Hi MM Team,
one of my user is created a subcontracting PO and try to create a delivery in ME20 at that time he is getting a error message
(Essential transfer parameters are missing in record:  000001) also added to it the vendor is a new toller vendor, one thing i want to confirm with you guys in ME2O once i select the material and go for CREATE DELIVERY one screen appears asking for the input of vendor,material, shipping point ,plant, storage location ,batch and quantity here i dint give the input of storage location and batch either this could be a problem for the error.
Thanks
Karthikeyan.P

Hi,
Check points in these notes:
Note 458938 - FAQ: SC stock monitoring list, Transaction ME2O
Note 323991 - Availability check:Subcontract PReq subcontract PO componnts
Note 199360 - Creation of a SD delivery from TA ME2O
Note 519559 - FAQ: Goods issue for the reservation
and related notes
Regards
Eduardo

Similar Messages

  • While creating sales order I am getting  Sanctioned party list blocked  but I am able to create delivery, and PGI

    Dear GTS Experts,
    While creating sales order I am getting  Sanctioned party list blocked, but I am able to create delivery, and PGI.
    Where Is the wrong ?
    Thanks a lot
    Venu gopal

    Dear Venu
    Based on your message shown in the system, can you check the field in Control Settings for System Reaction in the Document type settings via Application Levels in the feeder system. This Field '' System Response in Feeder system if SAP GTS fails'' should be maintained with ''A''. I think in your case it could be 'Blank'' Thats why the system is allowing you to create the subsequent documents accordingly.
    Please let me know if any further inputs required.

  • 1. Can we able to create GR for consubale without PO

    Hi ,
    I have two issues.
    1. Can we able to create GR for consubale without PO - invoice should be done with some reference. no direct posting.
    2. Can we able to create PO with Account assinment cat as "P or some other"  and without WBS element ? at the time of GR i want to give WBS element.
    Regars,
    Anil

    >
    anil kumar wrote:
    > Hi ,
    >
    > I have two issues.
    >
    > 1. Can we able to create GR for consubale without PO - invoice should be done with some reference. no direct posting.
    >
    > 2. Can we able to create PO with Account assinment cat as "P or some other"  and without WBS element ? at the time of GR i want to give WBS element.
    >
    > Regars,
    > Anil
    1. If settings for automatic PO is on, yes its possible when you create GR, Po gets created automatically, or you do GR against other with movement type 501 which is without PO.
    2. If you use P, then you need to enter WBS element. You can use U in combination with D =  service, then you enter wbs at service entry time.
    Edited by: Afshad Irani on Aug 13, 2010 11:26 AM

  • Error while creating delivery using ME2O

    Hi ,
    We are using ME2O to creat delivery for subcontracting . But I click on "Create delivery" button there is an error message coming.
    The error is as following:
    Global official numbering: Input parameter incomplete
    Message no. ICC_NUMBERING770
    If anyone has any solution for it could you please let me know.
    Thanks in advance.
    Sonali.

    Then make sure you have defined the LB in purchiasng for sub contract order
    Or Goto this document and check that you have did all the config
    External Subcontracting: Configuration Guide
    1     Purpose
    This configuration guide provides the information you need to set up the configuration of this building block manually.
    2     Preparation
    Before you start installing this building block, you must install prerequisite building blocks. For information on the prerequisite building blocks, see the Quick Guide for installing Chemicals (located on the DVD in BBLibraryDocumentationChem_Quick_Guide_EN_US.doc).
    3     Configuration
    3.1     Defining Shipping Data for Plant BP01
    Use
    The purpose of this activity is to maintain the shipping data for the supplying plant. (Shipping of the components)
    Here you maintain the customer number of the receiving plant. This customer number is used in SD shipping processing to identify the goods recipient (ship-to party) if provision has been made in Customizing for a stock transfer to be carried out with an SD delivery
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Materials Management à Purchasing à Purchase Order à Set Up Stock Transport Order à Define Shipping Data for Plants
    Transaction Code     SPRO
    2.     On the Change View “Stock Transport Order”: Overview screen, select the production plant BP01 and choose Details.
    3.     On the Change View “Stock Transport Order”: Details screen, make the following entries:
    Field name     Description     User action and values     Comment
    Plant          BP01     
    Customer no. - plant               
    Sales organization          BP01     
    Distribution channel          03     Intercompany
    Division for intercompany billing          01     Product division 01
    Language key          EN     English
    4.     Save your settings.
    Result
    The shipping data for plant BP01 has been set.
    3.2     Defining Delivery Type for Subcontracting
    Use
    The purpose of this activity is to assign Delivery Type for Subcontracting. For the supply of the input materials to be provided to the vendor (subcontractor) with respect to subcontract purchase orders, you have the option of creating an SD delivery from the list of stocks for a subcontractor.
    In this step, you can specify a delivery type for the delivery of materials to be provided to the subcontractor.
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Materials Management  Purchasing Purchase Order  Set Up Subcontract Order
    Transaction Code     SPRO
    2.     On the Change View “Subcontracting Data: Delivery Type f. Provision of Material” screen choose New Entries (F5) and make the following entries:
    Field name     Description     User action and values     Comment
    Supplying plant          BP01     
    Del. type f. subcon.          LB     SAP Standard
    3.     Save your settings.
    Result
    The delivery type LB has been assigned.
    3.3     Assigning checking rule
    Use
    The purpose of this activity is to assign the checking rule B = SD-Delivery to the MRP-Group 0000. This rule defines the checking procedure to be used for the availability check.
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Production à Material Requirements Planning  à MRP Groups à Carry out overall maintenance of MRP-Groups
    Transaction Code     SPRO
    2.     On the MRP-Group View choose Plant BP01 and MRP-Group 0000.
    3.     On the View choose the Button: Check.rule dep.reqmt screen make the following entries:
    Field name     Description     User action and values     Comment
    Checking rule          B     
    4.     Save your entries.
    Result
    The checking rule B will be used for the availability check for the components during creating the LB-PO.
    3.4     Defining item category determination in deliveries
    Use
    The purpose of this activity is to maintain the item determination for the delivery type LB and the Item category group VERP. (VERB is used in material master CH-4120)
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Logistic execution à Shipping à Deliveries à Define Item Category Determination in Deliveries
    Transaction Code     0184
    2     On the Change View “Delivery item category determination”: Overview screen copy the entry LB/NORM to LB/VERP. (The item category LBN will be found)
    3     Save your settings.
    Result
    For materials with item category groups VERP you can create a delivery.
    3.5     Assigning Picking Locations
    Use
    The purpose of this activity is to assign the picking locations to the combinations of shipping point and storage condition for every plant.
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Logistics Execution à Shipping à Picking  à Determine Picking Location  à Assign Picking Locations
    Transaction Code     SPRO
    2.     On the Picking location determination screen, make the following entries:
    Field name     Description     User action and values     Comment
    ShPt     Shipping Point     BP01     Shipping point BP01
    Plnt     Plant     BP01     
    SC     Shipping Condition     01     
    Sloc     Storage Location     0001     
    3.     Maintain another entry with the following values:
    Field name     Description     User action and values     Comment
    ShPt     Shipping Point     BP01     Shipping point BP01
    Plnt     Plant     BP01     
    SC     Shipping Condition     02     
    Sloc     Storage Location     0002     
    5.     Save your settings.
    Result
    Storage locations have been assigned.
    3.6     Searching Strategy for DL
    Use
    The purpose of this activity is to allocate the search procedure SD0001 to the order type DL.
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Logistic General  Batch Management  Batch Determination and Batch Check  Batch Search Procedure Allocation and Check Activation  Allocate SD-Search Procedure/Activate Check
    Transaction Code     SPRO
    2.     Copy any entry for Sales Org. BP01, Distr. Channel 03 and Division 01.
    3.     Change the Sales Doc.Type to DL and save your entry.
    4.     Choose Save.
    Result
    The search strategy SD0001 has been assigned to the sales DL.
    3.7     Activating Automatic Batch Determination for Delivery Item Categories
    Use
    The purpose of this activity is to allocate the automatic batch determination for appropriate delivery item categories.
    Procedure
    1.     Access the activity using one of the following navigation options:
    IMG Menu     Logistics – General  Batch Management  Batch Determination and Batch Check  Activate Automatic Batch Determination in SD
    Transaction Code     SPRO
    2.     On the Choose Activity screen select Activate Automatic Batch Determination for Delivery Item Cat and choose Choose.
    3.     On the Change View “Automatic Batch Determination for Delivery Item Category” screen, make the following entries:
    ItCa     Description     AutBatchDt
    LBN     "Mat. Provided" Item     X
    4.     Choose Save.
    Result
    The automatic batch determination for delivery item categories has been activated for appropriate item categories.
    4     Master Data
    The following activities describe the master data required for this Building Block. The steps do not describe the transactions in detail but list the relevant transaction and the corresponding master data file. For more details on using the individual transactions refer to the Online Help in the system.
    4.1     Creating Customer C-9000 for Subcontract Vendor (S-9000)
    Procedure
    1.     Access the activity using one of the following navigation options:
    SAP Menu     Logistics  Sales and Distribution  Master Data  Business Partner  Customer  Create  Complete
    Transaction Code     XD01
    2.     Refer to the following file for details of the master data required: SMB15_SD_CUSTOMER_O034_J30_Q15.txt.
    4.2     Creating Info Record CH-6120/S-9000
    Procedure
    1.     Access the activity using one of the following navigation options:
    SAP Menu     Logistics  Materials Management  Purchasing  Master Data  Info Record  Create
    Transaction Code     ME11
    2.     Refer to the following file for details of the master data required: SMB99_ME11_O250_J01_Q15.TXT.
    4.3     Creating Output Condition Record
    Procedure
    1.     Access the activity using one of the following navigation options:
    SAP Menu     Logistics  Sales and Distribution  Master Data  Output  Shipping  Create
    Transaction Code     VV21
    2.     Refer to the following file for details of the master data required: SMB99_VV21_O229_J01_Q15.TXT.
    4.4     Creating Quality Info Record
    Use
    The purpose of this activity is to create the quality Info records for subcontracting.
    Procedure
    1.     Access the activity using one of the following navigation options:
    SAP Menu     Logistics à Quality Management à Quality Planning àLogistics Master Data  à Quality Info Record: Procurement à Create
    Transaction Code     QI01
    2.     Refer to the following file for details of the master data required: SMB18_QI01_O002_Q41_Q15.TXT.
    Result
    The Q-Info record has been created.
    4.5     Change material (add or replace values on Plant data/stor1 - Plant data/stor2.)
    Use
    The purpose of this activity is to add the storage condition to the appropriate material.
    Procedure
    1.     Access the activity using one of the following navigation options:
    SAP Menu     Logistics à Materials Management  Material Master  Material  Change  Immediately
    Transaction Code     MM02
    2.     Refer to the following file for details of the master data required: SMB10_MM02_O011_P02_Q15.TXT.
    Result
    The storage condition has been added to the material master.

  • TF400463 :Can not able to create team project in tfs 2013

    HI
    When am trying to create new project in TFS Collection I cant able to create a project. Since am getting the below error "TF400463 Project Creation failed with error: Object reference not set to an instance of an object"

    Hi
    since the problem not yet solved ... can you share some more details so that I can try it .. find the below error message which am getting ...
    Error Code : TF400463
    <v:shapetype coordsize="21600,21600" filled="f" id="_x0000_t75" o:preferrelative="t" o:spt="75" path="m@4@5l@4@11@9@11@9@5xe"
    stroked="f"><v:stroke joinstyle="miter"><v:formulas><v:f eqn="if lineDrawn pixelLineWidth 0"><v:f eqn="sum @0 1 0"><v:f eqn="sum 0 0 @1"><v:f eqn="prod @2 1 2"><v:f
    eqn="prod @3 21600 pixelWidth"><v:f eqn="prod @3 21600 pixelHeight">
      <v:f eqn="sum @0 0 1">
      <v:f eqn="prod @6 1 2">
      <v:f eqn="prod @7 21600 pixelWidth">
      <v:f eqn="sum @8 21600 0">
      <v:f eqn="prod @7 21600 pixelHeight">
      <v:f eqn="sum @10 21600 0">
     </v:f></v:f></v:f></v:f></v:f></v:f></v:f></v:f></v:f></v:f></v:f></v:f></v:formulas>
     <v:path gradientshapeok="t" o:connecttype="rect" o:extrusionok="f">
     <o:lock aspectratio="t" v:ext="edit">
    </o:lock></v:path></v:stroke></v:shapetype><v:shape alt="cid:[email protected]" id="_x0000_i1025" style="width:723pt;height:275.25pt;" type="#_x0000_t75">
    <v:imagedata o:href="cid:[email protected]" src="file:///C:\Users\arockia_kumar.ITLINFOSYS\AppData\Local\Temp\msohtmlclip1\01\clip_image001.jpg">
    </v:imagedata></v:shape>

  • Unable to create delivery through ME2O in subcontracting process

    Hi,
    I am trying to create delivery for the subcontracting order in ME2O, but it was giving the error. Stock also exist for component material.
    The error messange is:
    "An item with no delivery quantity is not permitted. Item will be deleted".
    Please let us know the reason.
    Thanks in advance!
    Thanks,
    Jana

    Hi
    Please check the Stock overview MMBE of the material, in the stcok overview check the stock qty click on
    details and check if any stock qty is reserved for any delivery.
    Usually the delivery is created but PGI is not done , in such cases systme reserves the stock for that delivery, in the sytem it shows that stock is availble but that may be reserved.
    Thanks & Regards
    Kishore

  • Can't able to create accounting-Version - 11i, AP

    Hi Friends,
    I had month end issue while reviewing the unaccounted transaction report we identified some unaccounted payments during May-11, tried to do accounting manually (Actionscreate accounting) but its throws APP-SQLAP-10710 (Online accounting could not be created. Please submit the payables accounting process instead to create accounting entries for this transaction.) but tried running Paybles accounting process program also but still its not creating accounting.
    Please advice on the same its urgent. Thanks…
    Note: I have 10 payments vouchers for same invoice among them 5 is accounted other 5 I cant able to create accouting.
    Thanks,
    Sri

    Hi Pillair,
    Sorry for late reply...
    Ya using CM, yes one of the payment was voided in this batch.
    Thanks,
    Sri

  • Can fill-able forms created in Acrobat 9 work with SharePoint 2013 workflow?

    Okay so here's the deal.....
    I have a few HR forms that need to be searchable and created as workflows in SharePoint 2013. Creating a custom list will not work because it is not a built to create forms. Integrating InfoPath would be ideal, but it will not work either because the company
    will not pay for Enterprise licensing.
    So my question is....what if I created a fill-able form in Acrobat and uploaded to SharePoint. Can I create a workflow from the document. The only question is, when the user fill out the form, where it will go? There is no submit button.
    I guess the REAL question is, other than InfoPath, is there a work around to having forms on SharePoint that can be created as a workflow and made searchable. Did I mention that the forms must be fill-able.
    Hope I make sense.
    artisticweb

    No, you cannot submit form values of a acrobat to SharePoint. You can use list form for basic form, else try using jquery to build custom forms as an alternative for infopath. Refer to the following codeplex solution. You could use this or build one similar
    to that using the source code.
    http://forms7.codeplex.com/
    --Cheers

  • Can't able to create workspace in DTR

    Hi Guys,
    In NWDS / DTR perspective, I created a client and able to login in to the client. But In Repository browser  when I right click I can't see "create workspace/ folder" option.
    I didnt understand whats the problem. I am using sneak preview NWDS 7 version. So can you guys please help me what should I do?
    Thanks in advance for your help!!
    Naresh.

    Hi Naresh,
    See if any of the following link helps:
    <a href="http://help.sap.com/saphelp_nw04/helpdata/en/aa/b6b314e7c74fb3a3fff3824d66d24f/frameset.htm">Creating the Workspaces - NW04</a>
    <a href="http://help.sap.com/saphelp_nw04s/helpdata/en/aa/b6b314e7c74fb3a3fff3824d66d24f/frameset.htm">Creating the Workspaces - NW04s</a>
    <a href="http://help.sap.com/saphelp_nw04/helpdata/en/b4/21b1cb5fc36a478fd6b7a992c05e55/frameset.htm">Creating Workspace Folders and Workspaces - NW04</a>
    <a href="http://help.sap.com/saphelp_nw04s/helpdata/en/b4/21b1cb5fc36a478fd6b7a992c05e55/frameset.htm">Creating Workspace Folders and Workspaces - NW04s</a>
    <a href="https://www.sdn.sap.com/irj/sdn/thread?threadID=10161">https://www.sdn.sap.com/irj/sdn/thread?threadID=10161</a>
    <a href="https://www.sdn.sap.com/irj/sdn/thread?threadID=157778">https://www.sdn.sap.com/irj/sdn/thread?threadID=157778</a>
    <a href="https://www.sdn.sap.com/irj/sdn/thread?threadID=54978">https://www.sdn.sap.com/irj/sdn/thread?threadID=54978</a>
    <a href="https://www.sdn.sap.com/irj/sdn/thread?threadID=25480">https://www.sdn.sap.com/irj/sdn/thread?threadID=25480</a>
    Bye
    Ankur
    Reward points if it helps!!

  • Can't able to create service entry sheet in ML81n

    Hi Team,
    one of our user is trying to create the service entry sheet in Ml81n while carrying out the service entry sheet it is asking for order number and an operation no usually it won't ask for the same,kindly can anyone help me for solution.
    Thanks

    Mention what account assignment you are using in SES or in PO?
    If it is PM order then you have to enter PM order.
    If it is cost center then check GL A/c used in a/c assignment that GL must be having field status as order mandatory. Ask your accounts team to check this GL.
    Hope this helps.
    Njoy SAP....

  • Can't able to create callable object using UI pattern in CAF

    Hello
    I made one interface using object Selection UI pattern for one of my entity services. Now i am trying to make a callable object using this and i also have been successfully created it. But when I test this callable object, I got these error messages.
    1. Could not load execution container: Cannot access object class loader for deployable object sap.com/cafcoregpuivisibleco~container.
    2. Could not load execution container: ComponentUsage(container): Active component must exist when getting interface controller. (Hint: Have you forgotten to create it with createComponent()? Should the lifecycle control of the component usage be "createOnDemand"?
    Please tell me the problem

    Hi Saurabh,
    It seems you found a bug. The problem is that runtime library reference to sap.com/cafruntimeuicouplingapilib library from sap.com/cafcoregpuivisibleco~container dc is misspelled.
    So, I don't know whether or not according CSN is already created but I can propose you a solution.
    1. Unpack the cafcoregpuivisibleco~container archive from CAFKM0X_0.sca sca.
    2. Unpack sap.comcafcoregpuivisiblecocontainer.wda archive.
    3. Open the PORTAL-INF\portalapp.xml file and change the following entry of library reference:
    <property name="LibrariesReference" value="sap.com/cafruntimeuicopulingapilib" />
    to
    <property name="LibrariesReference"    value="sap.com/cafruntimeuicouplingapilib"/>And pack
    it pack it again in correct order(for ex.:
    jar.exe -Mcvf sap.comcafcoregpuivisiblecocontainer.wda .
    jar.exe -Mcvf sap.comcafcoregpuivisiblecocontainer.sda .
    And finally deploy it to your server instance and enjoy.
    Best regards,
    Aliaksei

  • Can we able to create a scenario in XI like, RFC to JDBC

    Hello,
    I want to know whether  there is any way to create a scenarion like RFC to JDBC.
    RFC sends a rfc call with some parameters on sender side.
    JDBC stores the data in the receiver side.
    Thanks ,
    Prakash

    Hi Prakash,
    Step-by-step RFC to JDBC scenario:
    https://www.sdn.sap.com/irj/sdn/wiki?path=/display/xi/step%2bby%2bstep%2brfc%2bto%2bjdbc%2bscenario
    XI: How-to on JDBC receiver response:
    /people/siva.maranani/blog/2005/09/16/xi-how-to-on-jdbc-receiver-response
    -Pinkle

  • Unable to create delivery of Sales order

    while doing VL01N error message given by the system is
    'Material 5000004 is not defined for sales org. 2000 distr.chann.  lang. E' .
    Where i have to maintain distribution channel for material so that i can be able to create delivery.
    Thanks
    Parimal

    go to MM01, now give the new combination of your Sales organisation + Dist.channel fill up the Sale relevant data.
    Select the sales org1, sales org2, sales gen plant, sales text etc and fill up the data and save it.
    Now, your material is extended to the required  combination. You proceed now as normal.
    Another way is to go for common master on distribution channel in VOR1.
    In MM02, click on the "Additional data" button and fill up the language "English" here and save.

  • Error in creating delivery document from stock transport order

    hi sd gurus plz help i m nt able to create delivery in vl10b from stock transport order me21n after giving shipping point and  po number also. can u help me out and can u tell me how to maintain copy control from stock tarnsport to delivery docu.

    Hi Debesh,
    The settings for Delivery type for STO is maintained using the following path:
    Materials Management>Purchasing>Purchase Order>Set up Stock Transport Order>Assign Delivery Type and Checking Rule . Here you assign the Delivery type to Stock Transport order (with reference of Suplying Plant)
    For creation of STO for delivery creation use T-code- VL04. Enter the Relevant Shipping Point and the Delivery Creation Date. Also tick mark the option Purchase order. If you already have a Purchase order enter the no.
    System will show the details of the STO here by using the Main Menu > Delivery> Create Deliveries you can create the Delivery against the STO. Then by using the VL02n option you can do the Picking / PGI for the Delivery.
    Hope the above helps you.
    REWARD if it helps you!!
    Regards,
    Ajinkya

  • Create delivery for zero conformed qty

    Hi,
    In the sales order the order qty is 100 but due to no stock in plant the system is showing proposed availability date 10.06.2009.In availability control screen i did not accept the proposed date given by the system as i need to create the delivery doc for this 100 qty.In sales order the conformed qty is zero.Now the system is not allowing me to do delivery doc. Error messege is"   No schedule lines due for delivery up to the selected date" due to zero conformed qty in sch line.
    The requirement is instead of zero availability in sales order i can able to create delivery doc.After the material available we will do PGI in VL02N later.
    Is it possible in standard or any  userexit will be required.
    Regards
    Debasish

    Hi Friend,
    This can be possible by one setting at the item category level in the delivery document..
    Goto the transaction code OVLP and select your item category and in the display  you can see the CHECK QUANTITY 0
    In that field CHECK QUANTITY =0 mantain the value as BLANK which means you can create the delivery for the items without quantity.
    Please revert if you need any further help.
    regards,
    santosh