we are purchasing  HSD from Indian Oil.  we giving 2 Type Purchase Orders 1- HSD   2 - Transporation Vedors
Transporation Vendors may be 3- 4 vendors  can supplying HSD to our company.
Every Vendors can be supply  5 times each. we are making service entry sheet of them. while making MIRO, payment will be paid.
BUT only the main concern is :
i want to know how to book TRPT Cost in to HSD Material.
please advise
Thanks

for add trans. cost to hsd,  dont create service entry sheet, u have to add this cost to freight condition  in hsd po, in cond detail badd vendor number of transporter,

Similar Messages

  • How to raise PO for a material with transport cost but no material cost?

    Hi experts,
    My client wants to raise a PO in SAP for a material that will be purchased free of cost.
    He only wants to invoice the vendor for delivery/transport costs.
    Now, as I see it, a free-of-cost PO is not possible because it does not allow adding any pricing conditions. May be I am not aware of some tweak that is available.
    Please provide your help on this. Thank you.

    Hello,
    Firstly Prepare a Po with a line item that you want, then chick the Free check box.
    then go to the Item tab (below), go to conditions & add freight (Freight % or Freight (Value) ) with the required amount.
    you can change the Assignment from the Vendor to a Transporter / Freight forwarder, that you want.
    That is it. you will have a Po with no Commercial Value but just Transport Cost.
    Thanks & Regards,
    Atul Sabnis
    Edited by: Atul29 on Jul 7, 2011 1:52 PM

  • Transportation cost before the reception of the material in MIGO (Stock in transit)

    Does it exist a way to make a reception of materials in transit and post the transportation cost before the reception of the material in MIGO ?
    The  material is own of company before to be receipt in plant.  We need to pay the transportation before that material is arrived at plant. 
    As the value is an important cost, we need that this cost be linked with the cost of the material.  We can put a condition, but it does not work if the material in not receipt in MIGO.  We can enter a subsequent debit memo, but the invoice of the reception should be enter in the system and by the way the reception too.  So how should we process to link the transportation cost with the material if this material is not received at plant and by the way in MIGO.
    Thanks in advance

    Hi,
       As of my knowledge, system will allow to process the shipment document - create shipment cost document and vendor invoice also, even before doing GR for the PO. Please check the scenario and revert back if you are getting any error.
       If you want the shipment cost as delivery cost, refer the note: 427944 - Info: Shipment costs as delivery costs during goods receipt
    Regards,
    AKPT

  • How to add the purchasing overhead costs to the material costs

    Hi,
    I have a requirement to add the purchasing overhead costs like transportation costs to the material costs so that the costs is added to the material costs and update my material price accordingly.
    Can u tell me how to do it for both standard price and MAP price?

    Hi,
    Please attach a accrual key in customization (Pricing procedure) to the overhead condition type you use.

  • Material product cost  and transport cost

    Hi, all
    my scenario,
    Company Z Order 100 carton from Supplier A at $15/carton.
    Company Z will born the transport cost ie per trip $500.
    assumption  one trip = 100 carton ($5 / carton / transport)
    how can i treat the transport cost in SAP as actual cost per carton = $20 / carton. 
    please advice
    many thanks

    Hi
    Product Costing is arriving at the Cost of Producing a particular material. For example
    Raw Material 1 +
    Raw Material 2 +
    Overheads
    Cost of Labour deployed +
    Cost of Other over head like Electricity exp.
    Overhead Cost
    Overhead Cost like/expenses which are incurred in process of maufacturing or rendering services are Overheads. We can term labour & electricity in process of manufacturing as overheads. Overheads are normally flow into CO thru COst Objects (Cost Center, Internal Orders, Profitability segments)
    Thanks
    Colin Thomas

  • Capture Transport cost in material overhead

    Hello
    How can we capture item's transportation cost in material overheads element while working in Average costing enviroment?
    Thanks
    Anshuj Rathi

    Hi,
    There are 3 important parts of the costing sheet - Base, OHrow and CR key.
    The cost element assignment to the material cost whatever you have talked about comes as part of the Base.
    For this base, you have define the OH rows applicable defining the rate of OH rate applicable - KZZ1
    In the credit key you have to give the cost center where the postings will go - KZE1.
    Then in the costing sheet, give these OH rows, CR keys applicable and the base row for which it is applicable.
    Now the OH costs will be calculated correctly.
    Good Luck!!!!
    Thanks and Regards,
    Bhuvaneswari.S

  • How can we capitalize the PR/PO, which are already booked in cost center?

    We are creating a capital Project for our department.  We have the structures ready and finalized with the budgets. But, the department has already done some commitments and expenditures in their cost center .Now, this expenditure and commitment values needs to be reflected in the report, so that correct values of assigned and available should be updated.
    1) Pls. suggest a process using which we can transfer this amount. Is this to be done by an FI entry or else we need to commit using sanction request?
    2) How can we capitalize the PR/PO, which are already booked in cost center?

    Hi,
    As we know the Contract is an Outline agreement for Quantity or Value for a particular Period with vendor.
    Without mentioning Plant also we can make contract for the Purchase organisation level for particular Material for the entire period
    Where as while creating PR  -it is an Indent for the material requiement for the specific Plant so when you refer Agreement inthe PR creation time System will ask you how much quantity to what plant you want to place indent. where as In PO  it ia an legal document so when you refer Agreement it will take all the details from Contract
    i think you are clear with my points
    With regrads
    Shrinivas gangoor
    Edited by: Shrinivas Gangoor on May 22, 2009 2:53 PM
    Edited by: Shrinivas Gangoor on May 22, 2009 2:54 PM

  • Reducing freight cost for undelivered material

    Hi Experts,
    Summary :  The material supplier vendor needs to be paid for full quantity of material. The freight transport is allowed an under tolearance of 0.5% on the material to be supplied. If the delivered material quantity breaches the 0.5% under tolerance then amount at 1.5 times the cost of material for the shortage is to be deducted from the transporter. A dummy GR will have to be prepared for the undelivered quantity for which we do not want the freight cost to be loaded. The details scenario is mentioned below :-
    We have to make a Purchase Order with material code say ABC for procured of some material. Suppose we make a Purchase Order for 100 nos. at a Unit Price of Say Rs. 10/- for Material Code ABC on say Vendor M/s XYZ. A freight condition is maintained in the Conditions Tab and suppose the Freight is Rs. 10 per unit of the material.
    While preparing the Goods Receipt through MIGO, in the Freight Tab we select say freight vendor say M/s PQR against the freight condition and post the goods receipt.
    While doing Invoice Processing in MIRO, when we enter the combination of Purchase Order and Planned Delivery Cost the system will populate the vendor codes of both the supplier of material and the transporter. On selecting the transporter the freight amount will populate against which the invoice of the tranporter can be processed.
    In the Vendor Master of M/s XYZ GR-Based Invoice Verification is activated.
    The vendor is allowed an under tolerance of 0.5% (i.e. the vendor should deliver at least 99.50 nos. of the Purchase Order). If the vendor delivers 99.50 or more then there will be no deduction in the freight charges.
    But suppose the vendor delivers only 99.4 nos. of the quantity. Then we will prepare the GRIR for 99.4 nos.only. But while processing the MIRO we need to deduct 1.5 times the value of the material from the freight amount for the shortshipped quantity, i.e.
    0.1     no (99.5 u2013 99.4) X Rs. 10/- * 1.5 = Rs. 1.5 are to be deducted from the final payment from the freight amount of the transporter.
    The material supplier will have to be paid in full 100 nos. of quantity and will raise an invoice for 100 nos. A dummy GRIR for the 0.6 nos. of undelivered material will have to be prepared for processing the invoice for the 100 nos. of the material supplier and a dummy issue for 0.6 nos. of undelivered material will be prepared to remove them from the system.
    Hence the freight cost for this 0.6 nos. of undelivered material will also go into the cost of the material and increase the MAP by that amount. Also the goods issue Cost will also have the effect of the freight cost.
    We do not want to load the freight cost for the undelivered material in the value of the material.
    Can any one please suggest a solution for the same.
    Thanks in advance.
    AJ.

    answered

  • Invoice transport costs with multiple account assignment

    Hello Gurus,
    My problem is the following:
    1) I create two sales orders with the same forwarding agent "A"
    2) I create the two deliveries with the forwarding agent "A"
    3) I create a transport for those two deliveries and the same forwarding agent A
    4) I create the shipment cost for that transport.
    So now we have the situation:
    2 orders --> 2 deliveries --> 1 transport --> 1 shipment cost
    when i go to transaction MIRO and I enter the delivery note number I get one line item with the total transport cost.
    If I click on the option "Multiple account assignment" I get a breakdown of all the amounts but I can not see which costs refers to which delivery.
    My question is: Is there any way I can link the amount to the delivery number or at least to identify which cost is linked to which delivery number?
    Thanks a lot in advance,
    Miguel

    gr non valuated is done in case ur procuring the material for direct consumption so at the time of gr no posting to accounts occur but at the time of invoice recipet the system debits the g/l account and crdits the vendor account 
    this multiple account ***. is also necessary to mark with gr non valuated and gr check box so that u can change the account assignment at the time of invoice and that acc. assg. should also be changebale in backend .

  • Transportation cost

    Hi Friends
    1.How the Transportation cost posting to the accountings?
    2.we created single shipment document for maltipul deliveries(3) the shipment cost document is 6000/-. can we divided this 6000/- to each sales order or delivery?
    EX: 6000/3: 2000/- like
    If Yes, what is the process.
    3.In sales order we taken KF00 fright condition the condition amount is 1000/-. ok, with this fright condition can we create shipment cost document for this 1000/-?
    If Yes, what is the process.
    and can we create shipment cost document manuvaly?How?

    Hi Sameer,
    You can do so as create service PO for transporter and Main PO for material
    do GR for material and service entry for transportation cost
    At the time of MIRO through Material TAB put material number and  Load
    Trasportation cost to the main material
    Hope this will help
    BR
    Diwakar
    reward if useful

  • Inclusion of planned cost to the material while Invoicing

    Hi Everyone,
    We are facing a problem, kindly guide me to solve it:
    We are purchasing 'X' Material (split valuated) through a Purchase Order in which we did not provide any planned cost.
    But after GR we came to know that planned cost should also have been entered in the PO. But in the PO, while creation we did not select any planned cost line for the item. So after approval of PO and GR, we were not able to enter any planned cost.
    Now while adding up planned cost during Invoicing through MIRO, we are facing an error message:
    Error saving valuation data for material P1S002 0002
    Message no. M8829
    Diagnosis
    Error occurred when the system tried to save the valuation data.
    Please guide me how to do invoicing by including the planned cost and booking the planned cost in the material.
    Thanks and Regards
    Edited by: MP Vashishth on Jan 10, 2011 2:21 PM

    Hi,
    Thanks for your reply please.
    When i am trying to enter this freight value in the Material Tab, i am facing an error message :
    Error saving valuation data for material P1S002 0002
    Message no. M8829
    Diagnosis
    Error occurred when the system tried to save the valuation data.
    Procedure
    Contact your system administrator.
    Please guide.
    Thanks and Regards

  • Service PO Transportation cost.

    Hi All,
        We process the Service PO with two line item Service material cost which will have a tax Code & Transportation Cost which will not have any tax. So for we will create 2 GR for one invoice. We need to make Service material cost & Transportation Cost in 1 GR, What is the Procedure. How to go about it. Help me in resolveing this issue.
    Thanks in advance,
    sapuser

    Hi,
    if I got you right, you want to da one goods receipt for one purchase order with 2 items.
    You could use your service material in first line. In the second you create a material type WERT. In the order you enter 1 ea and in gr you receive it.
    Then you have the two items in one gr.
    Or are there any other issues?
    regards, Paul.

  • Regarding Transportation Cost

    Hi,
    I have a doubt regarding how the transportation cost is included or excluded in the Invntory. e.g
    Material Cost: 10 $
    Transportation Cost: 1 $
    Now if I calculate the cost of the material along with the Transportation cost the inventory value will be 11 $. If I exclude the transportation cost the inventory value will be 10$ only. Please let me know where can I make this setting in SAP. Thanks in advance.

    Hi
    you need to create the transportation cost condition type by copying Freight condition and in your calcuation you can define the logic in such a way that if you want to load on the material  example:
    Pb00 -Material Cost: 10 $
    ZTRA-Transportation Cost: 1 $
    Procedure :ZRM000
    Control data
    counter     Condition type                               Des                           From   To
      10             P000                             Gross Price                     X     9
        20           ZTRA                     Transportation Cost                                  X      9                     
                    ZTOT                                          Total                               10           20
    Edited by: sunny on Dec 21, 2009 1:23 PM

  • Adding fields in costing view of material master

    Hi gurus,
    I need to add 4 fields in costing view of material master. I have followed the steps in SPRO, for configuring customized screen in material master.
    1) Created a function group YMMCO and copied the screen 2904 from program SAPLMGD1.
    2) Added 4 fields in my customized screen.
    3) Created copy of 01 ( Screen reference ) to z1 in OMT3B.
    Since 2904 is not there in the sequence . I changed one 0001 sequence at the end to 2904 . I also assigned my program
    SAPLYMMCO to it. I can see the changed fields in data screen and subscreen.
    4) Then I assigned the SSq to z1 in transaction OMT3E.
    But unfortunately, when I go to MM01 to create a material , I am not able to view the fields I added in costing view.
    I have checked the screen for the previous field, it shows 2904 only.
    Two days back, I did the same thing in basic data view 1 , it was working properly. As per client's suggestion I put it in
    costing view, it is not working . Please give me suitable suggestions.
    Thanks in advance.
    D. Mallick

    Hi,
    I also need to add custom fields to Basic data view. After copying & changing the screen sequence in Config, I could able to see the custom fields in Basic Data view.
    I have appended structure with custom fields to MARA table.
    But the values I enter in the screen is not getting updated to the table MARA.
    Can you please let me know the code, I should have have in PAI (Process After Input) module in the Sub Screen to update the values?
    Thanks,
    Dasa

  • In costing view in material master

    we are running some customized report
    The values are from costing view2
    at the time of running the customized report ,some value is zero for some material
    because at the time of running the report,there is no costing for that material
    after running the costing the values are updated in material master
    once again we run the customized report
    the values are not picking in our report

    Hi,
    Have u marked and released the std prices. check at table level which fields are upated and compare with the fields you use in the customized report.