Hi All,
I 've a requirement that the users should not be able to cancel custom declaration doc. using T.code /SAPSLL/CL_CUS_02(Cancel/Cancel request option) once border crossing for goods is passed and the process completed.
Currently it is possible in GTS to cancel customs declaration even once the process is completed.
As per my unbderstanding, the doc. status sholud be be changed to 'Completed' automatically once process is completed.
Can anyone give some suggestionss on this ?
Regards,
Manu.

Hi Manu,
Its very long time this query is posted, hope this issue got resolved. However, if it is not, Try to use the release button in Customs Declaration Tab in the Customs Export Declaration document.
Regards,
Shiva

Similar Messages

  • How can I cancel a Customs Declaration?

    Hi all,
    How can I cancel a Customs Declaration?
    Is this a special message type or how can I do this?
    Thanks
    Regards

    Gunther,
    In the GTS IMG, under SAP Customs Management >> General Settings >> Communications Processes >> Define Messages for Communications Processes there are seveal message types with "Cancellation" in the description.  For example:  I1011, I1050.  These depend upon the country for which you are configuring electronic communications.  Don't forget to enable email communication with the authorities for these messages (transctions SUGR and SCOT).  And don't forget to enable the message via message determination.  After you receive authorization to cancel the declaration, remember to "close" the transaction which marks it for archive.
    Perhaps Sameer or Satya can offer more advice regarding if it is possible to "do over" the transaction after cancelling it.  I have never tried that.  I believe once the initial message has been sent to customs, you cannot "complete" the billing document using VF02 (which releases the delivery back to be available for processing on a different billing document).  At that point, you can only "cancel" it in GTS.  I do not know how you would restore inventory in the feeder system for that transaction.
    Finally, if I have stated something wrong or in a confusing way, I apologize.  I'm confident the other SDN members will correct or clarify.
    Regards,
    -Greg

  • Client wants to block the order if customer's credit Limits exceeds.

    Dear All,
    Client wants to block the order if customer's credit Limits exceeds. But Sales order no. is to be generated.Later on that blocked order is to be released by Authority.
    I did all the configurations. Order is blocked if the customer credits exceeds, but order no is not get generated. Without order no, Authority can not release.
    Kindly guide me where i have gone wrong.
    Awaiting for your quick reply
    Regards,
    umapathy

    HI,
    Please do not put a credit block in the Credit Management settings. Instead check in the CMR and the VOV8 sales order setting. Also if possible maintain an incompletion procedure wherein SO number would created but the document would be blocked for delivery creation.
    Usually the SO would be released using v.23 by the proper authority,that should work fine and would not hamper SO creation process.
    Thanks
    Reward points if helpful

  • Automatic cancellation of Custom declaration not happening in GTS

    Hi All
    I need your help, when i am cancelling my proforma invoice (F9) in R/3,  custom declaration not cancelled automatic in GTS, I know i can cancel the custom declaration manually but again i want to cancel the declaration automatically as soon as the proforma invoice cancelled in R/3
    Please advise

    hi,
    I think you have already received an answer from support but I put it here again.
    You have to use invoices with SD document category 'U' and to cancel the proforma use the menu function 'complete'.
    Balazs

  • Block the vendor from quality side as process from the evoluation

    Dear All,
    How to Block the vendor from the quality side. i check the MK05 . but if i block thru this txn. the purchase people will change unblock the vendor from XK05 .
    I need to know , if the vendor is blocked . it will not be unblock by anyother than from the quality.
    or
    anyother process is there to block as a process
    say ex, in vendor evoluation, if the quation mark is less than 80 % , the vendor should be blcoked ,as a process.
    Thanks
    vraj

    Hi Sujit,
    What you  mean to say in the privious reply.
    is it possible in any other way or not.
    With regards
    vraj
    hi
    i think is other way round
    http://sapdocs.info/application-modules/mm-overview/mm-transaction-codes/

  • I recently purchased an iPad Mini. I went to sync it to my Mac Book, and everything synced up except my music. It keeps showing that the music is syncing, but once it is complete, I have no music on my iPad. Everything else synced up fine. How do I iPad?

    How do I sync my iTunes Library to my iPad mini. I have an iPhone 4, and a Mac Book. Those synced fine. Everything else is syncing, but my music. Help!

    Do you have your itunes for ios account set up on your ipad? And when you sync with your Mac Book are you doing it via itunes on your Mac Book? (When we got ipads, we had to set up an ios itunes app so it would sync to get music from itunes.)
    You might want to read this to see if it will help you.
    http://support.apple.com/kb/ht1386.
    Hope this helps. If not, I'm sure someone will read this soon and have an answer for you.

  • Completing the customs declaration document.

    hello all
    could someone explain me what is the impact on the customs declaration once the document  is closed manually and the document takes the status " document completed"
    will that be effecting the F8 proforma invoice doc  which is already created on ECC side?
    2 ) how do we cancel the customs declaration ?  what would be the impact on previous documents ?
    thank you

    Thanks alot ralph and gabriel
    that actually solves my problem.
    I have customs declaration which is not completely processed . I manually closed the document and I tried to go to transaction
    /SAPSLL/CDOC_CPLRES to cancel the closing and get the previous status to the document . but when im trying to cancel the closing of the customs declaation doc . its not allowing me  .
    am i missing any steps in between . The customs doc is still showing the Flag which says Complete.
    thank you
    Edited by: swethagts on Mar 30, 2010 6:15 PM
    Edited by: swethagts on Mar 30, 2010 6:29 PM

  • Document status blocked in Customs declaration

    Hello Team,
    I have configured the system for Customs declaration, where my message gets triggered successfully and gets blocked for further processing till the inbound IDOC receives with Customs Registration number. While IDOC simulation, I am able to get the Registration number but the document still remaining in blocked stage only which is not getting removed and I am not able to process next activities.
    have I missed any configuration related to message which is not allowing me to complete the activity.
    Request you to help me to resolve this issue.
    Thanks & Regards
    Rahul

    Hi Rahul,
    For which country & message type are you testing?
    Regards,
    Dave

  • Customs Declaration Cancellation

    HI
    - GTS System is configured to create a Customs Declaration Document automatically upon saving the Billing Document in SAP ECC System
            What is the process followed in the below scenarios:
            1) Billing Document has to be cancelled out in the ECC System and after this how do I cancel the GTS Customs Declaration document
             2) How do I cancel the GTS Customs Declaration document and recreate it
             3) How do I resend the changes made to the ECC Billing Document to the already existing GTS Customs declaration document.
             4) Would the standard GTS Customs Declaration document bring in the Batch Number and Serial Number from Feeder System
    Rahul

    hi Rahul,
    please check this link for a detailed description on cancelling customs documents:
    http://help.sap.com/saphelp_gts72/helpdata/EN/46/e145da219740e1e10000000a1553f7/frameset.htm
    Please do not forget to upgrade to the latest SP and make sure your settings are ok.
    to your scenarios:
    1. if you cancel the original invoice, the customs document should be cancelled automatically as well unless it has already been sent to the authorities
    2. you can cancle it in GTS choosing the menu Customs document, Cancel (see the above link)
    you can recreate the document in GTS manually or you can retransfer the corresponding sales document from your feeder
    3. this should happen automatically
    4. please check note 1002632
    usually it is only the main item that is tranferred
    if you need the batch item in GTS you have to change your settings in r/3, so that you invoice the sub items and only show the main item (see also note 77414). In this case also the main position is taken as reference.
    5. I think the serial number will be transfered from the delivery, but I'm not 100% sure of that
    Balazs

  • Is it possible to create a customs declaration for the document which is cleraed from customs

    Hi Experts,
    I want to generate a custom declaration for the declaration which is cleared from customs.
    Is there any function module for this requirement.
    Please post your suggestions ASAP.
    Thanks
    Srinivas

    hi Srinivas,
    It’s not possible to create a new declaration for a declaration that is
    already accepted by customs. There could be below 2 possible options
    1. U need inbound cancellation messages in the respective activity sequence,
    and then u can request customs by mail or phone to send the cancellation
    message. Once the cancellation message is received document gets cancelled and
    u can create new declaration
    2. U need a new optional activity sequence that will have outbound
    cancellation message. once u trigger the cancellation message, customs will
    reply back with the cancellation confirmation message and u can create a new
    declaration
    Hope this helps...
    Regards,
    Santosh

  • GTS CUSTOM DECLARATION

    Hi All,
    We have an issue related to GTS Custom declaration.
    Custom declaration is created manually after GR. Now I want the custom declaration to be cancelled and recreate a new custom decalration. We have deactivated the current custom declaration, since while cancelling it was throwing an error message stock poting already done so it cannot be cancelled.
    Could you please let me know how to process it. should we recreate the delivery in R/3 to create the custom declaration or we can use the same delivery and how to delete the custom declaration created in IPR or FC.
    Thanks

    Hi Ramakant,
    Bad news, I'm afraid.  As the system already informed you, it is not possible to cancel a Customs Declaration when the stock posting has already taken place.  Perhaps in time there will be a reversal process (as there is now for GR and GI in ERP), but right now there is nothing.
    I hope your client is still in "test" mode, rather than productive.  Just as in real life, not everything can be undone!
    Regards,
    Dave

  • How to block the creation of a Sales Orders without a linked Purchase Order

    Hi. I'm trying to block the creation of a Sales Order that doesn't have a linked Purchase Order. The first thing I did is using the SBO Transaction Notification as follows:
    IF  @transaction_type = 'A' AND @object_type='17'
    BEGIN
         IF (SELECT PoPrss FROM ORDR WHERE DocEntry = @list_of_cols_val_tab_del) = 'N'
         BEGIN
              SET @error = 1
              SET @error_message = 'Purchase Order Missing...'
         END
    END
    This works good. I create the Sales Order, I tick the purchase order field on the logistics tab, I click Add, and then the purchase order window appears...
    Then, the problem begins... If I click the Cancel button, the purchase order is obviously not created, but the Sales Order is created.
    Can someone tell me how to block the creation of the sales order If the user press the cancel button on the purchase order window (and the purchase order is not created)
    As far as I can see, after clicking the add button in the sales order document, the Sales Order is created on the DB. If there's no way of blocking the creation of the Sales Order, can I avoid closing the purchase order window by the SBO_TransactionNotification? (if the purchase order has not been created)
    Thanks...

    Hi Yail,
    I think you can't close the purchase order with the stored procedure.
    Try to catch the Event when the user click on Cancel button.
    So you can list the vents with event logger : https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/ede3be37-0e01-0010-1883-cd1b5293473e
    You can block the cancel button and force the user to create the purchase order.
    Hope i help you
    Best regards
    Michael

  • How to block the Creation of Mulitple Excise Invoice in J1IS

    Hi Sap Gurs,
    Can any tell me how to block the System allowing  to Create One more Excise Invoice in J1IS against Same GI Material Document no (Ref Trans Type:MATD) for Outgoing Materials ie:Stock Transfer from One Plant to onother Plant by Mvt Type 351(Single Step Procedure)
    In SD, System is not allowing to Create One more Excise Invoive against One Billing Document Untill we Cancell the same.
    I want to make it like same for the above Issue.
    Pls check it in your system and give a Feed Back.
    Thanks in advance.
    Bye
    Sathish

    Hi Yail,
    I think you can't close the purchase order with the stored procedure.
    Try to catch the Event when the user click on Cancel button.
    So you can list the vents with event logger : https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/ede3be37-0e01-0010-1883-cd1b5293473e
    You can block the cancel button and force the user to create the purchase order.
    Hope i help you
    Best regards
    Michael

  • Bonded Warehouse: Cannot create Customs Declaration

    Does anyone have any experience with Bonded Warehouse that they could help with the following?
    I have setup Bonded Warehouse in GTS, but am unable to create any Customs Declarations from the PO/Goods Receipt. After creating the PO, Delivery, and Goods Receipt in R/3, I am able to see the corresponding entry in the "Display Customs Declaration/Goods Receipt Quantities" report in GTS, however it does not appear in the "Display Assigned Logistics Documents from Worklist" and I cannot create the Customs Declaration for it.
    Does anyone have any ideas that could help with this? Thanks!

    Hi Tom
    This one is a fairly old thread that you had initiated. I am now in a similar situation in our project where we are trying to configure CWH and are not able to create customs declaration. The worklist shows the status as 'Customs declaration not needed'. Did you find any way out on this issue you faced? Please let me know.
    Regards

  • Import custom declaration

    Hello,
    Is it possible to create import custom declarations from purchase orders (duplicated from feeder system) without inbound deliveries? We did not implment the inbound delivery function in R3. From what i read, it seems that I can create the worklist for customs declarations prior to goods receipt directly from purchase orders.
    Please help.
    Thanks,
    Wen

    We have maintianed Tariff code as required. I can see the entry of Tariff code  by taking the GUID CTSNUMC from table  /SAPSLL/PRCTSC  and putting it in the table /SAPSLL/CTSNUMC .
    When we click the ?  mark it populates but not automatically.
    When you say product master i believe you referring to table /SAPSLL/PRCTSC   as the data element (/SAPSLL/CCNGN) you mentioned is present in this table.
    Kind Regards,
    Sameer