Blocking of work center capacity for capacity planning
How can i block a work center capacity for capacity planning during Machine breakdown( via a Preventive maintenance order)?
i believe it will reduce machine capacity, yet how can i view this, against the previous capacity? is there a possible report or can it be shown through a transaction?
Hi,
In capacity header details screen not exactly as "can be used for capacity evaluation " but
"relevent to finite sceduling"
"can be used for several operations"
"long term planning"
these all indicators you can deflag this and check the results ,it may helpful to you.
Similar Messages
-
Maintaining work center list in Capacity Planning: Selection List in CM01
Hi,
Where can find the config route in SPRO for maintain work center into the Capacity Planning: Selection List in CM01?
Thanks a lot!
MinMandy,
Couple of combinations you should check,
1. First try to identify "Selection Profile" which is used. In "CM01" go to menu Planning->Profiles->Selection Profile.
2.Check the defination of this profile using transaction "OPA2". Here you need to look for "Work center Set" which is assigned.
3. Now look at the defination of the workcenter set using transaction "CMS3", here is were we define as how the list is to be fetched.
Hope this helps....Reward your points and close the thread if so,
Regards,
Prasobh -
Block PP Work Center capacity when breakdown maintenance order create on that work center
Hi All,
My Client want to Block PP Work Center capacity when breakdown maintenance order create on that work center, how can i do it ..
Please help me.
PayalDear Sir,
I have Done Every think but still Production Order is create.
CM50
OIOI
CO02
Payal -
Work Center Hierarchy and Capacity
Hello SAP friends,
Can someone please help me with the following scenario?
I have 3 Work Centers
MAQ00 - (Capacity 10:00 x 2)
MAQ01 - 8:00 -- 18:00 (Capacity 10:00)
MAQ02 - 8:00 -- 18:00 (Capacity 10:00)
I have a hierarchy
HICY01
MAQ00 - Root of hierarchy
|_ MAQ01
|_ MAQ02
Then, I have a routing
10 - PP01 - MAQ00 - 1H
20 - PP01 - MAQ00 - 2H
If I go to CM01 for Work Center MAQ00 I can see the capacity and requirement, where:
Capacity: 10:00 x 2
Requirement: 3:00
But if I go to transaction CM21 for Work Center MAQ00 the capacity and requirement is not correct. Can someone please help me with this?
Thanks in advance,
Adelmo SilvaHi,
CM01 will give the cumulative requirement as 3 hrs but CM21(Gradhical View) shows the individual spread of oprn. 10 and 20 as 1H and 2 H resp.
Does the above help you?
-Thaila Shree -
How to construct Work center Hirerchy in Production Planning.
Hi Experts,
How to construct Work center Hirerchy in Production Planning.
Thanks in advance.Amit,
I guess you must have overlooked the rules of engagement for this forum. It is customary for questioners to first perform basic research before posting any questions.
First, search in the forums (search box in the upper right of this page). FYI The question you raised has been covered dozens of times.
Next, check online help. This help is generic, and not generally specific to a particular industry:
http://help.sap.com
Work Center Hierarchy:
http://help.sap.com/saphelp_erp60_sp/helpdata/en/b1/c037ae439a11d189410000e829fbbd/frameset.htm
Next, look for generic solutions solutions in Best Practices. Basic index at
http://help.sap.com/saap/sap_bp/BL_IN/html/Content_Library_BL_EN_IN.htm
Next look for industry specific solutions in Best Practices:
http://help.sap.com/content/bestpractices/industry/index.htm
If you are experiencing a problem, or you believe that SAP is not working per the online help, you can then search OSS notes.
http://service.sap.com/notes
Next search in one of the standard online search engines (such as Google).
Only after you have performed all of these tasks, and studied all of the online help that is supplied for free by SAP, should you then consider posting a question to these forums.
If you are unwilling or unable to perform such research, then you should probably engage a consultant to assist you. All consultants use searches to assist them in designing and executing solutions. If you intend to one day become a consultant, you would be wise to cultivate this skill.
Best Regards & Good luck,
DB49 -
How Can i Block the Work Center Once is used in Maintainence Order
Dear Experts,
How Can i Block the Work Center Once is used in Maintainence Order in PM module.
In standard its not blocking the Work Center automatically. How this can be achieved.
Regards
Raghu
Edited by: raghu m on Apr 21, 2009 10:36 AMHi Muthukumar,
1. You can using the user exit or BADI to control this.
CONFPP01 PP order conf.: Determine customer specific default values
CONFPP02 PP order conf.: Customer specific input checks 1
CONFPP03 PP order conf.: Cust. specific check after op. selection
CONFPP04 PP order conf.: Customer specific input checks 2
CONFPP05 PP order conf.: Customer specific enhancements when saving
CONFPP06 PP Order Confirmations: Actual Data Transfer
CONFPP07 Single Screen Entry: Inclusion of User-Defined Subscreens
BADI
WORKORDER_CONFIRM
the above are the user exits that are available fro the CO11N tcode.
2. we have to take a help of the abaper to write coding fort his.
3. The user exit should be called for the
Work Center : YYYYY
then check the relevant Work Center Once is used in open Maintainence Order and if it has a entry if then give a error message else allow the CO11N to perform.
Regards,
Sankaran -
Dears
Is it possible to block the work center from Quality department for creating any more production order because of quality issue
Like what we are blocking the vendor by using quality info record
Thanks in advance
FaisalYes Sujit
I understand that
But There is any method to evaluate Work center in QM prospective
In usge decision we have quality score is updating when ever we select respective UD code
Any tips on this pls
Faisal -
Block production work center during maintenance order
Dear Experts,
iam trying to do the integration between PM and PP, I want to block the production work center from any production order when there is any maintenance order opened for a certain equipment which is inside this work center ,
till now i did the following:
1) the production work center is now inside the equipment location tab
2) when i open any maintenance order i put system condition as zero
now what i only achieved ,
- in transaction CM25 the capacity is black for the period of the maintenance order
BUT the work center is not blocked and any production order can be created without any error
please help and much thanks in advance
Best RegardsHi,
Till time you have performed right things to integrate PP-PM & system is also responding according to setting.
Showing block capicity in CM25 against the Maintenance Order.
If you want to block production order as well, you need to do one more setting.
go to t- code OIOI, selection Production order types (those you want to block) & in capacity Availabilty choose Collect conversion as 3 : No creation if there is insufficiant caacity.
i hope this will definately solve your problem.
- Yatharth -
Read work center details for a notification
Hello All,
Is there an FM that I can use to read the work center that is assigned to a service / maintenance notification?
The problem that I have is that I use BAPI_ALM_NOTIF_GET_DETAIL to read the notification header.
In case of service notifications of type S1, I get the PP_WORKCENTER information but for notifications of type S3, i get the PM_WORCENTER.
I need one FM which will get the work center and plant for me so that I do not have to check the notification types.
Does anybody know of one?
Best Regards,
MithunHi;
Did you see:
http://www.aboutoracleapps.com/2007/08/oracle-general-ledger.html
Information Center : Oracle Cost Management [ID 1417659.2]
Regard
Helios -
Error message when blocking a Work Center
Hi,
In order to block the use of a workcenter, it is recommended to go to cr02 and change u2018usageu2019 field to u2018000u2019 All task list types (see previous topic To block the use of a specific workcenter)
When changing usage to 000, an error message appears : u201CThe work center is already being used, update task listsu201D. How could it be fixed? thanks
sbIf you don't want that operation , Then
Go to CA80- work center where used list
find out the routing, and delete the respective operation in routing.
Or
If you don't want the delete the operation, Then
In workcenter , CR02 Go to Extras-->status set lock
While creating a new production order, system won't copy the locked workcenter -
Work center assignment for plant
Hi experts,
I just want to know how can one assign the work centers for the given plant.
Useful points will be rewarded.
Regards,
Sankar.I just want to know how can one assign the work centers for the given plant
When you create work center in the initial screen we need to mention the plant as well.
regards-
Ravi Kumar -
Work Flow Behaviour for Organizational Plan
Hi All,
Would someone know how SAP Standard workflow behaves when the chief position is vacant? Will workflow ends with an error, or it will be smart enough to look for the next approver on the parent org unit? Any form of documentation will help too.
Thanks a lot.Hi
It totally depends upon u. If u want an error message than u can set an error message also if system doesnot finds any chief position or if u want that system should move to next upper position than it is also possibe.
Reward me if useful
Thanks
Sheetal -
Dear Gurus,
How can I use work center Hierarchy for Capacity Planning.
I have 5 Lathe machines. How can I use Work Center Hierarchy?
I also need Work Center Wise confirmation.
Please guide me. Also let me know how should I maintain data in work center as well as in routing.
Thanks in advance
RGCreate a new WC (in CR01) as category 0004. This will be the top level WC in your hierarchy. <BR sab="44">Create a hierarchy (in CR21). <BR sab="46">Add your 5 lathes and the newly created top level WC to the hierarchy (in CR22). This can be tricky: the WC you just created must be the top level, the other 5 must be under it. <BR sab="50">Pull the capacity data (in CM01) for the hierarchy: go to settings, hierarchy, check the cumulation of requirements and capacities and type the hierarchy name. <BR sab="54">Route things as before, to the original 5 lathes.
-
Capacity planning for Work Center
I programmed time for a Work Center on internal activity, for 40 hr using 100% of one resource, the work center it has a capacity of 8 hr each day, the activity gets a duration of 5 days and I indicated that it has to begin the first day of the next month.
When I executed transaction CM01, I notice that the 40 hours are planned for the actual day and don´t respect the dates of the internal activity, I think it is a problem with the work center but do not find the error.
Any suggestion where to look for?
The data used for creating the Work Center on Capacities:
- Capacity Category : 002 Person
- Other formula: SAP008
The data used for capacity:
- Base unit of meas.:H
- Start: 08:00:00
- Finish: 17:00:00
- Capacity utilization: 100
- No. of indiv. cap.:1
- Unit: H
- Relevant to finite scheduling: active
- Can be used by several operations: active
- Long-term planning: active
The data used for creating the Work Center on Scheduling:
- Capacity Category: 002 Person
- Other formula: SAP004
- Work dimension: Time
- Work unit: H
Best Regards...Hi,
Please activate the capacity requirement in Capacity tab in CNR2.
Thanks.. -
Trying to find Function modul for requirement capacity in work center
Hi Colleagues,
I have tried to find a function modul: Import - Work center , Export - requirement capacity.
but havn't succeed with.
I will be glad for any help.
tnx & best regardsI need a FM that export the requirement capacity of a Work center.
Report CM01 has the same functionallity, however, by debugging it I coudn't find any useful function, morever, I have found a thread in the forum with the same issue but it wasn't helpful.
an example for my needs is as followed:
Function: CAPACITY_REQUIREMENT_FOR_WORK_CENTER
IMPORT:
1. Work Center = MG1602
2. Plant = 1000
3.date from = 01.04.2011
4. date to = 01.05.2011
EXPORT:
1. Capacity Requirment (Total) = 240 [Hours]
2. Capacity Requirment (period) = 22 [hours]
Maybe you are looking for
-
Graphic problems/errors with Mainstage 3 and MBP (15'' 2011)
Hi, I bought Mainstage 3 for my MBP (15'' 2011). When i click con "perform" i get graphic errors. I have the same issue with the old Mainstage version since Mountain Lion. Also a fresh installation didn't help. I think i'm not the only one with this
-
i'm trying to update from 3.2, but when I try to transfer the download to the application folder I get the message, "The operation can't be completed because you don't have permission to access some of the items."
-
Another question: Upon creation of a billing doc and with regards to the creation of pricing procedure, this error occurs: Tax statement item missing for tax code S5 (tax code S5 is a deferred output tax) Message no. FF805 Diagnosis No tax item exist
-
Error while connectiong Oracle
Hi, I get the following error sometimes, while connecting to Oracle Database 9.2 using ODP.NET 9.2.0.7. ORA-03113: end-of-file on communication channel . Appreciate idea on this. Thanks, Ashish.
-
I would like to downgrade from ios 4.0 to 3.1.3. Unfortunately I didnt save the shsh blobs onto cydia or apple server, but I have the shsh blobs on my user account in folder .shsh. Is there any other way to downgrade to 3.1.3. I am extremely unhappy