Budget related activity control tolerance limits

Hi,
I am getting some issue with budeget related Activity Control tolerance limits.
I have made a setting like for warning - 100% and for error - 110%.
While processing for PO, at 100 % system works properly as it shows the warning.
But when I am entering the value exceeding 100% i.e. 101%, then system gives an error for that.
It is supposed to give the error at 110% as per the settings done.
Kindly help on this.

Hi,
Did you give, only 'warning' or 'warning and mail to person responsible'. If you have given 'warning and mail to person responsible', make sure you give the person responsible for the relevant WBS Element.
Regards,
Sagar

Similar Messages

  • No tolerance limits maintained in controlling area 5555, profile 000001

    Hi,
    While Doing internal order budget i am getting the below error.Kindly help me in fixing that error.
    No tolerance limits maintained in controlling area 5555, profile 000001
    Thanks
    Kishore

    Hi Kishore FICO,
    Menu path to maintain tolerance limit for internal order:
    SPRO > Controlling > Internal Orders > Budgeting and Availability Control > Define Tolerance Limit for Availability Control...
    regards,
    ng chong chuan

  • Tolerance Limits at all wbs levels

    Hi
    In our client process we need Tolerance limits at all  wbs elements for controlling budget process for ex in our process 5 to 10 wbs.
    wbs XXXX01 tolerance limit =100%
    wbs XXXX02 tolerance limit =102%
    wbs XXXX03 tolerance limit =103%
    Please advise to solve this issue
    Regards
    Sen

    hi
    Thanks for replay
    here client will create po at each level of wbs element.and now for one wbs element they are willing to allow more value  of limit form their budget.
    Regards
    Sen

  • Non Budget related GL accounts

    Hye Experts
    I have some Gl accounts which are not relevant for budget. I dont want this GL accounts to be checked for budget. What shall I do.
    Shall i create a committment item with not relevant for budget or any statistical committment can be created which will not check the budget controll.
    Thanks and Regards
    Suresh

    If the non budget related accounts you can create a derivation strategy to derive a tolerance profile that that has a usage rate of 999% .For example our accounts that end with a "1" derives a different tolerance profile that the accounts which we budget very strictly (100% usage rate).
    http://help.sap.com/saphelp_47x200/helpdata/en/3a/19f53be2145d48e10000000a11402f/frameset.htm

  • Tolerance limits on PO

    Dear All,
    I need to place tolerance limits on PO quantity. e.g 5 percent of the PO quantity is allowed to GRN.
    how can i do that,
    Thanks

    Hi
    The SPRO setting under Inventory Management > Good Receipt > Set tolerance key
    this is at company code level. if you set this, then each and every MIGO will pass through the limit
    this may have an impact on inventory inflation if MIGO is on higher side, especiallyfor A class items.
    Better to set tolerence key at various level mentioned by one of Gurus so that only the particular combination will pass through the tolerance Limit. and on the other hand you will controlled inventory.
    in spite of this client insist at Company code level then proceed with SPRO setting
    Also check the message setting if you want to give Error message if it is exceeding the tolerence Limit.

  • Tolerance limits for contract

    Hi all,
       Is there any possibility to maintain tolerance limits for Quantity in Quantity Contract (doc type MK),,,
      ex: Quantity Contract (MK) -- target quantity = 100
          it should allow me to create release orders (Purchase orders) for 105 quantity(tolerance of +5%)
    regards
    urendra

    Hi,
    By using Purchasing Value Key in Material Master you can control over and under deliveries.But its applicable to that material.
    If Purchasing Info Record exists for that material then tolerance limit which is given in inforecord takes priority.
    Regards,
    Ramesh
    Message was edited by:
            Ramesh

  • Tolerance limits in Purchase Requisition and Purchase Order

    Hi there
    I see there is some new functionality in ERP6 to control the price difference between the requisition and the order.  According to the documentation one needs to set up a tolerance key and then set the tolerance limits for price price variance.  Thereafter one needs to set the tolerance key on the document type.  I have looked in the document type and I can't seem to find any place in the config to set up or assign the tolerance key to it.  Has anyone tried this and how would I assign the tolerance key to the document type?
    Thanks
    Vinesh

    Aroop thanks for your reply.
    My scenario is not the same as in 3rd party processing. In fact my scenario is make to order and even repairs of other companies machinery. Now what we are trying to achieve is lets say in the repair or in production of the customers machinery or service, MM needs to make a purchase for a part or tool etc. That in itself has a price. Meaning our purchase mm dept has to pay the vendor for the purchase made and in return we need to charge our customer for that purchase. So we would like for the price of the purchase order come in our sales order condition type as a surcharge.
    We were able to fetch the price of the production order automatically thru condition type EK02.
    We would like to do the same from purchase order.

  • Purchase Order History Tolerance Limits

    Good Morning,
    I am hoping someone can clarify this for me.  Within MM_EKKO archiving object a reason why you can not archive is "The last purchase order history transaction for an item is outside the tolerance limit".  When SAP says Tolerance Limits for this item what are they referring to?  Is it Residence Time or is it the C MM-PUR Reorg. Sched. Agrmnt Extra configuration?
    Our current settings are as follows:
    Residence Time = 2500 days
    C MM-PUR Reorg. Sched. Agrmnt Extra = Validty Period is expired for more than  day.  No other settings are active.
    Thanks in advance.

    GR for movement type '101'. IR via tcode MIRO.IR happens first before GR only in case where friegth charges are paid to a third party.

  • Set Tolerance Limits for Price Variance when PO-based Purch.Requisition

    We must garanty that Price from Purch.Requisition will be the same at PO.
    IF some variance occur a error messag must be sent to user and PO could not be saved.
    I found at customzing under SPRO > Materials Management > Purchasing > Purch.requisition > Set Tolerance Limits for Price Variance .
    Reading the help of customizing it mean the system consists what we need..
    I have created tolerance limit NB, and set limits for all checks as 0,01.
    When I will activate messages as recommended on help no messages 601 and 602 have the text that guide us to correctly setting.
    The help mention that after create tolerance limit we must set this tolerance by document type..but I didn’t find this field at customzing
    Does anyone can help me ?
    See the help on customizing below…
    Set Tolerance Limits for Price Variance
    In this step, you can define percentage-based and value-based (absolute) tolerance limits for price variances between purchase orders and purchase requisitions. Variance types are mapped out in the SAP system by tolerance keys.
    You define the tolerance limits for each tolerance key and assign your tolerance key to the document types for purchase requisitions. The tolerance limit then applies for all documents of this document type.
    When processing a purchase order, the system checks whether the unit price of a purchase order item differs from the unit price of a purchase requisition item. If you have configured, activated and defined tolerance limits in document types, variances are permitted in the tolerance limits. If the variance exceeds the tolerance limit, the system issues a warning. If you have defined a percentage-based and a value-based absolute tolerance limit, the strictest of the two variances will apply for this check.
    Note
    You can determine whether the system messages (601 and 602) appear as warnings or error messages in step "Define Attributes of System Messages".
    To do this, go to the Materials Management IMG and choose Purchasing -> Environment Data -> Define Attributes of System Messages.
    Requirements
    The tolerance key must be defined in step Define Tolerance Key.
    Activities
    1. Define tolerance limits for each tolerance key.
    2. Define the tolerance key in step Define Document Types.
    Thx  and best regards,
    Ale

    HI
    SET   TOLERANCE  LIMITS  FOR PURCHASE  REQUISITION  UNDER THE  DEFINE  DOCUMENTS   FOR PR
    AFTER  SETTING  TOLERANCE  LIMITS  WHILE  CREATING  PURCHASE  U  WILL   GET  BASED ON  TOLERANCE  LIMITS  THERE   FOUR   WAYS  TO  SET  TOLERANCE  LITS 
    1
    ABSOLUTE VALUE
    2
    PERCANTAGE
    3
    TOTAL  PO  VALUE
    4
    QUANITY  BASED  PRICE  PER  UNIT
    OK  BYE

  • Set Tolerance Limits for Price Variance for PR missing from SPRO

    I'm looking into setting up tolerance limits for price variance at the PR level. But when i navigate here:
    SPRO > Materials Management > Purchasing > Purch.requisition > Set Tolerance Limits for Price Variance
    I'm not seeing that available in SPRO. It's available for PO's but not PR's. We want to be able to set tolerances on the PR to be applied to the PO for non stock items (material master). Please advise

    Hi,
       There is no standard configuration option to set the tolerance limit at PR level. You may set the tolerance limit for PO and control the price change. If you want the same functionality at PR level, then you have to go for development. Please check whether the BAdI: ME_PROCESS_REQ_CUST can fulfill your requirement. You may set the tolerance limit in OLME - PO - Set Tolerance Limits for Price Variance itself and write the logic in the BAdI to check the price variance in PR based on the same configuration (table T169G and similar).
       You may check the similar thread: PR VS PO Price Tolerance
    Regards,
    AKPT

  • Error "No changes in WBS possible as budget is activated"

    Hi all,
    While creating new WBS element in exiting project, system giving error  " no changes in WBS possible as budget is activated"
    Due to this we need to deactive the AVAC to add WBS element in exiting project. Again run CJBN t.code to activate the AVAC.
    I also checked user status. There is no user status which can restrict to create WBS.
    Pl guide. What are the possibilites?

    Dear,
    We used  same status profile to project def and WBS.
    In status profile we defined status
    1) ZWBS. It is initial status.  In this status, following business tranction are controlled
    Partially confirm WBS       forbidden
    Partially release project    forbidden
    Release                            forbidden
    Write budget line items    allowed
    Write plan line items        allowed
    and
    2)ZAPR. In this status, following business tranction are controlled
    released   allowed.
    I am not getting why the system is not allowing to create new wbs element in exiting project.
    Pl suggest the possibilities.

  • Maintain tolerance limits in the Tolerance key

    Hi,
    Could any one help me how to maintain these Tolerance limits in the Tolerance key. This is an error I receive  while creating a PO.
    Best Regards,
    Sridhar.k

    What is the Error Mesaage no you are getting??
    Solution is as Follows
    Set Tolerance Limits for Price Variance
    In this step, you define the tolerance limits for price variances.
    When processing a purchase order, the system checks whether the effective price of a PO item shows variances compared with the valuation price stored in the material master record. In addition, it checks whether the specified cash discount value is admissible.
    Variances are allowed within the framework of tolerance limits. If a variance exceeds a tolerance limit, the system issues a warning or error message.
    In the SAP System, the types of variance are represented by the tolerance keys. For each tolerance key, you can define percentage and value-dependent upper and lower limits per company code.
    Standard settings
    The standard SAP System supplied contains the following tolerance keys:
    PE Price variance, Purchasing
    Tolerance limit for system message no. 207. This message appears if the specified effective price exceeds the predefined tolerances when compared with the material price.
    SE Maximum cash discount deduction, Purchasing
    Tolerance limit for system message no. 231. This is a warning message, which appears when the specified cash discount percentage exceeds the predefined tolerances.
    Note
    You can specify whether the system message appears as a warning or error message using the menu options <b>Environment -> Define Attributes of System Messages.</b>
    Activities
    Maintain the tolerance limits for each tolerance key per company code
    Regards
    Biswajit

  • Function modules to get wbs level budgets and activity level cost

    hai gurus can any one tell me the function modules or any other bapis to get the wbs level budgets and activity level costs
    thanx in advance
    afzal

    ok

  • Is there activation control in LR 3.6? If so, how do I move it from one computer to another?

    I have LR 3.6 installed on my desktop and want to move it to my laptop.  What do I have to do to avoid activation control problems?  I cannot find any item in the menus that address this issue.
    Thanks for any help
    Bob Chapman

    There isn't, so you're on the honor system.  Install and put in your serial number on the new machine.

  • How to do budgeting at activity level and WBS element level in project syst

    Dear GURU's,
    Can any one please suggest me how to do budgeting at activity level and WBS element level in project systems, friends please I required set by step process.
    I need how to do this configuration to map this scenario.
    Regards,
    Bhanu

    Hi Bhanu,
    Use this link :
    http://help.sap.com/saphelp_45b/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm
    after page opens , click on BUDGET MANAGEMENT , There you will find each and every step you want .
    Thanks ,
    Dhruv Kumar Malhotra

Maybe you are looking for

  • Problem with Div and table

    I have a table that contains data parsed for a weather station page.  It also has a webcam picture on the page.  Up until now, the webcam pic has loaded via an applet but I want to change that to a jquery slideshow so it's accessible to more mobile d

  • Movie download

    HI,  when I buy a movie it starts the download process of both the HD VERSION and the normal version.  It starts downloading on both my IPAD and ITunes on my PC.  I really only want the HD version.  I also want to download it on my PC and sync it to

  • The headphone jack desease has cought me too

    Well after like 2 months of having my zen micro.. the headphone jack is screwing up on me... sound shuts off.. i hear only the backround of the songs.. sometimes i hear the music in mono.. i dont know what to do i cant even listen to my music any mor

  • Sub- Archiving billing document

    HI everybody, 1 clarification--am facing 1 issue see ,we ve created 1 invoice in vf01-and the inv no is 700----we ve done some mistake in that inv no 700.... we want to cancel it.......but because of some obligations we want the same invoice no.700??

  • EMBED tag SAXCompiler error

    hi all I'm trying to embed a pdf file (now, later a word document) into my web page I have coded this         <h:panelGrid id="embeddedPdfDocumentoPanelGrid"                rendered="#{selectedSGCDocument.pdfType}">             <f:verbatim>