BOM Explosion in Delivery w/o Reference

Hi to all,
can anybody tell me if BOM Explosion is working in combination with the creation of a delivery w/o reference (LO).
I made the neccessary settings for the item type consideration but when I try to create a LO-Delivery, the system is only creation the header position of the BOM but without the explosion.
Thanks for a short reply.
Rgds.
Jörg

Hi Jitesh,
thanks for your reply.
I checked my settings but from my point of view everything seems to be right.
My material has pos.type.grout LUMF
I like to have an explosion with DLP for the header an DLN for the components.I think normally DLP is intended for P-acking but as there are no other specific settings on this type I took it as the corresponding one to TAP which I have in the order on the header position.
For DLP I set the BOM settings to A / SD01 and X for creating delivery group.
For Pos.type determination I have
LO LUMF                       DLP
LO NORM             DLP   DLN
But I still only have the header position without explosion.
If you have any ideas left pls. let me know.
Thanks in advance.
Jörg

Similar Messages

  • BOM Explosion in Delivery (VL01N)

    Hi,
    I have business requirement in BOM Explosion in sales.  At the time of sales order (basically this is created when receive the PO from the customer), BOM is not finalised in the system and this is finalised before producing the material & even sales BOM also finalised before production.  So, when i copy the item from order to delivery, in that level requirement to explore BOM.
    Can please help in this.
    Regards
    Gautam

    Hi,
    Thanks for your reply.
    As per your answer, ur saying we can change the item category but item category is grey at the sales order level and its not modifable.
    Can please help how to make editable.
    Rgds
    Gautam

  • BOM Explosion in Delivery

    Hi,
    We have a requirement for exploding delivery in outbound delivery only.
    Our client wants to explode the BOM in outbound delivery as they want to use BOM components only for the purpose of packing.
    They are not showing the BOM items in the Sales order. ( SO has only BOM header, as they have a seperate process for BOM items consumping against the SO in PP module )
    Please let me know if there is a way of doing this in SAP.
    Please let me know what kind of customizing and requirements ( both at header and item level in copying control ) need to be maintained.
    Thanks
    Venkata Rama Reddy.K

    Hi,
    You have the option of Item Category Determination for Deliveries.  You need to have different item categories for SO and Delivery and this has to be mapped in the copy control.  In the Delivery Item Cat determination, you need to mention the Higher Level Item Cat and the Sub-item IC. 
    Hope by this way you will be able to explode BOM in the Delivery.
    Thanks
    Krish.

  • Sale order bom explosion in delivery doc

    hi all
    there is an urgent requirement for my clint
    issue is my clint want the BOM should not expolde in sales order, should expolde at the time of delivery only.
    is there any possibility please suggest
    thanks
    sridhar

    Hi,
    Thanks for your reply.
    As per your answer, ur saying we can change the item category but item category is grey at the sales order level and its not modifable.
    Can please help how to make editable.
    Rgds
    Gautam

  • Problem regarding Sales BOM explosion in Delivery

    Dear SD Gurus,
    The problem is,
    I've a BOM with Higher level item TAP.
    when i do a partial delivery, only for the first time the BOM is getting exploded and later on whenever the user tries to create the delivery, only the  header item in the BOM is displayed in the delivery. The user has to enter all the sub-items manually and also the quantity.
    what must be the reason?
    Please anyone try and throw some light. Its hard for the user to do so much data entry
    Thanks & Regards

    Hello Srikkanth,
    Thanks again
    but yes the check box for create delivery group is checked & also the structure group is A.
    This is basically a quantity contract against which the user has cretad four release orders.
    And for one order out of four user has created a partial delivery and invoice. Everything went fine until here.
    Now when he wants to again create a delivery against the same order, only the header item for the BOM is displayed.
    But the system is allowing to manually enter the sub-items and its quantity in the delivery and do the PGI and Invoice.
    This is what i am not understanding,
    and I hope you have understood the problem. Please ask me if any doubts.
    Thanks

  • BOM Explosion needed on PO and/or Delivery for Stock Transfer PO Process

    Good afternoon,
      I have been researching the SDN and web for a solution to my problem to no avail so far. 
    The business problem I need to solve is the requirement for our STPO process to explode certain BOM's that are transfered from one company/plant to another company/plant in order to record batch/serial # component information by the delivering plant on the delivery and verification of the batch/serial # in the receiving plant during MIGO processing of the delivery.  This is needed by our Service Mgmt department in order to track servicable items within the Finished Good (medical devices industry).
    It appears on the SDN that a BOM can not be exploded on a non-Subcontracting PO (which would be ideal for us), but barring this problem, we are trying to have the BOM explode in the Delivery created from the STPO via the VL10B transaction.
    The STPO generates a Delivery doc with type NLCC and item category NLC.  I have maintained the material master for the BOM material to have an Item Category Group of ERLA, and I have modified Item Category Determination in configuration in Logistics Execution for deliveries to include ERLA, usage V, and NLC as default item category.  But, the deliveries generated from the STPO still do not explode, like what normally happens if the delilvery of the BOM was created from a standard Order.
    The components for the BOM need to be displayed on the Delivery (if not the STPO), so the cleark can record the Batch/Serial #'s for each component.  Then when the receiving plant posts the Goods Receipt for the delivery a user exit we have (based on movement type and material document code) builds a Service Mgmt table that is then processed to De-install the BOM and components from the former plant and install the BOM and components at the receiving plant (and then subsequently at the ultimate customer's location when a normal sale is made), generating a new Functional Location.
    Has anyone here had to do anything like this before?  Would any of you have any ideas on how this BOM explosion might work on the PO or Delivery?
    Thanks in advance.
    Scott.

    No responses to this question.
    Subject dropped.

  • BOM Explosion needed on Delivery for Intercompany Stock Transfer Order

    Good afternoon,
    I have been researching the SDN and web for a solution to my problem to no avail so far.
    The business problem I need to solve is the requirement for our STPO process to explode certain BOM's that are transfered from one company/plant to another company/plant in order to record batch/serial # component information by the delivering plant on the delivery and verification of the batch/serial # in the receiving plant during MIGO processing of the delivery. This is needed by our Service Mgmt department in order to track servicable items within the Finished Good (medical devices industry).
    It appears on the SDN that a BOM can not be exploded on a non-Subcontracting PO (which would be ideal for us), but barring this problem, we are trying to have the BOM explode in the Delivery created from the STPO via the VL10B transaction.
    The STPO generates a Delivery doc with type NLCC and item category NLC. I have maintained the material master for the BOM material to have an Item Category Group of ERLA, and I have modified Item Category Determination in configuration in Logistics Execution for deliveries to include ERLA, usage V, and NLC as default item category. But, the deliveries generated from the STPO still do not explode, like what normally happens if the delilvery of the BOM was created from a standard Order.
    The components for the BOM need to be displayed on the Delivery (if not the STPO), so the cleark can record the Batch/Serial #'s for each component. Then when the receiving plant posts the Goods Receipt for the delivery a user exit we have (based on movement type and material document code) builds a Service Mgmt table that is then processed to De-install the BOM and components from the former plant and install the BOM and components at the receiving plant (and then subsequently at the ultimate customer's location when a normal sale is made), generating a new Functional Location.
    Has anyone here had to do anything like this before? Would any of you have any ideas on how this BOM explosion might work on the PO or Delivery?
    Thanks in advance.
    Scott.

    No responses to this question.
    Subject dropped.

  • BOM explosion in Quote to Order

    Hi
    In our sap instance we use the item category AGN in the Quotation and the BOM does not explode in the quote, when we create a order with reference to quote we want the BOM to explode item categoyr used in the order is TAP.
    Checking the "Rexlopde structure/free goods" works but i am wondering why the BOM automatically explode when we copy from contract to order even without checking the flag "Reexplode structure/free goods"
    thanks,
    Meyyappan.

    All depends upon ur item category and its determination.
    In quotation,
    QT + LUMF = (Item category?) which is not relevant to BOM Explosion
    but,
    OR + LUMF = TAP (relevant for BOM expolsion)
    OR + NORM + TAP  = TAN
    Please check and inform me the Item category settings
    (( even if u want the BOM to explode in QT also, u can do the item category "structure scope"settings))
    Edited by: kaleeswaran bhoopathy on Jan 25, 2008 3:27 PM

  • BOM explosion in subcontracting order according to revision level

    Hello experts
    I have different revision levels available for a subcontracted material, e.g. the BOM of this material has different versions depending on the validity date.
    When a BOM explosion is carried out in the subcontracting order (either in the purchase request or in the purchase order) the selected version of the BOM is done accordingly to the delivery date. It does NOT take into account the revision level even when I change it manually.
    Do you have any idea if it is possible to force SAP to consider the revision level instead of the delivery date for the BOM explosion ? (custo, user exit, BAdI, ...)
    Many thanks
    Amaury

    Hi
    BOM explosion in Subcon PO will be carried out automatically when you select the item category L.
    If you want to control the BOM selection based on the Alternative then you can go with Production version option and get the help from PP consultant to create the production version.
    Assign the production version in Subcontracting Inforecord.
    Click the BOM explosion button the switch to alternative BOM during the PO creation.
    Hope it helps
    Thanks/Karthik

  • BOM Explosion problem

    Hi,
    I have multilevel BOM (almost 10 levels with around 1500 materials), in which many materials repeat at different levels.
    I am facing problem in one of the material during MRP, This material is used at 10 different levels. Altogether to produce a FG it requires in 36 numbers. In different levels quantity of it required is different. Say 8,1,4,2 etc but total qty is 36.
    When MRP is run the requirement generated for this material is same at all levels i.e 36(total qty) / 10  (BOM levels) = 3.6
    But actually system must generate requirements as per BOM quantity. Not sure what is wrong.
    Requesting you all to reply quickly for this issue.
    Regards,
    Pavan

    Hi,
    Below is the little knowledge i have which want to share with all the august people around.Hope it would be helpful enough for you to get the results.
    A BOM is not exploded in the following situations:
    - No BOM is effective:
    -- On the explosion date and in the given area of validity
    For the given effectivity parameters
    - The BOM has a deletion indicator.
    - The BOM is a multiple BOM, and has no alternative that matches the lot size for your required quantity.
    - No BOM matches the selection criteria of the BOM application you selected.
    - This is possible in the following situations, for example:
    -- The application does not take all BOM usages into account.
    For example, the application only takes BOMs that are relevant to production into account, so a BOM that is relevant to sales and distribution is not exploded.
    -- The application selects a specific alternative on the explosion date you require. The material master record supports alternative determination by Explosion date.
    If the specified alternative is not valid on the explosion date, the BOM is not exploded.
    -- The application takes production versions in the material master record into account, but no production version has a BOM that is valid on the explosion date you require. The material master record supports alternative determination by Production version.
    The system only explodes the BOM defined for the production version that matches the alternative and/or usage entered on the explosion date required.
    -- The application only takes BOMs with certain status indicators into account.
    For example, the application for MRP only explodes BOMs that have at least the status Explosion for MRP.
    Further checks:
    - Do the proper Scheduling in Routing (Backward/forward). In md61 give the requirement in next month.check your in-house production, planned delivery time in md02 give MRP Control parameter Rexplode BOM and Routing.
    - Check BOM explosion data in MRP4 view of material master view ( Individual/Coll data).
    Please revert with your response
    Thanking You in Anticipation
    Regards
    Chandra

  • BOM explosion not done because there is no free item number anymore

    Hello,
    I have a problem with BOM explosion when creating a sales order.
    All the following actions are done with VA01 :
    -  I enter a material (main item 10) with a rejection reason, so the BOM explosion is not done :OK.
    - Then  I add the same material (main item 20) without rejection code, so the BOM explosion is done, it means sub items 21, 22., ...,31,32 are determined:OK
    - Finally, I remove the rejection code on item 10, the problem is that there is no place anymore to do the BOM explosion because I have 12 sub items (10 +12 = 22 and it is not possible as I have already an item 20).
    I have a popup with message V1-142 (There are not enough item numbers free for a structure explosion).
    I know that it is possible to change the increment with VOV8, but my customer want to keep this one: 10 by 10 for main item and 1 by 1 for sub item.
    He told me that he think that there is a user exit in order to put the remaining sub items at the end of the sales order like this
    10 main item A
    11 sub item 1 (A)
    12 sub item 2 (A)
    19 sub item 9 (A)
    20 second main item (B)
    21 sub item 1 (B)
    22 sub item 2 (B)
    32 sub item 12 (B)
    33 sub item 10 (A)
    34 sub item 11 (A)
    35 sub item 12 (A)
    Maybe it's a strange idea, but could you please tell me what are the different possibilities to manage sub items when there is no place to put them :
    - put a higher increment in VOV8? Ok but my customer don't agree
    - other solutions?
    Thanks.

    Hello,
    Did you ever find a solution for this? The notes mentioned in the earlier post dont appear to be relevent for 6.0.
    I have a similar issue when dealing with Cross Sell items. When it tries to insert the additional items I get the V1142 message, then the items are copied at the end of the list but the higher level item reference is incorrect for the cross sell items.
    I do not want to change the increments but it appears to be the only option.
    Any ideas are appreciated.

  • BOM Explosion - R12

    Is there any other API for BOM Explosion in R12 other than the one given below?
    Bompexpl.Exploder_Userexit
    Thanks
    Manu

    hi Janardhan,
    phantom assembly is the assembly which is not kept in stock rather it consumes directly.
    Use of phantom assemblies are as below
    Phantom assemblies are assemblies that have their own product structure, but whose assembly does not actually physically exist. The components of the phantom assembly are incorporated directly in the superordinate product. The product structure of the superordinate product contains a reference to the phantom assembly.
    example - A car with music system.
    During backflush, only the goods movement for the phantom assembly components are posted. The phantom assembly is marked as backflushed but does not trigger any goods movement.
    Experts pl correct me if i'm wrong.
    Regards,
    Anil

  • BOM Explosion - special procurement  type 52 (collective order)

    In BOM explosion, special procurement type -> collective order (52) for the item  is considered as phantom assembly. I wish to know the business reason for this. Any help please ??

    hi Janardhan,
    phantom assembly is the assembly which is not kept in stock rather it consumes directly.
    Use of phantom assemblies are as below
    Phantom assemblies are assemblies that have their own product structure, but whose assembly does not actually physically exist. The components of the phantom assembly are incorporated directly in the superordinate product. The product structure of the superordinate product contains a reference to the phantom assembly.
    example - A car with music system.
    During backflush, only the goods movement for the phantom assembly components are posted. The phantom assembly is marked as backflushed but does not trigger any goods movement.
    Experts pl correct me if i'm wrong.
    Regards,
    Anil

  • BOM Explosion for Multiple Process Orders

    Hi,
    I hope someone can assist me with the following: Is there a report I can run or transaction I can do to have BOM explosion for multiple Process Orders? I would like to input process orders for a week and see the BOM details per PO.
    Thanks

    Dear Sukendar,
    1.For this requirement you have to go for a Z report and you can give the Functional Spec's to prepare
    this report to your ABAP consultant.Prepare the input format,logic of the program and the output format.
    In the logic part you can make use of this Functional Modules's CSAP_MAT_BOM_READ or 
    CSEP_MAT_BOM_READ  or CS_BOM_EXPLOSION   or CS_BOM_EXPL_MAT_V2 .
    2.Using CEWB helps you to identify all the material that's having the BOM,but here the report does not
    shows you the level by level by BOM for a FERT.
    Check and revert back.
    Regards
    Mangalraj.S

  • BOM explosion in subcontracting PR

    Hi...
    I have one issue of BOM explosion in subcontracting PR.
    I have created BOM, routing & PV. Production version maintained in info record.
    While creating manaul subcontracting PR , BOM is not exploded giving error message as "Not possible to determine any components".
    I have checked validity of BOM, PV found ok.
    Also Proc. type X & Spl. proc type 30 maintained.
    Any suggestion to the problem appreciated
    Regards
    Tushar

    Dear Tushar,
    Check this link
    [Sub contracting PO - BOM components are not seen;
    Regards
    Madhu

Maybe you are looking for

  • How to get the list of collaboration rooms for a particular user??

    Hello Experts, I have a requirement to get the list of all the collaboration rooms for a given user. I have started developing the Web Dynpro application by reusing necessary jars required to the web dynpro application. on some action I am trying to

  • Need XI Interview Questions and Answers

    Hi Experts, Iam New to XI, i have an Interview I need Interview Questions with answers,if anyone is having please help me. regards, sush

  • Many to many relationships between Fact and Dimension

    Hi All, I have to solve two kind of many to many relationships between Fact and Dimension. 1. Many to Many relationship between Fact and Dimension, using a bridge table, with FKs in fact and dimension to bridge table’s PK. 2. Many to Many relationshi

  • Another 'Cannot mutate bound sequence' Question

    Hi Everyone, The below code throws a "Cannot mutate bound sequence" when the line (id:'a') is pressed first. However it runs fine when lines 'b' or 'c' are pressed first. But the output shows the correct line 'a' has been deleted when pressed first.

  • Can I re-download videos from 3 years ago?

    A laptop I had awhile back crashed and I had a ton of purchased tv show episodes on it. Is there a way to get them back even after these years?