BOM Selection Mandatory while creation of Production Order

Hello Friends,
I would like to know that is there any option other than production version which makes it mandatory to have valid BOM must for creation of Production order / coversion of planned order to Production order.
I have tried with Production version option but it doesnt throw any error in case BOM with inactive status has been selected in it & also Production order gets created & released.
Before going for user exit / enhancement option, I just wanted to ensure that it is not possible with standard SAP.
Kindly share your views on the same.
Your urgent replies will be highly appreciated.
Regards,
Tejas

Hello Tejas,
I think this is standard SAP Behaviour.
Try with following exits:
PPCO0018
PPCO0012
Also check out the following link:
[How To Make BOM Mandatory while creating Production Order;
Regards,
Vinod

Similar Messages

  • Capacity check is not working while creation of Production order

    HI Gurus,
    I want to restict the system that in case of insufficient capacity at the work centers, sysstem should not create the production order. For that i did the setting
    1) Unchecked the tick for the Capacity check & enter the profile SAPSFCG013 in the OPJK for the business functions 1 & 2.& also make the setting for the Release order '3".
    2) Maintain the same profile in the production profile & maintain that profile in the Mat Master
    3) In the CR02, activate the tick for the finite scheduling & uncheck for the can used for several operations.
    But i have creted the production orders & at the time of capacity check system is giving the message " Capacity avaiolable at all the work centers. But i check in the CM50, all the work centers are overloaded at the respective date.
    But i can create & release the p[orduction order.
    Requesting all to give your comments & solutions.
    Regards
    ACP

    ACP,
    ....after confirming all the operations system is allowing me to save
    When you confirm an order, you are by definition saying that the capacity existed for that order (you have just declared to the system that all operatons have been performed, and therefore all capacity was available).  I can't imagine why you would not wish to save that order, since you must somehow post the physical work that has already been done.  Capacity availability check is really only useful when the order to be checked has not yet been executed.
    CM50 displays capacity requirements.  CM50 does not perform the same function as Capacity availability check.  To ensure that all of your orders fall within you capacity constraints, you must perform capacity levelling.  Capacity availability check does not work the same as a Material availability check - don't assume that what you know about a material ATP will be applicable for a capacity ATP.  Read the help on Capacity levelling.  It is not generally possible to stop a manually created production order from being saved, due to any capacity situation, without using an enhancement.
    http://help.sap.com/saphelp_erp60/helpdata/en/60/13e308133a11d3bf550000e83235ee/frameset.htm
    Naturally, you can use enhancements to have the system meet any business requirement that is not met with the standard Cap Availability check.
    Best regards,
    DB49

  • WM error  while creation of production order.

    Hi ,
    I am trying to create a production order . I am getting below error in log as"Movement type for production supply missing in whse 112, storage type SHP" .
    Can anybody tell me which movement type i am missing here ?
    Regards
    Rohit Chavan

    In OMK0, click on Assign & check if you have assigned mvt. type 319 for the w/h - storage type combination.

  • Serial number creation while confirmation of production order

    Hi team
             Can we crete serial numbers while confirmation of production order. I know how to create serial no while creation of proudction order, while taking usage decision in quality. Is there any way to create serial no while confirmation of production order.
    regards
    ssp

    Hi siva
        There is no way to create serial number at production order confirmation, only at creation and release the order.
    but u can maitain MMSL profile and the sno will create at GR from shop floor to warehouse
    I hope it will help to u
    Regards
    S.Anbalagan

  • Serial number error while creating the production order

    Hello frds,
    I am getting the following error while creating the production order.
    "Item 000000 requires exactly 100 serial numbers for the asset".
    If i give 100 serial numbers in the order, the error is solved. But i do not want to assign 100 serial numbers, i want to assign only 2 numbers.
    I have tried using the new serial number profile also, but it is giving same error.
    Kindly guide.
    Regards,
    Narendra Bora

    Dear Narendra
    Select the serial number profile and go to serialization procedure and set the ser. usage status 02 - Optional as below.
    Procd Procedure description Ser.Usage
    PPRL PP order release 02
    since the serail number creation is optional for order relase this will allow you to relase with out error and with serail number assigned in partial.
    Regards
    Soundar

  • Co- Product Error while creating a production order

    Hi,
    While performing the Co-Products Approtionment at the time of creation of Production order..
    we are facing a problem regarding cost apportionment I have crated a Source Structure and the cost element is assigned to that Source Structure but still iam facing this issue
    kindly help me out.
    the error msg is
    Debit with cost element 9460404 cannot be settled.
    Message no. KD549
    Diagnosis
    Costs/revenues exist for cost/revenue element 9460404.  This cost/revenue element was given source assignment 40 in the source structure (-> settlement rule for sender -> parameters).  However, there is no distribution rule with settlement type FUL for this source assignment or the total of the percentages for the rules is less than 100.
    Note:
    Full settlement settles all the costs and revenues which have occurred up to the settlement period and have not already been settled. In the case of periodic settlement, you can configure the settlement profile so that all the costs occurring in the settlement period are settled, or if an amount less than 100% can be settled.
    Procedure
    Maintain the distribution rules for source assignment 40 and settlement type FUL or use periodic settlement to settle less than 100%.  Change the settlement profile for the sender as necessary.
    Change settlement profile
    Note:
    Cost and revenue elements receive source assignment " " if you have not entered a source structure in the settlement rule parameters.

    Hi Krishna Murthy I went through the note but i couldnt recive a big help from that note.
    I will explain the step by step process that i have done.
    I am attaching the Screen shots of the issue.
    1. For co-products I have created a source structure and Sec. Cost Elements were assigned in the source structure.
    2. The source structure was assigned in the Material Master for co-products equally distrubuting the amount between 2 materials.
    3. When we are trying to create a production order the error was displayed but the costs was getting calculated properly.
    4. When I was settling the production order the same error was getting displayed.
    I have tried various methods to resolve it.
    1. I have created a periodic settlement rule and tried to settle but it didnt work
    2. I have assigned the source structure in the settlement profile this also didnt work.

  • Creation of production order with reference to sales order

    dear all guru's,
                       i m having a requirement of creating production order with ref to sales order but without changing my old strategy of make to stock.
    regards
    ujwal

    Hi,
    For the purpose of creation of production order with reference to sales order while maintaing MTS strategy you need to maintain Make to stock strategy 40 in strategy group in MRP-3 View of Material Master.
    This is the only Make-to-Stock Strategy which enables you create Production Order against both Sales order as well as Demand / PIR.
    So if your strategy group is already 40 then you need not change it.
    However if you are using any other Make-to - Stock strategy like 10, 11 etc. then it is not possible to create Production Order against Sales Order since they dont consider Sales Order in planning.So you need to change them and set strategy group as 40.
    Hope this helps.
    Revert if you have any doubt.
    Regards,
    Tejas
    Edited by: Tejas  Pujara on Sep 27, 2008 8:50 AM

  • Header Material Repeated during creation of production order

    Sir,
    I have defined bom as one component and 3 co product.
    During creation of production order in operation overview i found header material is repeated in components.
    Pl. suggest me where i have made mistake.
    Regards,
    Vivek

    Hi
    Check whether BOM is recursive or not? also check the movement type against the header material.
    Also check in CO03>Goto> Material list
    Regards
    Anupam Sharma
    Edited by: anupam sharma on Jan 30, 2012 12:17 PM

  • Purchase Requisition on creation of Production Order

    Dear Experts,
    Please clarify the following points
    1 In our Business Scenario on creation of Production Order for a Material, Purchase Requisition is being created on creation of Production Order itself for all Dependent Materials where the items are declared as Non Stock items in BOM  and for the stock items only on MRP run the Purchase Requisitions are created. Is this the standard procedure, or can we customize to create the PRs for all the items on creation of Production Orders??
    2 What exactly the processing indicator in MRP list indicate?
    Thank you,
    Regards,
    Ramakrishna

    For Non Stock items it is understandable, that a PR has to be created with production order creation , as they are not in the stock.
    For Stock items, the creation of PR cannot be linked with Production order creation but can be done with MRP run.
    We can make the system create planned orders or Purchase requisitions or PR in opening period during MRP.
    Processing indicator gives you the scope of PLanning.
    PLanning all the materials within the Planning horizon  --NETPL
    Plaqnning all the materials beyond also--NETCH
    Deleting the current plan and recreating the plan.-regenarative PLannng
    regards
    Ratan

  • Problem During Creation of Production Order

    Dear Sirs
    Hope you all are well. I am facing a problem in PPDM during creation of Production Order which is that when I try to release the order System shows me material availability error for BOM items but when I check those material in MMBE(stock overview )all materials are available in UN-restricted use stock. I am facing this problem and not able to resolve it please help me out in it.
    Thanks
    Regards ,
    Haseeb Khan
    Senior Consultant

    Dear
    Did you maintain Work Schedulimng View of the Material ??
    Did you maintain any Production Storage Loaction in MRP2 view and same is appearing in Goods Movement Tab in CO11N screen with Movement Type 101 ??
    Did you maintain the Operation Control Key -pp03  which should have Auto GR check box marked in OP00 ?? Goto Operation Control key -Detail information -Check whther Auto GR is marked or not ??
    If you are using Serrial Number Profile and Serial Number , then Auto GR is not possible .Make sure that you are not haveing functionality because it does not support Auto GR fro serialised material and need to do it through MIGO/MB31/MB1C.
    Make sure that you have used PP03-Control key only at last operation not all the operations.You need to maintain PP03 at Routing level and call the function by Read PP Master data  at production order level   (co02-function read pp master data )
    Regards
    JH
    Edited by: Jiaul Haque on Feb 14, 2011 12:55 PM

  • Automatic creation of production orders via planned orders

    Hello experts!
    is there a way via customizing to trigger an automatic creation of production order from a planned order when the planned order finished date is within the next week?
    thanks

    David,
    Not in customizing.
    Most people create a job step after the RMMRP000 program step in their MRP job, using program PPBICO40.  Dynamic date range is available as a selection criteria against the opening date, which is the standard criteria for selecting and converting planned orders (not finish date).
    Best Regards,
    DB49

  • How do we Prevent Creation of Production Orders for Phantom materials.

    Dear Experts;
    We have some materials which are Phantoms.
    We have set "special procurement type" as 50 in MRP2 and "Strategy Group" as 59 in MRP3
    These are non stchable items, but have BOMS.
    We dont create orders for them, however at the mement the system allows order creation. How do we prevent creation of production orders for these items in the system.
    Thanks in Advance
    Richard.

    Dear Richard,
    Check using this BADI - WORKORDER_UPDATE using method IN_UPDATE or Release by including a check if MATNR and for
    WERKS combination if SOBSL = 50 from table MARC,then do not allow to save.
    Check whether this works or else you have to set a plant specific status using OMS4  for not allowing production order
    creation and assign this value in the material master of the phantom assemblies.
    Check and revert
    Regards
    Mangalraj.S

  • Error While saving the Production Order

    Dear Experts
    Pls let me know why am getting the below error while saving the production order after release..
    PSFC_STD_LAYOUT does not exist
    Message no. SSFCOMPOSER004

    Dear,
    Please check have you assigned the scheduling profile in work scheduling view of materail master?
    Then go to OPKP check the same scheduling profile where you have activited the On realese execute printing remove this tick mark and then try with new order.
    Or you can do the configuration in Tocde :OPK8 here assign the PSFC_STD_LAYOUT in forum.
    Regards,
    R.Brahmankar

  • Error while release of production order u201CNext period is not openu201D

    Hi Experts,
    Need your opinions on this issue where my client is facing a problem while create and release a production Order on the last day of the month (Last day of period change).
    While create and release of production order for Plant xxxx, system uses to give the error; period Next (e.g. 12) is not open. Same thing if I have created the order using T. code CO01; but when I tried to release and save the order through T. code CO02 then it gave me the same error (Next period is not Open), it checks for the next period to open.
    The above scenario happens only on last day of the month. Earlier this kind of error was not there so the question is why the period check is happening while saving the production order.
    After speaking to the user, it is determined that they are facing this problem since upgrade (Since last 8 month). Hence need to check what additional check has been implemented with upgrade from R/3 4.7 to ECC 6.
    Error Message No F5201
    Appreciate your help how to dig up this issue.
    With Regards
    Anant

    Hi Guys,
    Please throw some light why on the last day of the month (Last day of period change) at the time of release the order user is getting error: Period Next (FI Next period) is not open ( message No. F5201).
    My question is why system carried out period checks at the time of release of Production Order.
    With Regards
    Anant

  • Reg:Bapi for mass creation of production order/confirmation

    Dear Experts,
    I wanted to know with the following BAPI is it possible to create Multiple production orders for different semifinshed Materials along with material availability check and other functions similar to CO01 transaction.
    I knew there are standard transactions for mass confirmation for production orders. But i need a confirmation on this BAPI . As i am planning to go-ahed with ,mass creation of production order creation / Order confirmation in single custom transaction.Need back flush activity even supported.
    BAPI_PRODORD_CREATE to create the orders.
    BAPI_PRODORD_RELEASE to release the orders.
    BAPI_PRODORDCONF_GET_TT_PROP to get the default data for the confirmation.
    BAPI_PRODORDCONF_CREATE_TT to ost the confirmation of production order.
    Along with this BAPI do i need to commit any other BAPI to carry out back flush for components.
    Need your suggestions to take it further.
    Regards,
    Daya.

    Dear SAP Daya
    If the issue has been solved, please close this thread.
    You have already mentioned that the issue has been resolved, thefore, you should not ask for help on another thread before closing this one, as it looks like you are trying to force people to answer your threads.
    Users are always trying to answer as many threads as possible on good will we don't need this kind of "incentive".
    Please read carefully the The SCN Rules of Engagement, especially point 8:
    Be responsive. If an SCN member has answered your question, please mark the answer as "helpful” or “correct”. Mark the discussion as “answered,” so that other members can find the answers more easily
    Also, I checked your old threads and I could observe that there is only one closed. Please review your old threads and close those already solved.
    BR
    Caetano