Can i use Solution manager ADS for ECC6 ABAP

Dear All,
          We have landscape of ECC6 ABAP (Dev, Qua, Prd), can i install and configure ADS on Solution manager(ABAP+JAVA) and connect all Dev , qua and prd to same solution manger for Adobe interactive forms. is it possible ?
for production environment?.
Regards
Vinay

Hello!
This was already discussed. E.g. here ADS install in Solution Manager.
While it is technically possible (to connect several systems to one ADS) it is not recommended for productive environment for some reasons (security, stability, performance and easy of maintenance). I say you can use you ADS on SolMan for DEV, QAS and number of your training/demo systems, but install separate J2EE with ADS instance (better on separate server) for productive use. You can then check ADS updates/patches on SolMan first without breaking productive system and only then (if successful) update productive.
Regards,
Petr Perstnev

Similar Messages

  • Solution manager adapter for HP Quality Center

    Hi All,
    We want to use Solution manager adapter for HP Quality center. Can you please provide some documentation/information regarding it's installation prerequisite, installation process and Licences.
    Regards
    Vivek

    >
    vivek b wrote:
    > We want to use Solution manager adapter for HP Quality center. Can you please provide some documentation/information regarding it's installation prerequisite, installation process and Licences.
    As a first overview:
    [SAP Solution Manager Adapter for SAP Quality Center by HP    |http://service.sap.com/~form/sapnet?_SHORTKEY=01100035870000725149&_SCENARIO=01100035870000000202&]
    Best regards,
    Ruediger

  • Is it a must to use Solution manager for ECC 6.0 upgrade

    Is it a must to use Solution Manager for ECC 6.0 (FICO & HR) upgrade? I am told Solution Manager is required only if it has ABAP and JAVA stacks, or involves Enhancement Packages; and could be optional if it is only ECC 6.0 with ABAP stacks.

    Hi,
    I'm having a difficult time finding some guidance for setting up our R/3 Enterprise system in solman properly, so that I can create the upgrade XML file required to go directly to ERP 6.0 EHP4. 
    I've set up the R/3 system fine, but when i create a maintenance transaction i cannot for the life of me figure out how to tell it I want to go from r/3 to ERP6 ehp4.
    Any docs out there for this?
    Thanks!
    I figured it out... i had to add the R/3 Enterprise logical components to my system landscape.  After that I was able to select R/3 as the initial data in the maintenance transaction and then the system i wanted to upgrade, and then the option to upgrade.
    Never mind!
    Edited by: Tom Janes on Sep 9, 2009 12:52 AM

  • CCMS is used for system monitoring , why should we use solution manage ?

    CCMS is used for system monitoring , why should we use solution manage ?
    Whats the relationship between CCMS system and SolMan?
    Thank you .

    hi,
    I just want to ask a question. At our client we have solution manager and CCMS. There is data in CCMS I can extract, it is loading on BW side ok the same number of recs,  but the problem on CCMS cubes says there are the same number of record in the cube and also showing as the data is ready for the reporting. But when I run the report and view the data as listcube it is empty. 
    ANy of you have the situation like this cube say it has the data but when do th BEX or infocube contents the cube is empty nothing in there. The same thing is happening with hourly, 15 minute and daily cubes.
    Anyhelp on this matter is appreciated

  • CAN I USE THE ONLINE WORKSPACE FOR MY COMPAY'S DATABASE MANAGEMENT?

    Hi Forum,
    I am the Database Management System Administrator for the company I am working with. The company has branches in other regions of the country. In order to control and centralize its operational information management I have realized the need for the database to have internet link to help achieve the purpose. I have tried to connect my apex 11g to the internet but I have not succeeded. I am thinking of an alternative of using the Oracle Online Worskspace. Would Oracle allow me to use it? I shall also be glad if someone can still help me to configure my apex database to be accessed on the internet that can be used to manage large geographical operations.
    May God bless you and OTN forum
    Regards,
    Godis-Tei

    Godis-Tei wrote:
    I am the Database Management System Administrator for the company I am working with. The company has branches in other regions of the country. In order to control and centralize its operational information management I have realized the need for the database to have internet link to help achieve the purpose. I have tried to connect my apex 11g to the internet but I have not succeeded. I am thinking of an alternative of using the Oracle Online Worskspace. Would Oracle allow me to use it? No. The following conditions apply to use of apex.oracle.com:
    >
    This service is for demonstration purposes only. Use of this system to store sensitive data is prohibited.
    >
    and
    >
    This hosted Oracle Application Express instance is provided as a free demonstration service to anyone. Use of this system to store sensitive, offensive, unauthorized, or illegal data is prohibited. You are also prohibited from running production applications on this service.
    >
    May God bless you and OTN forumIn line with the OTN Terms and Conditions, please do not use religious language in the forum. It is irrelevant and likely to cause offence to users who do not share your beliefs.

  • CTS+ Configuration for Transporting non-ABAP objects in Portal Landscape using solution manage 7.1 sp8

    Hi,
    Currently we have cts+ already configured for our portal systems in our landscape through solution manager 7.0.
    Recently we had setup a new solution manager 7.1 and need to perform cts+ configuration using this new solution manager 7.1 as we are planning to remove our old solution manager 7.0 very soon.
    We are using NWDI system for transporting our portal transports.
    Please help me with steps on how to configure cts+ using solution manager 7.1 using NWDI.

    Hi Naveen,
    Please find given below BBPCRM & SAP_BW version..
    BBPCRM     500     0013     SAPKU50013     BBPCRM     BBP/CRM Supp. Pack.
    SAP_BW     701     0003     SAPKW70103     SAP Business Warehouse     Component Supp. Pkg.
    This problem is not only with  Bussiness process tab (T-Code: Solution_manage) also System monitoring Still i searching solution for this But once we are restarting System that time this problem is not occuring but after some time system is giving this DUMP
    Regards,
    Suresh

  • How to monitor BI & PI using Solution Manager 4.0

    Hi, we have installed Netweaver 04S SR2 SP11 BI & PI components. We want to use Solution Manager 4.0 to setup monitoring for these 2 systems. Any guide or documentation will be greatly appreciated.
    Thanks in advance.
    Arshish

    Hi Arshish,
         To setup monitoring you will first have to include these systems in the system landscape of SAP solution Manager 4.0 in transaction SMSY.
    The steps in the order are :
    1. Create Server ( Server name ,IP and Fully qulaified Host name)
    2.Create Database  (Give the database you are using)
    3.Then you have to create the system itself. and give the information as required.You will be able to do it when you will go through it.
    Then you have to generate the RFC's from solution manager to satellite systems and back.These RFC's have to be trusted.Assign role SAP_S_RFCACL or profile S_RFCACL  to the users in SOLMAN as well as satellite system.
    Follow these steps and create a Logical component for the system that you have added.
    Follow these steps first.More information can be found out on
    service.sap.com\solutionmanager
    or you can look for the RKT'S on service marketplace.If you need any furthur assistance do reply back.
    please award points if found helpful
    Best Regards
    Amit

  • Project Management using Solution Manager

    Hi,
    We are trying to use solution Manager for managing our IT projects - specifically for SAP projects.
    We browsed through the existing functionalities that are available and are not able to get info on the following:
    ___Project Admin tab for Roadmaps :_ __ In the transaction RMMAIN, we are able to define the scope of the activities at each phase and assign team members and track the status of the activity / task.
    However we do not have the tab for tracking the planned start date / end date and the actual start / end dates. Similar is the case for efforts.
    So not sure how to track these?
    Integration of Roadmaps and Blueprints : Once we have defined the project and assigned the Roadmap, we have all the activities that need to be tracked. In addition in transaction SOLAR01 / SOLAR02, we can define the scope and configurations which in itself are a kind of sub projects to be embedded withing the Blueprint and realization phases respectively of the main Projetc Plan.
    How to link these Blueprint specific plan and the realization related plan to the main project plan created out of the Roadmap chosen and to track them as one single project?
    Synchronization wih ms project : I see only the option to download the plan as an mpp file. But is there any option to upload mpp as well so that the project can be tracked using mpp and synchronized with Solution manager at frequent intervals?
    Your answers would definitely be helping us a lot and would be greatly appreciated.
    thanks in advance.
    regards,
    suresh velan

    Hi Suresh,
    Solution Manager is a Project Management tool. But it is not for Project Planning. If you want to do Project Planning also from the SolMan system, then you have to enable cProjects component of SolMan.
    Synchronization between your MS Project and cProjects is possible. But synchronization between SolMan's RoadMap/Blueprint and MS Project is not possible.
    In RoadMap, you can capture and track the status of all phase-wise activities as to what is their status. Here capturing date details is not possible.
    In Blueprint/Configuration you can capture and keep track of the individual object's blueprinting and configuration activities. Here you can capture the planned/actual start/end dates for each object.
    As I said earlier, Solution Manager provides lot of Project Management features, but Project Planning is not possible. For that we have to start using cProjects component in SolMan.
    Hope it helps.
    best regds,
    Alagammai.

  • EP 7 systems in Solution Manager 7 for EWA activation

    Dear Expert,
    Greetings from Partha.
    I need to include our EP 7 systems in Solution Manager 7 for EWA activation. Current lanscape scenario
    Solution Manger     7.00   Installed
    EP                          7.00   Installed
    No central SLD configured and all the system have local SLD.
    1. As per the installtion guide & SAP notes we need to install
    a> SM Diagnostics Agent & Wilo Introscope in Solution Manager (manging system).
    b> Diagnostics Agent in every manged system(s).
    For managing system we can download Diagnostics Agent installation DVDs from SAP Service Marketplace
    at: http://service.sap.com/swdc --> Download --> SAP Support Packages --> Entry by Application Group
    --> SAP Technology Components --> SAP SOLUTION MANAGER --> SAP SOLUTION MANAGER 7.0
    --> Entry by Component --> Agents for Managed systems --> DIAGNOSTICS AGENT 7.11
    --> <choose operating system of managed>
    Our Solution Manager 7 is already installed and @SPS 17. My question is
    1. Can we use the same file for SMD installtion in Solution Manger or we need to download it from some other area ?
    If it is different then kindly let me know what are the DVDs to be downloaded and from where?
    2. In our Managed System SMD installtion we have decided for
    --> Installation Strategy as Direct Solution Manager Registration
    But what strategy we should take for SMD installation on Sol Man 7 that is
    Local SLD (wrt Sol Man) Registration or Direct Solution Manager Registration
    3. What is the need for the SAP Host Agent Installattion ? Is it mandatory ?
    Help will be appreciated.
    Regards,
    Partha

    1. As per the installtion guide & SAP notes we need to install
    a> SM Diagnostics Agent & Wilo Introscope in Solution Manager (manging system).
    b> Diagnostics Agent in every manged system(s).
    For managing system we can download Diagnostics Agent installation DVDs from SAP Service Marketplace
    at: http://service.sap.com/swdc --> Download --> SAP Support Packages --> Entry by Application Group
    --> SAP Technology Components --> SAP SOLUTION MANAGER --> SAP SOLUTION MANAGER 7.0
    --> Entry by Component --> Agents for Managed systems --> DIAGNOSTICS AGENT 7.11
    --> <choose operating system of managed>
    Our Solution Manager 7 is already installed and @SPS 17. My question is
    1. Can we use the same file for SMD installtion in Solution Manger or we need to download it from some other area ?
    If it is different then kindly let me know what are the DVDs to be downloaded and from where?
    Check the pdf attached in note 1234387 - Inst. 7.1 EhP1 - Diagnostics Agent installation
    If you have SP17, you must follow note 1357812 and install Diagnostics Agent 7.01 SR1
    2. In our Managed System SMD installtion we have decided for
    --> Installation Strategy as Direct Solution Manager Registration
    But what strategy we should take for SMD installation on Sol Man 7 that is
    Local SLD (wrt Sol Man) Registration or Direct Solution Manager Registration
    It doesn't matter what strategy you'll decide. You could decide Direct Solution Manager registration
    3. What is the need for the SAP Host Agent Installattion ? Is it mandatory ?
    As you have solution Manager SP17, you can't install Saphostagent 7.11 and for this reason you can't use SAphostagent.
    Agent 7.01 => No Saphostagent
    Agent 7.11 => Must install saphostagent
    Agent 7.20 => Already have SAPhostagent installed

  • Solution Manager information for Java stack systems

    Hi,
    Could someone please help with the setup of Solution Manager, and how to connect to the backend of a Java stack system. For our ERP systems this is working via RFC, but I was hoping to get more information on the procedure for java. I can specify manually via SMSY, but I am sure there must be a setup that can pull the information for the system itself. Could anyone shed some light on this if possible please.
    Regards,
    Chris

    Dear Chris,
    ABAP Stacks use RFC as you know for inter system communications.
    Java stack systems use Solution Manager Diagnostics.
    You will need to run Solman_Setup > Managed System Configuration
    First you should visit the link http://service.sap.com/diagnostics
    There you will see a link to the media library, and there you will find complete documentation.
    Hope you find this information Helpful.
    Regards,
    Paul

  • SAP Solution Manager Adapter for SAP Quality Center by HP (ST-QCA)

    Hello Folks,
    I am configuring Solution Manager, and the current activity asks to download to add-ons that I can't find in the Marketplace - they are required to activate Solution Manager Enhancements:
    SAP Solution Manager Adapter for SAP Quality Center by HP (software component: ST-QCA)
    SAP Support Enablement package (software component: ST-SEP)
    Does anyone know where to get those components?
    Thanks a lot,
    Marco

    Hi Ravindra babu/ Murali:
    I have one very quick doubt and would be really glad if you can help clarify.
    As per documentation from SAP and also IMG screens etc. it seems like 'a project' in SolMan will hand-shake with 'a project' in QC.
    Can I therefore assume that if there is only one instance of SolMan (productive) and one QC server alone (again, productive), any number of trials I carry out between SolMan project and QC project will not spill over into other projects in these two systems and thus have no impact whatsoever at server level.
    The reason for my asking this - in my project, Testing has started using QC in a standalone mode already. We have just one server. If I have to carry out any tests/ demo between SolMan and QC, it shouldn't impact other 'standalone' projects being done in QC.
    Regards,
    Srini

  • How to use solution manager in upgrade projects

    Hi,
    How to utilize/use the solution manager in upgrade project like R/3,BW,CRM or entire landscape.
    if we are upgrading the r/3 4.6c to ecc6 and bw3.5 to bi7.0 how to use the solution manager
    please help and thanks in advance.
    Edited by: MAHIPAL REDDY on Jan 1, 2009 1:28 PM

    Hi,
    Check [this document|https://websmp208.sap-ag.de/~sapdownload/011000358700002696532005E/310_320_SOLMAN_URMP_EN.doc]. This will help you to proceed further.
    This is a detailed documentation on using Solution Manager for your upgrade project.
    This will solve your problem.
    [This Pdf |https://websmp208.sap-ag.de/~sapdownload/011000358700000208052007E/Upgrade_FAQ_SolMan_70.pdf]of FAQs on upgrade project is rich in information.
    Feel free to revert back.
    --Ragu
    Edited by: Raguraman C on Jan 3, 2009 5:27 PM

  • Solution Manager Adapter for HP QC (12)

    Hi,
    As you know, HP has recently launched the version 12 of HP QC.
    We plan to use Solution Manager (7.1) in combination with HP QC (12).
    The only version of Solution Manager Adapter for HP QC I can find on SAP Market place is ST-QCA 100.
    Do you know if there is a newer version of Solution Manager Adapter for HP QC (12) or is it independent of QC version?
    Thanks for your help.
    Regards.

    Hi Priya,
    It is independent of QC Version. I recently integrated ALM 11.52 with Solution Manager SP10 using ST QCA 100 and it worked ust fine. Just make sure with SAP that they support the ALM 12 officially, there might be some changes in ALM 12 which *might* give some problems. SAP as of now did not list ALM 12 in their compatibility matrix;
    I hope they are using the same Enterprise Integration adapter in ALM 12 that they used in 11.52. If so it should work. Give it a try  !
    Regards,
    Vivek

  • How to create a "blueprint" using solution manager?!!

    I have been asked to create a 'blueprint" using solution manager!! I have absolutely no clue how this can be achieved using solution manager!! Please guide me on what is to be done.Would appreciate if you donot give me links of help.sap as the same is not making sense to me.
    I have to create a blueprint for 20 countries of SAP reports available for FICO. Some of these reports are country specific while others are generic.

    Hi Suchita,
         You can create blueprint document using SOLAR01 transcation, provided you must have included all the organizational data, business process, master data,,
    Follow the path
    transaction SOLAR01->Business Blueprint-> Generate Blueprint
    You must have created a solution and a project assigned to that solution also.
    further clarifications feel to post the query
    regards
    Naveen
    Edited by: Naveen kumar Palanichamy on Jan 2, 2008 7:16 AM

  • Why use Solution Manager?

    Hi,
    I wonder if you can help.  We have been advised to install Solution Manager in order to manage the upgrade from 4.6c to ECC 5.0, but have also heard conflicting advice that states that this is not necessary and is an overhead.
    Can anyone advise if SolMan is worth installing and what the benefits are of running the upgrade through this vs using normal methods.
    Many thanks.
    Sean

    Hi,
    Wel solution manager is an awesome project tracking tool.
    Say for e.g it will generate reports for the overall testing using which you will be able to know who is testing what is testing and how much testing is compeleted.
    It stores all the log for automatic test cases whether ECATT or External (mercury QTP).
    I have written several blogs on testing and ecatt and qtp integration can view the same on sdn.
    In addition to above if you use solution manager you can get accelerate roadmap documents and also provide you reports which can show you the current progress of your project with time and dates.
    Provide e-learning and also can use solution manager as document management system.
    If you are not going to use the same,You are missing all above.Decision is your's.
    Please reward points if it helps.

Maybe you are looking for

  • Fax picks up fax AND voice calls

    I thought when you have an external modem fax set up, the computer is supposed to tell if it's a voice call or a fax call. For some reason, the fax keeps picking up on ALL calls on the first ring (or any ring # I set it for) and no voice calls are ge

  • Exporting LOGON trigger with per schema filtering

    I am using the datapump on 10.2g (on linux) to export three schemas. I am using the "SCHEMA" option in the dbms_datapump.open() procedure and then using the metadata_filter with the SCHEMA_EXPR option to limit down to my three schema. I also do some

  • Single press iPhone 4 home button multitask....

    Hi my name is Raj... I'm having a issue but I don't really know is it a serious issue or not... I want to really know weather anyone experience this problem... My problem is when the 1st time I bought my iPhone 4 I realize that when I press the home

  • Reworking Photoshop layer renaming script for Illustrator

    The Photoshop scripting guru Paul R over at RetouchPro has created a really cool script to batch rename and number selected Photoshop layers. I haven't found anything similar on the Illustrator side. He's given permission for me to post it here in my

  • HT204384 Can I use an sd card for an iphone 5c?

    Can I use an sd card for an iphone 5c?