Dear EH&S people,
I am trying to upload a vendor MSDS'. I am not succesfull in this. The reason is that the status of the generation variant is not "Released".
I am not able to set the status released in the Generation variant. I am using report category IBD_MSD which should be the standerd one for Vendor MSDS.
Together with an abap consultant we found via debugging of the matchcoded of the search of the status that he takes the DMS document type SBR as a basis. It should however be IBD.
Has somebody encounter this problem before and have a solution for this?
Is there somewhere customizing which controls for a certain category which DMS document type to use?
Thanks in advance for your answer.
Regards,
Pascal

Hi All,
I found the solution.
I looked at the detailed customizing of the document type SBR. Note 1091699 explained detailed settings of the different document types.
SBR was not correct customized.
It sounds strange that SBR is used for the report generation status for Vendor MSDS. I think it is because SAP treads it as if it is a raw version. So that could be an explenation why it searches for the status of that document type.
After I updated the SBR-type correctly, I was succesfull in uploading Vendor MSDS. The DMS type which was used to save the document was IBD.
Thanks all for your help.
Issue closed.
Regards,
Pascal

Similar Messages

  • How to set the Release Strategy without classification for PR

    Hi,
    I am able to set Release Strategy for PO with classification, however, now I want to set the Release Strategy for PR with classification. Can someone tell how to proceed to set the Release Strategy to PR with Account Assignment.
    I crated the Release Codes, however not able to find what options to choose in the following steps :-
    Release indicator
    Assign Release Indicators
    Release Points: Prerequisites
    Determination of Release Strategy
    Regards,
    Yogesh

    1. Release codes                                                            
       Create the release codes.     For  Purch. Officer, Manager and Sr. Manager                                                                               
    Like PO, MG, SM                                      
    2. Release indicators                                                       
       Define release indicators and branch to the detail screen. Here you      
       define whether fixed purchase requisitions may be changed by Materials   
       Planning, for example, and whether an RFQ or a purchase order may be     
       created from the requisition.                                            
       You can also determine the field selection here.                                                                               
    In the area "Changes after the start of the release procedure", you      
       specify whether a requisition may be changed after the release           
       procedure has begun. You specify whether the strategy has to be          
       redetermined after changes, or whether the release procedure has to      
       start all over again from the beginning.                                                                               
    This parameter bears a relation to the parameter "Value change". For     
       example, previous releases are not cancelled if the value of the         
       requisition item after the change does not exceed plus 10% of its        
       original value.                                                                               
    Attention:                                                               
       Be sure to create a release indicator (e.g. B for "blocked") that        
       serves as the starting point for subsequent indicators. Do not set the   
       indicators for release for the issue of RFQs and PO on the detail        
       screen for this indicator.                                               
       Also create a release indicator characterizing the released status.      
       Set the indicators for release for the issue of RFQs and PO on the       
       detail screen.                                                           
    You can use sytem defined indicator in this case you don’t have to do anything                                                                               
    3. Assignment of release indicators                                         
       Assign a release indicator in dependence on the status of the release.                                                                               
    Example:                                                                 
       You create a release strategy S1 consisting of two release codes 01      
       and 02. Release with 01 is a prerequisite for release with 02. If        
       release has been effected with 01, the requisition has been given the    
       "all clear" for the issue of RFQs.                                       
       You have created the release indicators B (blocked), 1 (cleared for      
       issue of RFQs) and 2 (cleared for RFQs and PO).                          
       Now enter the following as assignment:                                                                               
    Strategy   C1  C2  C3 ...                                                
       S1                          B (blocked)                                  
       S1         X                1 (RFQ)                                      
       S1         X   X            2 (RFQ/PO)                                                                               
    4. Release prerequisites                                                    
       Define which release codes are involved in a release strategy. Specify   
       whether a code is set for a release status following release, and        
       whether one release status is a prerequisite for another (+).            
       Example:                                                                 
      Strategy   Code  C1  C2  C3 ...                                  
    S1         01    X                                               
    S1         02    +   X                                                                               
    5. Determination of the release strategy                            
    Determine the conditions under which each release strategy is    
    assigned. The criteria are account assignment category, material 
    group, plant, and value of the requisition item.                                                                               
    Here you can define the you criteria but one thing you keep in mind that you hae to define all criteria.
    E.G if you will not define the Material group here but it will default in req in that case this will not work that’s the reason you have to work with Classification.               
    <b>In the classification whatever criteria you need that only you have to include like in your case you care about A/C category and value only.     </b>

  • Table entry for Valuation variant for material prices

    We want to define a valuation variant for costing run.  In that we need to select the material price based on the plan price.  We have provision of entering three plan prices in the Costing tab-2 in the material master.  But we want to enter plan  prices for more than three dates. For this, we propose to enter the dates and prices in a separate table and that table needs to be accessed in the valuation variant for material prices closest to the date of valuation.  How we can go about this ?

    Hi
    When you create Valuation Variant, choose Strategy U i.e. Price from userexit
    Then code the exit COPCP0005 with the help of ABAP consultant
    The logic should be:
    a. Refer the "costing date from" entered in Ck11N
    b. refer the Z table... and pick the price relevant on that date
    br, Ajay M

  • Breakpoint was not set due to a generation error

    Hi,
    I have this problem, there is a transaction that doesn’t execute in the productive environment, BUT the transaction can be executed in quality and DEV environment.
    So when I set a breakpoint (in productive), this message come up “Breakpoint was not set due to a generation error for ZCO_AllTheJazz_DETAIL” (the program).
    The Question is: WHAT does it means and HOW can I fix it?
    Any suggestions are welcome
    Ubadawan

    Ok sorry max I didn't think that the name was important.
    The name is ZCO_OBJECT_CO_DETAIL
    The message number is ED057 and its main program is SAPLSHL2.
    Im going to explain some more, when I execute the transaction a screen with the syntax error (like you said Rob) said:
    The following syntax error occurred in the program ZCO_OBJECT_CO_DETEAIL. "Field 'G_GLOBAL_OBJECT-HIEART' is unknown"
    The thing is, I checked and is declared on
    INCLUDE ZCO_OBJECT_CO_DETAIL_top.
    Like this -> data: G_GLOBAL_OBJECT type kkb_global_object.
    This means that it is declared.
    I’m starting to think: this two errors are related.

  • Generation Variant(CG2B) Transport to QUA

    Hi Experts,
               How do i  transport Generation Variant create in CG2B to Quality System..?

    Hi Prakash
    Generation Variant is a kind of Master Data and not the configuration Data. Only Configuration data can be Transported and not master data.
    Moreover, Transferring  / copying the Master Data e.g. Quantity to Production is a part of Cut Over activities.
    In this phase, the Master Data will be moved may be via BDC or LSMW.
    Generally this method is being used for very large Master Data e.g. Material Master data for 10,000 Material etc..
    Most of the time, Generation Variant list is not as big as other master data thus most adopted method,  at least for Generation Variant,  is to create the New one in Target System.
    Regards
    Amol

  • How to set a Default variant for VL06O (Outbound Delivery Monitor)?

    Hi All,
    I want to set a DEFAULT VARIANT for  VL06O (Outbound Delivery Monitor) selection screen with "For Picking", "For Confirmation", "For Goods Issue" and "List of Outbound Deliveries" button option.
    I have already created a variant with those 4 buttons. But I cant find a way to set it as DEFAULT.
    Appreciate your help on this.
    Please note I'm using SAP ERP 6.0 Ehp 4.
    Thanks & best regards,
    Anupa

    Hi Indranil,
    Superb !
    This is what I was searching for.
    That works really fine. Thanks a lot!
    Best regards,
    Anupa

  • Can we use two costing variants for standards cost estimate release.

    Hi,
    We have 2 plants (plant 5100 and plant 5200) under company code 5000.
    We have run standard cost estimate(CK11N) for material 98001000027 at plant 5100 using costing variant ZG01 and at plant 5200 using costing variant ZG02. First, we released  standard cost estimate (CK24) for this materia at plant 5100 and set (in marking allowance) costing variant ZG01 and costing version 01. Next time when we are trying to release the standard cost estimate for the same material for plant 5200, it is automatically picking ZG01 as costing variant in marking allowance and it is not allowing to change the costing variant to ZG02 saying Company code 5000: Release already carried out, cancellation not possible, Message no. CK797.
    Is it possible to use two different costing variants for release of standard cost estimate for a material at two different plants at the same company code? If so how?
    Please suggest.
    Thanks,
    Bijay

    Hi,
    Thanks for your reply again.
    What is the benefit of assigning "Single Valuation Variant same to different Plants" ? In costing variant also we can assign maximum only one valuation variant and this valuation variant will default for all the plants, and hence I dont think it is necessary to assign same valuation variant to different plants.
    My  issue is :
    Example: ( Standard Cost Estimate for material 98001000027)
    Plant - 1
    Material Cost                                             Rs.100
    Labour Cost                                               Rs.50
    Overheads (10% of Labour Cost)                  Rs.5
    (say ,through costing sheet - 1)
    Total Standard Cost Estimate                      Rs.155
    Plant - 2
    Material Cost                                             Rs.150
    Labour Cost                                               Rs.100
    Overheads (20% of Labour Cost)                  Rs.20
    (say, through costing sheet - 2)
    Total Standard Cost Estimate                      Rs.270
    Now, Please explain why we cannot have two Standard Cost Estimates for a material at two different plants? If it is possible to have two standard cost estimates for a material at two different plants, how to take care of  overheads (rate of which varies) at two different plants (plant - 1 > 10% and plant- 2>20%) as we can assign maximum one costing sheet to a valuation variant variant?
    How to map the system so as to meet the above requirement?
    Thanks,
    Bijay

  • I forgot the administrator password for my mac and cant set a new one without it how can i set a new one

    i forgot the administrator password for my mac and cant set a new one without it how can i set a new one

    Reset Password 10.7, 10.8...
    http://reviews.cnet.com/8301-13727_7-20087723-263/how-to-run-the-password-reset- utility-in-os-x-10.7-lion/

  • How to set up Dynamic Variants for job which is based on Pay Period

    Hi,
    We need to set up dynamic variant for payroll interface.  This interface is based on Pay periods and that is why we need to use different variant for each month.  Letus know how to set up dynamic variant which will take care of Pay Periods

    Hi,  Thnx for reply.
    We are not changing the control records, current period will be some old period in system. 
    payroll is not processed in SAP,

  • National Instruments releases LabVIEW Report Generation Toolkit for Microsoft Office.

    The new LabVIEW Report Generation Toolkit for Microsoft Office is a library of flexible, easy-to-use tools for programmatically creating and editing Microsoft Word and Excel reports from LabVIEW. Whether you need to generate reports summarizing manufacturing test results or compile process statistics to improve your production yields, this toolkit speeds your development of customized, professional reports.
    To see examples of this toolkit or get more information please visit :
    http://www.ni.com/labview/report_gen_toolkit.htm

    It is a bit limiting though. I built my own set of VI's, a toolkit if you will, that does some of what this tookit does. But, I also wrote some functionality that isn't available in NI's kit, such as creating charts as separate worksheets and linking the charts to data on another worksheet. All in all, the toolkit is great, but you can't get as much out of it as you can using the ActiveX calls yourself.

  • HT4623 i still cant update my latest version of ios for my i pod touch 1st generation, please assist. can i still proceed to update the latest version?

    i still cant update my latest version of ios for my i pod touch 1st generation, please assist. can i still proceed to update the latest version?
    Thank you.
    Regads
    Jason Loh
    have a nice day

    Hi
    The blunt awnser is you can't - sorry
    But you can- unadviseably as it is illegal - but there is still websites that do it but if you want to get the further iOS' then you will have to purchase a new ipod :)
    Hope I've helped
    Matt

  • Since they just released iOS 7.0 for the fifth generation, are they going to release anything for 4th generations?

    I need to know if they are releasing a new update for 4th generation iPod touches now that they released iOS 7.0 for 5th gen.

    Very very unlikely
    All the iOS devices compatible (iPhone 4 and later, iPad 2 and later, and 5G iPod touch) with iOS 7 have at least 512 MB of memory (RAM). The 4G iPod only has 256 MB

  • Set variant for PNP LDB select option of pernr

    Hi All,
    I want to set variant for PERNR of PNP LDB in one of the program through other program using RS_CREATE_VARIANT FM.
    Please help to solve this problem.
    Thanks,
    Shailesh S. Malkar.

    REPORT  ZTEST.                   .
    tables: pa0003.
    ranges pernr for pa0003-pernr.
    * Fill neccesary PERNRs
    pernr-low = 1000.
    pernr-sign = 'I'.
    pernr-option = 'EQ'.
    append pernr.
    pernr-low = 1112.
    pernr-sign = 'I'.
    pernr-option = 'EQ'.
    append pernr.
    SUBMIT RHINTE00 WITH PNPPERNR IN PERNR.

  • How to set default variant for selection screen

    Hi,
    I want to make one variant as default for selection screen for one user.
    For eg., take COOIS. For the selection screen, i have 3 variants. But i want one variant to be default. Thsi is not for all users. Thsi is for particular user.
    I am not seeing any way to do this. please help me..
    Thanks
    Srini

    Hi,
    If you are using Z program then you can ask your developer to get Variant name Runtime from Parameter ID.
    This means you decide a Parameter ID name : ZVAR in your Z program and ask your developer to load variant each time your Z program loads.
    Now, second step will be using SU01 transaction you can set value of ZVAR in Parameters tab for the user. This value will be the variant which you created for this user.
    This will solve your problem and you can make n number of variants and assign it to different users.
    Regards,
    Arpit

  • Workflow variant for payment release

    Hello ,
      I have done the configuration of workflow variant for payment release but still the invoice is not getting blocked when we are paying it .
    Find below the configuration done for it . SPRO-Accounts Receivable and Payable-Business Transactions-Release for payment
    1.t.code  PPoce: Users is  assigned to each position and this was assigned to approval path
    2. Create workflow variant
    3.Assign Company code to workflow variant
    4.Define Release Approval Groups for Release for Payment
    5.Define Release Approval Paths for Release for Payment
    6.Assign Release Approval Paths for Release for Payment
    7.Assign Release Approval Procedure for Release for Payment
    2010-2010-1000-inr-WS10000052-WS00400011
    9.Define Users with Authorization to Payment Release
    11.Define Payment Block Reason for Payment Release
    Then in the vendor master i have inputted the relase group  also .
    But when i make the payment for that vendor , no blocking of invoice is happening nor it is going for approval procedure.
    Please guide me what all other checklist available for executing the Workflow variant for payment release .
    Thanks.

    Thanks Kiran ,
    Now hte invoice is getting blocked automatically and i am getting the error as
    Line item not relevant for payment release
    Message no. F5783
    for which i changed the error message to warning mgs and saved the invoice .
    But while making the payment i was not getting any payment block. I was able to make the payment
    Actually I should get the payment block while I am making the payment and then i should release it through FB13 .
    Please let me know if I am wrong .
    Thanks