Cant Assign Plant to Shipping Point

Dear Gurus,
I've defined my Plant then later defined my shipping points. When it came to OVXC I could not see my plant so therefore I could not assign my shipping points to it. What is the reason for this .. did I miss a step? Thanks in advance.
Best Regards,
Jin

go to define plant and see whether ur plant is appearing there and whether u have maintained the address for the plant, if yes check whether u have maintained these things:
1.define sales org.
2.defien division
3.define sales office.
4.define shipping point.(check if u have maintained the address for the shipping point)
5.assign sales org. to company code
6.assign distribution channel to sales org.
7.assign division to sales org.
8.set up sales area
9.assign sales office to sales area
10.assign sales org, dist.channel to plant
11assign shipping point to plant

Similar Messages

  • Plant and Shipping point assignment

    Dear All,
    As a standard process we have copied the plants and shipping points in the development client and i have deleted the default shipping point and assigned the newly defined shipping point.I have forgotten to assign one plant and shipping point and i have even deleted the default shipping point.Now i have to assign the plant x to the shipping point x where i am not able to find the plant in the  ovxc screen.Is there any way to find the missing plant or i have to delete all the assignments and reassign again.
    Help required as early as possible.
    Thanks in advance,
    Ramesh.

    1)  Check in OX10 whether you could see that plant
    2)  Check in OVXD whether you could see that shipping point
    If the answer to both is yes, then you should be able to see in OVXC also.  If not, better try to delete in the above areas also, recreate and then check in OVXC
    thanks
    G. Lakshmipathi

  • How to get automatic plant and shipping point and storage location

    hi,
    sap gurus,
    how to get automatic plant and shipping point and storage location automatically into the sales order
    i have done all the config settings for that
    but its not appearing automatically.
    regards,
    balaji.t

    Hi
    Balaji...
    U can get the plant in sales order,  by doing the default the same in customer master or in  material master. In customer master -- sales are data--shipping tab delivering plant there u can assign and get the same in order for that customer. it is better to do in customer master rather than in material master.
    Shipping point is getting determine in sales order and u can not make it default like plant. Shipping point is determine in the basis of Shipping condition of customer ( ship to party)+ loading group of material + Deliverying plant there u have to assing the shipping point and it will flow in the sales order. Tcode OVL2
    For S loc u have to enter manually in the sales order u can not get it automatically.
    Hope this will help you.
    Thx.

  • Relation between plant and shipping point

    Hi all,
    my simple question is,  what is the relation between plant and shipping point ?
    in book i read, it is                      many to many,
    but in some web link it is showing 1 to many
    what is the logic behind these two ans.
    pls tell me the ans...
    Regards
    Avinash

    Hi Hegal . K . Charles,
    it is correct,  as we discussed above it may be MANY to MANY .
    Suppose, we hv 2 plant 1 in delhi and 2nd in nagpur. and this company want to export via inland water ways, in this case we can assign mumbai port to delhi and nagpur plant as well.
    as you said it is correct, It is just  not to overload the master data maintenance 
    Ex- In case of Sales Org. Its is always advisable to keep it minimum to per company code. Because master data records are multiplied by each additional org. element.

  • Plant and shipping point have no connection but still order got created.

    Hi All,
    An order was created and subsequenty delivered and invoiced. Later on the goods were returned.
    The problem which occured is that the return order have plant A  and shipping point B, which are in no way connected to each other. There is no configuration done to attach this two, still the order got created.
    I wanted to know even if plant and shipping point is different, can a order be created and saved.
    Please giude me.
    Regards,
    Satish.

    yes Satish
    this is possible, take a scenario, suppose one company is having 3 plants A,B,C with shipping point A1,B1,AND C1 respectively. But the requirement is such that they will collect the material from plant A and deliver it form B1 shiiping point which is linked with plant B.
    so it is possible to create and save order if plant and shipping point is different.
    bye

  • Available plants & redetermine shipping point

    Hi experts, i have two problems. First, i will describe the situation and then the problem.
    in our system , we maintain delivery plant field into customer master. From this reason, when i create a sales order, SAP copy this plant as default value in sales order.
    Let's assume that we make a sales order for customer 10 which has plant P1 as default delivery plant.   And material M1 with following available stock:
    - in M1 plant 0 qty
    - in M2 plant 10 qty.
    First problem:
    In this case , when i create a sales order, SAP will propose automatically P1 as delivering plant, but in P1 there are no stock (0 qty). Is there any way to propose automatically another plant  when in proposed plant there are no available stock ?
    Second problem:
    In our system we have some generic materials which always will be delivered and shipped from one plant. So, let's assume that this plant is P1. If a customer has default plant P2, then in sales order will copy default plant from customer master. I solve this problem from a user exit (userexit_move_field_to_vbap) -- i make some modifications-- but the real problem is that, when i do this forced change, shipping point is not redetermined. 
    Is there any way to redetermine shipping point in this case (forced change of delivery plant) ?
    I give you an example:
    -customer 10, default plant P1
    -material MG01 (this material should always deliver from plant X1, shipping point X1)
    - two shippping points: P1 and X1
    When i create the sales order, SAP propose automatically P1 as default plant...but in background, in user exit userexit_move_field_to_vbap i have some modifications: if material is MG01 then plant would be X1. But , in this case, shipping point will be determined based on old plant (P1) not based on new forced change plant (X1) so shipping point will be P1 instead of X1. So, is there any way to redetermne shipping point ?
    Thanks in advance.

    Hi,
    Is there any way to propose automatically another plant when in proposed plant there are no available stock
    As fara s my understanding there is no automatic replacement of plant.you can do it manually
    For determining shipping point as you used userexit for plant as like this you can force to change shipping point.
    Kapil

  • Plant Switzerland -- Shipping point Germany

    Hello SAP masters!
    We have our plant in Switzerland and some shipping points to this plant in Germany.
    Is this with SAP possible?
    Or we need for the shipping points in Germany a separte plant also in Germany?
    Thanks for your held?
    Best wishes
    Petra Schober

    Technically there is no problem to make this happen, even the shipping point has its own adress which is different from the plant adress. But technically these are just numbers that get assigned to each other.
    From a logistics point of view, I see already an inconsistency.
    If the plant is in Switzerland, how can you ship then from Germany?
    You have to get the materials to Germany first to be physically able to ship from there. Of course you can set up a storage location to your Swiss plant that is located in Germany.
    Germany is in EU, Switzerland not, so you might get bigger issues with necessary legal reporting to tax authorities as well as statistical offices (Intrastat report) with this setup.
    Best you meet with Finance guys to talk about requirement and setup.

  • Plant and shipping point is determined at Header or item level?

    Hi,
    Shipping point is determined at Header level or item level of Sales order?
    How about Plant??
    Thanks!!

    Both Shipping point & Plant are determined for each Item in the Sales order automatically by the system.
    For determining Plant, system first search the CMIR,
    if not found the Plant there or CMIR is maintained then system searches Customer master of the SH, i
    f here also not found then system sarches the Material master.
    This is called Priority rule which is hard coded in SAP and can be changed by customisation.
    For determining Shipping point, system takes three fields into consideration, they are
    1. Shipping condition (first check Sales doc type , if not found then takes from Customer master of SP)
    2. Loading group ( material master> sales org group 2)
    3. Delivering Plant
    So, they are (Shipping point & Plant ) item specific data in sales order.

  • OVL2 Is showing not maintained shipping point determination even i have maintained

    Dear SD Experts  ,
    It seems Basic question but i have maintained all settings properly but still issue is same please let me know
    Issue is while creating sales order in VA01
    And i have properly maintained In OVL2
    But when i have checked in OVL2 That information is not Populating, but when trying to Maintain New one again but system is showing all ready Maintained
    Here showing Like not maintained even i have maintained
    CMR, And VOV8 Also same Maintained
    MMR
    Finally assigning plant to shipping point
    So tell me why OVL2 Is showing not maintained shipping point determination even i have maintained
    Even Not Maintained OVL2 Shipping point details combination for plant system is showing
    Any entry is maintained all ready ,,
    Side Note : Recently Installed Ides and Doing testing on this so some time First time this problem is coming ?

    Dear Venu Gopal,
    Here while creating configuration in you IDES system , you taken existing 1000 as company code and under that you created your plant and shipping point . sometimes while creating or assignment of plant, sales origination ,distribution channel, shipping point you taken reference and created your own plant, sales origination, shipping point  at that time shipping point determination also taken as a copy and created . so you got this type of error . these type of errors will occur usually while copying .
    so kindly select the particular line item and delete then save ,after saving then you create your own then only system will accept other wise it will show this error .
    see the below screen shot .
    Regards,
    C.B Reddy.

  • Assign Shipping Point to Plant

    Hello Everybody,
    I Created a plant and shipping point in IMG config. However, when I tried to assign the shipping point to the plant via OVXC I couldn't find the plant. Did i miss something?
    Please help.
    Thanks,
    Sirisha Matta

    Hi,
    You also need to assign the plant to the sales area & distribution channel. After making those settings, you will be able to assign a shipping point.
    MdZ

  • Assigning Printers to Specific Shipping Points

    Hi,
    Our system has multiple Sales Organisations, within each - one plant/warehouse/shipping point.
    I have added additional plants to a few of these sales orgs, along with the relative warehouse and shipping point.
    Sales users now have the option of selecting a plant when in a sales order - depending on stock availability at each. We successfully have multiple deliveries generating for differnt plants, under 1 sales order.
    However:
    I don't know how to assign a separate printer device to each shipping point/plant. The plants are separate warehouse locations therefore it needs to be automatic.
    I've tried VP01SHP, however all 60 shipping points that alreeady existed showed the same data, there must be somewhere else that defines them to a separate device?
    Any help greatly appreciated.
    Dan

    Go through this IMG path to find the settings about LD00 output type (as shipping point related data will be maintain in appl V2).
    SPRO path
    IMG - LE - Shipping - Basic Shipping Functions - Output Control - Output Determination - Maintain Output Determination for Outbound Deliveries - Maintain Output Types, here you can find the LD00 Output type.
    For more settings go through this IMG steps
    -Maintain Condition Tables, 21-DlvType/Shipping Point
    -Maintain Output Types, LD00 (Std Access sequence 0005-SalesOrg/Customer), so, to modify create Z Output type by copying LD00 and .
    -Maintain Access Sequences, try 0010-DlvType/Shipping Point
    -Maintain Output Determination Procedure, V10000-Header Output
    -Assign Output Determination Procedures
    Hope this can assist you in understanding or refer [output determination|http://wiki.sdn.sap.com/wiki/pages/viewpage.action?spaceKey=ERPLO&title=outputdeterminationusingconditiontechnique&decorator=printable] for the same.
    Thanks & Regards
    JP

  • Shipping point ZHYD is still assigned to a picking

    HI Experts,
    I have created ZHYD shipping point through copy from 1000 shipping point. Now i am going to assignment but the shipping point ZHYD is assigned all plantsu2019 am trying to delete all plants except ZHYD.but system showing fallowing error message,
    Shipping point ZHYD is still assigned to a picking
    Please advice how can i over write this problem.
    Thanks in advance,
    Chandhu

    Hi,
    Refer Error in deleting shipping point assigned to plant
    regards

  • Deliveries that belong to different shipping point assigned to shipments

    Hi,
    We have a scenario, where we have one plant - one shipping point and one transportation planning point.
    Users in the traaffic department are able to (human error) assign deliveries that belong to different shipping point to one shipment. In our case user is trying to create a shipment for canada warehouse by mistake he assigned couple of deliveries that belong to one of US warehouse. Is tehre any setting in the system to restrict this.
    thank you

    hi,
    Unfortunately into selection of deliveries there is no authority check for the shipping point.
    User only selects deliveries but not display/change.. Here it is when check is done but not
    at selection.
    It could only be achieved under modification into LV56LF01 FORM alle_lieferungen_lesen
    adding a check for authority object v_likp_VST.
    Good luck,
    david

  • Shipping point and Plant in CRM 4.0

    Hi experts,
    Where do i find Plant and Shipping point in CRM Sales transaction? of CRM 4.0 version.
    Thanks in advance.
    Regards,
    DV.

    Hi DV,
    For sales order exchange scenarios please check the following notes:
    541113 - Data exchange scenarios for orders (CRM-R/3)
    511074 - Change of CRM documents in R/3 Backend System, part 1
    520045 - Change of CRM documents in the R/3 Backend System, part 2
    705200 - Data exchange - Scenario X, Y and Z (old version)
    889051 - Scenario A: Overview and settings (new version of 705200)
    620139 - Scenario A: Interdependent changes in sales documents - R/3
    Kind regards,
    KZ

  • Assignment transportation zone at the same shipping point

    Hi Experts
    How can I affect several transport zones at the same shipping point (OVL7)?
    Thanks
    Hachim

    Hi Hachim,
    The transportation zone has to be unique: It is the starting point assigned to the shipping point.
    Why do you believe you need several transportation zones?
    Regards,
    Franck

Maybe you are looking for

  • Cash Management - AutoRecon without errors, but still unreconciled?

    Hi guys, Pretty interesting question: I have multy period's bank file (transactions for 3 accounting periods), all settings are according the manual on AP and CM sides done. Statement's Import finished without errors, AutoReconciliation finished with

  • How to add AS JAVA system in Solution Manager

    Hi all,        we have installed Solution Manager, now i wanna add Enterprise portal sysyetm in SMSY.can anyone tel me the steps pls rgds, rajesh

  • Xilinx version availability for labview fpga compile

    While trying to compile a Labview vi for target NI PXI 7831R, at first I didn't have any Xilinx compile so I asked my network guy to instal it.  Now it complains that it needs 10.1 when 11.5 is available.  I asked him to install the 10.1 and he did b

  • 10.1.3.3.0 Request invoke issue

    Hi, Currently I have 10.1.3.3.0 Linux redhat application server. When I deploy following jsp and invoking from browser http://myname/testJSP, after 5 minutes I can see System.out.println("*****Start**** " ); message again. for example in log file Sys

  • Variable-length word builder

    Could someone please help me find out why this doesn't work. It supposed to build multi-byte values with variable byte lengths. Positive values below 64 bits work, but not negative values. int byteSize = whatever; int bitSize = whatever; byte[] buffe