Cancel material exchange via ADSUBCON - subcontracting flow
Hi all,
I'm facing an issue related to the subcontracting process. Actually, a key user made an material exchange via the T code ADSUBCON and SAP system has created automatically a sub item line into the PO (item line 11 against its higher level item 10). Afterwards, the user has noted he made a mistake and now he wants to cancel the material exchange. He tried to cancel the sub item line 11 directly into the PO but SAP deletes also the higher level item 10.
My question is : How I can cancel the material exchange without deletion of the higher level item from SAP system ?
Thanks for your help.
Regards,
LYD
Hi,
If I set the deletion indicator to the sub item selected, the whole item gets deleted in the PO by SAP. but actually we do not want that SAP deletes also the main item. We need to keep this main item.
The customer would just like to reverse a material exchange made with T. code ADSUBCON.
I've just try with material without serial number it is working via T. code ADSUBCON. The deletion indicator is set only on the sub item into the PO. This is what we expect but when we try with material which has serial number, all item lines of the PO get deleltion indicator set.
Regards,
LYD
Similar Messages
-
How to cancel reversed document via MBST
Hi Gurus,
is there any way how to reverse material document cancellation? I mean revese document cancelled via MBST.
I tried procced via MBST, but got error M7067 (all items of the material.doc entered have already been reversed.
I need to process this step due to wrong period booking.
Thank you for help!Cancelation via MIGO does not help. Still got the same message as through MBST:
All items of document 5000900204 already cancelled/reversed
Message no. M7067
Diagnosis
All items of the material document entered have already been reversed.
System response
The system cannot take any items from this document for reversal.
Procedure
Do you want to display the list of cancelled material documents? -
Error While cancelling material document
Hi ,
I Want to cancel a material document which was posted some five months back in current period because already the period is closed and mean time the price of the material also has changed ,now while I am trying to cancel the document system throughs an error that document cannot be posted error in price determination what may be the cause and how to rectify.
Regards
kanthaHi Vijikantha,
If you are trying to cancel material documents created related to delivery, you can reverse the delivery through VL09. Any material documents for goods receipt can be cancelled through MBST. If there is a problem with the posting period, please take the help of Finance guy to open the previous period and try to post the document.
Best Regards
Srinivas -
Supersession(material exchange)in 3rd party PO(DIMP/IS Auto)
Hi,
Could anyone please tell how the material exchange is handled in supersession for 3rd party PO?
I tried to do material exchange in PO created against a sales order and I got the error message MPN01032 (This function is only possible for certain item types/The material exchange functions do not support the item category selected for the main item).
I believe the change should be done first from sales order to PO. For this the item in PO needs to be deleted. I am not sure if this is the correct way or if anything I am missing. How this can be handled on a daily basis by an interface ?
Your help would be much appreciated.
Thanks in advance,
anandHello Anand
Did you ever get to the bootm of this - I have exactly the same issue?
Any assistance would be greatly appreciated.
Regards
Tony
[email protected] -
How to clear the stock of material provided to vendor(subcontracting stock)
Hi SAP Gurus,
Please let me know how to clear the stock of material provided to vendor(subcontracting stock) and need your help in what senario this stock will show in " Matl prov. to vendor "
Thanks and Regards,
SHARAN.Hi Sharan,
Matl Povided to Vendor stock will appear in Subcontracting scenario.
If at all you have given some material to a subcontractor , this will be consumed automaticaly when you will recieve the ordered material from subcontractor.that is 543 movement will take place in the backgroung when u do the GR.
In case if u need to clear the stock u can do 542 and take the stock back to unrestricted.
Edited by: Donsandy on Jan 21, 2009 6:19 PM -
Material delta changes are not flowing into CRM
Dear All,
material delta changes are not flowing into CRM, because the product hierarchy on material has been changed to a new product hierarchy. I do not want to download again the object DNL_CUST_PROD1 because it maight cause inconstancies in CRM. (I have already defined some z product hierarchies in CRM)
Do I need to create the new product hierarchy also in CRM manually?
Appreciate any inputs
RajHi Raj,
Use the transacrion R3AR2 to create a z object for DNL_CUST_PROD1 and assign DNL_CUST_PROD1 as the object name
Then in request detail screen for new z object enter the details like table name (T179 in your case) and the name of the product hierarchy that you want to bring in. Save the transaction
Then use the transaction R3AR4 to initiate the download for your new z object as you normally do in R3AS.
Then go to SMW01 and reprosess the struck Bdoc.
Reward points if helps,
Regards,
Paul Kondaveeti -
How to cancell material document in decentralized scenario
Dear All,
How to cancel material document in a decentralized WM (WMS)??? I know that in a centralized scenario I should use MBST or VL09. Is there any solution?
I would be grateful if you help me.
PiotrekDear Piotr ,
If you want to cancel/reverse material document posted , you will enter into MBST and reverse it only.
For goods issues with delivery use VL09 as you have mentioned.
Other solution is enter material without referente , but you can have problem with traceability if you control receipts in your enterprise, because you have done one receipt without purchase documents.
And to finish you can adjust your stock doing an inventory document and adjust stock.
Best regards,
Carlos Moçatto -
Long Time: Fill Internal Header Table for VBUK via Doc. Flow Predeces
Good Morning Support,
I have installed DMIS (2006_1_620) and DMIS_CNT (2006_1_620), both atthe level of SP = 13. Data Base = Informix.
The activity "Header Fill Internal Table for Predicting Flow VBUK via Doc" is taking a long time in execution.
I wanted to create an index to improve performance according to the note 1256679 but I can not because the tables VBFA and VBFCL are "Table cluster" and I have no way to create index.
Any suggestions?I open the remote connection.
Thanks,
Hugo.Hello Hugo,
There are 2 ways out of this :
1. Either convert the Cluster Table to Transparent Table.
2. Enable Cluster Handling by setting P_CLU to Y. But in this case, you will have to set the parameter for all the 3 activities for VBUK i.e.
a) Fill Internal Header Table for Table VBUK (Initial) -
> TD05X_FILL_VBUK
b) Fill Internal Header Table for Table VBUK via Document Flow -
> TD05X_FILL_VBUK_1
c) Fill Internal Header Table for VBUK via Doc. Flow Predeces. -
> TD05X_FILL_VBUK_2
Then re-run the previous activities in the above order so that the cluster gets filled.
Hope this helps.
Regards,
Suman -
Block cancel material document after MIRO
Hello Guru
Is it possible to set config which it could block cancel material document in MIGO or MBST after invoice document in MIRO ?There is no provision in config cancel the document after the MIRO.
You only can block the payment which is the next step.
To cancel the material document, reverse the MIRO document and then cancel the material document. -
Cancel Material Doc.- Return to vendor created by Quality decision
Hi,
How to cancel material document which is created as Return to Vendor ( Mvt. type 122) using Usage decision in Quality module.
One bypass may be to recive GR agianst the PO.
Is there any other better solution than this?
KrishnaHi,
Yes. the best option is to receive returned parts w.r.t PO.(ie; GR with resp to PO), if there is no Z-Tcodes in place for this process.
Regards -
Fill Internal Header Table for VBUK via Doc. Flow Predeces.
Good Day,
I'd executed the step Fill Internal Header Table for VBUK via Doc. Flow Predeces in System Analysis Phase. It has been running for the past 7 days. We know that the problem might be that the "update statistics" is not updated since Febraury this year, this table has 20 million records.
Is there a possibility or how or where to find how much time is left, how many records it has been analyzed for this activity?
Thanks in advanced.
AnatoliiThank You very much dear colleagues for your advices and help!!!!!
I was able to resolve this problem with the following:
(as you told me before) Create standard M1 Index, in my case ZM1, with the field parameters VBEL, POSNV and VBELN ( MANDT it was not needed)
Using HINTS parameters from "Note 130480 - Database Hints in Open SQL for Oracle"
and changing the program: "CNV_TDMS_05_TI_I_CO_VBUK_2_C_N" in the sender system
before it was:
%_HINTS ORACLE 'full(VBFA) parallel(VBFA, 4)'. "#EC CI_NOFIRST
i was changed to:
%_HINTS ORACLE 'INDEX("&TABLE&" "VBFA~ZM1" "VBFA^ZM1")'. "#EC CI_NOFIRST
The Procedure finished successfully =)
With best regards,
Anatolii -
Changing "material status" via "project transfer"
HI,
I known that I can change the "material status" by transferring an item to a specific stock Locator that I already defined.
Is it possible to change the material status via project transfer?
For example my item's status is "active" and it was assigned to a project named "ACTV_PROJECT" I transfer this Item
to a random locator whose project is "HOLD_PROJECT". while I perform this transaction, item status will become "HOLD" (Hold is a status that I already defined)
Thanks for your
Help
CeyhunHi
I assume you refer to Item Status Control.
You can update the item status code using the designated form Item Status. This will automaticlly update the values of the following attributes -
BOM Allowed
• Build in WIP
• Customer Orders Enabled
• Internal Orders Enabled
• Invoice Enabled
• Transactable
• Purchasable
• Stockable
Project Transfer is a inventory transaction, that moves certain quantity of the item from one project locator to another project locator. Such transaction is not changing the item status.
Dina -
Subcontracting flow: outbound delivery & billing status
Hello,
I have the following subcontracting flow:
1) Create subcontracting purchase order
2) Create outbound delivery
3) Create and confirm transport order
3) Goods receipt of subcontracting components from subcontractor (101)
3) Register invoice document for subcontracting provider
However I have the following problems:
- The status of the inbound delivery remains "ongoing"
- In VF04 (billing due list) the system considers that the "client" (subcontracting provider) has not been invoiced. The billing type is F2 and it is not possible to invoice the delivery type NB (which seems correct).
Can anyone advise me about these issues (I'm not sure if they are related).
Thank you very much,
Annabelle R.The problem was that in the customizing the item category was relevant for billing, although in the subcontracting flow the subcontractor should not be invoiced.
So I updated SPRO: Sales and Distribution > Sales > Sales documents > Sales document item > Define Item Categories
with Delivery relevance: "None" instead of "A" (Delivery-related item document)
Now the subcontracting delivery does not appear in VF04 any more. -
Material Replacement in ECC, Material Exchange in 46C
There is this material replacement icon in ECC6 Item details.
When it is pressed, it copied the whole line item and create another record which refer to the original line item as higher level item.
Nevertheless in 46C, Material Exchange button, there will be error: "Material XXX has no defined relationship with Material XXX"
Questions:
1) Is this change of standard behaviour from 46C to ECC6
2) how to define the relationship
a) in 46C
b) in ECC6
3) how to change the ECC6 setting so that it will behave like the 46C with errorX-plant material status=blank in BD1 view of Mat Master
plant-specific material status=blank in Purchasing view of Mat Master
MM06=No entries
Anyone with a clue?
Regards,
Lars -
Table for cancel material docs
Can any body tell me the table name where I canget cancelled material documents ?
Regards,
VM - Learning MMhi,
You can select the transaction code of the relevant mat. doc been created by this field.
MKPF-TCODE2
So in MKPF you can filter the mat. docs which has "MBST" .
Here is the code for that,
Select MKPF-MBLNR into MKPF-MBLNR
from MKPF
where MKPF-TCODE2 = "MBST".
And also if you want to get the reference documents of the canceled docs then go to MSEG and find "MSEG-SMBLN" and that contains the reference doc of the canceled doc.
Hope this will useful,.
Thanks & BR
sandun
Maybe you are looking for
-
Problem in Distributed transaction with Oracle 8.1.7 and Weblogic 7.0
Hi, I am using two unmanaged weblogic 7.0 servers and oracle 8.1.7 enterprise edition. I am using oracle.jdbc.xa.client.OracleXADataSource for creating connection pool in weblogic. The pool gets created fine bu
-
Class not found error when jar in war file
I am using Java Creator 2 and have a project. The required libraries have been added to the library manager and the "package" checkbox has been checked. This means they will be added to the deployment. After deployment, I check the war file and it co
-
Hello, I've recently purchased Mainstage 2.2, and Reason 6.5 on a MacBook Pro with 10.7.4 and 8gigs of RAM. I can't seem to get Reason to talk to mainstage via ReWire. I've tried running both apps as 32 and 64 bit, and of course I launch Mainstage
-
Tuning Oracle Integration Adapters for Performance
Hi, I would like to know about tuning Oracle Applications adapter for performnace . I got a document for performance tuning of BPEL PM. I am searching for similar kind of document which helps to fine tune the adapters for performance. Please help me
-
[Universal Apps] Working around XamlRenderingBackgroundTask restrictions
Hi, I'm still trying to wrap my head around the introduction of the XamlRenderingBackgroundTask for Universal apps. I'm currently planning my next app and I want it to have custom XAML bitmaps on tiles. Now I have a few questions on this: All samples