i want to know........we maintaing By Product in BOM in Sub Contracting Process.sometime what happen i send Spray bottle  to Sub contracting, but before complete the finished product. i want to get back Spray bottle back from vendor.
Process
1.Mixing of RAW.
2.mould.
3.Spray.
4.heat.
5.polish
After completing the 3 Process of Spray, it getting empty so i take back, before completing the Finished product.
i would like to have solution, where i can take my empty Spray Bottle, ( i have maintain  empty bottle as by product in BOM) before finished Product.
Regard
NAbil

hii
Thanks for explanation.
But still i am in confusion, because what is the difference between raw material and scrap as bottle.
In BOM or in material master where the major difference will come??
Becasue i wanted to know how system know that , this is scrap and this raw material for consumption ??
Any input from experts .......
Thnaks
Edited by: MM group on Dec 1, 2010 8:39 AM

Similar Messages

  • Goods receipt of by product in subcontracting process

    the by-product are produced in subcontracting.
    we have to take back this by product into our company from the subcontractor.
    we have to use which movement type to take it back and the transaction code

    I think we need a better understanding of the stock in question. Different stock categories will require different movement types (since the mvmnt types are partly defined by the stock catagory).
    Also are these "by-products" to be recieved along with a finished good (FERT) as a consumption? (or do you actualy need the inv. available for putaway on the WM level)?
    If there is a finished goods reciept that will also take place and the stock is stock type "O' that needs to be consumed along with a finished goods then the material (by product) should be consumed from stock type "O' as part of the GR in MIGO.
    So two totaly different cenarios here,
    1. simply move the stock into your warehouse from the venders stock (MB1B transfer)
    2. consume the stock durring GR in MIGO as a componant type c0nsumtion of the goods that is issued along with the 101 MIGO GR. (separate movement type posted for the same line viewed as a drop down from the finished good material)

  • Cross company production with subcontracting

    Hello Experts,
    I have two company codes say C1 & C2. When I get the requirement of 1000 nos of FG X, all material will be procured in C1 & 1st operation will be performed in C1. Due to capacity issue, 2nd operation have 1 production line in C1 & 1 production line in C2.  So the 2nd operation for 700 nos will be carried out in C1 & 300 nos will be carried out in C2. All materials required on prod line in C2 will be send by 57F4.
    How to go for this scenario? 
    Regards,
    Sagar

    Hi Sagar,
    Create 2 level of BoM in C1 like FG = X and SFG = Y.
    Here, the output of SFG  = Y will be called Input for FG in Plant C1 and as an Input again for Plant C2.
    Say you need 1000 SFG to manufacture 1000 FG. You have got capacity constraints for producing 1000 FG in Plant C1, the please follow the below process,
    1. Create, Release, Issue RMs and GR a Production/ Process order for SFG for 1000 in Plant C1.
    2. Create, Release, Issue SFG and other required RM and GR a Production/ Process order for FG for 700 in Plant C1. Here you will consume 700 SFG.
    3. Create a subcontracting PO for 300 FG. With the Subcontracting PO transfer 300 SFG to Plant C2. You need to show Sales Purchase for SFG 300.
    4. Create, Release, Issue SFG and other required RM and GR a Production/ Process order for FG for 300 in Plant C2. Here you will consume 300 SFG.
    I think the decision of how much to be transferred to Plant C2 is totally depedant upon capacity available in Plant C1. The Production Planner or the Line Scheduler is the right person to decide how much quantity to be subcontracted to Plant C2.
    The SD and MM processes are pretty straight but as far as Excise configuration and requirements are concern the composite meetings and decision by PP, MM, SD and CO team would really help you.
    Regards,
    Shoyeb
    Edited by: Shoyeb A on Dec 12, 2011 12:55 PM
    Edited by: Shoyeb A on Dec 12, 2011 1:03 PM

  • By-product and subcontract

    Hi All
    There is a purchase order, and it is subcontract purchase order. and there is by-product in BOM. When I do goods receipt for this subcontract purchase order, there is an error information:Value of the goods movement is negative. therefor I cann't save the document.
    I would like to know how to solve the error?
    Thanks!
    DanDan

    HI
    While doing the GR select variant subsequent adj.  in place of good reciept
    step a) give your po no.
    If under coverage of component then mark the check box in front of line item and give the quantity
    and by product can be received in production plant By t code MB1b and MVt type 542,.
    Check and revert
    Regards
    Anupam Sharma

  • Inhouse production vs. subcontracting

    Dear All,
    What are the proper settings for materials that are produced inhouse and procured externally as subcontracting goods at the same time? (maybe inhouse production will be ceased)
    The material was produced inhouse (proc. type 'E' [so it has got BOM]) but we plan to outsource this activity.
    Thank you for your help.
    Csaba

    Hi Csaba,
    There is no problem it the material has a BOM.
    Still you can got ahead with 'X' both procurement.
    There are two methods.
    Method 1.
    During MRP Run, a planned order will be generated.
    Convert this partially into PR for the required qty from subcontractor. Then tick the closed indicator.
    For the remaining qty you can convert the pl order into Prod order for in-house prodn.
    Method 2
    Use quota arrangement.
    Given
    1.E - inhouse prodn 50%
    2.F-External procurment with L-sub-contracting - 50%
    Also, In the lot-size T.code OMIE tick the splitting qutoa.
    During MRP run, a pl order & PR will be created.
    Pl.reward if useful.
    Regards,
    Senthilkumar SD

  • Subcontracting in Production, 2 subcontracting vendors involved

    Hi,
    We have a scenario where in production 4 operations needs to be performed, one of which is a external process [subcontracting]
    Process 1 - Drilling
    Process 2 & 3 - Subcontracting [External process] u2013 2 processes
    Process 4 u2013 Finishing
    After drilling process, material is sent to subcontractor A for cutting, after this is done Vendor A will sent product to Vendor B directly for further operation . Once this is done We receive from Vendor B
    Then it will go to Process 4 [Finishing]
    Can you please help in mapping this scenario in SAP
    If there is only one vendor involved then I believe process will be like one subcontract PR [system creates automatically], we issue goods and we receive finished goods
    In this case Subcontract vendor A sends directly to Vendor B
    Both Vendor A and B sends invoice to US
    Any pointers in this regards will be of great help
    Thanks

    Hi ,
      While raising the subcontracting order for vendor A enter Delivery address vendor B address & save.
    Raise one more P.O(subcontracting ) with vendor B
    when vendor supplied material to vendor do the migo.
    then in sap stock will increase at vendor B.
    when material recieved from vendor B do migo stock will increaes in respective plant.
    you can procees invoice with P.O wise
    Try this one & let me know
    Rgds
    venkat

  • 545 Goods receipt from by-product from subcontracting

    Hi ALL,
    If a scrap component is entered with a negative quantity for the subcontract order, the receipt of the by-product is posted during goods receipt for purchase order or during the subsequent adjustment.
    Now, when i'm doing MIGO, it's automatically using mtype 545 + O to receive my scrap to vendor stock. The screen filed of special stock indicator (GOITEM-SOBKZ) is not changeable.  I want receive the scrap to normal unrestricted-use stock ( only 545 ) . So how to set the field be changeable?
    Thank you .
    Wayne.

    Hi
    By product will be received as special stock during goods receipt.
    To transfer the by-products quantities from the "stock of material provided to vendor" to the unrestricted-use stock, you please enter a transfer posting using movement type 542 (reversal of the provision of the components).
    warm regards
    sairam akundi

  • Goods receipt for subcontracting material

    Hello friends,
    i  am doing operation subcontractiing. My first operation is subcontracted. So, I have assigned PP02 control key to first operation (external processing and no auto goods receipt indicator)  and maintained external processing data for opration in routing. When i saved the order, for that operation PR gets generated.
    Now, I converted PR into PO and assigned raw material that has to be send to vendor. By 541 mvt. type material is issued to vendor. When i do goods receipt in MIGO, system is not showing storage location field. I dont find material in stock anywhere.
    But i can see quantity received in external processing tab of first operation in routing overveiw in order.
    Then how can i issue the material from storage for second operation if it is not in stock?
    How can i get stock of subcontracted material by MIGO?
    Please help me.
    Thanks in advance!

    Kiran,
    Since your scenario is Subcontract of operations, you will not find a material referance in your PR/PO, so there is no GR of Material happening, in this Scenario GR means delivery of the operation.
    If you really want to track, then you need to create an additional material number and assign that material number with Special Procurement key "30", here in this case you can recieve the product after subcontract as this is product sub contract process. In this case Production order is not relevant.
    Regards,
    Prasobh

  • Subcontracting Handling ByProducts

    Hi I created a BOM with two components and there is one component as negative qty which is generated as By Product.
    When I am creating a subcontracting PO with Item Category "L" I am able to expolde the BOM with Two Components only
    and the negative qty is not coming.
    Also when I am doing GR against this PO the system is doing 101 movement for FG and 543 Movement for two subcomponents
    but it is not creating the stock of by product at vendorend with 545 + 0 movement type.
    Please advice am I doing something wrong,
    Lekhrams
    Edited by: Lekhram Sharma on Jan 2, 2008 2:37 PM

    You can use subcontract orders to plan the receipt of by-products from subcontracting:
    Similiar to production order processing, by-products are entered in the subcontract order as components with negative quantity.
    In the provision of the components (with reference to the purchase order, for example), the system ignores the negative component items.
    In the goods receipt for the purchase order, the system automatically posts the receipt of the by-products. In the material document, you can identify the by-product items from their movement type 544. Note that the by-products are posted to the "stock of material provided to vendor" (also referred to as "subcontracting stock").
    The receipt can still be corrected using the Subsequent Adjustment function.
    Due to the receipt of the by-products, the value of the manufactured material is reduced.
    To transfer the by-products quantities from the "stock of material provided to vendor" (or subcontracting stock) to the unrestricted-use stock, you enter a transfer posting using movement type 542 (reversal of the provision of the components).

  • How to Create Purchase Order with Co Product greater than Consumption

    Hi All,
    I'm new to SAP. Can any one please help with the steps to create PO with Co Product greater than Consumption.
    Thanks in Advance.    

    Hi Srinivasu,
    If you are talking about handling by-products during subcontracting follow the following steps.
    Create Purchase order with item category "L". In the components tab maintain by-product in negative quantity. If you are not sure about the actual quantity, enter theoretical quantity ( Actual quantity can be adjusted in Subsequent adjustment in Goods receipt).
    Hope this helps you.
    If this has not helped you, please elaborate your requirement.
    Thanks
    Vasuki B S

  • A subcontracting Scenario

    Hi ,
    In  subcontarcting PO scenario please explain me the following.
    I am sending x kg of material A to SC Vendor .
    I am expecting y kg of Material B from SC vendor.
    By product in the procedure is C.
    I have maintained BOM as A material to be send A, finished assebly is B and byproducts C in cs01.
    Steps Involved are
    1. I sent x KG to  SC Vendor . ( Explain how to issue goods to SC vendor with Movement type involved.)
    2. Found that actual consumption was less than expected in BOM, So i want reverse those extra parts i sent to SC vendor.( How to reverse them and using which Movement type)
    3. After completion of process i want to do GR for the Finished product XX.(How to do GR and Movement type envolved)
    4.In last stage i want to recieve the by-products from the vendor.( Movement type)
    5 Scrap generated in process to be recieved in companies own stock( Movement type)
    5. What are various excise document which are involved if vendor sends me the finished product within subcontracting period.( 180 days)
    6. What is the " Reconcillation the SC challan ? Meaning of reconcillation?
    Edited by: Shreya Sinha on Dec 29, 2007 12:30 PM

    HI All,
    Can anybody help me regarding subcontracting. Any help would be much appreciated.
    Talking about subcontracting, right now we are facing some issues.We have right now what we call dismantle subcontracting,
    Scenario 1:
    Normally we send material A,B,C to vendor 1 for subcontract and receive material D.now on vice versa, we want to send material A, to Vendor 1 to receive material B,C and D.
    while Material B,C,D will remain in vendor site after dismantle process is done.
    I know, i can input one of the subcomponent say : A in PO as a parent component then put rest of others as a subcomponent with addition negative quantity for material D.
    but the problem is , a lot of subcomponent for dismantle is involved and the customer is minded if they have to put a lot of subcomponent every time they create PO(while this PO subcontract may vary every time).Any other way for resolved this objection.
    thank you,
    Regards,
    Daniel Tan

  • Purchase Order of Subcontract process

    how do you raise a Purchase Order for a subcontract process. In JDEdwards, we use OX type to create a requirement to generate a PO on a line in the Routing. Not sure how it works in SAP

    Hi,
    Check the below links...
    Subcontracting process in Production
    Assembly Subcontracting in Production
    Thanks
    Kumar

  • Subcontracting work handling in CO

    Hi ,
    For my client , we need to configure and handle  subcontracting business both for subcontractor & subcontractee . Both under the same corporate group but separate leagal entity . For example , A is giving a subcontracting owrk to B .   In the books of A  subcontarcting configuration and the corresponding steps  are clear to me . But not sure how to handle , in the books of B in SAP from CO perspective . .
    Any inputs how to handle the same in books of B from CO perspective  ?
    Thanks in advance for help .
    Regards ,
    Arnob

    Hi Deve.,
    Thanks for your reply . but our senario is bit complicated . We are raising Subcontracting order in the books of A  and the subcontracting vendor is B . Doing 541 & 542 mvt type for giving the subcontracting material to B and reciving back the same from B .  So far B is concerned ,  he is doing some small services . So as per the subcontracting procedure , neither input materials from A  , nor the final product after subcontracting work will hit the books of B , for the entire cycle it will remain in the books of A --. Consumption as well inventorisation .  In the books of B , we have some small expense items for doing the subcontracting work.
    Now , in my clients scenario B will pay the Exicsie duty and thats  why they are looking for production order in the books of B . Since , neither we have the input materials nor the final products in the books of B , I am unable to create production order .
    One  possibility , is to create a service order in the books of B to capture this activity in the books of B along with Excise duty .Unfortunately , we do not have CS module in place .  Excise liability on the part of  B is confirmed one  and quite unique considering the business model .
    Any thoughts based on the above inputs.
    Regards ,
    Arnob

  • Change in finished product inventories / cost components

    Hello,
    We are in the process of implementing SAP and couldn't get an answer to the following.
    Our understanding is that the production cost of each finished product is calculated by SAP based on cost components. After manufacturing, the finished products are transferred to the finished product inventory. The change in finished product inventory account (say 713000) is credited with the production cost of the product.
    Instead of having this single 713000 account impacted, we would like to have the change in finished product inventory broken down into several, say 713001 raw material component in finished product, 713002 labour cost component in finished product, 713003 subcontracting cost component etc. Can we get SAP to credit automatically each of these accounts based on the cost component (or group of cost components) information in the system ? How should we configure it ? (is there a link between the cost component or group of cost component and the account)
    Many thanks for your help
    Best regards

    Hi Vincent,
    In my understanding you are not clear with the requirement and therefore you are struggling with SAP. Please understand the following:
    1. The posting of GL accounts are determined by valuation class in material master. So if you want to post on different GLs please define those many valuation class in MM and assign the correct Valuation class to FG goods.
    2. When you confirm the production, SAP post the goods issue (i.e. material you define in BOM) by debiting the Material consumption account and credit  the invertory accounts. And also post the goods receipt posting by debiting the FG inventory account and credit the Factory output a/c.
    3. Here you have to convience your client that it is best pratice to have one inventory account for one material type, like RM inventory, SFG inventory and FG inventory. Normally we classify the consumption posting in different GLs like Material consumption, Labour consuption, Overhead utilization etc. and that you can define in your cost component structure by grouping the relevent GLs in given cost component items.
    4. You have to explain them how SAP works in product costing and how GL documents are posted. You have to also explain them the posting impact in P&L and BS.
    I will suggest that you should rediscuss the requirement and explain them the SAP way of valuation and posting. It is a big change management issue and as a CO consultant it is most challenging task.
    Thanks and all the best,
    Vivek

  • Reversal of subcontracting

    hi
    generally we r sending rawmaterials and we r getting finished product from subcontracter
    my problem is i have send a assembled product to subcontracter and he has to dismandle it and send back the dismandled products how can i approch this.
    help me in this

    Hi,
    Suppose Material code for  Assembly is - X
    And Material codes for components after dismantle will be - A, B, C
    Then create a BOM for any of the component for e.g. A and maintain materials X, B and C as components under it in CS01.
    Here only keep in mind that
    For 1 qty of A, keep 1 qty of X and -1 qty of B and C
    And then create a Subcon PO for material "A" in ME21N and specify dismantle charges in PO
    Do transfer posting of "X" in MB1B w.r.t. Subcon PO (Using mvmt type - 541)
    Goods Receipt of A w.r.t. Subcon PO in MIGO, (Here "A" will get received by 101, "X" will get consumed by 543 O from Subcontractor Stock, "B" and "C" will get received in Subcontractor stock via 545 O)
    Now do transfer posting of "B" and "C" in MB1B (Using mvmt type - 542)
    MIRO - LIV for dismantle charges w.r.t. Subcon PO

Maybe you are looking for

  • How do I get my iPhone 4 to transfer purchases to a new computer?

    I got a new computer (Windows) and I want to switch my iPhoneover so I don't have to use my old computer to sync anymore.  I did the "backing up the original library and restoring it onto the new computer" thing, but that apparently didn't copy over

  • HP Officejet Pro 8610 Unsuccessf​ul Network Installati​on

    I just purchased a new HP Officejet Pro 8610.  I was able to install its software on two of our three computers, but the third gives the error messages "Unsuccessful Network Installation" and "The printer was unable to be installed over the network."

  • How to restrict data that is displayed  in adf query

    Hi all, i have a VO with query criteria, which i have added to the jsf page as adf query panel with table. There may be particular queires that return large number of records. Suppose i want to restrict the number of records being displayed to 10,000

  • Scheduling maintenace order

    HI fds while creating maintenance work order. scheduling is not carried out it is giving the following msg. Scheduling log does not contain any entries Message no. C7119 i have maintain all the scheduling parameters , so scheduling should be carried

  • How do I change the mobile number re messages on iPad air

    How do I chane the mobile number re messages on my new ipad air.  It seems to be coming up with my husbands number ...