Capacity Leveling error CM22
Hi,
I get a problem when I do capacity leveling in CM22..I can perform the leveling in CM21 successfully while I get error msg in CM22..I search this forum but no answer for this similar question..
error msg:
I try CM21 and it works..I didn't save the leveling result in CM21 and switch to CM22,but I get this error msg..
Capacity not availableMessage no. C7056
Diagnosis
The system could not find any remaining available capacity within the planning period.
things checked:
I checked CM01 and I am sure there are enough capacity available ,the planning period in CM21 is also correct (2011/7/1 to 2012/3/31).I also check the strategy(finite schedule and planning direction checked)..
Hi,
Overall prof: SAPSFCG006 SFC: View work cntr/ind.cap. (tabular)
Select.profile: SAPSFCS006 SFC: View center -> ind.cap. (tabular)
Control profile: SAP___C001 Gen: Planning table (tabular form)
Time prof: SAP___Z002 Gen: short-term (3 month)
Evaluation prof.: SAP___A001 Gen: Standard evaluation profile
Strategy prof.: SAP___T012 Gen: Finite sched.backw./alloc.& dispat.
Capacity planning table (tab.form): SAPSFCR002 SFC: with indiv. capacities
Layout ID SAPSFCLA04 SFC: Individual capacities (tabular)
Ind. width
FormulaRem.avail.capacity 2 Remaining av. cap. = Av. cap. - dispatch
Dispatch time 08:00:00
Rqts to be displayed 3
I use CMCH to check the overall profile and I don't get any error msg..But I still get error msg"no available capacity" when do leveling in CM22/CM25...Pls help...thanks..
already fix it..it is due to the evaluation profile problem..
still not fix..anyone can hep on it?thanks..
Edited by: Monst Yang on Nov 29, 2011 9:05 PM
Edited by: Monst Yang on Nov 30, 2011 8:00 PM
Similar Messages
-
Hi All:
While running capacity leveeling on capacity over loading,I am getting error "Errors Occured during time stamp calculation.Calendar:IN Time Stream". Resource consumption on SNP ppm is defined as day wise.
Ashish GuptaHi :
This is the scenario which I am modelling.I am using factory calendar as IN which has 5 working days in a week.It has been assigned to a resource.I have crerated a time stream which the same factory calendar and it has been assigned to the plant.
I am using standard planning book of SNP 9ASNP94 where storage bucket is defined as 9ASNP.
I am not able to assign same time stram into that storage bucket.Should I assign it to the same or is there any other way to solve this issue.
Ashish Gupta -
Capacity Planning vs. Capacity Leveling
My production facility is looking to divide up our shop floor by work centers. There are about 20 individual work centers that are composed of 10 people each. Each material we make is divided up into 3 operations which go through 3 separate work centers. Each operation has a corresponding work center that it goes through.
Right now we are unsure which program suits our needs better, Capacity Planning or Capacity Leveling.
Our goal is to measure each individual work center (not the workers that make up the work center). Each work center has a specific goal involving the number of materials they can produce, whether or not they reached that goal and by how many.
In a nutshell, we want to be able to measure how long it took each work center to reach their individual goals by the materials they produce.
This is all about measuring the individual work centers and how efficient they are. Our goal is to be able to utilize this data within SAP.
What is the difference between Capacity Planning and Capacity Leveling, and which would better suit our goals?
Our production facility is not very complicated and we're looking for something simple and basic within SAP to accomplish these goals.
All help is appreciated. What would be your recommendations for this type of situation?HI
Capacity evaluation
In the capacity evaluation, available capacity and capacity requirements are determined and compared with each other in lists or graphics.
Capacity leveling
The objectives of capacity leveling are:
Optimal capacity commitment
Selection of appropriate resources
In most applications, you can use two types of planning table (graphical and tabular versions) to display the capacity situation and to carry out capacity leveling.
In some applications such as Repetitive Manufacturing (PP-REM) or Sales and Operations Planning (PP-SOP), there are application-specific planning tables for capacity leveling.
T codes for Capacity Planning
Work Center view - Capacity Evaluation
CM01 - Load
CM02 - Orders
CM03 - Pool
CM04 - Backlog
CM05 - Overload
Capacity Leveling
CM21,CM22, CM27,CM28.
Hope it will help u
Regards
Anupam Sharma -
Capacity Leveling - CM22 - Question
Colleagues,
We are using CM22 for performing capacity leveling functions.
1) In the standard system the Total capacity requirements (First column), are updated based on confirmation. We noticed that
only confirmaton yield is posted, the capacity requirement is deducted. However, we would like to know if capacity requirements can be deducted, just by confirmin the operation hours alone.
2) In the standard system, the Total capacity requirements incudes all the time buckets against an operation and sums it up as requirement. Therefore, if you have setup time, processing time in an operation both are added to the total capacity requirements and displayed. We would like to consider only processing time and not include setup time in to the total capacity requrements field.
If any of you have modified the total capacity requirement field on CM22, I would appreciate your thoughts and inputs on how to go about doing this.
Thanks,
PKVHi, I didnt get your 1st question correctly. please elaborate.
For point No-2, From a business prespective if you dont want to capture setup time in ur capacity reqmt, then you should'nt be entering the same in the work center. For some of the clients we have used only process time so that we can plan actual capacity reqmt. But in those case, the setup time was negligible when compared to process time.
Regards -
Use of Planning Table (MF50) in Capacity Levelling with Production Order
Hello Experts
I wish to know that is it possible to perform Capacity Levelling in planning table (tcode MF50) with respect to a Production Order ? It is known that MF50 is used in Repetitive manufacuring to do the capacity levelling with respect to Planned orders. But in our discrete manufacturing scenario we want to use planning table to the capacity levelling with respect toa Production order.
Any clue or help pertaining to this will be highly appreciated.
Thanks in advance
Regards
JayantaDear ,
MF50 is does the cacapcity leveling based on mateail -run schedule order (planned order ) where as in discrete manufacturing , when you run the MRP , MRP system assume Infinite Capacity and schedule the order as per your selection in MD02(2,1,3,3,2) and then you convert those planned order to Production order .Here you checkied the Capacity in Production Order level .
In stanadrd SAP , it is not possible to use MF50 for discrete production order.
In discrete order or process order , do the caapcity leveling , there are seperate planning table available based on Over all Capacity Profile and Schedule type .This can be done in following way :
1.CM31-Production Order Wise -Tabular
2.CM23-PO wise -Graphical
3.MC88: Ruf Cut Planning
Work Centre Wise : CM21 -Graphical , CM22-Tabular Planning Table .
Make sure the below set up before you carry on the Capacity leveling :
.Define time profile in OPD2.
Define the strategy profile in OPDB
Define the Overall profiles in OPD0.
In OPJK maintained check capacity with SAPSFCG013 profile for your production order type
In OPU3 , scheduleing parametre s: Generate Capacity , Scheduling Type , Automatic Log ,Start date in Past as per your req.
In OPJU , chekc the contol tab of the scheduleing as per OPU3
In OPKP- Production scheduling paranmeters assing the overall capacity profile -SAPSFCG013 with finte scheduling tick.
Master Data :
1.Materials Master define the Production scheduler and production scheduling profile
2.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
3.Routing - enter the values for the standard values. Use control key with scheduling.
Hope this will help you .
Regards
JH -
Capacity Leveling of Work Center
Hi all,
I have a problem with Capacity of Work center (WC).
I have a Internal Activity, and i assigned a WC for this Internal Activity. WC's capacity is 100H/day for 1 number of element.
Work of this WC is 250H, duration 5 days, number of element 1. Default capacity of this WC is distributed by Distribution Key define in Activity. . And they are divided equally between factory days in 5 day. That is capacity requirement is 50H/Day
So, i want to edit this WC's capacity following value:
Day 1: 100H/day
Day 2: 50H/day
day 3: 0H/day
day 4: 0H/day
day 5: 100H/day
How can i do it?? I try to use Dispatch Manually but i cant solve this problem.
Please help me for this case.
Thank all.
NLQDear
Capacity leveling depends on some of the basic set up of Capacity Requirement Planning .You need to have proper CRP set up frist .
Couple of check points : -
Did you work centre is relevent for finitie scheduling in CR02-Capacity Header and wht is the over laod percentage for work centre ?
Did you have Capacity Requirement Related Set up like Over all profile , time profile , Startegy Profile -OPD0?
Did your Capacity Check -OPJK -Order Control at order level are active for availibilty Check 1 and 2 and assinged Over all Profile ?
Set up :
1.Please assing a operation control key like PP01 where Details Capacity Check and scheduling is active .
2.In CR02-Work centre -Capacity Header -You should have Follow check box marked
1.Releven for Finitie Scheduleing
2.Can be used for multiple Operation
3.
3.OPU3/OPU5 -Define Scheduling paramter -Mark Scheduling and Capcity Check for planned order or production Order
4.In SPRO -Shop Floor Control-Define Production Scheduling Profile -You need to matian the relevent Parameters like
1.Schedueling Automatically 2.Scheduling Log 3.Adjust Scheduling -Basic date , Depedent Requirement date 4.Scheduling Type -Backward etc .
These are all basic level set up beside CRP overall profile and other profile like strategy /time etc which may in place as you are analysing in CM01.
Please find below some of the useful CRP details : Refer this threads which are self explaintory :
http://help.sap.com/saphelp_47x200/helpdata/en/8a/a5a3154adc11d189740000e8322d00/frameset.htm
http://www.scribd.com/doc/17026521/SAP-ECC-60-PP-Capacity-Planning-httpsapdocsinfo
capacity planning
http://help.sap.com/printdocu/core/print46c/en/data/pdf/PPCRPSFC/PPCRP_SFC.pdf
Capacity Planning
capacity requirements planning
How to dispatch operation to do Capacity Leveling at Work Centre Level :
1.Frist Check the over load at work centre . Goto -CM07/CM05-give plant only -then hit the Stnadard view -You will find weekly or daily baiss load ( Requirement , Avaliable Capcity , Overlaod etc )
2.Check the week in which days you are tring to dipatch -if you selet the week check box and double clik it will show u all the dataiul load .Basde on the available capacity in other week-days u need to dipatch in CM22/CM31 or CM25/CM21
While dipatching in CM22/CM31-Select the Stragegy button on the top header -Mark Date entry when dispatching so that when you select the operation of any production order or planned order for certain work centre , it will pop with window having information of Date , Work Centre , Time .Onec you did this you will receive Scheduling log with certain information .
Hope this helps
regards
JH -
If I have an order that requires 85 hours of production, and the work center responsible only has available capacity of 14 hours per day, how can I divide up the order in a Capacity Leveling Planning Table (CM22)? When I dispatch the order, it automatically overloads the work center instead of spreading itself out over several days. When I created the production order I gave it a start date 2 weeks away from the finish date. Yet in capacity leveling, when I dispatch the order, it only goes to one day and overloads the work center by several hundred percent?
Basically, how can I take this single order and divide it up over 7 days in Capacity Planning?In both the "strategy" box of CM22 and the "capacity" tab of CR02, I have made sure that the relevant boxes for finite scheduling were checked. However, the system still overloads the work centers. This would mean that there is a 'finite' capacity in each work center and that each center cannot be overloaded, but my work centers still load themselves to nearly 1000% capacity! Why is this? How can I make sure that when a work center reaches capacity, it's quantities flow into the next available slot?
How can I spread the requirements over a period of several dates and not just one?
Edited by: Cameron on Sep 21, 2009 3:08 PM -
Capacity Leveling vs. Plant Maintenance
What is the difference between Capacity Leveling Planning Tables (CM21, 22, 27,28,31,23) and Plant Maintenance Planning Tables (CM33, 34, 30, 24)?
In what type of scenario would I want to use either one? What would the end result of utilizing these tables be?Hi
Mark the control key for generating capacity requirement.
Give the formula SAP008 in Work Center Capacity Tab.
Use CM01 to check Capacity Planning
Use CM22 for Capcity Levelling.
Explore these options
Regards
KG -
dear gurus,
can any body explains the concept of capacity levelling with t-codes.i already posted the same thread.but i require some more light.if any body explains it will be better for begginers.if anybody is having any doccuments regarding please send to [email protected]
-gunaHi,
The following points will be useful to understand the concept of Capacity Levelling.
Capacity levelling is only relevant for inhouse manufactured products and the existing capacity over load in work center with in a plant can be overcome by shifting the operation performed on the overloaded work center to a future period where capacity is avialable by using CM22
Example :
1) An order consist of 4 opns let us suppose ( opn 10,20, 30 & 40)
2) Opn 30 is being performed on a work center " WC1"
3) Assume Capcity load on this work center WC1 is 150% (TCode : CM05)
4) Shift some of the orders in the over loaded work center to a future period where capacity is available . When we are shifting Opn30 to a future period say 15th october , this opn date will be taken as reference & for all the preceeding operations backward scheduling carried out (ie for opn 10, 20). For all the succeeding operations (opn 40) Forward scheduling will be carried out.
5) Capacity levelling by shifting the operation can be used for MTS items with out any problem. In the case of MTO we should take in to account the customer requirement date while shifting the opn/orders to a future period.
Regards,
Ramasamy -
Hello ,
When the t/c cm21 or cm22 is excecuted , which 'overall profile' does the system select ?
Where do we define this.
Regards
ShankarRHi,
T,code:OPDQ,OPDE,
Most of the settings are under "'capacity levelling and extended evaluation'" in SPRO
Hope it helps
THNX
HKR -
Hi pp friends,
I have done all required settings and i can see periodrequirements in CM22 but don't know how to carryout lelling execution steps and how will it benefit in case of production order.
If possible send screen shots.
Thanks in advanceHi,
Capacity levelling can be performed more easily from transaction CM21(graphical) rather than CM22(Tabular).
CM21 displays planning table with 4 separate parts. upper left part gives details of work center, lower left part gives corresponding planned order./production orders(you can restrict in selection screen only production orders/planned orders). lower right part gives Orders pool and load will be shown in red colour. Upper right part gives any changes mode to capaciry requirements.
Please go through Standard SAP documentation related to Capacity levelling for more details.
http://help.sap.com/saphelp_47x200/helpdata/en/49/e6f3340cdb8c44e10000009b38f844/frameset.htm
From this transaction you can see capacity Overlappings on each work centers clearly. By levelling the capacity of production orders from here will change the scheduling of the operations.
Regards,
Krishna Mohan -
Is capacity leveling is in ltp
Is capacity leveling possible in the Long term planning i.e after simulative mrp run.
Regards,
Sunil PatilHi Mr.Sunil Patil,
Please check the help given by SAP.
SAP allows this.
http://help.sap.com/saphelp_470/helpdata/en/92/bf055544bd11d182b40000e829fbfe/frameset.htm
Leveling Capacity in the Planned Order
Prerequisites
The planned order must be scheduled.
Procedure
Starting from the Long-term Planning node, choose Long-term planning ® Simulative planned order ® Change.
The system displays the details screen for the planned order. From this screen, you can call up the capacity check, if necessary, by choosing Edit ® Capacity check. The system then checks available capacities. If no overload exists on the work centers in question, the system displays a message stating that no overload exists. If an overload does exist, the system branches to the capacity situation where you can make any necessary changes.
To level capacities, choose Goto Capacity leveling.
The system displays the dialog box entitled, Settings for Capacity Planning if you have not yet defined any parameters for capacity planning.
Select the appropriate planning type and the period type for capacity planning. If necessary, select a period of examination. Choose Continue.
The system carries out scheduling using the parameters set in Customizing.
If scheduling could not be carried out free of error, the system displays an overview of the scheduling errors based on the planned orders in question. From here, you can access the scheduling log to check the details on the scheduling errors. To do this, choose Log.
5. Choose Continue. The system displays the evaluation of the capacity situation.
Capacity leveling is also displayed with reference to a work center and a capacity category (for example, machine or person) and the unit of measure is displayed from the work center. Here, the following is valid: If a planning work center (routing header) is entered in the routing the system first displays this work center with the corresponding capacity category. Otherwise, the selection is random. The system also displays the following data:
Order number, order quantity and order finish date
Available capacity
Total capacity requirements for the selected work center
Capacity requirements for the material
Capacity requirements of the selected planned order
Capacity loads resulting from the selected planned order are specially indicated.
Regards
Mangal -
Resource scope when performing capacity leveling with Optimization method
Hello,
Can anyone tell me if, when performing the Optimization method in Capacity Leveling for transportation resources production resources are validated? I am currently testing this and I found out that if the capacity variant of the production resource is no 00, 01 or 02 the system will give an error message when trying to level a transportation resource, the message indicates that there is no available capacity for the production resource.
When reading documentation in help.sap it appears to me that Capacity Leveling should only focus on the resource to be level not in other resources and in this case my transportation resource has available capacity that shouldn't be affected for master data errors of production resources...
Could somebody help me clarify this issue?, I have already open a message and they suggested me to change the capacity variant of the production resource, evidently when I do this everything works but I still don't understand why capacity leveling, with Optimization method, of a transportation resources is checking on production resources.
Thanks!
ErikaHello Ian,
I am not talking about the SNP Optimization Run that is certainly manipulated by the constraints that you update on the optimization profile; in this case "Capacity Leveling with Optimization Method" the constraints are automatically set by the system and what I need to know is if these constraints are considering not only the resource that is to be leveled (in this case the transportation resource) but also the production resource.
Sorry but your answer does not correspond to my request, because you are talking about the Planning Optimization run and I am talking about "Capacity Leveling with Optimization Method".
Erika -
Workcentre change in capacity levelling
Hi Guys,
In capacity levelling of planned orders i want to move planned orders from one workcentre to another workcentre , could any one explain me how to do this.
Thanks and regards
Thamizhchelvan GDear,
Yes you can dispatch planned orders in CM21, CM22, CM25, CM27, CM28
Usually the following std profiles are used.
SAPSFCG021 SFC: Standard overview in order view
SAPSFCG022 SFC: Standard overview in indiv.cap.view
Just need to select the order then click on Dispatch(press F5)
Or,
1. CM 25
2. Select multiple operations ( Edit> Select> objects that belong together
3. Press Shift button and simultaneously press mouse left/right button then drag and drop .
Please refer this link for capacity levelling,
http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPCRPLVL/PPCRP_LVL.pdf
Regards,
R.Brahmankar -
"Multi-level error propagation carried out" in SCM 5.0
When I use the SNP PPM Generation With Lot Size Margin function in SCM 5.0, I got the following error:
Multi-level error propagation carried out
Message no. /SAPAPO/OM242
Could you please give me this help?
Thanks,
LianHi,
Thank you for the information, but the problem is still there though I de-activated all user-exits...
I also saw the following error:
Invalid planning version
Message no. /SAPAPO/OM015
Thanks,
Lian
Maybe you are looking for
-
Further invastigating ther error mentioned here: https://social.msdn.microsoft.com/Forums/azure/en-US/14afa50f-287d-4158-852a-c9532f9f30eb/test-published-web-service-experiment-error-with-status-code-400?forum=MachineLearning I have made an even sim
-
Hang Form Builder 10.1.2.3 for fmb files more than 2MB at Windows VISTA& 7
Hi When i open fmb files more than 2MB with Form Builder (10.1.2.3) at Windows 7 form builder Hange and Close. Please help me if have any configuration or patch for forms builder. Regards Adel
-
Oracle forms 6i hangs while connection to database
Hi, We are runing oracle forms 6i with patch 17 on windows xp and windows 7 with oracle database 10g(10.2.0.4) 64bits on window 2003 64bits every thing is fine but sometime all of the sudden connection get stuck and unable to get access to database b
-
How do I change the data format on a SPA9000 to dd/mm/yy?
-
Ms Sql Management Studio 2014 Express + Azure
Hi everyone I have SSMS 2014 Express and I use Azure SQL DB with SQL Database Update V12 (preview). Now I have the restricted access to my DB from ssms, but there (http://blogs.msdn.com/b/sqlreleaseservices/archive/2014/12/18/sql-server-2014-manageme