Capacity assignment to persons?

Hi EAM Gurus,
At my client project , there is a requirement where we want to assign Work Center available capacity to individual persons.
So in my work center the standard available capacity is say : 80Hrs,
And in HR assignment I have maintained Org unit or HR work centers where I have assigned 4 employees.
No I want to divide the available capacity proportionally in between these 4 persons > how can I achieve this?
Waiting for your reply....
Thanks in Advance
Adi

hi
check is there any calculation standard key can be used in the work center

Similar Messages

  • Error while assigning the persons to the Project activities

    Dear Experts,
    In Workforce planning, I am facing the below error
    No requirements were found for the selection criteria
    Message no. C#043
    I have created a project and assigned the work center to the activities, the work center is having the persons assigned. I have maintained other formula as SAP007 in the work center capacities tab.
    In the network activity when I choose the option to calculate work, the work is calculated correctly, and in the network header Capacity requirements tick is enabled. But still I am not able to assign the persons in Trnx CMP2.
    Can you please advise on the above to resolve the issue.
    Note: The project status is CRTD.
    Thanks and Regards,
    Praveen

    Hi,
    This problem mainly arises when scheduling is not done. Schedule the WBS under which these activities fall. The WBS should not have the status as NTUP. Note that these comments are in addition to what Ahmed has mentioned in his post.
    Also check you workforce planning profile if need be. Try this and revert.
    Regards,
    Gokul

  • Assigning HR persons to work center

    hello
    What is the diffrence between assigning HR persons to Work center and assigning HR persons to capacity of work center. And what is the impact of these 2 assignements to capacity planning in activities in PS?
    THX

    hello
    I have been still reading docs for this topics. Now yes you are right there are 2 places for adding HR to work center. As I have read there is a reason for this.
    If you add HR to work center you will add people to work center indirectly. Now I'm not sure yet if I should add HR work center to work center and then add people to capacity in addition. But I will check it soon.
    And the second way is to add people from HR to capacity directly.
    The benefit for this second way - directly to capacity - is you can use capacity of added to work center people as standard capacity of this work center.

  • How to assign contact person with user id to vendor via upload

    Dear All,
    We have successfully uploaded external business partner (Vendor) from ECC6 to SRM5.0  via BBPGETVD. So vendor is available in PPOMV_BBP.
    Now we would like to assign the contact person with user ID to this vendor so that he can logon to our system and update Bid.
    If we create contact person (employee) via "Manage Business Partner", system provides the option to create contact person and User ID under "Employee for Business Partner".
    But we can create contact person one by one, if our client have 600 vendors from ECC and already transferred to SRM.
    How to rapidly create and assign contact person to all vendors ?
    Who have any ideas for upload via text file or excel sheet please advice me.
    Best Regards,
    Theerat.

    Hello Theerat,
    Try these FM
    BBP_CREATE_CONTACT_PERSON
    BBP_CREATE_CONTACT_USER
    muthu
    Edited by: Muthuraman Govindasamy on Oct 7, 2008 9:16 AM

  • How to assign a person to work center

    Hi All,
    Can you please let me know how to assign a person to work center?
    Regards,
    Nima

    Dear Nima,
    what is the exact query
    Go to
    Spro > Production > Basic data > Wrok center > determine person responsible
    click new entries & create
    Go to CR01, Basic data tab & in the field person responsible press F4 you can get
    List created in the above Spro
    Regards
    Madhu

  • Assignment of Personal resource on PPOME

    We are on MRS 7.0 and I am trying to configure and test the system to get the demands show up on the planning board.
    I have done the configuration as per the config guide, defined the HR work center and linked it to a Logistics work center.
    On PPOME transaction, I am not able to choose the view 'Assingment of personal resource' to see the linkage between a Person to a HR work center and to a logistics work center.
    How do I define a resource planner ?
    What steps are required to link the resource planner to a person / user ?
    I would appreciate if someone could post what steps need to be done from the HR side, other then the above ones.
    Would appreciate your help / inputs
    Thanks
    Venky

    have you resolve this problem?
    i also do not see view "Assignment of personal resources" in PPOME.

  • Assigning a person to two projects at a same time with different salary

    Dear All,
    Can any one guide me how to assign a person for two projects at the same time, this can be done by assigning him to the two projects as 50%, here the issue is his salary is varied from one client to other.
    please tell me how to do in the SAP
    Thanks in advance
    Regards
    Karunakaran
    Edited by: Karunakaran on Mar 4, 2010 7:02 AM

    Hi,
    Will you record the time worked for each project and pay accordingly, or will you pay 3 & 8 hours fixed?
    If the second one is the case, what comes to my mind is you can assign him in IT0008 a base salary with wage type PR01 and this would refer to the full-time project.
    The the salary for the second projects may be given to the employee via IT0015 in terms of amount directly or hours.
    However, this scenario has nothing to do with the project system module or timesheet data.
    Regards,
    Dilek

  • How to assign a person not employed to tasks?

    Hi,
    I assign employees to tasks in the PS module (project builder). I have a few contractors (persons not employed in the company) I'd like to assign to tasks in the same way I assign employees. Is this possible?

    Hi,
    I case u need to assign some external labors, they have to be maintained in the HR master data as external employees. Then u can do workforce planning and also do the CATS timesheet entry.
    Regards,

  • Assign multiple person responsible and effort spent

    Hi all,
    Apparently, we have implemented service desk function in Solution Manager 7.0 (EHP1). Normally, when user creates/logs a ticket, it will flow to SAP support team, and eventually, the ticket will be assign to a support consultant. Although this is possible to assign multiple support consultants (maybe 3 person responsible, which include functional, technical, and BASIS), by adding 3 custom fields at the screen of Fast Entry -> 'Reference' section of transaction code CRMD_ORDER. However, I wish to make it more flexible, as some times there could be more that 3 support consultants to handle a ticket. Is there a way to do this, as 'Reference' section has limited space to add more custom fields?
    If the above can be achieved, is there a way to capture the total time spent by all the involved support consultants? E.g. functional spent 3 hours, ABAP spent 4 hours, and BASIS spent 2 hours. Total effort for this ticket is 9 hours.
    Appreciate your input.
    Thanks and best regards,
    Patrick

    Hi Patrick,
    As a standard there is no way you can add effort anywhere. You can only create custom fields may be under the "Transaction Data" tab --> Custom Addon fields to capture the effort. This tab does  not have a limit to the number of fields that can be added.
    Hope this solves your issue.
    Thanks,
    Rinkal

  • Function Module to assign contact person to account

    Hello,
    is there a standard function module which can be used to create the relationship between existing contact persons to an existing account?
    Thank you very much.
    Kind regards
    Manfred

    Hi Manfred,
    The simplest call to that BAPI can be done like this:
    CALL FUNCTION 'BAPI_BUPR_CONTP_CREATE'
      EXPORTING
        businesspartner = <partner_number>
        contactperson   = <contact_person_number>.
    CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'.
    This will connect a business partner with an existing contact person.
    You only need to field the other fields if you want to add more details to that relationship, like default relationship setting, telephone number or email, but that only depends of you purposes.
    Kind regards,
    Garcia

  • Business App Purchase Assigned to Personal Computer?

    How do I purchase an app for my business and put it on a specific employees computer (Macbook Pro) who has his own Apple ID without using a gift card scenario?

    You can authorize apps on up to five computers and you can mix content from any number of accounts on the same computer. So if you have a particular business account that you normally use for Mac App Store content, sign into the MAS on this enplyee's computer and install the app n question. Make sure to authorize the computer to use the app. You will have to sign into the business account on this computer if you wish to update this app.
    This scenario would work for a small company. Otherwise, contact Apple's volume Licensing for businesses;
    http://www.apple.com/mac/volume-licensing/

  • Capacity over load message with Persons assignment in Maintenance order

    Hi experts,
    I have maintained the system with the following parameters and system is showing capacity detail / finite popup when capacity find overload in maintenance order screen.
    Work center number of individuals: 1
    HRMS assignment in work center: only one person is assigned
    Settings maintained in OIOI transaction (check availability during order creation): Overall profile under capacity availability, SAPPM_G013 and Collect. Conversion, 1
    Settings maintained in OIOI transaction (check availability during order release): Overall profile under capacity availability, SAPPM_G013 and  Release order, 3
    My query is when I assign more than one, number of individuals in work center and then plan those persons in maintenance order operations data and assign persons in Operation general data --> Requirements Assignments --> Assign persons from work center assigned on operation and maintained work for each person.
    In this case, system does not show any capacity overload message and I am free to create orders in same date and time with the same work center assignment in maintenance order operations.
    Can anyone tell me where am I doing mistake or where should I maintain configuration ?
    Please also tell which transaction must be used to dispatch person wise operation like transaction CM25 ?
    What is the correct profile ID of transaction CM25 in both cases of 1 / multiple persons assignments in operations?

    Dear Experts,
    What I am doing. I assign number of individuals in work center capacity as 2 and create work center in by clicking HRMS button and I assign 2 person in PERSON folder.
    Further, I assign work center in maintenance order operations, enter number of person as 2, then I press internal button, click on button Requirmnt Assignment and I assign persons those are attached in work center.
    When I create 2 order on same date, time with assignment of same work center and persons on operations, In this case system is not showing me the capacity popup.
    Please advise, what should I do?

  • Person assigned to a work center

    Hi,
    We are using work force planning to assign resources to activities. We have some problem with one of the work centres. When we click on the person dropdown box in the personal assignment tab then we would expect to see the individuals that are in the work centre associated with the activity. We can see six persons from project builder and when we checked work center master data we could see only four persons.
    When checked thoroughly, the data at work centre master data is picked from HRP1001 and its showing only 4 persons. At the project level, the data is picked from the same table but initially fetches with work centre as input and then capacity ID as input. Finally it combines the data (6 Persons) and show from CJ20n and its different from the work centre data.
    is this the standard behavior or we missing something
    Regards,
    Laxminarsimha

    I think you have assigned two person at capacity category level for that WC.
    Open your WC  in CJR3 --> Click on capacity header icon -->on new screen click on HRMS link button  ( check no of person assigned here  it should be two )
    With Regards
    Nitin P.

  • Person assignment with workforce planning

    Dear All,
    I plan activity for one day 8 hours & assigned person to activity in CMP2 & distribute work for same day & for same hours,
    when i assign same person with diffrent activity with diffrent project with in CMP2 system not showing any message with same person is assigned same day with diffrent project.
    How same person can work two project with same time,
    Kindly share yours experiance.
    Regards
    Gajjen

    Hi,
    I tested with without person assignment in work center, yes you can assign any person to any project if have capacity but when we distribute work in workforce planning by assignment of person with day & time then same person how can assign to other activity ,because his working hours are fixed,if working time is 8.5 hours & person assign for 8 HR to activity then same person should not work to another activity more than 0.5 hrs,system should not allow.
    May i know Standard SAP allow it or not?
    Regards
    Gajjen

  • Problem on Assigning Person to a Position

    Hi SAP-HR folks,
    I would like to ask for your assistance on my problem below.
    I've hired a person using New Hire action type. During the hiring process, I've assign the person to a position which I've created also. Then, there is a need for this person to be re-assign to another vacant position. Re-assigning should be done using drag and drop in transaction PPOME.
    I've successfully done the re-assignment of this person to another vacant position using drag and drop. But according to the test scripts that we are following, the expected result should be that the system should refuse the re-assignment after filling in the dates. Re-assignment can only proceed after delimitation of the assignment of person to position.
    May I know if the action that I've done is a normal behavior of SAP? In the case the test scripts are right, may I know on how to successfully follow the scripts?
    Thanks in advance!

    whenever transfer employee from one positon to other position don't do this by drag and drop from ppome.
    just do this by PA40, Org Reassignment action.
    as ppome not support 100% for such change.
    and also if u do this from ppome, it0001 can't be updated for both positions.