Budget Availability Control for Maintenance Order

Hi,
Can anybody tell me that how to activate Budget Availability Control for Maintenance Order ? For Internal orders, it is already activated but for Maintenance Order (Category 30, type PM01), it is not activated.
Please tell the procedure for activation for the same.
Thanks in advance,
Regards
Satadal

Thanks.
But I have added Budget profile from Plant Maintenance -> Order type settings.
So, I can assign only maintenance related Investment program  and positions in my Maintenance Order.
But as availability control is not activated, System is not stopping me to issue Goods against that Order even if there is no Budget.
I need to have that control for Maintenance Order that we should be able to issue material against that order only if there is a budget.
That's why I want to activate this control but don't know how to do it.
Can you tell me how I can do the same - depending on order type or individually?
Thanks and Regards
Satadal

Similar Messages

  • Can we create a Budget & Availability Control for revenues with internal orders?

    Dear SAP Gurus,
    I have created an expense budget with the help of an internal order and have assigned the same to an expense GL (cost element). I have done all the necessary system settings and the system gives an error message when the F-02 document posting exceeds the budget.
    My query is, I want to replicate the the above for revenue postings. I have done the same system settings for revenue posting however the system does not give an error when the budget amount is exceeded.
    Can I please get some assistance with this requirement?
    Best Regards,
    Akshay

    Hi Akshay,
    System will not give the error in the case of Revenue GL. Because all the revenue GL will be hit for credit. It means it will update negative against the budget available. It means
    Current Budget-(-Revenue Budget)= Current Budget + Revenue Budget= Available Budget
    Because of this system will never give the error.
    Regards,
    Ankit Agarwal

  • WBS budget functionality for Maintenance Order

    Experts,
    Can we use the Availability control functionality of WBS budget with Plant Maintenance orders? If yes what are the necessary config/settings required to do that?
    Thanks
    Arya
    Edited by: Arya Singh on Sep 17, 2008 11:08 PM

    Hello Arya,
    For budget availability control to get activated against MO thru WBSE, you should create MO as a subnetwork of an activity in PS.
    Please try following
    1) Create a Project, WBSE, Network with one Internal activity. T-code CJ20N.
    2) Assign Budget to the WBSE. T-code CJ30.
    3) Assign Budget profile at Proj Def level. Choose activation type as 1 in profile.
    4) In MO, in additonal data tab, enter the network and activity number. WBSE will be fetched automatically by the system.
    5) For point 4 above do config setting @ T-code OPTP. Enter following in two columns
                               1) Network type Subntwrk = MO order type.
                               2) Ntwktype replaced act = PS network type.
    6) Assign a component or raise service PR  such that it exceeds budget. Sytem will throw an error for budget unavailability.
    7) To check report S_alr_87013558 to know Budget/commitment/Assigned funds/Remaining budget.
    Please post ur observations.
    Thanks
    Saikishore Ganga.

  • Budget Process (Linked the maintenance Order into Internal Order) in EAM

    Dear Experts,
    Scenario for Repair & Maintenance with only MM & FICO module live w.e.f. 2007 (PM not live)
    Process Managed thru Internal Order (Order Type: RPMT)
    Budget managed through Investment Management (IM); Budget is directly entered against the IO using transaction IM52
    Scenario for Repair & Maintenance with only MM, FICO & PM module live (PM went live in 2010)
    It was proposed to assign budget against each Maintenance Order.  Since the number of maintenance orders being used is very high, it was decided to link the MO & IO so that budget will be assigned to the IO and when the MO is settled against the IO, the budget in IO can be deducted accordingly. The proposed process to assign budget in Internal Order against each Maintenance Order are given below-:
    1.)     In EAM process one can plan/procure material and External Services only when the Maintenance Order is created & released but practically it has to be planned long before any Maintenance Activity (Maintenance Order to be linked with the estimate so that PO can be created against the estimate).
    2.)     The no. of Maintenance Order generated in EAM Module is very large as Maintenance order is created for almost each and every maintenance activity. It is cumbersome to allocate the budget to each and every maintenance order. There should be a single estimate for maintenance activity (as in MM module) and that should be linked to maintenance order so that the actual cost of Indent/Service Entry Sheet can be deducted automatically from the estimate (Maintenance Order is to be linked with estimate).
    3.)      While doing return Indent the cost of return material is not being added to the maintenance order automatically (Maintenance Order is to be linked with estimate).
    4.)      If Material & External Services not planned in the maintenance order (estimate), the user must be able to do that through Internal Order (estimate), hence the Internal Order must be link to the Maintenance Order. They should able to record the planned & actual cost in the maintenance Order.
    Process followed:
    1.) Created Internal Order in KO01 for Repair & Maintenance Order Type
         Assigned budget to Internal Order thru IM52
    2.) Created PM order and assigned Internal order against Settlement Order in tab  
         u2018Locationu2019 and in Settlement Rule with 100%. In this Section attach the Internal  
         Order with selection type u2018ORDu2019. 
    3.) Released both orders and issue the Material for particular Operation and then   
         determine the Cost for material .After that performed MIGO for consumption of
         materials.
    4.) Settled the PM order in KO88.
         Settlement process was successfully saved.
    Problem faced:
    After posting the goods movement (against each Maintenance Order) and settlement of the maintenance order against IO, we still find the budget assigned to the IO is not consumed/deducted.
    1. Actual cost of maintenance is not reflected in the internal order
        immediately. We have to run cost settlement (t-code KO88) for the
        maintenance order each time the actual cost is incurred in the maintenance order.
    2. Also in the case of return indent, the value of returned material is not directly 
        added to the available budget of internal order.
    3. When the material is issued from store through the reservation generated by 
        maintenance order, system does not check for budget in the internal  
        order/maintenance order while issuing material from the store.
    4.  It must not be allowed to create reservation from the internal order of order type
         RPMT.
    5.  In case of external service in the maintenance order, the unit of
         measure in the requisition is set to u201CD (days)u201D by default. System does not allow  
         changing the unit of measure in the requisition (it should allow to change the unit
         of measure or set the unit of measure u201CJOBu201D).
    6.) When the material is issued from  the store through reservation generated  in
         maintenance order, system does not check for budget in Internal Order  
         (estimate)/Maintenance Order while issuing material from store.
    Thanks & Regards
    Deepak Soni

    Hi,
    1. Actual cost of maintenance is not reflected in the internal order
    immediately. We have to run cost settlement (t-code KO88) for the
    maintenance order each time the actual cost is incurred in the maintenance order.
    As per the standard system budgeting is done against the actual cost only. And until you settle your order the actual cost from
    maint order are not getting transfered to IO. Once they are transfered system is checking for the budget.
    2. Also in the case of return indent, the value of returned material is not directly added to the available budget of internal order.
    This is similar to first point, when you return goods there will be negative cost on the order, this has to be settled until that system will not compare the IO budget with maintenance order actual cost.
    3. When the material is issued from store through the reservation generated by maintenance order, system does not check for budget in the internal order/maintenance order while issuing material from the store.
    The budget you have assigned is at IO, how can system will check the budget while issueing goods for maintenance order. We may have to develop or use some user exit over here. Which will trigger checking of budget from the settlement receiver IO for that maintenance order.
    I think you may have to go for development. These are my observations from my experience.
    Regards,
    NNR

  • Budgeting & Availability Control

    Hi Gurus
    We had activated Internal Order Budgeting & Availability Control check & had used it to procure Fixed Assets. The internal order is created (t-code KO01) & budget value is assigned (t-code KO22). The internal order is assigned to an asset (t-code AS01). This asset is used for procurement in MM module - purchase order (t-code ME21N), goods receipt (t-code MIGO) & subsequently invoice verification (t-code MIRO).
    We have a unique situation. Some of our colleagues have created the order, assigned the order to the asset & completed the procurement cycle without assigning the budget. Now we would like to assign the budget to the internal orders we had missed & would like to check the availabilty control for all the transactions we had carried out. Is there a way to meet our requirement. What are the alternatives available to us?
    Thanks,

    Hi,
    I suggest you collecting the data on these orders (KOB1/KOB2), sum up the amounts and check what budget these orders required. There is no retroactive availability check possible. You can switch it on, but it will be active only for future postings.
    Regards,
    Eli

  • Automatic Creation of Settlement Rule for Maintenance Order

    Hi,
    While doing TECO for Maintenance Order, its asking for Settlement Rule. IF I click settlement rule, message is coming as Maintain Settlement Profile with options like With Default, Without Default & Cancel.
    I have maintained the Cost center in Equipment Master. Also I maintained Cost Center as Default Settlement receiver.
    Also I have gone through setting in Automatic Creation of Settlement Rule under Controlling Category.
    But I couldnt understand that. Can you please tell what are the steps to be done?
    Regards,
    Maheswaran.

    Hi,
    Please check the indicatorsin Actual cost/cost sales  and Valid recevivers in settlement profile.
    If for cost center : 1 settlement optional is maintained in valid recevivers and also for order
    and in actual cost/ cost sales: indicator to be settled in full is selected.
    Also check Allocation structure too if you have assigned the valid allocation structure.
    **check if you have assigned the valid settlement profile to order types.
    *****Most important after doing all these settings you need to create new order. for same order you will not get the automatic settlement rule
    Hope this helps.
    Regards,
    PMAddi

  • Warning Messages related to Reconstruct Availability Control for Project

    Hi Gurus,
    In Transaction IM52 - Change Original Budget for Investment Management Program, after changing the Budget Values of Investment Management Position and when we check the transaction for error, we get Warning Messages, the warning message is as follows:
    You Must reconstruct the availability control for Project P.000XXX.
    We tried to reconstruct the Availability Control in Transaction CJBN and again checked for errors in IM52, then also we get Warning Messages.
    As these are only Warning Messages we can ignore and save the modified budget values for the Investment Management Program.  But we want to know whey these Warning Messages are keep on cropping up inspite of reconstructing the Availability Control for Project.
    You inputs on this will help us immensly.
    Thanks,
    KRN

    hi KRN!
    I am also facing the same issue.
    Even if i am having enough budget, while making a PO, the system says " Budget exceeded".
    i could processs the PO, after performing CJBW (deactivate), CJEN (refresh) and then performing CJBV ( activate availabilty control) for that project.
    This is repeating everytime i make a PO. is there any permanent solution?
    Even after performing all the above, if i check in IM52, and check for budgets (perform from menu), the error is " You Must reconstruct the availability control for Project P.000XXX"

  • Can Budget Availability Control be turned off at WBS elements Level?

    For Project and WBS elements, we activate the budget  availability control in the budget profile and assign the budget profile to the Project. So once we budget one WBS elements under that project and release the project, the availability control is active for all WBS elemens under this project.
    My question is whether we can turn off the availability control for one WBS element under that Project and let the availability control on for the other WBS elements under that project.
    thanks,
    Ting

    Hi,
    I doubt if this can happen. CJBW will deactivate avalability control for entire project. Try OPSX for that particular WBS, it will reset budgeted status. Not sure if this will help, try and confirm.
    One more way could be assigning userstatus to the WBS and restricting 'Availablity control' by that status. This option looks more practical.
    Regards
    Edited by: Shrikant Rakate on Sep 10, 2008 9:21 AM

  • Multiple PR doc type for Maintenance order - Non stock item category

    For non-stock item requirement in PM, we create a maintenance order and indicate item category as "N" in components tab. Accordingly a purchase requisition is created as per configuration. We have assigned PR doc. Type “FO – Framework requisition” for Maintenance Order Category.
    SPRO - PLANT MAINTENANCE & CS - Maintenance and Service Processing - Maintenance and Service Orders - General Data - Define Account Assignment Cat. and Document Type for Purchase Requisitions
    Now according to the new requirement, we need to have different PR Doc type as per CONTROL KEY mentioned in the Maintenance Order.
    Example:
    If the Control Key is “PM01 - Plant maintenance – internal” the purchase requisition document type should be “NB – Purchase Requisition”. If the Control Key is “PM03 - Plant maintenance-External(services)” the purchase requisition document type should be “FO – Framework Requisition”.
    Please advise how to configure the same.
    Regards
    Sathish Kumar Balakrishnan

    Hi Partha,
    This is a simple enhancement. In our scenario, we had configured PR document type "FO" in SPRO settings for "Document Type for Purchase Requisitions".
    Hence to have "NB" PR document type whenever material components are being indented through maintenance order, we used this enhancement COZF0002
    Please instruct your abaper to add similar logic, as shown below.
    Enhancement:COZF0002
    Functional module:EXIT_SAPLCOZF_002
    Include: ZXCOZU02
    Logic:
    IF sy-tcode eq 'IW21' or sy-tcode eq 'IW22' OR sy-tcode eq 'IW28'  OR sy-tcode eq 'IW31' or sy-tcode eq 'IW32'  OR sy-tcode eq 'IW38' .
      IF resbd_imp-postp = 'N'.
        eban_ord_cust_chg-bsart = 'NB'.
      ENDIF.
    endif.
    Hope this helps.
    Regards
    Sathish K B

  • BPC - Budget Availability Control

    Dear Experts,
    I am interested in knowing whether Budget Availability Check functionality is available in BPC. If not, then does it mean that when both SAP ECC and BO-BPC co-exist, the Budget Availability Control configurations are required to be maintained in SAP ECC through modules such as Funds Management, Internal Order or Project System.
    Thanks,
    Sudhakar Shetty

    hELLO,
    Can anyone provide a specific answer on the possibility of having Budget Availability Check in BO-BPC. I understand that data has to be transferred from an operational system like SAP ECC to BPC. And, so a real-time Budget Availability Check may not be possible in BPC. But, wanted to know whether there is a solution to this.
    Thanks and Regards,
    Sudhakar Shetty

  • Query related to Service Entry Sheet for maintenance order

    Dear Gurus,
    I am little bit confusing while entering SES for maintenance order,
    Do we need to enter both Maintenance Order# & Cost Center# in Account assignment tab of SES?
    What is impact of entering both in SES?
    What is standard procedure of accepting services for maint order?
    Thanks in advance.
    Regards,
    Amol.

    Hi Amol
    Why you created Framework Order ?.. You can not change account assignment category in service entry sheet..e.g. K-Cost Center.. F- Order
    But depending upon settings, you can change account assignment values such order 1 to order 2
    If there are requirement that SES can created for  Account assignment F or K. I recommend you to use following approach
    1. Create a Contract - ME31K with AAC as U- Unknown (If business already have rates negoiated with vendor for services)
    2. Create release order with reference to contract and system will prompt you to enter AAC- it can be K or F
    3. Perform SES w.r.t to Release Order.
    Other Approach can but not strong one.. create two line items in the PO. one with K and Other with F.. then choose the line item at time of SES creation that business want to book the cost on CC or Order.
    Thanks,
    Jagdeep

  • Manual Reservation for Maintenance Order

    Hi,
    Can anyone suggest some procedure so that I can stop automatic reservation creation from Maintenance Order (Transaction:IW31, type PM01, Category 30) and create manual reservation for the same.
    Presently Manual reservation is not allowed for Maintenance Order.
    Thanks
    Satadal

    To the best of my knowledge this is possible. To the best of my knowledge G/L account determination for every material happens after a series of checks are done internally by SAP. By checks I mean the sequence of steps as customized by the consultant in the configuration. Now at the end of the sequence if SAP has not succeeded in identifying a G/L account it will open up a tab in which u can manually enter the G/L account. For non-stock item you can anyway enter it.
    I would suggest that you post this query in the MM forum also.
    thanks
    Bala

  • Manual Reservation for Maintenance Order (Category 30)

    Hi,
    Can anyone suggest some procedure so that I can stop automatic reservation creation from Maintenance Order (type PM01, Category 30) and create manual reservation for the same.
    Presently Manual reservation is not allowed for Maintenance Order.
    Thanks
    Satadal

    Hello Satadal
    nobody's answered you because it's not possible to create a manual reserve for logistic orders as Network/PP orders or PM orders.
    If you want inhibit the automatic reserve creation :
    - customizing (transaction OIOE) : set "Never" in field "Reservation Relevance/Generation of Purchase Requisition". The reserves will be created but they will be not relevant for MRP.
    - Hide the field AUDISP "Reservation Relevance/Generation of Purchase Requisition"  at component level (OICMPD) and operation level (OIOPD)
    Good luck
    silvia

  • Query about Manual Reservation for Maintenance Order Category 30

    Hi,
    I have a problem. Generally from Maintenance Order type PM01 under Order Category 30, when we give some materials requirement, SAP automatically generate reservation for those materials and take the GL as Consumable Item.
    But in my case, that GL has to be changed depending on what perpose we are using the material. But Manual reservation is not allowed for the order category 30 and no GL can be changed for automatic reservation.
    Can anybody suggest any way-out so that we can give our desired GL No. for the reservation for Maintenance order (say Order type PM01 under category 30 which is SAP internal).
    Thanks in advance,
    Satadal

    To the best of my knowledge this is possible. To the best of my knowledge G/L account determination for every material happens after a series of checks are done internally by SAP. By checks I mean the sequence of steps as customized by the consultant in the configuration. Now at the end of the sequence if SAP has not succeeded in identifying a G/L account it will open up a tab in which u can manually enter the G/L account. For non-stock item you can anyway enter it.
    I would suggest that you post this query in the MM forum also.
    thanks
    Bala

  • How to calculate work in process for maintenance order

    how to calculate work in process for maintenance order i.e raw materials not used

    Hi,
    Generally, when u create PR from maintenance order, account assignment category should be F. Cost of services first settles on the order when u create service entry sheet. Further it got settled onto settlement receiver given in order.
    If you want to change the category from F to K for maintenance orders then follow the IMG menu path as given below.
    Plant Maintenance and Customer Service > Maintenance and Service Processing > Maintenance and Service Orders  >
    General Data > Define Account Assignment Cat. and Document Type for Purchase Requisitions