Capacity calculation in PM module

Dear all gurus,
Inspite maintaining settings in workcenter,shifts and controlkey , when i make order <b>PM01</b> type and try to check capacity it is giving message
<b>No reqmts/caps exists or not relevant to finite scheduling.</b>
Along with this alarm what ever help message settings mentioned I have maintained still the message is coming and when I click OK it says
<b>All capacities are available.</b>
Inspite of that I could not find load on work center in <b>CM01</b> T-code
Kindly help me.

Nandipati,
What is the workcenter category you have used? Looks like here is the problem.. generally formulas for PM will have to be assigned in Other forumla as rightly pointed out by Thyagaraj.
Also you need to check the scheduling parameters for PM order, there also you need to activate check box for Generate Capacity Requirements for the order type/plant combination. I dont remember the transaction also will not be able to say as I dont have access to system now.
Regards,
Prasobh
<b>
Rewarding points to usefull answers motivates us to reply.</b>

Similar Messages

  • How SAP standard run the interest calculation in AR module

    Dear expert,
    would like to seek for your advise, how SAP standard run the interest calculation in AR module ?
    Also advise,does the interest calculation generate the interest base on the dunning run?What are relationship between interest calculation generate ?
    What are the T-code for running the interest so that able to generate the interest posting according to baseline due date?
    On top of that, does SAP have standard AR interest calculation report and what are the T-code ?
    Between, do you have any ideal the Interest Indicator ZB stand and reminder date it is the last reminder date,waive,KIV and charge Interest and also noted item amount mean for in the AR Interest Calculation report?
    Please help.
    Regards,
    Karen

    Hi,
    Thank you for the promtp reply.
    I still have query would like to seek for your advise.
    1.Does the interest calculation generate the interest base on the dunning run?For example, the interest is only can be post/generated when there is dunning run and vise versa.
    2.What are relationship between interest calculation generate ?Does interest generation depand on the dunning run?
    On top of that, does SAP have standard AR interest calculation report and what are the T-code ?
    3.Between, do you have any ideal the reminder date it is the last reminder date,waive,KIV and charge Interest and also noted item amount mean for in the AR Interest Calculation report?
    4.For posting use F.2B and that will calculate interest on open items of customers. Does this posting is post as noted item or posting document? Beside, do we every day need to run this posting  F.2B in order to update the AR interest calculation report and post the interest for the overdue invoice?
    5.Do you have any reference link/document /SAP notes on calculate interest on arres F.2B?
    a)How the program calculate those overdue invoice for example: does sap calculate the interest  base on interest + due amount until the customer made the payment?
    b) If customer made payment on the due amount and not the interest and vise versa? How theF.2B program logic work on the calculation ?
    Please help.
    Regards,
    KH

  • Excise duty calculation in MM module

    We need to capture excise duty in percentage as well as lump sum in the purchase order in condition type. will u pl help me how to configure this additionally.
    regds
    Raghu

    Hi,
    We can capture only one type of either Percenatge based or Amount based, multiple assignment of  Calculat.type to condition types.
    Calculation type for condition
       Determines how the system calculates prices, discounts, or surcharges in
        a condition. For example, the system can calculate a price as a fixed
        amount or as a percentage based on quantity, volume, or weight.
        The calculation type can be set when generating new condition records.
        If this does not happen, the calculation type maintained here is valid
        for the condition record.
    regards,
    Rama Mohan Bangaru

  • Required capacity calculation in cProjects automatically

    Hi
    For a project, in the structure tab tasks have been created and role/responsible person has been allocated with duration.
    In the resoruces->staffing tab, the requried capacity is still shown as zero.Also in resoruce->tasks tab, tasks assigned to project role is not getting popualted automatically even though these details are alsready in the structure.
    Should we have to redo the task/capacity assignment manually again or does cProjects do automatically from structure? Any help?
    Regards
    Senthil

    Hi,
    The capacity requirements & scheduling is done as per the formula given in the capacity & scheduling tab page in the work center (cr02).
    In work center the standar value is maintained , this contains the parameters (eg: setup, machine time etc.) to be used in the formulas.
    You can define the parameters using t.code op17,
    Standard value key using op19 & Formula using op21.
    Then when you create a routing, when you enter the corresponding work center in the opetation details, the system will ask for setup,machine time etc.
    Here you can enter 10 min as setup time & no. pcs which can be machined/processed in one minute.
    Then when you create a production order & if it forward scheduling, then the system will start scheduling from 6.00 am say the start of the shift.
    6.00 to 6.10 am setup will take place & then from 6.10 machining will start. Then end time is determined by the Order quantity.
    Regards,
    Senthilkumar

  • Event definition and capacity calculation

    Hi,
    Due to the implementation of a CSM, there are a couple of things that I need to clarify in order to be sure about the Server requirements.
    1. What is the definition of an event in a security device? Is it a violation to rules? Is it a connection fail??
    2. How could I posibbly know the storage capacity required to handle the events send by an ASA? Is there an especific size for this logs/packets???
    Thanks for your comments.

    Hi Douglas,
    The events from the ASA are simply the syslogs that are generated by the firewall. However, certain syslogs are "deeply parsed" by CSM to provide additional details. Here is a list of syslogs that are deeply parsed (the rest are displayed as raw syslog data):
    http://www.cisco.com/en/US/docs/security/security_management/cisco_security_manager/security_manager/4.0/user/guide/evntchap.html#wp191617
    As for the storage requirements, this will depend on the amount/level of logs that are generated by your ASA.
    Hope that helps.
    -Mike

  • Capacity calculation

    Hi Gurus,
    Question related to process industry.
    I have different resoures. I used 5 resources in one product Recipe.
    The same resources will be used for other product manufacturing with different time length.
    But two product will not be processed at time. Manufacturing will be one after one only.
    The suitable demand for one month                                    Product- A is 2000 Kg (It requires 20 Days) and Product B is 500 Kg requires 10 days.
    Now question is,
    I have given demand for -A is 3000 in MD61 and ran MRP. Planned orders and dependents created accordingly.
    Now I given demand for -B as 500 Kg, and ran MRP,
    Planned orders and dependents created accordingly.
    According to monthly plan, available capacity is 2000 Kg- A and 500 Kg- B,
    But we have given excess demand.No ware system restricted and warned regarding capacity.
    Is there any solution for this?
    can any body give me solution.
    rewards will be given,
    Adv. thnx & Regards,
    Anand.M (Hyderabad)

    Dear,
    Please note that MRP is only plans material and schedules as per the routing or material data maintained. Once you run MRP, you need to goto capacity planning table and there it will show the excess load with red line.
    Run MRP with folloiwng setting
    Scheduling = 2-Lead time scheduling and capacity planning.
    Then goto CM01, give the work center and execiute the report it will show overload.
    In capacity planning table like MF50 or CM21/CM22, you need to dispath the requirement in such a way that there is no overload.
    I hope you got some idea.

  • Stock calculation report in mm module

    Hi all,
    I have developed report for stock calculation in mm module. my opening stock and closing stock is not matching with that of MB5B.can anyone provide the guidance into this as I have worked on mm reports.
    Regards,
    Harshada

    declarations:
    * Structure type Declarations
    TYPES : BEGIN OF STYPE_MSEG_LEAN,
               MBLNR             LIKE      MKPF-MBLNR,
               MJAHR             LIKE      MKPF-MJAHR,
               VGART             LIKE      MKPF-VGART,
               BLART             LIKE      MKPF-BLART,
               BUDAT             LIKE      MKPF-BUDAT,
               CPUDT             LIKE      MKPF-CPUDT,
               CPUTM             LIKE      MKPF-CPUTM,
               USNAM             LIKE      MKPF-USNAM,
               XABLN             LIKE      MKPF-XABLN,        
               LBBSA             LIKE      T156M-LBBSA,
               BWAGR             LIKE      T156S-BWAGR,
               BUKRS             LIKE      T001-BUKRS,
               BELNR             LIKE      BKPF-BELNR,
               GJAHR             LIKE      BKPF-GJAHR,
               WAERS             LIKE      MSEG-WAERS,
               ZEILE             LIKE      MSEG-ZEILE,
               BWART             LIKE      MSEG-BWART,
               MATNR             LIKE      MSEG-MATNR,
               WERKS             LIKE      MSEG-WERKS,
               LGORT             LIKE      MSEG-LGORT,
               CHARG             LIKE      MSEG-CHARG,
               BWTAR             LIKE      MSEG-BWTAR,
               KZVBR             LIKE      MSEG-KZVBR,
               KZBEW             LIKE      MSEG-KZBEW,
               SOBKZ             LIKE      MSEG-SOBKZ,
               KZZUG             LIKE      MSEG-KZZUG,
               BUSTM             LIKE      MSEG-BUSTM,
               BUSTW             LIKE      MSEG-BUSTW,
               MENGU             LIKE      MSEG-MENGU,
               WERTU             LIKE      MSEG-WERTU,
               SHKZG             LIKE      MSEG-SHKZG,
               MENGE             LIKE      MSEG-MENGE,
               MEINS             LIKE      MSEG-MEINS,
               DMBTR             LIKE      MSEG-DMBTR,
               DMBUM             LIKE      MSEG-DMBUM,
               XAUTO             LIKE      MSEG-XAUTO,
               KZBWS             LIKE      MSEG-KZBWS,
               retail(01)        type c,                       
               oiglcalc(01)      type  c,                     
               oiglsku(07)       type  p  decimals 3,     
               insmk             like      mseg-insmk,      
    * the following fields are used for the selection of
    * the reversal movements
              SMBLN    LIKE      MSEG-SMBLN,    " No. doc
              SJAHR    LIKE      MSEG-SJAHR,    " Year        
              SMBLP    LIKE      MSEG-SMBLP.    " Item in doc
    TYPES : END OF STYPE_MSEG_LEAN.
    TYPES: STAB_MSEG_LEAN        TYPE STANDARD TABLE OF STYPE_MSEG_LEAN
                                 WITH KEY MBLNR MJAHR.
    * Data Declarations
    DATA : G_S_MSEG_LEAN         TYPE STYPE_MSEG_LEAN,
           G_S_MSEG_UPDATE       TYPE STYPE_MSEG_LEAN,         
           G_T_MSEG_LEAN         TYPE STAB_MSEG_LEAN,
           AKTDAT                LIKE SY-DATLO,
           INDEX_2               LIKE SY-TABIX.
    DATA: BEGIN OF IMSWEG OCCURS 1000,
            MBLNR LIKE MSEG-MBLNR,
            MJAHR LIKE MSEG-MJAHR,
            ZEILE LIKE MSEG-ZEILE,
            MATNR LIKE MSEG-MATNR,
            CHARG LIKE MSEG-CHARG,
            BWTAR LIKE MSEG-BWTAR,
            WERKS LIKE MSEG-WERKS,
            LGORT LIKE MSEG-LGORT,
            SOBKZ LIKE MSEG-SOBKZ,
            BWART LIKE MSEG-BWART,
            SHKZG LIKE MSEG-SHKZG,
            XAUTO LIKE MSEG-XAUTO,
            MENGE LIKE MSEG-MENGE,
            MEINS LIKE MSEG-MEINS,
            DMBTR LIKE MSEG-DMBTR,
            DMBUM LIKE MSEG-DMBUM,
            BUSTM LIKE MSEG-BUSTM,
            BUSTW LIKE MSEG-BUSTW,                              
            oiglcalc(01)         type  c,                      
            oiglsku(07)          type  p  decimals 3,      
            insmk                like      mseg-insmk,       
          END OF IMSWEG.
    DATA: BEGIN OF SUM_MAT OCCURS 100,
            WERKS LIKE MSEG-WERKS,
            MATNR LIKE MSEG-MATNR,
            SHKZG LIKE MSEG-SHKZG,
            MENGE(09) TYPE P DECIMALS 3,                             
          END OF SUM_MAT.
    Edited by: Kartik Tarla on Aug 5, 2010 7:06 PM

  • Capacity requirement in workcenter.

    Hi all
    Please explain about  setting for determining actual capacity requirements in workcenter.
    Also explain how it is useful?

    Hi,
    Capacity planning is divided into two components in SAP
    1. capacity leveling
    2.capacity Evaluation
    Capacity Leveling
      Following elements will create Capacity requirements,
      1. Planned order with Lead time scheduling
      2. production orders
    Following elements will be used to calculate  required capacity  and Capacity Percentage:( Actual capacity calculation)
    1. Work center formula
    2. Routing Base qty.,activity times
    3. Number of Individual capacity
    4. production order/ Planned order Order Qty
    Capacity Evaluation
    Capacity evaluation is fully controlled by setting maintained in IMG 'Overall profile'
    This is Just an overview about CRP.
    Regards,
    Velmurugan S

  • BAPI's for capacity Leveling (CM21)

    Hello Friends,
    Can anybody let me know the list of BAPI's available for the CM21 Transaction(CAPACITY LEVELING in PP Module).
    Thanks
    Naresh

    Thanks Siddharth.
    i got it

  • Current Month Capacity Availability in Capacity Data View

    Capacity Data View Does Not Roll Forward - current month still shows full monthly capacity being available (744 hours for January 2008) even though we are on 01/11/2008 (504 hours left in January 2008).  Where in the configuration this value is calculated?  What change I need to make to the configuration to make the monthly capacity view rolling forward.
    Appriciates all of your help.
    Thanks.  Tom

    I am not sure if you can debug the code. Anyway when you go into Macroworkbench, you can right click and pickup the option to look into the ABAP code generated behind the macros. It may be definitely more than 1000 line code and so am not sure if you want to go there. You may want to eliminate the macros in the capacity view one by one to exactly isolate the code that does the capacity calculation.
    Alternatively as I suggested, you can use a user exit macro to do the calculation. The UE macro can look into tables such as /sapapo/editquan to exactly calculate the resource per day and finally interrogate location calendars to calculate available capacity which can be published in a user defined key figure.(even a planning book KF should do unless you want to generate DB alerts).

  • Warehouse capacity values

    Hello All,
    I am looking for the the functionality in SCM that would help my organisation put "capacity" for warehouse/plant may be for every day or even every hour so when when the order scheduling takes place, it takes into account the capacity and possibly allocate the next day delivery if there is no capacity available.
    Example: On 23rd Feb, our warehouse can process 200 orders having 1200 units. If there is a backlog of 180 orders with 1150 units, the next upcoming order of 50 will be processed today so system should provide CGID of today but if the order is for 110, then it goes to tomorrow's CGID. The capability should definitely exist somewhere because how else can you set the GATP to work accurately if you don't have restrictions enabled.
    If such functionality do not exist, I want to understand what is the nearest capabilty that we can take advantage of.
    Thanks,
    Ali
    Edited by: calyps on Feb 23, 2012 5:33 PM

    The storage type customizing defines how you do capacity checks.
    No capacity check
    Check according to maximum weight
    Check based on palletization accord. to SUT 1
    Check based on maximum quantity per bin in storage type
    Usage check based on material
    Usage check based on SUT
    Usage check based on material plus SUT
    Based on these settings SAP allows maintenance of appropriate fields in create/change storage bin and uses those storage bin fields and fields from material master to calculate capacity values for the quant (table LQUA) and capacity usage in table LAGP.
    Capacity calculation is a wide area  in WM, almost no customizing, small maintenance in master data, but a large area for creating errors in fields of table LQUA, LAGP while doing movements.
    I recommend to read the single field helps (F1) and compare all with the info from OSS note 392776.

  • Overhead Calculation for Internal Order

    Hi Gurus,
    I have created one internal order and made the reservations.
    I have configured all Overhead Keys and Overhead Groups. I have also maintained the rates for the same.
    Now while i m running the overhead calculation for internal order, I am getting below stated result:
    Y141  Machine Cost 5000 INR 100 KG Rs. 555.27
    Y142  Labour            60    INR 100 KG Rs. 1110.54
    Y143  Utility              60    INR 100 KG Rs. 2221.08
    Y144  QC/QA Exp     5000 INR 100 KG Rs.4,442.16
    Now u can see that overheads are doubled evrytime. I have made the configuration perfectly. I m demn sure abt it.
    But i think i m lacking somewhere because such kind of ridiculous overhead should not come.
    Pls help me in this regard.
    Hope to get back u frnds!!!!!!!!

    hi
    check work center settings. i.e capacity calculations
    regards,
    sreekanth

  • P965 Neo support Aeneon 1GB DDR2 800 module???

    HI there, i got a MSI P965 New mobo with me... currently running on 1 GB Kingston DDR2 667 Mhz... planning to upgrade to 2 x 1GB Aeneon DDR2 800 Modules... does tis mobo support it??? coz in the manual it stated 1GB DDR2 800 not supported... thanks for expert advice

    Hello downcast,
    Quote
    coz in the manual it stated 1GB DDR2 800 not supported
    If I am not mistaken, this statement is no longer part of the manual.  At least I was not able to find it in the latest manual on the product page:
    http://global.msi.com.tw/index.php?func=downloaddetail&type=manual&maincat_no=1&prod_no=265
    In any case: The limitation it mentions do not refer to the memory capacity of a given module (1 GigaByte), but to the implementation/organisation of chips on that module.
    Compare the datasheets of the following corsair modules for example:
    TWIN2X1024 - 6400 C4
    --> http://www.corsair.com/_datasheets/TWIN2X1024-6400C4.pdf
    Quote
    Implemented using 64M x 8 DDR2 SDRAMs [64x8 = 512 Mbit]. 
    The limitation only applys, if you are using memory modules whose capacity is "implemented using 128M x 8 SDRAMs [128x8=1024 Mbit= 1 GBit]. 
    As long as the actual chips on your 1-GByte-modules are organized as 64M x 8, you should have no problem @800 MHz.

  • Work center creation in PP

    Please guide me step by step procedure to create work center in PP module so that if i reference the same in Poduction order it will generate all costs (estimated, planned , actual costs).
    Thanking you in advance.

    Hi,
    you can go to transaction CR 01 to create work center put plant work center name and then category of ur work center i.e. machine ,labour,production line 
    1. Basic data - general details of ur work center. -- category person responsible and with that standard value key with six parameters
    2 default values -- put ur control key,and unit of measurement for ur parameters like min. hour ,second.
    3. capacity - here you mention all the details of ur standard capacity details header details and capacity calculation formula
    4. scheduling - here you mention ur scheduling formula and standard queue time
    5. costing - here you put ur cost center and controlling area with validity period dates and activity types and formula for it
    Then save.
    reward points if you find it useful .
    regards
    pradeep

  • Resouce (Manpower) planning in PS

    Hi All
    In our R & D projects, mangement wants to track Resources(Personnel,Manpower) means planning, allocation and tracking of Persons involved in a project. As per my knowledge we can use Resource planning in PS but for that integration of HR module with PS is required, but in our company HR module is not implemented.
    My question is that am i correct that we can only do manpower or personnel planning and tracking thru PS if HR module is there?. And, if it is possible to do without HR module being implemented then how can we do that?
    Please Advice..
    Thanks in advance

    Create work centers equal to the number of persons(identify each work center by a unique name so that it can be co-related with a person) in your system. Define working time for work centers  and put capacity,scheduling formulas for the calculation of capacity and scheduling. Also assign the correct cost center(where the person's all expenses such as salary etc.are going to collected), and assign the activity type (determine the correct rate at which this person will be utlilised in the project). Do the price planning for the assigned cost center and activity type(KP26).
      Now these work centers can be assigned to network activities for the required duration. Activate capacity calculation for the project, and in various capcity planning reports you can evaluate the capacity requirements and level the capacity.
    These very brief steps of the process.
    Regards,