from one SAP system to other due to business split. Regarding PP data, can Planned orders be migrated as it is from one SAP System to another? What is the impact if we do so?
    Appreciate your response.
    Kind Regards,
    tanuji

    hi ,
    As suggested , you can propose to migrate only Firmed Planned orders from SAP  to SAP system .
    How to acheive it ?
    You can use below BAPI to extract details of planned order from Table PLAF and upload in TARGET SYSTEM
    BAPI_PLANNEDORDER_CREATE
    Please note  newly created Planned order in Target system would not have BOM EXPLOSION and Scheduling .
    If need , Make a BDC recording as a add on step to explode Bom and Schedule by clicking those icons in Planned order .
    Technical Team can do this .

  • Unable to view planned order from exceptional summary window

    Hello All,
    I have ran ASCP plan and it details out the exceptions and recommendations, but I am unable to view planned order from exceptional summary window>recommendations>cilck discrete jobs, no planned orders visible. This issue also shows up for other exceptions, on click of exceptions details it shows up the items but unable to take any actions.
    I have tried by giving large no of days to view recommendations in preference.
    Can someone help me to reslove issue.
    Thanks,
    Edited by: user604737 on Jul 18, 2011 6:09 AM

    We don't have any query built on the exceptional window. As I am able to view below recommendations
    Recommendations
    Discrete Jobs 8
    Purchase Req 27
    When we click on discrete jobs/purchase req, its not showing any planned orders in supply window.
    Can you please let me know, which is the backend table which stores supply information which are displayed in exceptional window.
    Edited by: user604737 on Jul 18, 2011 9:15 AM

  • BAPI to get Planned orders from SNP,PPDS in APO

    Hi Sap Gurus,
    i want to find out a BAPI to fetch the planned orders from SNP,PPDS in APO BY PASSING THE parameters like Resource id ,Start time and End time.

    hi,
    check out this , if u find any new BAPI , just add to this list.
    https://www.sdn.sap.com/irj/sdn/wiki?path=/display/scm/apo-technical
    regards
    Prabhu

  • Tracing Planned Order from Purchase Req.

    I want to find the Table - field relationship to trace a Planned order from Purchase Requisition.
    Once we convert planned order to purchase requisition, system deletes planned order in MD04.
    Is it possible to find out which planned order had been used to create purchase requisiton.

    Hi Raj,
    Generally Peggeed requirement is nothing but it represents the Higer level material. For example if raw material purchase requisition for 100 nos, then it is a Pegged Requiremet of the Assembly or the FERT. Simple its a dependent requiremnt for FERT or SFG.
    MD09 is used to find out the Pegged Requirement. If you give the Purchase Requisitiion of the Raw material, then system will tell you the pegged requirement i.e. the production order order to which the purchase requisition belongs to.
    Pegged requirement may be a Sales Order,Reservation,Production Order,Project,Network,WBS etc.
    Select one MRP element in MD04 screen and if you select pegged requirements system will show you these elements created for any higher level material or not.
    Note :Once a GR is done to PO, there is no more pegging possible for the PO, as it is in Inventory. Pegging is possible as long as it is an open order (PO, PR etc.)
    Apart from above case If you have other requirment you to devlope your own.
    Regards,
    Ram

  • Can't Release firm planned order from ASCP.

    I can't release firm planned order from ASCP the following massage appear " FRM-40200 , Field is protected against update ".
    appreciate your help on that.
    regards.
    Ahmad.

    Please post the details of the application release, database version and OS.
    I can't release firm planned order from ASCP the following massage appear " FRM-40200 , Field is protected against update ".
    appreciate your help on that.Please mention the navigation path along with the form name and version.
    Thanks,
    Hussein

  • How to create planned order from the sales order for a processing item

    In the MTO sceanrio, assembly order is created directly from the sales order. I would like to create a planned order from the sales order.
    I tried the Planning strategy group 81 in the material master but it didnt work.
    Could you please let me know how to do it? Is it Schedule line config that controls whether planned order is created?
    Thanks
    Harish

    Narayana,
    Planning strategy 82 is the best & standard way of getting production order created on sale order create.
    just assign this strategy  in MRP 3 view under strategy group.
    If not then using sale order reqt type ( KMFA- Assembly with production order) & assigning this to your sale order item category is also another way to create prodcution order without using planning strategy in material master.
    Follow steps in SPRO-->Sales & dist --> basic functions >avail check &transfer of requirements> transfer reqts-->determination of reqt type using transaction
    Here you may select the item category you in sale orders & assign KMFA to your item category. this will then give option in sale order create to change reqt type to KFMA for assebly orders.
    If you need KFMA to be default assign it to Item cat/ MRP type ( PD) combo.
    Regards
    Ritesh

  • Merge of planned orders from the same product

    Hi Experts,
    We have some lines where we process materials with different properties so setup time/costs between ones and anothers are very important.
    If we run the PPDS Optimizer or scheduling based on setup groups for a period of 2 weeks then depending on the demands we may get 2 or 3 orders of the same material followed. Is there a possibility that once we have the short-term plan and we have this situation we run a heuristic that merge orders from the same material into one order? Capacity Driven heuristic does not fulfill our requirements.
    Ex:
    Order 1 = 10000 PC
    Order 2 = 20000 PC
    Order 3 = 5000 PC
    They are followed in the resource so we would like to have one of 35000 PC.
    Right now, we are using a simulation so looking at the total amount of the followed orders then we can get an idea of which should be the minimum lot size to be used .   They can also modify the total quantity of the first order with the sum of the others but none of these 2 options makes the customer totally happy.
    Any suggestions?
    Regards
    CTF

    After PPDS Optimizer .
    Get the list of all FG PPDS orders into an internal table.
    Use     BAPI_PRDSRVAPS_GETLIST2
               BAPI_MOSRVAPS_GETLIST2
    Consolidate the orders which are in scheduled status for each product, resource and PPM.
    Sum the quantities.Create the Orders and delete the old orders.
    Use BAPI_MOSRVAPS_DELEMULTI (For deleting the Orders)
    Use BAPI_MOSRVAPS_SAVEMULTI3( For creating a new Order)
    Thanks,
    nandha

  • Release of Planned Orders from ASCP to Internal requisition

    Hi All,
    Is there a way to stop creation of ISO from IR which is released from ASCP Workbench?
    As per my knowledge, when we release a Planned Order, it will create an IR and ISO automatically. There is no such functionality like in Purchasing side where we can use ASL to restrict the PO creation process.
    Thanks for your pointers.
    Regards,
    N

    Hi,
    Yes but in that case the responsibility being used to release the planned orders should not have access on any OU.
    Below is the other thread where i gave the solution for requisitions.
    Release from Planner's workbench auto-triggers WIP Mass Load, how do we restrict
    Please let me know if you are interested and we can do it at user levels also if can't implemented at resp level..
    Thanks,
    Abhishek Sharma
    Please mark the post correct or helpful, if answered

  • BAPI_MOSRVAPS_SAVEMULTI3 creating planned order from Restricted Stock

    Hi,
       We have a requirement where we need to programmatically replicate the Push Production functionality as in /SAPAPO/RRP3 transaction. We are using the BAPI - BAPI_MOSRVAPS_SAVEMULTI3 and it is working fine for conversion of planned orders and Process Orders to component planned/process orders and dependant demand for the parent material. The issue is when we are trying to convert a restricted stock to a planned order and dependant demand using the BAPI, we are getting a message "No valid source of supply could be found". Please let us know if anyone has a resolution to this issue or if any further details are required.
    Edited by: ARKAJEET DASGUPTA on Apr 1, 2011 7:28 AM

    Hi,
        Tlane is not a field name,I wanted to say Transportation Lane(T-Lane) exist or not in the system for that product-location combination.
    For the SOURCE_NAME field, it is clearly mentioned in the documentation of BAPI that,
    Selection of sources of supply (for example, PP/DS PPM)
    ORDER_END_DATE is used as standard as the selection time for the source of supply (in-house production). If ORDER_END_DATE is empty, the value from ORDER_START_DATE is used instead.
    If a different time should be used to select the source of supply, this can be set using the EXPLOSION_DATE field.
    If a date field is not specified for an order change, the date of the last explosion of this order is used for source of supply selection.
    The entries in the MASTER<...> fields also play a role for source determination. That is, possible sources of supply are searched for on the basis of product, location, quantity, and so on.
    For the selection of sources of supply, the setting from the product master for plan explosion is used.
    If several possible alternative sources of supply are found, the system chooses one source of supply as standard.
    However, if you want to select a specific source of supply that has been found, you can use the fields PLAN_NUMBER + PPM_NUMBER, PROD_VERSION, or SOURCE_NAME. Note that only one combination may be used; you cannot use both PLAN_NUMBER and PROD_VERSION at the same time because both are valid for different source of supply types.
    Please check with the functional consultant, in plan explosion field in product master what value they have maintained.
    Because BAPI will try to get the source of supply name on basis of that field which is mentioned in the documentation.
    Regards,
    Saurabh

  • Macbook stolen and recovered, but i delated it from my devices, how can I bring it back without had the drive erased and blocked as I ordered from ''find my Mac''?

    I had my Macbook Pro stolen about a month ago... so i went inmediately to ''find my Mac'' and ordered the system to erase the drive and block the Mac as soon as conected to interent. 
    I recovered the device a week later, so before turning it on, i went to ''find my mac'' and couldnt find any other option to tell the system that i found my stole device, so i clicked ''forget device''
    i turned the Macbbok on, and nothing happened, it worked perfectly.  but it doesnt appear anmore on my devices.
    is there any way to get it back to ''my devices'', and use features such as ''find my mac'' wothout bringing the order from the system to erase and block the device as i ordered before??????
    thanks a lot!!!
    Arturo.

    You must take it back to Apple
    They are the only ones that remove the block
    Allan

  • Distinguishing PIR related planned orders from Customer related.

    Dear all, what could be the best way how to distinguish planned orders generated basing on PIR from ones generated from real Customer Orders. The main idea behind is to make sure that orders generated for real customer orders are processed with first priority and orders from PIR with second. Thank you. Regards,Andrey.

    Hi ,
    System will not always create one plan order for one demand. If lot sizing procedure is WB-Weekly lot size , it wll generate one plan order for customer orde r& PIR falling in same week. Hence , there is no flag or field which will help identify which Plan order is feeding what demand /how much qty of demand.
    You should look at altering Planning strategy. If you implement Make-To-order strategy(20, 50, 59 ) , system will create Planning segment(Blue color seperator in MD04 screen)
    System will ignore lot sizing procedure & always create one plan order for one demand.
    Alternatively , you can implement SAP-SCM which has pegging reports & priority based processing.
    Hope it helps,
    Jatin

  • Capacity Booking by Planned orders from MRP

    Hey All,
    I would like to know how Capacity is booked on the Planned orders resulting from the MRP run.
    Regards.

    Hi Danish,
    On the basis of Delivery Date or requirement date system schedules the order either it is though Backward or Forward scheduling. For this calculation system considers the Inhouse Production Time , GR Processing Time , Routing data etc.And during this calculation system will ignore the available capacity on particular date means you have to perform Capacity Leveling later.
    And on the basis of that Routing which is selected during MRP run system generates the Capacity requirement on the relevant work centers / Resources.
    Refer below link,
    [Detail Scheduling|http://digilander.libero.it/vietrim/]
    Regards,
    Dhaval