Capacity leveling. Aim is to have oders scheduled within 1 day if possible

Hi All,
I have a list of 10 prod. orders with same basic/scheduled start/finished date= today
In capacity leveling, if i select a whole list of these orders and dispatch them, i get all orders with start day= today, finish date= today+ x days.
I would like to have orders scheduled with start/finish date within 1 day.
I have available capacity of 4 hours per day. Each order takes around 1,5 hours, thus i can have 2 orders scheduled for today, and so on. This is exactly what i need.
My kind question to you is how to setup SAP in a such way.
NB: If i do leveling for each order one by one, then i get what i want: e.g. order is scheduled within 1 day.
Best Regards,
Andrey

Dear Andrey
Your requirement is, Automatic capacity levelling based on the available capacity.
In SAP R/3 PP module, only manual capacity levelling is available. Automatic is possible in APO.
If the requirement dates are same for multiple orders, system will through all the orders in the same date and it will display overloaded. So manually we need to dispatch the overload to the required date.
Please check the below thread also.
Re: Triggering Finite Scheduling
Hope it helps
Regards
Bala

Similar Messages

  • Infinite scheduling with capacity leveling.......

    Hi there ,
                   If we go for infinite scheduling & then after MRP run go for capacity leveling ..........
    then will we get the same effect as finite scheduling .....
    Please suggest me
    Regards
    Kaushik

    Hi Kaushik,
    If my understanding is correct, you are asking for the difference between manual and automatick despatching of orders in capacity levelling?
    when we set finite scheduling in capacity header view of work center, and run MRP with scheduling parameter 2 set.
    In capacity planning the availabile capacity will be compared with the required capacity and the load will be depicted as a graph or in table format. This only gives the load situation against the period.
    For this the despatching of order will be done manually based upon the load per day by a scheduler in capacity levelling.
    And to add more,
    In R/3 finite scheduling is not there and this is drawback and APO was put in front for this purpose.
    Can you confirm me whether the system automatically levels the order or despatchs the order in finite scheduling.
    Best Regards,
    Sendil

  • Capacity leveling problems

    I have some troubles with implementing capacity leveling. I cannot level with planned orders (cable solution), so it is only possible to plan production orders.
    The setup matrix is used (because setup times can be greatly reduced, depending on the succesor).
    For some operations, simular machines can be used. CM21 (work center view) is used. Version: R/3 release 4.6C.
    Now a couple of problems rise.
    Problem 1:
    Since there are simular machines, normally production versions are used for capacity leveling. However, we have to level with production orders, so production versions are not applicable.
    Making one workcenter with different individual capacities is also no solution, since SAP messes up with setup times then (i.e. two operations of different production orders have to leveled onto the work center. Normally, the setup is 20h, but if it is a right succesor, it has to be 0h. This is mentionned in the setup matrix. If we dispatch now with a specific strategy for setup time optimization, only one operation will have setup time and the other operation will be schedule from the start on of the other operation's setup... In reality, two setups has to be done, since there are two machines!).
    Alternative sequences is also no solution. While leveling, the alternative sequence will never be used by SAP, in my view.
    Problem 2:
    The strange logic of SAP: setup of the next work center can only be done if the production on the previous work center has finished. In reality, the setup of the next work center can overlap with the production of the previous workcenter.
    Besides these two problems, there are some more troubles with capacity planning in SAP. SAP messes up sometimes by putting the setup time before the wrong operation (sometimes, the first operation has no setup time and the second does. However, this should be the other way around.).
    If you plan an operation manually, SAP doesn't take into account the setup matrix.
    Does anyone has a solution?

    Hi  Walravens,
    What i have understood is, u have the avilability of multiple resouces to produce same material, if any capacity bottle neck, u level the different production order of same material from "one work center" to "another workcenter".
    At  cm21, select the mutiple workcenters (selection criteria) and dispatch the operation as need.
    For setup time overlap, how to system know ur producing two operations (from two different orders) with same setup.
    Even the operations from same production order, system consider the set up time of the second operations unless u define overlap function. . Am I understood your problem in correct way.
    So remove the set up time for second operation and dispatch. 
    Regards
    Pradeep

  • Delivery Schedule within the Firm Zone of a SA not firming

    Hello,
    We have delivery schedules within firm zone (defined in the Additional Data in item detail) of a SA but they are not firmed by MRP run.
    Here is the material master setting and other relevant information:
    MRP Type = PD (firming type = blank)
    Planning Time Fence = 0 (in MRP1 view)
    Not check the flag in OMIN to firm only the transmitted schedule line
    Maintained Firm/Trade-off zone (as mentioned above) and Binding on MRP = '1' in an item of a SA
    The delivery schedule supposedly be firmed based on the firm zone but is keep pushed out instead after MRP run.
    I appreciate very much if you can tell what's causing the problem and how to remedy it.
    Kind Regards,
    Eddie

    Eddie,
    Your batch job is OK however until the delivery schedule with new schedule line proposals has been transmitted they can be changed by MRP as they are not yet firm.
    From my experience the OMIN settings affect the MRP type firming settings (P1, P2, ...) not the SA related firm settings. Here the binding on MRP key is determining what MRP can change or can not change.
    See here the extract out of the help function on the OMIN setting.
    Firm Only Schedule Lines Transmitted to Vendor by Purchasing
    If you set this indicator, the system only firms the schedule lines which have been transmitted to the vendor by the purchasing department.
    Use
    This function is used if you use a planning time fence in the planning run. If you use firming type 1 ("Automatic firming and order proposals are displaced"), the system automatically firms existing schedule lines when they move into the planning time fence.
    Use this indicator if you only want the system to firm schedule lines that have already been checked and passed on to the vendor per message transfer. If, for example, the quantity of a schedule line was changed but the changed quantity has not yet been passed on to the vendor, then the old quantity that has already been passed on to the vendor is firmed as soon as this schedule line moves into the planning time fence.

  • Capacity leveling, after Deallocate scheduling dates getting changed.

    Dear Experts,
    I have a issue in Capacity leveling using transaction CM25 - Online. I have created some production orders (using forwards/backwards scheduling) for overloading of WorkCentre's. When I dispatch orders it’s getting scheduled perfectly, but when I Deallocate same orders scheduled dates are getting  changed.
    Even after deallocation production orders schedule dates should be the same. Can you please help me in this regard?
    Thanks in advance.
    Prashanth

    Hello Prashanth,
    From SAP help Date Determination in Dispatching and Rescheduling - Capacity Leveling (PP-CRP-LVL) - SAP Library
    The current dispatching data is cancelled. The status "dispatched" of the operation is reversed. The order is rescheduled.
    If further operations exist for an order which has already been dispatched, the system automatically carries out midpoint scheduling. If no other dispatched operations exist, the system carries out lead time scheduling.
    If order date is in past then it schedules to current date during de allocation if you do not have enter number of past days allowed to start date in scheduling parameters.
    Br
    KK

  • Work schedule display in capacity leveling cm25

    Hello,
    In our company we have created a work schedule (tcode OP4A) and have associated to a work center (tcode IR02).
    However, capacity leveling (tcode CM25) doesn't display the work schedule associated to our workers in the graphical planning table.
    Do you have any idea how to solve this problem?
    Thank you very much,
    Óscar

    It could be issue with your over all profile..
    Use - Over all profile SAPPM_G001  
    Overall prof: SAPPM_G001           PM: Ind.cap/tab/day/avail.lab./norm.schd
           Select.profile:                     SAPPM_S001      PM: Tab/work center/lab/
           Control profile:                    SAPPM_C004      PM: Capacity planning table individual
           Time prof:                          SAPPM_Z0T1      PM: Tab. short-term (1 month)
           Evaluation prof.:                   SAPPM_A001      PM: Plant maintenance
           Strategy prof.:                     SAPPM_T002      Lead time sched. backwards
           Capacity planning table (tab.form): SAPPM_R001      PM: Plant maintenance/Individual caps.
    Note: Don't modify the Standard profile .

  • Sequential scheduling of orders in capacity leveling

    Dear All Hi,
    I working on capacity leveling where in the clients want the following requirements, please give your valuable inputs & your help will greatly appreciated & rewarded.
    The following is the scenario:
    If have 3 orders scheduled on 3 consecutive days (considering each order completes in a single day) then if drags the first order to forward date, then the system forward schedules only the selected order but the client wants order number 2 & 3 to move automatically. That is if I push the first order, then sequentially 2nd & 3rd order should move automatically & gets rescheduled sequentailly.
    Similarly it should happen when I drag the 1st order to left then the proceeding orders should simultaneously move along left in leveling screen
    Thanks in Advance.

    Hi Mario,
                   Thanks for your reply.
    All the 3 orders are independent & are of finished goods. All the orders are scheduled on the same work center. Due to machine break down during the processing of first order, there's a loss of time, so i will select the first order & dispatches to forward date & at the same time i want the 2nd & 3rd order to get resheduled correspondingly.
    Suggest the solution for this, Thanks in advance.

  • Error while creating production order (capacity leveling)

    Hello Friends,
    For capacity Planning - Leveling, i am using overall profile  "SAPMPSG006 - MPS/MRP: Capacity availability check", in Production scheduling profile, which i have attached in the material master.
    In Availability check parameter, checking control for the combination of Plant,order type and business transaction 1, in capacity availability section also, i have maintained the overall profile "SAPMPSG006 - MPS/MRP: Capacity availability check'.
    Now i have created the production order for a particular period (start date 17.03.10 , finish date 20.03.10). In CM01, agaist the work center, i can see the load. Hence available capacity and required capacity is same for three days.
    Now again i have created one more production order for the same period (start date 17.03.10 , finish date 20.03.10), system is showing the window with the message work center with overload.On the same screen, when  i click on finite scheduling tab, than system showing the new latest start date and time the same as earlier date i.e 17.03.10.
    Here my question is , when i click on finite scheduling tab, than system should propose the date 21.03.10, as on and after this date capacity on this workcenter is available. But system is not proposing the dates, where capacity is available.
    When i checked the dispatching log, there i found two errors.
    continued..................

    Dear,
    That's great production order system is proposing the future date automatically.
    Few check,
    1) Factory calendar for holidays?
    2)Any other production order on that days?
    3)Your capacity profile and its setting?
    Basic dates
    Check whether scheduling should be performed with a time being specified. For this, check the scheduling data of the scheduling type in Customizing. OPU3
    Do the basic dates change?
    Check whether the alternative "Adjust basic dates" has been selected for the scheduling parameters.
    Check whether the basic dates are set correctly on account of the operation dates. So check operation dates also?
    Regards,
    R.Brahmankar

  • After capacity leveling  dependent requirement s to be adjusted

    hi
    iam planning a fert product on 30 th agust for 100nos
    created md61 -pir for 100 nos
    done mrp run at mdo2 and got scheduled dates for 100nos which has gone beyond the requirement date as i was chhosed leed time scheduling  and made dependent reqirement proposal for the order operation date.
    here the important thing is the work center which i nedd to produce was fully engaged inthe period (schedule period which system proposed)  .hence i made capacity leveling and planned order dates were changed again
    which are actual producion dates
    after capacity leveling my planned order was firmed
    my problem here is  the dependent requirement proposal date also
    need to be changed with respect to firmed planed order.
    how to achive this
    i tried with opu5
    but no changes in dependent reuirement proposal (planned order)
    plz suggest
    sasikanth
    vst-it projects

    hi
    i tried it but unfortunatly it is creating a new planned order and giving exemption messge to the firmed planned oder as cancel the proposal
    which is not at all acceptable
      means for a single PIR
    i made mrp run AND got planned order , after leveling the planned order was firmed
    means my pir was satisfied with this
    i made mrp run without changing PIR dates and quantity by expecting that it should propose a new dependent reqirement 
    but system created a new planed order to  pir date which sholud not happen.
    plz elobrate your view
    sasikanth
    vst-it projects

  • Capacity Leveling of Work Center

    Hi all,
    I have a problem with Capacity of Work center (WC).
    I have a Internal Activity, and i assigned a WC for this Internal Activity. WC's capacity is 100H/day for 1 number of element.
    Work of this WC is 250H, duration 5 days, number of element 1. Default capacity of this WC is distributed by Distribution Key define in Activity. . And they are divided equally between factory days in 5 day. That is capacity requirement is 50H/Day
    So, i want to edit this WC's capacity following value:
    Day 1: 100H/day
    Day 2: 50H/day
    day 3: 0H/day
    day 4: 0H/day
    day 5: 100H/day
    How can i do it?? I try to use Dispatch Manually but i cant solve this problem.
    Please help me for this case.
    Thank all.
    NLQ

    Dear
    Capacity leveling depends on some of the basic set up of Capacity Requirement Planning .You need to have proper CRP set up frist .
    Couple of check points : -
    Did you work centre is relevent for finitie scheduling in CR02-Capacity Header and wht is the over laod percentage for work centre ?
    Did you have Capacity Requirement Related Set up like Over all profile , time profile , Startegy Profile -OPD0?
    Did your Capacity Check -OPJK -Order Control at order level are active for availibilty Check 1 and 2 and assinged Over all Profile ?
    Set up :
    1.Please assing a operation control key like PP01 where Details Capacity Check and scheduling is active .
    2.In CR02-Work centre -Capacity Header -You should have Follow check box marked
    1.Releven for Finitie Scheduleing
    2.Can be used for multiple Operation
    3.
    3.OPU3/OPU5 -Define Scheduling paramter -Mark Scheduling and Capcity Check for planned order or production Order
    4.In SPRO -Shop Floor Control-Define Production Scheduling Profile -You need to matian the relevent Parameters like
    1.Schedueling Automatically 2.Scheduling Log 3.Adjust Scheduling -Basic date , Depedent Requirement date 4.Scheduling Type -Backward etc .
    These are all basic level set up beside CRP overall profile and other profile like strategy /time etc which may in place as you are analysing in CM01.
    Please find below some of the useful CRP details : Refer this threads which are self explaintory :
    http://help.sap.com/saphelp_47x200/helpdata/en/8a/a5a3154adc11d189740000e8322d00/frameset.htm
    http://www.scribd.com/doc/17026521/SAP-ECC-60-PP-Capacity-Planning-httpsapdocsinfo
    capacity planning
    http://help.sap.com/printdocu/core/print46c/en/data/pdf/PPCRPSFC/PPCRP_SFC.pdf
    Capacity Planning
    capacity requirements planning
    How to dispatch operation to do Capacity Leveling at Work Centre Level :
    1.Frist Check the  over load at work centre . Goto -CM07/CM05-give plant only -then hit the Stnadard view -You will find weekly or daily baiss load ( Requirement , Avaliable Capcity , Overlaod etc )
    2.Check the week in which days you are tring to dipatch -if you selet the week check box and double clik it will show u all the dataiul load .Basde on the available capacity in other week-days u need to dipatch in CM22/CM31  or CM25/CM21
    While dipatching in CM22/CM31-Select the Stragegy button on the top header -Mark Date entry when dispatching  so that when you select the operation of any production order or planned order for certain work centre , it will pop with window having information of Date , Work Centre , Time .Onec you did this you will receive Scheduling log with certain information .
    Hope this helps
    regards
    JH

  • Capacity Leveling Problem

    If I have an order that requires 85 hours of production, and the work center responsible only has available capacity of 14 hours per day, how can I divide up the order in a Capacity Leveling Planning Table (CM22)? When I dispatch the order, it automatically overloads the work center instead of spreading itself out over several days. When I created the production order I gave it a start date 2 weeks away from the finish date. Yet in capacity leveling, when I dispatch the order, it only goes to one day and overloads the work center by several hundred percent?
    Basically, how can I take this single order and divide it up over 7 days in Capacity Planning?

    In both the "strategy" box of CM22 and the "capacity" tab of CR02, I have made sure that the relevant boxes for finite scheduling were checked.  However, the system still overloads the work centers.  This would mean that there is a 'finite' capacity in each work center and that each center cannot be overloaded, but my work centers still load themselves to nearly 1000% capacity!  Why is this?  How can I make sure that when a work center reaches capacity, it's quantities flow into the next available slot?  
    How can I spread the requirements over a period of several dates and not just one?
    Edited by: Cameron on Sep 21, 2009 3:08 PM

  • How to run mrp and capacity leveling through heuritics.

    Hi,
    How to run mrp and capacity leveling through heuritics.
    What are the setps required for production planning run this thing in the heuritics in pp/ds?
    Regards,
    Sunil

    Sunil,
    APO PP/DS doesn't have a 1-to-1 match for MRP/Cap levelling per se.  There are, though, a limitless number of ways to achieve the results you want.
    Start with a basic PP planning MRP - SAP_PP_002, which will should create all necessary planned orders
    Then try a DS heuristic to schedule your orders according to capacity.  Schedule Sequence SAP001 is a good starting point.  This can be used to schedule your cap relevant work centers such that they fully load the capacity available, similar to cap levelling.
    Rgds,
    DB49

  • Work Center(Capacity Level) Change Documents

    We have a requirement to capture work center change documents at the capacity level which I understand is not supported by standard SAP; note 352485(point 15). Is there, though, a customized solution that can be developed? Any thoughts would be greatly appreciated.
    Thank you in advance.

    Hi Usman,
    I have already tested the method you are mentioning. You cannot save a order without work center. So, you need to use a dummy work center and change all the open orders.. if you want to change capacity category from A to B. New capacity category should be mentioned in dummy or original work center.
    When you replace the work center, order will be gng for scheduling.. which leads to change of Basis start date and earliest start date... this is an inconsistency...
    To avoid it... i followed below steps
    1. Uncheck the capacity requirement indicator in all open orders
    2. when u try to delete, it will say "Capacity is still being used"
    3. Table KBED, use capacity ID and run, it will list out the pending orders
    4. When the table has no entries, delete the capacity category
    5. check all capacity indicator
    - Pithan

  • How to do capacity levelling

    Dear Frndz,
    Pls help me how to do capacity levelling.....
    Scenario:
    I have created two production orders for the same finish date as a result the work center is overloaded.Now I want to do capacity levelling.Tell me the step by step procedure to do capacity levelling, so that the capacity problem is solved.
    Regards,
    Srini.

    HI,
    Capacity leveling after order creation
    This process covers capacity leveling of requirements from the production process, monitoring the capacity after different periods, and how the system determines the new values for the current order after changes are made to the quantities, times, and dates.
    1) T Code CM21
    2) Enter the field Plant & work Center
    3) Choose Enter.
    The current orders whose operations result in capacity loads at the selected work center are displayed. By scrolling through the different charts in the planning table, you can analyze the information provided.
    4)For a better view, choose Settings ® Scale ® Monthly period split.
    5) To automatically dispatch one or several operations of an order, click the red rectangle in the order's diagram section to select the order and choose .
    The order disappears from the order pool and reserves a time segment in the work center section.
    6) To manually dispatch one or more operations of an order, select the order in the diagram section, drag it to the work center section with the mouse, and place it in a time period that you select.
    7) To deallocate an order, select it in the work center's diagram section and choose .
    The order is again displayed in the order pool.
    8) To analyze the changes made in scheduling, select an order in the order's diagram section and choose Order.
    9) Choose Item and write down the start and finish dates of the operation you selected.
    10) Choose Enter until the Planning Table: SAPSFCG001 Finite Scheduling Forw./All Functs.Active screen appears.
    11) Drag the order to a valid section in the work center's diagram section. Make sure that you move the order to a valid and defined start and finish date.
    13) Select the order in the work center's diagram section and choose Order.
    14) Choose Item and compare the new start and finish date.
    15) Choose Enter until the overview tree appears.
    Regards,
    srivas

  • Issue with Capacity Levelling-CM25

    Hi Everyone,
    We use CM25 for capacity levelling.
    Issue:
    Total Capacity req. = 186.8 Hr
    Available Capacity on 01.01.2012 on the resource = 380.2 Hr
    Now when I try to dispatch the capacity req. for a planned order manually on 01.01.2012, system distributes the capacity-
    Distributed   Period
            5.0    31.12.2011
          23.8    01.01.2012
          23.8    02.01.2012
          23.8    03.01.2012
          23.8    04.01.2012
          23.8    05.01.2012
          23.8    06.01.2012
          23.8    07.01.2012
          15.6    08.01.2012
        186.8
    But we want to dispatch capacity say on one particular day or split it onto two different days i.e. 90 Hrs on 01.01.2012 & 90 Hrs on 02.01.2012. Is it possible? If yes, how?
    Additional Information-
    Capacity Defination in resource-
    No. of indiv. cap.   16
    Operating time       23.76
    Capacity             380.16
    Relevant to finite scheduling
    Thanks,
    Parashar.

    Hi Amol,
    Thanks for your input.
    As I have said I already have Capacity more than what is required.
    Capacity Available per day: 380.2 Hr
    Total Capacity Requirement: 186.8 Hr
    I am trying to know that whether what issue has been raised is possible to solve in Capacity Levelling & How.
    We are not maintaining shifts in SAP at present.
    Thanks,
    Parashar.