BOM explosion in process order

Dear PP experts
In my scenario, the sales order and process orders for the corresponding line items got generated by uploading some details of master contract through some Z code. The client provide me details regarding the BOM for the process orders from their third party software, which process through XI. I have to trigger that bom into process order. for that i first maintain the bom details in CS61 and then trigger the "Read Master Data" in process order manually. Now i have to do it automatically. means when the BOMvdata flows from third party software, it should get updated in cs61 and simontaneously "read master dat" should get triggered. how can i do this. please suggest

Hi,
Check for any BAPI / Function Module in SE37 which can fulfill your requirement.
Search BAPI with SAP component ---> PP option in search help(F4).
Regards,
Tejas

Similar Messages

  • BOM explosion in sales order

    Hi Experts,
    I have met a problem in BOM explosion in sales order.
    I have maintained the BOM with usage 5 and the conversion between header material and component of the BOM. But in the sales order entry, no matter how many qty I entered for the header material, after the BOM explosion, the qty of component is 1.
    Can anyone help?
    Regards,
    Emily

    Hi,
    Go to CS02 and select ur bom and go to components give 1 that means 1;1
    hope u get it
    regards,
    sadanandam kasarla

  • Changing BOM-items in Process Order not allowed

    that Hello,
    Mi client is asking me if it is posible, once created a Process Order, upon modifying the order (COR2), that the user can not change any of the cuantities and batches of the material list (BOM) updated in the Process Order.
    Is there any way one can protect the material list from being modified once created, or once liberated the order?
    Is it posible, moreover to just protect the BOM ítems updated in the Process order but let the option open to add exta BOM ítems manually.
    Is there a userexit or a Badi one can use to acomplish this?
    Thanks for any reply.
    Aart

    Hi Aart,
    Yes, you can use BADI to protect the BOM items from not to change the BOM items in Process order.
    In one of our project we have taken the help from the ABAPer, has has done the same thing.
    Then we have acheived the same requirement.
    You check with the ABAPer, he will help you for the requirement.
    Thanks

  • Material BOM explosion in Service Order components

    Hi experts,
    I created a Material BOM with transaction code CS01.
    Then I try to add this BOM in the component of a service order.
    What I expected is the BOM to be exploded in the service order. But this behaviour doesn't occur.
    Do you know what I can do to trigger a Material BOM explosion at service order level.
    By the way, the BOM is not exploded after the service order (in the reservation or in MIGO).
    Thank you for your help.

    Hi Özgen,
    Thank you for help.
    Special Procurement 50 didn't exist in my system.
    I created it in SPRO for the plant with the Procurement Type F (External Procurement) and the flag Phantom Item checked..
    Then I created
    - Material A (MM01)
    - Material BOM A (CS01) with:
    -- item 1 Material B (which has Spec Proc Type 50 in MM02-MRP2)
    -- item 2 Material C (which has Spec Proc Type 50 in MM02-MRP2)
    After that I created a Service Order (IW31)
    I put Material A in the Component tab with quantity 1.
    The BOM remains unexploded.
    Did I miss something?

  • BOM explosion date after order finish date

    Hi
    We have issue with BOM explosion date. In process order, BOM explosion date is geting calculated after order finish date.
    Any idea why this is happening.

    Hi,
    Just to understand the issue better, can you list the scheduled and basic dates on the order.
    Anup.

  • Bom explosion in sales order mrp(MD50)

    Hi Experts,
    In sales order MRP i.e. MD50 Getting the planned orders for header material(Finished goods) generated but for raw materials (BOM items) Purchase requisitions are not getting generated.
    Details:
    Header material A and raw materials B and C.
    In material B in MRP 4 coll/ind indicator is 2 And same indicator for C is blank.
    Now when we are running the MRP sales order based it will generate the purchase requisition for C only but not for B.
    In OPPQ we have done the setting for sales order BOM explosion.
    Can anyone please throw some light what is the setting missing in customization or in front end?
    Thanks in advance.
    Regards
    Vilas

    Dear,
    If you select individual requirement then system will not consider available stock and generate Proposals for every single requirments. Check in MRP4 view Individual / Collective .
    Also you will find PR and Plan order with account assignment of Sales order (in case of MD50).
    - If you select collective requirement then system will not generate planing proposals through MD50.In that case you have to go for individual MRP (MD02 / MD03)
    Please try and come back.
    Regards,
    R.Brahmankar

  • BOM explosion in Sales order with material variants

    Dear all,
    we would like to work with Variant Matching in the Sales Order. Additionaly we would like to explode the BOM....according to the SAP help this is not possible....
    http://help.sap.com/erp2005_ehp_06/helpdata/en/bd/05a7d69d3211d190380000e8a49aad/frameset.htm
    Does anybody of you has any ideas how and where to make this happen?
    Thanks for your help and kind regards
    Jan

    Hi,
    I have gonethrough the SAP link referred by you but never come across with any problem in type matching during Sales order even if the BOM explosion is set for Multilevel in Configuration Profile provided the other pre requisite set up was perfect.
    Regards
    Brahmaji D

  • BOM explosion from Production Order

    Hi All,
      I understand from SAP Help files that we can explode BOM from Production Order using Read PP Master Data. But it also says, that we cannot do this if items have already been issued out. So would like to know is there anyway out to ensure that the production order is reading the latest version of BOM.
      The reason i want to know is because, at present the BOM keeps getting updated & so the work order has to reflect the new items. The BOM contains about 300 or more items, so manual changes is very tedious & error prone at the moment. Furthermore some components are outsourced. So i want to receive them back & post new materials for them. Hope my problem is clear & await inputs
    Vivek

    Hi All,
    Thanks for the inputs. I think for the situation am facing, the Order change management method, should be of help, as the BOM changes does not take place on scheduled dates, for me to fix the BOM explosion dates & assign them. As of now the BOM gets changed, depending the customer requirements, which is unpredictable.
    Clarification required:
    1. The profile which is created using OPL7 & assigned in OPL9 is unique, i.e. for any change numbers of BOM will always follow the profile entered in 'Overall Profile' in Work Scheduling view & i do not need to create new profiles for each new change number of BOM
    2. Once i run the COCM with the new change number, in the production order - components view will i be able to see any error message for those items which no longer feature in the new version of BOM? & will the materials added in the new BOM automatically feature in that list or do i have to manually add these to the order & if so, how will i know which materials need to be added?
      Hope the clarifications sought are clear, await inputs
    Vivek

  • Track Deleted BOM item in Process Order

    Hi Guys,
    I am facing one issue which is described as below.
    when user is converting the Planned order into Process order at that time he has deleted 1 BOM item.
    Now i he is saying that i have not deleted that item and after that he released and done the GI conf GR.
    Now i want to track the change history but i am not able to find the changes done by him.
    I have check so many blogs but i come to know that if he is deleting BOM item during creation we will not able to find.
    Pls help

    Hi D R,
    To the best of my knowledge at the time of creation if some component has been deleted, you can not  track. Because up to that time table entry has not happened. After saving you can see the component.
    If you have some existing process order which is without item deletion, you can compare and check. As well Check the BOM in CS03 and check the BOM inside process order. You can easily find out the component.
    Hope this clarifies and at per your requirement.
    Success.
    Regards,
    Krishnendu.

  • No BOM explosion in assembly order

    Dear Experts,
    I am running a assembly order, type PP04 which is directly created from a sales order.  During the creation, the BOM is exploded.
    My question is that how can I disable the BOM explosion as I want to enter all the components according to our customer rule instead of a predefined BOM.
    If there is no BOM of that material, there will be a error message when saving the production order.
    Thanks.
    Claude

    Hi,
           following settings to be made in Customization for the Assembly Order If you don'twant to explode the BOM
    1) Create the selection ID with priority & BOM usage in OPJI
    2) Create the BOM Application & Assign the selection ID created in above step & Also mantain the following cheks in OPJM
    uncheck the Sales Order explosion indicator--OPJM
    3)Assign the above Application to the Order type & Plant in OPL8
    Thanks,
    Rajanikanth

  • No BOM Explosion in Planning Order

    Hello Folks,
    i have a problem with the BOM explosion at creating a planning order.
    Our BOMs are created without plant number and are enterprise wide available.
    If we create new BOM's with direct plant association via CS01, the BOM explosion in creating a planning order is possible.
    I've already searched in Customizing and Transactions and didn't find anything to make a BOM explosion possible with an enterprise BOM.
    Do you have any idea how it is possible to do that? We don't want to create new BOMs because it is too much workload to create all new BOMs. We use a SAP ECC 6.0 with IS-Retail.
    Hope you can help me.

    I think that it is a must to have the BOM defined for plant to be exploded in a planned order.
    Nevertheless, you don't need to create it a gain for each plant, you can instead just do a plant assignment (CS07).

  • BOM explosion in subcontracting order according to revision level

    Hello experts
    I have different revision levels available for a subcontracted material, e.g. the BOM of this material has different versions depending on the validity date.
    When a BOM explosion is carried out in the subcontracting order (either in the purchase request or in the purchase order) the selected version of the BOM is done accordingly to the delivery date. It does NOT take into account the revision level even when I change it manually.
    Do you have any idea if it is possible to force SAP to consider the revision level instead of the delivery date for the BOM explosion ? (custo, user exit, BAdI, ...)
    Many thanks
    Amaury

    Hi
    BOM explosion in Subcon PO will be carried out automatically when you select the item category L.
    If you want to control the BOM selection based on the Alternative then you can go with Production version option and get the help from PP consultant to create the production version.
    Assign the production version in Subcontracting Inforecord.
    Click the BOM explosion button the switch to alternative BOM during the PO creation.
    Hope it helps
    Thanks/Karthik

  • BOM explosion in sales order for configurable materials and variants

    Hi,
    I have these materials:
    A: configurable material (header)
    B: variant material (header)
    C: configurable material 1 (position)
    D: configurable material 2 (position)
    E:variant material 1 (position)
    F:variant material 2 (position)
    I can in the sales order explode in this way the BOM (using SD01 application in the position type of the header material):
    1) A --> C+D
    2) B --> E+F
    while I can't make the explosion in this way: A --> EF and A --> CE
    is this possibile? I want to make an explosion of a BOM for a configurable material  and having variants material as sons, or having mix sons (one configurable and one variant)
    Thank you
    Sandra

    Hi Sandara,
    Just check the BOM in cs03 u have maintained !!! If u have maintain the variant material there in the config mat BOM with object dependencies than u can explode !!!!
    Please let me knwo if u any query and also if u elabore more than will help u out

  • No BOM explosion in Sales order item if another item exist

    Hi Experts,
    I have the following problem:
    If I have one item in sales order, it explodes multilevel and everything is OK.
    If I have 2 items in sales order,
    the first one(item 10) has to explode and
    the second item (item=20)has as higher-level item the first sales order item (UEPOS=10),
    there is no explosion.Item 20 is not in the BOM of item 10.
    I don't understand why item 10 doesn't explode  if there is another item in sales order with higher level to him. Any help please?
    Thank you.
    Kind regards,
    Danijela

    HI,
    Chck the Item Category Grp. of line item 2 & line item 1 BOM materials.
    I feel the item category of BOM Material is not NORM...
    Also with that pls. check the item category of 2nd item.
    try this i hope this will help you..
    revert me if not solved...
    Regards
    Deepak
    Edited by: Deepak Dhingra on Jun 18, 2009 10:43 AM
    Edited by: Deepak Dhingra on Jun 18, 2009 10:52 AM

  • BOM explosion in Sales Order acting weird

    I am trying to make a simple BOM explode but it just wouldn't although as far as I can see it should. The details:
    1. I created a sales BOM (T-FUA01) with usage 5 (S&D), entered the components (automatically got L - stock item), entered the plant no. and saved it.
    2. I went to the Material Master of the sales BOM and changed the item category (not the general Item category) to ERLA.
    3. I checked that OR - ERLA -blank - blank combination leads to a TAQ from Customization.
    4. I checked that structure scope of single level BOM (option A) has been selected for TAQ.
    When I make the Standard Order (OR) though with Material T-FUA01, the sales BOM simply gets the Item Category of TAN and upon manually changing it to TAQ explodes when it should be doing this automatically. This made me think that apparently the system is using:
    OR-NORM-blank-blank
    that allows 4 different options to be manually entered (hence I can). But why is it taking up NORM instead of ERLA or even LUMF is simply beyond me. In frustration I even changed the General Item Category which has nothing to do with this but as expected did not help.

    Hi
    just re-check the following:
    1) in your material master, the item category group is ERLA in sales org 2 view field: 'Item category group'.
    2) You re-created the order after you changed the material master.
    3) You're using standard item categories?
    Regards,
    Raghu.

Maybe you are looking for