Block production work center during maintenance order

Dear Experts,
iam trying to do the integration between PM and PP, I want to block the production work center from any production order  when there is any maintenance order opened for a certain equipment which is inside this  work center ,
till now i did the following:
1) the production work center is now inside the equipment location tab
2) when i open any maintenance order i put system condition as zero
now what i only achieved ,
- in transaction CM25 the capacity is black for the period of the maintenance order
BUT the work center is not blocked and any production order can be created without any error
please help and much thanks in advance
Best Regards

Hi,
Till time you have performed right things to integrate PP-PM & system is also responding according to setting.
Showing block capicity in CM25 against the Maintenance Order.
If you want to block production order as well, you need to do one more setting.
go to t- code OIOI, selection Production order types (those you want to block) & in capacity Availabilty choose Collect conversion as 3 : No creation if there is insufficiant caacity.
i hope this will definately solve your problem.
- Yatharth

Similar Messages

  • Work Center in Maintenance Order.

    Hi ,
    Due to Process Change some maintenance work centers become obsolete.
    Can it possible to hide or work center do not see in F4  help in Maintenance order.

    Dear Ashu
    Jogeswara Rao Kavala input is the most suitable in your case however another work around would be :
    If you are using the "Person Responsible" for your work center, then remove the entry from the person responsible for such obselete work center as they will not be used any more and no person will be responsible for their maintenance and co-ordination. This will help in all other reports selection and analysis also.
    While searching for work center(F4 Screen), default the tab "Person Responsible".Now when you select any work center based on person responsible, automatically that work center will be excluded from your selection screen.
    Pre-requisite: You use Person responsible assignment in ALL work centers....
    Other way would be to set deletion flag to this work center so that even if they are included by user without looking into F4 help, system will prevent those work center from including in the work order for further processing.
    Hope this helps
    Regards
    Murad..

  • Replace Main work center for maintenance order

    hello
    I have to change the work center maintenance orders to 1000.
    Is there a standard transaction to make this change in mass?
    or I'll have to create a LSMW?
    thanks
    Paulo Picarra

    Hi Paulo
    though you have closed this thread I would like to tell you that In standard T- code IW38 there is a carry out mass change option available through which you can change many data including Main Work center. Pl check the following steps
    Select the orders through IW38 & click on order (at the top menu) & select carry out mass change (or CTRL+F11)
    you will get a popup screen for selection of fields to be changed.
    Pl check & give feedback
    Regards
    Shakti

  • Report for work center hours , maintenance order wise for SAP 3.1i version.

    Hi Team,
    We are using older version of SAP, that is SAP 3.1i. Here we don't have any transaction code such as IW47. Is there any other way to get report of work center and work center hours-order wise.
    Please respond.
    Regards,
    Kiran

    Have a look at table AFRU
    PeteA

  • Block PP Work Center capacity  when breakdown maintenance order create on that work center

    Hi All,
    My Client want to Block PP Work Center  capacity when breakdown maintenance order create on that work center, how can i do it ..
    Please help me.
    Payal

    Dear Sir,
    I have Done Every think but still Production Order is create.
    CM50
    OIOI
    CO02
    Payal

  • Change Work Center during production order confirmation

    Dear All,
    I must to modeling this situation:
    I created an production order. In routing I used an work center A.
    After I confirmed a half of quantity, the work center A was damaged and I must to change it, with the work center B.
    The system allow this change, but when I checked the costing, the situation isn't real. The system counted the costs just for the work center A, and no for work center B.
    My question is: it's possible to change the work center, during production order confirmation and the costs updated with new cost?
    Thank you for your answer!
    Regards,
    Marian

    once a Order is released, the Process order detaisl for that order is frozen.
    however if you want to do it, change the order status to CRTD after reversing the Movements done.
    Do READ MAster data , this will copy the new Work center , redo the previously done Moevements.
    if the change is long term.
    or
    Just manually add the new work center and do the processing. if the change is temporary.

  • Blocking of Production Work Center

    Hi All,
    I have already maintained the following PM-PP integration points:
    1) Production work center is maintained in equipment master
    2) System condition is entered in maintenance order as "Not in operation"
    Please let me know how to block the production workcenter for production work when same workcenter (as equipment in PM)is planned for maintenance.
    Sundar

    Hi,
       Once you have done the settings, if you have Maintenance Order on particular eqpt belonging to PP Work Center ,
    Then based on system condition the PP Work Capacity will be 0 i believe ..but system will still allow you to create a PP Order on that PP work center .. better thing is to perform Capacity Availablity Check while releasing the PP Order at that PP Work Center and if capacity is not avaialble then u can stop release of the PP Order..
    In PP ->OPJK for combination of PP Work order type and plant u have for business function 02 , u have give Overall Profile
    Release Capacities as 3
    The Overall profile which ur using has control profile & this  should have presentation type as 04  for Capacity availability check to happen ..
    regards
    pushpa

  • How Can i Block the Work Center Once is used in Maintainence Order

    Dear Experts,
    How Can i Block the Work Center Once is used in Maintainence Order in PM module.
    In standard its not blocking the Work Center automatically. How this can be achieved.
    Regards
    Raghu
    Edited by: raghu m on Apr 21, 2009 10:36 AM

    Hi Muthukumar,
    1. You can using the user exit or BADI to control this.
    CONFPP01            PP order conf.: Determine customer specific default values           
    CONFPP02            PP order conf.: Customer specific input checks 1                     
    CONFPP03            PP order conf.: Cust. specific check after op. selection             
    CONFPP04            PP order conf.: Customer specific input checks 2                     
    CONFPP05            PP order conf.: Customer specific enhancements when saving           
    CONFPP06            PP Order Confirmations: Actual Data Transfer                         
    CONFPP07            Single Screen Entry: Inclusion of User-Defined Subscreens            
    BADI
    WORKORDER_CONFIRM
    the above are the user exits that are available fro the CO11N tcode.
    2. we have to take a help of the abaper to write coding fort his.
    3. The user exit should be called for the
    Work Center : YYYYY
    then check the relevant Work Center Once is used in open Maintainence Order and if it has a entry if then give a error message else allow the CO11N to perform.
    Regards,
    Sankaran

  • Blocking of work center capacity for capacity planning

    How can i block a work center capacity for capacity planning during Machine breakdown( via a Preventive maintenance order)?
    i believe it will reduce machine capacity, yet how can i view this, against the previous capacity? is there a possible report or can it be shown through a transaction?

    Hi,
    In capacity header details screen not exactly as "can be used for capacity evaluation " but
    "relevent to finite sceduling"
    "can be used for several operations"
    "long term planning"
    these all indicators you can deflag this and check the results ,it may helpful to you.

  • Automatic change of Work Center during Confirmation.

    Happy New Year to all!
    Just want to ask if anyone of you encountered the scenario during confirmation in which the backflushed work center was changed. The user claims that they did not do any changes during confirmation nor did they change manually the order itself. The confirmation happened last December and they only noticed it this month when they were checking the reports.
    I did not configure their system so that they can change the Work Center during confirmation. By default, the work center is grayed out during confirmation.
    Hope to hear from some of you soon!
    Thanks and regards,
    jLmendoza
    Edited by: John Luis Mendoza on Jan 4, 2011 3:15 AM

    Dear
    If your production order operations are re-scheuled and dispatched after Capacity Avalaiblity check in cm21/cm22/cm31 etc  , then during the dispatch of operation ,  you have option to change Work Cnetre , time , date based on the selection option in Startgy profile (CM31/CM21-Enter the WORK CENTRE /Order )  and check wether work centre is changed.
    One more option may be in Order Change in CO02-Operation Overview -Operation -Work centre -Here user may change the Work Centre .
    If you have Order Change management active then you can trace the same .
    Refer : Production order change history
    Otherwise , there is not such confirguration in SPRO where work centre can be changed automatrically during confirmaiton because it will grade out based on the ste of confirmaiton default screen in OP00.
    Hope it clarifies
    Regards
    JH

  • Blocking the work center

    Dears
    Is it possible to block the work center from Quality department for creating any more production order because of quality issue
    Like what we are blocking the vendor by using quality info record
    Thanks in advance
    Faisal

    Yes Sujit
    I understand that
    But There is any method to evaluate Work center in QM prospective
    In usge decision we have quality score is updating when ever we select respective UD code
    Any tips on this pls
    Faisal

  • Profit Center to be picked from Equipment Cost center in Maintenance Order

    Hi All
    We are not maintianing any costcenter in work center and only maintaning the cost center in equipment master.
    So when i create the maintenance order, profit center is not picked up in Additional Data Tab from Cost center maintained in equipment master.
    Please  provide your valuable sugesstions.
    Regards
    Praveen

    Hi,
    The profit center is derived from the cost center of the responsible work center when the order is first created. If a cost center is not available then I expect the profit center cannot be automatically filled on the order. The user can manually enter a value.
    The exit IWO10005 is frequently used to determine the profit center. You may want to look at implementing some custom logic there.
    -Paul

  • Change history of work center in Prodn Order

    Hi All,
    We currently are changing the work center in prodn order via an ABAP program number of times based on various conditions. We would like to know the change history for the work center in prodn order. Is there any <b>transaction or report or function module </b> that we can run for a given prodn order to know these changes. This change info is not captured in AUFK or AFPO or AFKO or logs for Prodn Order.
    We have not activated audit trail for this. Please can anyone suggest a soln for this.
    Thanks

    Hi Bala,
    AFRV table contains  Confirmation pool information. But I am looking for change history for the work center in prodn order. Like after creating the prodn order u changed the work center and then again after release of prodn order u changed it to some other work center (for some particular business reason). I would like to see all this change history.
    Swapnil

  • Changing operations work center during creation of  PM order

    Hi all,
    I am looking for BADI or EXIT in order to change operationS work center which created from maintenance calls.
    Does anyone know such possibility?
    Assaf

    Assaf,
    Have a look at BADI IWO1_TL_INTEGRATION2.
    Also see [OSS Note 925072|https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=925072]
    Which system are you running?
    PeteA

  • Error message when blocking a Work Center

    Hi,
    In order to block the use of a workcenter, it is recommended to go to cr02 and change u2018usageu2019 field to u2018000u2019 All task list types (see previous topic To block the use of a specific workcenter)
    When changing usage to 000, an error message appears : u201CThe work center is already being used, update task listsu201D. How could it be fixed? thanks
    sb

    If you don't want that operation , Then
    Go to CA80- work center where used list
    find out the routing, and delete the respective operation in routing.
    Or
    If you don't want the delete the operation, Then
    In workcenter , CR02 Go to Extras-->status set lock
    While creating a new production order, system won't copy the locked workcenter