Cannot see pick list on releasing production order for WH managed material.

Hi guys
I created workcenters, routing, bom, control cycle record and prod. verison for the material before creating the Prod. order. Now, I am neither able to see the Pick List nor Material Staging (Simulation) after releasing my Prod. Order. The exact error is "No WM relevant components exist". All my materials are warehouse managed.
Any help gurus??
Regards,

Hi
you are mentiuoning that control cycle .
Have assigned the coponents to the storage location which is assigned to ware house.
pl. chk this.
Regards
YMREDDY

Similar Messages

  • Cannot release production order for a plant

    Hi:
    When I try to release a process order , I get this error message:
    "CAnnot release production order for plant".
    I get this message  for a particular material in the plant. For other materials, it's working fine.
    Please give your suggestions!
    Gautham

    Hi,
    Check the Tasklist usage for your routing for that material.
    For this usage ,check in op45 against the task list type whether until release indicator has been enabled.If so remove
    and do the release.
    or
    check whether workcenter which is used for producing the   material has been locked in work center itself.
    Indicator: Usage only until release in orderIndicator used to specify for a task list usage and a task list type that an operation in the order cannot be released.  This occurs when a work center group that is not intended for production is allocated to this operation.
    When this type of operation in the order is released you must enter the work center where production should take place.
    Regards,
    nandha

  • Costing the production order for the configured material

    We are trying to cost the production order for a configurable item.  But the system is not calculating any cost in the production order.  Sales order related to this configurable material is costed.  What additional setting I need to cost the production order for the configured material ?

    Hi Niki
    If your SO is costed, thats enough from a System's perspective... Planned cost will be the sales order cost estimate because SO saves the Chars required for the Configurable material
    Planned cost in Prod order depends on the Costing variant you have assigned in the order type... Check the error log if there is any error in cost calculation in prod order
    br, Ajay M

  • Pick List and Open Production Order

    Our WMS clerk confused about open Production Order and Pick up due list for the Production Order.We want to check the list of open production order and what are the materials due for picking up the open production order   Please suggest us the best way you are doing for your Production Order.
    Thanks

    Nick,
    Co27 will give only open orders and materials to be picked.
    Open production orders mean - orders which are not teco/closed/deleted.
    All the materials will appear in the list which have a status - FInal issue not ticked.
    You can slos use coois
    with list = components
    profile = picking profile.
    here we have more options.
    please come back if required.

  • Error in GR for a Production Order for a particular material....Unique case

    Hi Dear Gurus,
    I am facing the following problem:
    There is a production order for a material (say X, matrl type FERT) of order qty 21EA. First we did GR of qty 9EA. but when we are going to do GR for the rest of the qty i.e.12EA it is not happening system showing Error message " Account XXXXX requires an assignment to a CO object".
    But while we are going to do GR for the rest 12Ea qty in two parts i.e. first by doing GR of 11EA then 1EA system is accepting.
    Interestingly if do the GR for the same order as first by 8EA and then the rest 13EA that is also accepting.
    Eventhough, for any other material (of same type and group) if we make a production order of the same 21EA and then doing GR firstly by 9Ea and then 12EA that is also getting posted properly.
    What would be the reason for the error message for that particular case?
    Here the system is SAP4.5B version, material MRP type is M0, lot size  FX & fixed lot size 10Ea, safety stock 8EA, Reorder point 15.
    Thanks in advance for your inputs.
    Regards,
    Arghya

    REfer this link..
    [https://forums.sdn.sap.com/click.jspa?searchID=25161817&messageID=7040673]
    [https://forums.sdn.sap.com/click.jspa?searchID=25161817&messageID=7159723]
    hope the above helps..
    karthick

  • Don't release Production Order for negative stock.

    Actually i don't want Production Order to be released, if component (child) items falls into negative stock. Is there any solution for that. If yes, please help me out.
    Thanks

    HI!
    you can write a SP to block Release a production order from planned state.
    Check the onHand stock of all child items w.r.t the warehouse and block updating the status to release

  • Batch management in production order for WM managed components

    Hi Experts,
    Iam having WM managed components in my production order which are batch managed as well. I have to do batch determination for these WM managed components.
    I would like to know the steps involved in it and the required configuration.
    Can anybody throw some light on this please
    Thanks & Regards
    Enrico

    Enrico,
    For setting up Batch determination in production order please follow
    [Batch determination in production order|http://help.sap.com/saphelp_470/helpdata/en/25/283c3f4f7811d18a150000e816ae6e/frameset.htm]
    http://help.sap.com/saphelp_470/helpdata/en/25/283c3f4f7811d18a150000e816ae6e/frameset.htm
    As far as WM managed components it will still be the same as WM transfer order is created only after goods movement document is posted.
    Hope this helps. Else please come back.
    thanks,
    Ram

  • How get all released production orders

    Hi experts,
    I need to get all released Production Orders for a specific plant. I noticed that usually you don´t select directly from table AUFK. Most of people use function module WCFS_STTXT_GET to get the status of an order. I know that table AUFK has fields ASTNR (status) and PHAS1 (released) however those fields don't reflect the status of an order (thatu2019s why WCFS_STTXT_GET is used).
    Also, I know that table JEST contains status for an order; however, for a simple order that table shows more than one status (I guess is like a history of all status the order had).
    So my question is: How can I get all released orders for an specific plant? If I use WCFS_STTXT_GET I would have to select all orders and check the status one by one, which is obviously not efficient at all.
    Thanks!

    Hi Carlos,
       As far as i know, it is not possible to get the latest status on a production order. if we see a production order in CO03, we see that all the status' are displayed on the order which it has been through.
    I remember we had to include the system status logic similar to the transaction COHV, and we had used the table JEST for the same.
    Kindly update the solution if you find any.
    Thanks.

  • Production Order for a material without BOM and Routing

    Is it possible to create a production order for a given material without routing and BOM, I know we can
    create a production order for a material without a BOM (with a default routing) just wanted to check with
    the above criteria
    Thanks in Advance!!

    Members:
    Thank you for your valuable replies and time
    Santosh:
    Tried what you have mentioned, but system still picks up a default routing
    Kaushik:
    Maintained Default values in OPJG for the given order type, but system still picks up
    default routing
    Mangalraj:
    have no issue in creating a production order without a BOM, but I am trying to see
    is there a way where I can create a production order without a BOM and routing (not
    even default operation )
    Any suggestions on how to create a production order for a material without a BOM
    and routing (not even default one )

  • Error while converting planned order to production order for config materia

    Hi experts,
    While converting a planned order to production order for a configurable material.I am getting the following error meassage. Message No.CO684,
    "You cannot make an assignment to make-to-order stock"
    ( DiagnosisThe component cannot be allocated to an individual stock because make-to-order production and engineer-to-order production cannot be executed with this order.
    A possible cause is that you are trying to create an order with reference to a sales-order/project, where an account assignment to a sales order/project is not allowed in the settlement profile that is assigned to the chosen order type. This is inconsistant.
    System ResponseThe following responses are possible:
    Order processing is cancelled.
    The system resets the special stock indicator back to the original value.
    Procedure
    Choose another order type).
    I have checked some of the threads related to this error. But no where there is any solution.Please tell me if there is any settings to make so as to work on this scenario.
    Thanks,
    Sham

    Hi,
    This will be a MTO scenario. Please check your requirement type,Requirement class and strategy type config along with your Item category and schedule line category from SD.
    Also check your Production order type config and settlement profiles.
    I mean to say that you need new production order type to be configured for specific above mentioned combination.
    Are you working on a production system..?? is it the first time you are creating the order for this config material..??
    Regards,

  • How to get a list of production orders for a work center?

    Hello SDN Community, 
    I have an requirement to display in a pop-up window a list of production orders for a work center.
    Does anyone know which screens/transactions would show this relationship?
    Or better yet, does anyone know how to demonstrate this from the tables themselves?
    Thank you,
    Dean Atteberry.

    Hello Mangalraj.S
    >>Goto COOIS-->For the field List select PPIOO000 - operations and layout -->standard layout
    >>and execute,by this you will be able to see the operations for each order and to which
    >>work center they are assigned.
    The system I am working on is ECC 6.0.
    For this system the values in the dropdown for the "List" field are "Capacities, Items, Order Headers, Sequences, Trigger Points, etc".  But nothing that says PPIOO000 - operations and layout.
    >>Or else in the in input screen of COOIS,enter the work center for which you want to see which
    >>are the production order's assigned and execute.
    For system I am working in, I do get a grid display when entering a work center.  It has columns like "Order, Material, Icon, Order Type, MRP cntrlr, etc."   But no column with Work Center.
    Any further insight into how to use this transaction to display a list of production orders for a work center would be greatly appreciated.
    Thank you,
    Dean Atteberry.

  • Releasing production order using workflows from outlook.

    Hi  ,
    i am working on workflows and my scenario is whenever production order creates it will send mail to approver in his/her outlook. And approver will approve/reject from outlook only by just clicking on approve or reject tab.
    As of now mail is coming from SAP to outlook but the problem is how to release production order by just clicking on approve or reject tab in mail.
    please help on this its urgent.
    point will be awarded.
    Edited by: Rahul Bhasin on Dec 27, 2007 7:00 AM

    Hi satish,
    Thanks for ur reply first .
    as u told me create an event for relaesing production order , but as per my knowledge event are somethings that gets trigger at some point like creation , deletion. with events one cannot process things those are only for alerts so please confirm the same and how to process it.
    Thanks,
    Rahul

  • List of Open Production orders

    Hi all,
    How to find the list of open production orders. Is there a transaction to find the list of open production orders.
    Regards
    Hemanth

    Hi,
    With COOIS you can check the Open Production Orders.
    For this you need to create a new Status Profile, in this you need to set the system statuses like below.
    Transaction BS42..
    Active PCNF, PDLV etc.
    Not active CNF, DLV, TECO, DLFL, DLT etc..
    Regards,
    Siva

  • Material shortage ( soft or hard error ) while releasing production order?

    Hi Guys
    I  am a SAP tech guy wrote a BDC program to release production order. It worked fine in one enviroment but not working another enviroment saying ..Material shortage.
    My BDC program can't afford any hard errors in the process. The execution stop abruptly for any hard error.
    How to change that Material shortage from hard error to soft error or any info message.
    Any ideas? any thing to do with material master or spro?
    Thanks
    Hari

    Hi
    You can make settings in SPRO, so that the material availability check will not restrict you to go further...
    follow the path:
    SPRO>Production->Shop floor control>Operations->Availability Check-->Scope of check
    There you will find the settings for order creation and release (1 & 2)..
    You have remove the restriction there.
    Regards
    Bala

  • Abap dump error while release Production order

    Dear Gurus,
                          Abap dump error is creating while release production order , pour some light on this issue.
    Regards,
    Kamal

    Hello,
      use transaction ST22 to analyze the error type. There you have the detail of the error message, the program and the line of the ABAP code where the dump was triggered.
    Best regards,
    Andrea

Maybe you are looking for

  • What to delete on internal HD if using external HD for storage

    Need to free up mac mini 2010 HD space of 200 GB of music.  Currently have an EHD as a backup and may add another for backup.  What gets deleted on the internal HD if I have my itunes backed up to the two EHDs.  I deleted somethiong on my emac years

  • Status in  BAPI_SALESORDER_CREATEFROMDAT2

    Hello, I am using above mentioned FM to create a sales order, i have to make status completed (INDL)for item during the creation,is there any field to do this purpose. Would appreciate if anyone let me know answer. Regards, Suresh

  • Still image that shimmies and shakes

    There are 2 still images in this piece I'm finishing up that that shimmy and shake. They are only on the sreen for 3 seconds, but it's noticeable. I thought I'd found the answer when I pulled them ouf of the Timeline, into the Viewer to have a look,

  • Best way to transmit data

    Hi, I have an application which uses HTTP requests to send and receive data from a C server. On the server I have an array of structs, the information in which is changed frequently. I want to be able to send (on request) the data in this array to th

  • WL-10.3.5 Error Creating Wildcard Hostname Verifier for Facebook OAuth

    Hi, I am writing an application that uses OAuth for 3rd party login. However, Weblogic 10.3.5 does not by default accept the way Facebook uses a wildcard in their SSL Certificate. Caused By: javax.net.ssl.SSLKeyException: [Security:090504]Certificate