Budget exceeded message not raised after changing PO

Hi,
We are having a budget problem while changing a PO after having done the Goods Receipt. The Budget exceeded message (BP604) is raised only at the time of creation of the PO and before the Goods Receipt is done and accounted. The quantity and the price are controled.
But after the circuit that was fulfilled (the Goods Receipt is done and accounted and the committed budget becomes
real) we change the quantity or the price of the PO in order to exceed the budget and there is no control now. The available fund amount becames negative (negative value).
Regards,
Martin.

the behaviour is as expected
you ned to check your budget tolerances and if that includes Preq and PO then the moment the PO is created the commited is checked against budget.
When GR is done the commitment reduces and actual cost increase hence no effect on budget
if you change the PO then you need to establish rules around this - should earlier GR be undone etc
also try running CJBN to reconstruct the budget

Similar Messages

  • "Budget Exceeded" error not appearing at the time of changing PR but appearing at the time of PO change.

    Dear All,
    At the time of PR value change after creation of PO budget exceeded error is not appearing even though the PR value exceeds the budget. But at the time of changing the same value in PO, budget exceeded error is appearing.
    List of steps:
    PR created.
    PR released
    PO created with reference to PR and released.
    PR value changed to a value more than the available budget - No budget exceeded error.
    PO value changed in accordance with the PR - System throwing the budget exceeded error.
    Now the issue is why the system bypassed the budget exceeded error at the time of PR value change and only giving the error at the time of PO value change. Also, we observed that while changing the quantity in PR which results in exceeding budget, system is giving the error. But while changing the value system is not giving the budget exceeded error.
    Your inputs will be highly appreciated. Thanks in advance.

    Hello Saurabh,
    Thank you for your inputs. Below is the output of CJI5.
    Ref,Doc Category  Debit Date     Oty       Object    Cost Elem.   Val/CO Area Crcy   Total Qty.     UM
    PREQ                  28.05.2014    WBS     XXXXXX    XXXXXX           0.00                         0            EA
    POrd                    28.05.2014    WBS                                       14,000.00                1000          EA
    From the above output i think system is not capturing the PR commitment. I'm not sure as i'm basically into MM and  dont know much about PS.
    Why the system is stopping with budget exceeded error at the time of PR creation and not giving any error while changing the PR value after PO creation. System is giving budget exceeded error if quantity is changed in PR. Please explain the standard system behavior and suggest how to enable control at the time of PR value change.
    Thanks in advance.

  • Text Messaging stopped working after changing Apple password, although it is still working on my iPhone.a

    Text Messaging stopped working after changing Apple password, although it is still working on my iPhone.  I tried changing the password in the Settings>Messenger, but can't get it to work.  What do I do?

    After I type in the message and click on the Send button, "Sending" is displayed, but at the end of this process, a message under the message says "Not Delivered".

  • E7 Nokia Messaging not working after anna update

    hi
    nokia messaging not working after anna update. when i
    -choose provider (hotmail/gmail/yahoo...etc)
    -enter username & password
    -click OK to T&C
    -get error message: "cannot enable this service on the device"
    any ideas?

    I'm having a similar issue. It appears to only impact Hotmail accounts. For me though, this happened without updating the OS. The email client is simply failing to connect to the Hotmail interface. Only two possibilities, either Microsoft changed something on the email gateway or Nokia changed something on their end. Either way, it's not working and has been out of commission for the past week. If this is how corporate friends get along, I'd hate to see what happens in a adversarial relationship.

  • Error msg: "Config message not received after 45 seconds"

    I have developed a simple stateless session bean. After being called once, the following is output to the log:
    Thu Jan 04 18:15:46 CST 2001:<I> <RJVM> Signaling peer 3978882810638278829C198.171.129.36 gone: weblogic.rjvm.PeerGoneException:
    - with nested exception:
    [java.net.SocketException: Connection reset by peer]
    Exactly 45 seconds later the following is output and I can no longer access a JDBC connection from my pool:
    Thu Jan 04 18:16:31 CST 2001:<I> <CliCon-#|myserver|0.978653734170> Connection to client for ClientContext - id: '#|myserver|0.978653734170', bound: 'true', dead: 'false' has been unexpectedly lost be
    cause weblogic.rjvm.PeerGoneException: Config message not received after 45 seconds.
    Initiating hard disconnect.
    Can anyone shed some light on this for me?
    Thanks in advance!

    Hi,
    this is the explanation why this occours:
    If there is a t3 Client connects to the server, every ( weblogic.system.configTimeoutCheckVal
    ) time, ConfigTimeoutChecker will run to check the t3 client is disconnected or
    not. The problem is, if the client has already disconnected, the ConfigTimeoutChecker
    still runs every time to check the disconnected t3Client again and again.
    This should be solved with SP11.
    Christian Plenagl
    Developer Relations Engineer
    BEA Support
    "kelvin" <[email protected]> wrote:
    >
    I am using WLS 5.1 sp8 128SSL, I got this error. I results that the java
    object
    in the JMS channel is sometimes missing. I increased the weblogic server
    thread
    from 15 to 30. But still can't help. I also ugrade the client server
    to use the
    same sp8. But can't help. Some one mentions the sp9 can solve this problem.
    It
    is true? anyone have it for unix ? where can I download it? I can't
    find it in
    weblogic web site.
    Kelvin

  • B210a will not print after changing router\modem

    b210a will not print after changing router\modem. Says it is connected to network, but will not print and says unavailable

    Good morning,
    Please use the second section of the following article to fix:
        http://www8.hp.com/au/en/campaigns/wireless-printing-center/reconfiguring-system-help3.html?jumpid=r...
    Regards.
    BH
    **Click the KUDOS thumb up on the left to say 'Thanks'**
    Make it easier for other people to find solutions by marking a Reply 'Accept as Solution' if it solves your problem.

  • Sql is not working after changing from MsAccess into sql server

    Following Sql  is not working after changing from MsAccess into sql server. 
    sum(trn.sales) as sales,
    sum(trn.cost) as cost,
    sales - cost as profit // Here is not working . can we not use sales a column. Please advise
    from trn
    Kind Regards
    pol
    polachan

    It will not work if use two different column from the table or column  from two  different table
    Example
    sum(trn.sales * trn.rate) as salesAmount,
    sum(trn.cost) as cost,
    sum(trn.salesAmount)-sum(trn.cost) as profit ----- Here is not working . can we not use sales a column. Please advise
    from trn
    Regards
    polachan

  • Budget Exceeded : Message No BP603

    Hi Experts,
    I am having problem with budget exceeded error.
    Scenario - When trying to invoice the P.O it prompt budget exceeded error but budget was available when checked the S_ALR_ report.
    As it was very urgent, Budget was supplemented to pass the Invoice for P.O and after it is invoiced I could still see the budget available more than already available budget.
    Example.
    Invoice for Commitment PO - 200000
    Budget Available - 50000
    Supplemented Budget by 20K to pass on the Invoice as it thrown error while invoicing, Hence New Budget available after supplement is - 70000
    After the invoice of PO - 200000
    Budget report showed the same available amount as 70000 ( No Change in the original value of budget even after supplement of 20K)
    so now I tried to reduce the budget back to 20k and roll back the budget back to 50K but system throws me the error as attached here.
    I have tried to analyze the report such as CJI3, CJI5, CJ31 also executed RKANBU01, CJBN, CJEN.
    This is done on lower level WBS and I have checked all P.Os and tax charged towards it to see if the available budget has been consumed with the tax amount or not.
    Real values on the scenario are given below. I am not able to get the point on where the 4641.43 USD is budget exceeding
    USD
    930451
    commitment
    345550
    actual
    1276001
    total Budget Consumed
    1289263
    Current budget
    13263
    available
    Appreciate experts help and comments.

    Hi Amit,
    We don't have release functionality maintained for budgeting.
    This is for child level wbs and sufficient budget is available.
    As requested I have attached the screen shot.
    Standard Report shows the budget in USD
    And CJ31 also displays the budget in USD
    I have also attached screen shot of budget in AUD, Where in on the available budget amount I am trying to reduce it by 20K in CJ38 which pops the budget exceeded error message.
    Thanks

  • Message Server Unreachable (after changing IP address at host)

    Hi guys,
    I changed the IP address in my server. According to note 403708, I updated the new IP address in /etc/hosts. The note also suggests me to change in /etc/services but I see no IP address for me to update.
    Later when I restart my sapinstance, I see the disp+work.exe is "Running, but Message Server Unreachable". I've also updated the IP address in SM59 but I see no change.
    This is what I got from dev_rfc.trc:
    ERROR file opened at 20071206 221839, SAP-REL 620,0,674 RFC-VER 3 549374 MT-SL
    T:5048 Error RFCIO_ERROR_MESSAGE in abrfcio.c : 1400
    T:5048 <* RfcDispatch [1] : returns 1:RFC_FAILURE
    This is what I got from dev_disp:
    WARNING => DpNetCheck: NiAddrToHost(1.0.0.0) took 5 seconds
    ***LOG GZZ=> 1 possible network problems detected - check tracefile and adjust the DNS settings [dpxxtool2.c  3212]
    Anyone has any idea?

    Yes I'm on Windows, the path that i'm refering is:
    winnt/system32/drivers/etc/services
    winnt/system32/drivers/etc/hosts
    Anyway my prob is fixed now. Probably the problem is due to I did not restart the server after changing the IP. Anyway everything looks pretty fine now
    Thanks guys

  • Payment Budget Exceeded Message Number BP 628 & 629

    Hi all,
    We encountered "payment budget for year 2008 exceeded" problem when releasing the Service Entry Sheet in ML81. The message number is BP 629.
    The standard SAP FM report shows that there are sufficient available budget for that funds centre and commitment item. We have also checked and verified that the necessary funds centre, commitment item have been duly created and assigned to the corresponding cost centre and G/L account.
    Would greatly appreciate if you experts can help us with the solution. Many thanks.
    Regards,
    Nathan Janardhana

    Hi,
    Pls check the below SAP notes:
    Note 879348 - Payment budget exceeded when creating a new line item.
    Thanks
    Aravind
    Assign points if helpful

  • Master-detail: detail field not displayed after changed by master field

    I want to use the Depends on item with Clear/refresh value functionality in a master detail situation. Within the same group it is no problem to use the setter method of a field to change a second field and then displaying this new value. But in the detail group, I can not select items from the master group as a depends on item.
    In the setter of the master field, the value in a field for each row in the detail (table layout) is updated. The only problem is that this updated value is not displayed, the old value doesn't change. When saving the changes, the displayed value is committed to the database. When de updated field is not displayed at all, the correct value is saved, so I know the detail field is updated.
    How can I make sure the displayed value in the detail is displayed after changeing a master field? I already gave the detail field the correct partial trigger.

    Wouter,
    I guese you don;t see the changed value when you display the detail item because after the depends on item update changed the detail item, JSF procesing continues and the detail table changes are sent to the server which will override again the detail item attriibute, resetting it to the old, still displayed value.
    So, the trick is to get PPR working. Make sure the partialTYriggers property of the detail item is set to the value of the id property of the master item. If it still doesn't work, try setting the partial triggers property on the table, instead of the individual item.
    Steven Davelaar,
    JHeadstart team

  • Why does my iPod Gen6 not sync after changes made in iTunes on PC?

    I make changes in my music in my iTunes program on my PC (check/uncheck certain music/songs) and these changes are not reflected after I sync my iPod Gen6; all music is the same as it was before on the iPod.

    How is your iPod configured to sync with your iTunes library?  Automatically or manually?  In other words, what options do you have enabled from under the iPod's Music and Summary tabs?
    Syncing music to iPod or iPhone
    B-rock

  • BPM Multiple message not stopped after exception

    Hello All,
    I have scenario:
    DB -> XI -> SAP (IDOC)
    In one message from DB I am sending multiple rows which I am transforming to multiple IDOCs. Everything works fine until one of rows have an error in data. When error occur BPM process stops and is not sending rest of the rows. I would like this scenario to not break after error row and send all messages except error ones.
    I tried to use exception, but it does not work the way I want - it does not sent rest of messages.
    Thank You in advance for your help.
    best regards
    Dawid

    Hi Dawid,
    1. what kind of error do you mean ? mapping error ?
    if it's a mapping error maybe you can catch it inside your mapping
    so that it will not result in an exception and you can just
    remove the incorrect IDOC from the R3 (bd87) and the rest would be
    processed correctly?
    2. <b>why do use use a BPM to map DB to multiple IDOCs?</b>
    Regards,
    michal
    <a href="/people/michal.krawczyk2/blog/2005/06/28/xipi-faq-frequently-asked-questions"><b>XI / PI FAQ - Frequently Asked Questions</b></a>

  • Prompt constrain - prompt values are not refreshed after change in calendar

    Hello,
    I have prompt with Date, OrgUnit and Employee field in OBIEE 10g.
    Date - calendar component "date between"
    OrgUnit - multi-choice
    Employee - multi-choice
    I have checked "Constrain" checkbox on Employee field, because I want to show only employees from selected OrgUnit and also I have checked constrain on Date field.
    After first selection everything works fine. I select some dates (I have calendar component - date between), some OrgUnit and I can see list of employees constrained by selected OrgUnit and Dates
    - physical select is executed to get list of employees to multi-choice component
    After that I change date interval, open employees multi-choice component but no physical query is executed and I will get back some cached result from previous request.
    It seems that change in calendar component does not force refresh of data in other constrained components.
    If I select some other OrgUnit, Employees are refreshed.
    I tried to change component for Date from calendar to multi-choice. After some change of dates in multi-choice component. OrgUnit and also Employees are refreshed.
    I also tried some different combinations of constrain checkboxes but with no success
    So my question is: How can I force refresh (force execution of sql query) data in constrained fields after some change in calendar component?
    Thank you

    In my case It doesn´t refresh after change in calendar component. It does refresh after change in multi-select promot, or dropdown component, but doesn't refresh after change in calednar component.
    BI server cache is not enabled.
    If I open employee multi-choice component for the first time, physical query is executed. I change date to some other, open employee component for second time and no query is executed and I will get old values from previous action...

  • Apple wireless mouse does not reconnect after changing batteries

    The wireless mouse on my iMac quit working after I changed batteries. There was no response to mouse clicks, or movement, or scrolling. Eventually I connected a USB mouse, did an orderly shutdown of the system, rebooted, and the mouse started working again.
    The long story ...
    The first time I encountered this problem was the first time I changed batteries in the Apple Wireless Mouse that came with the iMac 3.06 GHz Intel Core 2 Duo I purchased in January 2010. (The OS is 10.6.2 without updates.) I switched the mouse on, the green light on the bottom of the mouse blinked for awhile (at least a minute), but clicking or moving the mouse got no response. The new batteries were Eneloop 1.2v rechargeables. I tried clicking and moving the mouse several times over a period of ten or fifteen minutes, nothing.
    I started searching the web for clues about what to do and maybe a half hour or so later I tried the mouse again and it worked.
    A few days later I wanted to see if the problem was reproducible. I don’t remember now whether I removed the batteries and reinserted them or just power cycled the mouse, but again the mouse quit working. The green light would blink for awhile, about a minute, then would go off completely. I took this to mean the mouse was searching for the Bluetooth network, not finding it, and giving up. Over the period of half an hour or more I tried switching the mouse off and back on several times. The green light would blink, but nothing more.
    I started searching for tips about reconnecting an Apple wireless mouse after changing batteries. I ran across a (2005) discussion on MacRumors forums titled “Wireless mouse troubleshooting problem...” The symptom was a little different, the mouse was partially functional. In this discussion some contributors thought weak batteries could be to blame. So I replaced the rechargeable batteries with new alkaline batteries. Still no go.
    I attached a USB mouse and looked at the Bluetooth preferences pane. I was surprised to see the Apple Wireless Mouse was listed there with status paired and connected. Still at this point switching the mouse off and on would produce blinking light on the mouse, but no functionality.
    I tried various things in the Bluetooth preferences to see if I could get the mouse connection to restart. When I tried to delete the mouse connection there was an alert saying this was the only mouse connected, was I sure I wanted to disconnect. I said yes, but nothing changed in the Bluetooth preferences pane. I tried unchecking the Bluetooth “On” box, etc. Eventually I only succeeded in losing response to the keyboard as well.
    I attached a USB keyboard, shutdown the system, and rebooted. I didn’t know if having the USB keyboard and mouse plugged in would interfere with the wireless devices, but it did not. After the reboot both the wireless keyboard and the mouse were functional again.
    Since then I have tried removing the batteries briefly a couple of more times to see if the problem would recur. I actually put the rechargeable batteries back in. Both times the connection was remade as soon as I clicked the mouse. I also now have seen the Apple support article about setting favorite Bluetooth devices http://support.apple.com/kb/TA21371 . I'll try that if this issue comes up again.

    Hi, is this a question" Post?
    or are you just offering an insight into your Mouse Issue?
    Generally and at times we all have little idiosyncrasies appearing with the running of our Macs.
    I use the same Logitech BT with my MBP. MB & iBook..(not at the same time) Only ever had one issue
    and the cure was to completely Delete the mouse from BT -> Repair Permissions & Reboot then Re Install the BT mouse..Ihave just put a new set of batteries in the Logitech (only 2nd set ever)...L

Maybe you are looking for

  • Problem with installing Lightroom 2 onto Macbook Pro running OS10.6.8 - any ideas why it will not install??

    To be able to work on my older laptop on location I wanted to install Lightroom 2 onto a MacBook Pro which runs 10.6.8 It stops at the end of the installment and tells me to contact Adobe for info.... that's nit very easy anyway. Has someone a quick

  • Error on import statement.

    I got compiler error for an import statement which is: import MyClass; It said: '.' expected at the end of the statement. However, MyClass isn't any package. Also, I can compiler the same code with the import statement as above on other machine with

  • Can't remove music from Flash file

    I decided not to use a music (wav) file and want to delete it from my file. I deleted it from the library and also the layer it was on. I publish the file and the sound still plays! I have no idea how to get rid of it!

  • FI document park & Post Workflow WS10000051 Error.

    Hi Guru's, I am facing a issue with workflow WS10000051, when Approver REJECT the FI document from work item, then FI Document goes in change mode. Because of this the WF_INTIATOR is assigned with Approver name. So instead of workflow should go to or

  • Different currency  CN41 report

    Does Anybody knows how to change the CN41 report currency? This report usually shows the project costs in controlling area currency. The customer wants to see both, the controlling area currency and another chosen currency. Thanks James