Capacity load in planned order

Hi,
I am facing problem to see a load as per planned order wise in CM 02 & CM 07. But I can see the load in md12 after rescheduling .I have done the following settings
1. While running MRP I have selected Lead time scheduling & capacity planning.
2.In Control key capacity tick is there
3. In work center relevant to finite scheduling
4 For scheduling & .Cpacity formula in IMG relevant for capacity tick is there.
Regards,
Balu

Hi,
For capacity =MACHINE * Operation quantity / Base quantity
For Scheduling =MACHINE * Operation quantity / Base quantity
I am using those formulae.
Regards,
Balu

Similar Messages

  • "CLOSED": HOW TO LOAD FIRM PLANNED ORDERS OF ANOTHER PLAN INTO ASCP PLAN?

    Hi everybody,
    How to load firm planned orders of plan 1 into plan 2?
    Business Case:
    Customer uses a separate planning for order intake. During order intake the requested due date is validated based on ASCP Gantt Chart. Bottlenecks are resolved. For make items firm discrete jobs are created, if adjusted suggested due dates are manually changed. For buy items firm planned orders are created for manually changed suggested due dates.
    If the order is accepted the demand is transferred from the Order Intake MDS into the so called Operational MDS. The firm discrete job will be automatically visible in the operational ASCP Plan (after data collection/running ASCP Plan).
    But how is it possible to include ONLY firm planned orders of another plan into your current plan?
    PLAN1 asigned master demand schedules
    - O_MDS1
    - O_MDS2
    PLAN2 assigned master demand schedules
    - O_MDS1
    - O_MDS2
    - T_MDS
    I want to transfer the firm planned orders from plan2 to plan1.
    Thanks for all your inputs,
    Catalina
    Message was edited by:
    user447176

    Since you need to run a data collection to load the new discrete job, I suggest you to add a custom step in the data collection.
    This custom step will
    1) select all firmed planned order in plan 2
    2) put the firm planned order into a new schedule through staging tables (MST_ST_SUPPLIES) .
    3) collect the data
    Then run plan1 with this schedule defined as demand schedule for your new plan.

  • Capacity check during Planned order to production order conversion

    Hello Gurus,
    I have a strange situation during capacity check.
    While Converting the planned order to Production order, I release the order and I don't get any warning. All work centers are available
    But for the same material/quantity/dates, if I create the Production order manually, release it, system check the capacity and I got the message the Capacity Over loaded (which is correct also as there are overload on the work centers).
    My question is why I am not getting this message while converting the planned order to production order.
    There are overload on the work centers and manual creation of Production order is working fine, but problem is during planned order to production order conversion.
    For information, I have maintained Finite scheduling indicator in OPKP, capacity availability indicator "NO CHECK" is also blank in OPJK.
    It will be grateful if you can please help me here.
    Thanks in advance,
    Sandeep Kumar

    Hi KK,
    Thanks for your feedback.
    I have checked all these settings but still no success.
    I am surprised but it is not a customizing issue I believe, because capacity is checked in Dev client while converting planned order to production order. I am facing this issue only in Staging client.
    Master Data is same. In CM01, in Quality(Staging) client, it is showing overload. while creating production order, it shows overload but only when convert from planned order to production order, it does not show overload .
    Please suggest what else I need to check.
    thanks in advance.
    Br,
    Sandeep Kumar

  • PP - Phantom Assembly Alt Item in BOM not loaded in Planned Order

    Hi all,
    I have a scenario where in my finished product, I have several components organized in Alternate Group, and for each group, I define a component as Prime (100% usage) and others as Alternate (0% utilization). Among these there are some components that are configured as Phantom (Special Procurement 50), and these Phantom items, when they are Alternate in the BOM, ie, 0% Probability of Use in Alternate Item Group, it is not loaded in the list of components in Planned Order. Only the Phantom that is as Prime in BOM is showed in the Planned Order, together with their subcomponents.
    The other components that are not phantom, usually appear within the Planned Order, those that have 100% utilization, and those who have 0% utilization set in the BOM. Obviously, all requirement is pointed in the Prime Item, but I can change according to availability of material in MDVP or manually in CO02.
    When the Production Order is created directly by CO01, without conversion of planned order, the list of components typically brings all the Phantoms, independently of the Probability Use %.
    Someone tell me if there is some kind of configuration to allow the Phantoms Optional also be uploaded to the component list of planned orders without having to change the percentage of use in BOM.
    Thanks in advance.

    Hello MCantos,
    When you have maintained the usage probability as 0% for a alternative component, that means you do not want that partular material to be planned further. In short this is just an Engineering Relevant Material (is not required in Production activity).
    When this alternate material with usage probability 0% is phantom material, you want its components to be proposed. But you yourself have answered that this phantom material has usage probability 0% and this means it is not required in Production and thus its components as well are not required. Thus system is not exploding the BOM and proposing the material at the time of Production activity.
    Hope I answered your query. Please check your usage probability for phantom assembly part and if required correct the same so that you can achive what you want.
    Thanks,
    Rahul.

  • Capacity Booking by Planned orders from MRP

    Hey All,
    I would like to know how Capacity is booked on the Planned orders resulting from the MRP run.
    Regards.

    Hi Danish,
    On the basis of Delivery Date or requirement date system schedules the order either it is though Backward or Forward scheduling. For this calculation system considers the Inhouse Production Time , GR Processing Time , Routing data etc.And during this calculation system will ignore the available capacity on particular date means you have to perform Capacity Leveling later.
    And on the basis of that Routing which is selected during MRP run system generates the Capacity requirement on the relevant work centers / Resources.
    Refer below link,
    [Detail Scheduling|http://digilander.libero.it/vietrim/]
    Regards,
    Dhaval

  • Capacity planning at Planned order level

    Dear All,
                      In my current scenario i'm able to see load of process orders against the workcenter in CM01. My requirement is to do capacity levelling at the planned order level.
             I have created Production version also & attached to the planned order. Still in CM01  no load or planned order is shown on workcenter.
    when i convert it into process order then it shows load / process order.
    pl.let me know how i can do the capacity planning at planned order level.
    Thanx & regards,
    dev

    Hi,
                       In MD12 when click on Go to > Capacity Levelling >
    Error Message : No work centers with capacity requirements were found
    I have given formula : SAP006 in capacity & Relevant to finite schedulling indicator is also active.
    what may be the cause ?
    thanx & regards,
    dev

  • Capacity for only Production orders only.

    Hi
    I am checking capacity loads in CM01.
    In this t-code its considering my Planned orers also.
    I want to capacity load for production orders only.
    we dont want during planned orders stage.
    where can i check.. what are the settings i have to do for checking capacity for only production orders.
    Regards,
    srihari.M

    Srihari,
    This is a standard requirement.
    Planned orders in a non-repetitive environment typically are not dispatched nor confirmed.  They do not, therefore, become part of the 'Basic Load'.  The capacity requirements of planned orders are there mostly so you can view the capacity requirements in sum with the production order capacity requirements (CM01 and similar).  They do not 'consume' from total available capacity.  When performing a capacity check of a production order, it will not 'see' the capacity requirements of the undispatched planned orders.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/60/13e30b133a11d3bf550000e83235ee/frameset.htm
    Best Regards,
    DB49

  • Planned order capacity requirement load on holiday

    Hi ,
    We have some cases , the planned order capacity requirements be load at weekend (holiday), but we have no same issue for process order , that's means the resouce set up is correct.
    Is any customizing related with planned order capcaity requirment ?
    Thanks !

    Hi,
    If you select the Workday indicator  = 1 (Working days (overrides factory calendar) at "Interval of available Capacity Screen" of Workcenter screen system will schedule the  Order during the Holiday.(CA02)
    This is applicable for Both Planned Order and Process Order.
    Pradeep

  • Planned order based capacity planning

    Dear Guru's,
    Is it possible to view & analyse work load on work centers for planned orders in R/3? Please let us know the settings to be done if needed.
    Regards,
    SAP CONS

    Hi,
    Yes it is possible to view and analyze the work load on work centers for planned order..other than standard configuration settings and master data set up no separate settings required for this....still wait for the answers from the other forum experts.
    Ensure while doing MRP run  on MRP control parameters use option 2 for scheduling as shown below..
    Please check the below link....
    SAP的学习和考试 Learning & Examination: ~ CP04 Leveling with Finite Capacity Forward Scheduling
    Thanks
    Kumar

  • Load distribution of a Planned Order Operation

    Hi All,
    Need help in understanding an issue here.
    For a Planned Order, detailed scheduling happened ,and schedule and Cpacity requirements were generated.
    This is the case with just 1 operation. The requirement of this operation is of 1 Hour and schedule was created in Planned Order for the date- 01.07.2014.
    But when we go for the capacity evaluation, in CM01> It shows load devide over two periods> 30.06.2014 and 01.07.2014.
    That is,
    For, 30.06.2014 load is-->0.614 hrs. Though, Latest start data and time still is same as in Planned order[01.07.2014]
    and for 01.07.2014 load is>0.386 hrs. Latest start data and time still is same as in Planned order[01.07.2014]>Which is normal
    That is a total of 1 hour.
    Please help me understand what made this happen in Capacity evaluation, why we have different data in Planned Order and in CM01.
    Why the load got devided over
    Regards,
    Avinash

    Hi,
    To add further and to more precise, the issue is:
    In CM01[or in any capacity evaluation tcode], In a particular maonths load[Period] the opeartion from different month is showing up.
    For example: if Period[month] 06 is veiwed of a Workcenter load, a line[load appears], whose earliest date is in 7th month[01.07.2014].
    I expected to see, only Workcenters scheduled in 6th month to show up in the load evaluation.
    Please look at the screen shot.
    Regards,
    Avinash

  • Sales order schedule confirmed date will consider Production capacity load

    As we know about schedule confirm delivery dates of sales order will consider based on material master lead time ,shiping point etc
    How to consider production capacity plan on sales order's delivery date.
    Say for example :
    Production workcenter capacity to produce the XYZ material 10qty in a Day.
    today i have created the sales order XYZ materail qty of 100. lead days has give based of MMR 21 days 17-07-2010( 3 sundays)
    and in same day i have created other sales order XYZ material qty 5000 ,the lead days again it will came 17-07-2010.
    Now my client requiremnt is when the schedule days is confirming in the sale order it sholud also consider the production capacity planning also(CR01,CR02)
    Even though my work centers are overloaded it is confirming the sales order on 17-07-2010 (based on leads days in MMR)
    Need your Inputs on issue

    Hi,
    This is a complex issue; best solution is by using APO/GATP.
    If not, then in ERP only, the second best is:
    1) Work with assembly processing in SO, meaning that a production/planned order is automatically created in the customer order during order creation.
    2) Then, after the order is created it is scheduled, and the delivery date proposal is based on that.
    3) Now you can check in the order that there are no capacity overloads, and all capacity required to produce on the proposed date is available. If yes, you're done. If not, it gets a bit complex, since you actualy need to switch to capacity planning, do capacity leveling and dispatch (PP), and the you get a new feasible schedule proposal based on that.
    APO/GATP could do all that automatically!
    Regards,
    Mario

  • SNP Planned order not following resource bucket capacity/factory calendar

    Hi gurus,
    SCM 5.0
    I am running SNP heuristics for a product and expecting planned orders for it.  It has corresponding production data structure and multimixed resource.  The resource has an assignd factory calendar and SNP bucket capacity.  The bucket capactiy availablity dates of the resouce is consistent with the factory calendar workdays/holidays.  Using simple lot for lot strategy, I am expecting heuristics to schedule the planned orders on the dates of the demand in compliance with teh SNP bucket capacity availability of the resource.  APO does not schedule on holidays consistent with bucket capactiy.  This is true until...
    We have a public holiday in factory calendar that needs to become a workday. To remedy this, we put a special rule for the factory calendar and explicitly made that holiday into a workday.  The changes were synchronized with APO, and this is also reflected in the bucket capacity of the resourc: former holiday now has bucket capacity after the calendar change.  However, when running heuristics, it still does not create SNP planned order on that former holiday that has been changed into workday.  Even if it is a public holiday, there is already a special rule for the factory calendar and the resource bucket capacity reflects this correctly. But SNP heuristics seems not to follow this change.
    Any ideas on this? looks like a bug.

    Hi Edgar,
    Yes, when your resource reflects the addional capacity of the holiday turned working day, then it is expected to be considered for the SNP planned order.
    Instead of SNP heuristics, you may try to check interactively in SNP planning book, if manual order creation in the bucket works out.
    Since this is a mutlimix  resource , it can also be checked if in PPDS planned order can be created on the day.
    The above checking may not solve your problem , but will get to know if at least manully the bucket is being considered or not.
    regards
    Datta

  • Planned order splitting during capacity planning

    Hello,
    anybody plese help me during the capacity planning in T.code.CM31 i want to split a planned order and want to assign alternative sequence. how can i do this and the capacity should be reschedule automatically to my requirement date. i am using backward scheduling.
    plese suggest immediately
    Thanks and reagards
    Bhakta

    Dear Bhakta
    MRP does not perfom any Capacity Requirement Planning .While  you are executing MRP with Lead Time Scheduling , MRP proposes Planned Order Dates based on the Routing Operation Timing not based on the Work Centre available Capacity because in SAP Std R/3 we did not have scope to check the finite scheduling and capacity requirement chek .MRP assume that Work Centre has infinite available capacity .
    In MRP run , it will give you Detail scheduling of the Operation in Planned Order -Detail Scheduling tab  and copied the routing , BOM as master data .When you convert that Planned order to Production order , it will copy the Routing details based on the Order Type denpendt Parameters -OPL8-Routing -Alternative sequnce  and Automatic selection -3 option
    Thats why we have Capacity Requirement Planning  for Detail Capcity check and production order scheduling  .
    Note : Earlier to my first  reply , please note that you have option in CM21  enter sequence number  at order level which may applicable to you .CM21-Work Centre -exectute -Select the Order from order pool -Goto Order -Sequence number maintainence
    This number( sequence number operation /order )  that can be assigned to production orders or planned orders at the level of the task list header and is therefore valid for all the operations in an order.
    Hope this is clear .Revert if you nees farther help
    Regards
    JH
    Edited by: Jiaul Haque on Jul 5, 2010 3:32 PM
    Edited by: Jiaul Haque on Jul 5, 2010 4:01 PM

  • Use of Planning Table (MF50) in Capacity Levelling with Production Order

    Hello Experts
    I wish to know that is it possible to perform Capacity Levelling in planning table (tcode MF50) with respect to a Production Order ? It is known that MF50 is used in Repetitive manufacuring to do the capacity levelling with respect to Planned orders. But in our discrete manufacturing scenario we want to use planning table to the capacity levelling with respect toa Production order.
    Any clue or help pertaining to this will be highly appreciated.
    Thanks in advance
    Regards
    Jayanta

    Dear ,
    MF50 is does the cacapcity leveling based on mateail -run schedule order (planned order ) where as in discrete manufacturing , when you run the MRP ,  MRP system assume Infinite Capacity  and schedule the order as per your selection in MD02(2,1,3,3,2)  and then you convert those planned order to Production order .Here you checkied the Capacity in Production Order level .
    In stanadrd SAP  , it is not possible to use MF50 for discrete production order.
    In discrete order or process order ,  do the caapcity leveling , there are seperate planning table available based on Over all Capacity Profile and Schedule type .This can be done  in following way :
    1.CM31-Production Order Wise -Tabular
    2.CM23-PO wise -Graphical
    3.MC88: Ruf Cut Planning
    Work Centre Wise : CM21 -Graphical , CM22-Tabular Planning Table .
    Make sure the below set up before  you carry on the Capacity leveling :
    .Define time profile in OPD2.
    Define the strategy profile in OPDB
    Define the Overall profiles in OPD0.
    In OPJK  maintained check capacity with SAPSFCG013 profile for your production order type
    In OPU3 , scheduleing parametre s: Generate Capacity , Scheduling Type , Automatic Log ,Start date in Past as per your req.
    In OPJU , chekc the contol tab of the scheduleing as per OPU3
    In OPKP- Production scheduling paranmeters assing the overall capacity profile -SAPSFCG013  with finte scheduling tick.
    Master Data :
    1.Materials Master define the Production scheduler and production scheduling profile
    2.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
    3.Routing - enter the values for the standard values. Use control key with scheduling.
    Hope this will help you .
    Regards
    JH

  • Remaining capacity requirements scheduled for operation in Planned Order

    Hi all,
    I'm workig with planned orders, and I need the "Remaining capacity requirements scheduled for operation" data to list it in a Z Report, but I don't know how to get it.
    You can see the info in the "Detail Scheduling" of the planned order in MD13.
    Anyone knows how to get the info? Any table or any FM to get it?
    Points will be given for helping
    Thanks in advance!

    Did you ever find out where the planned order capacity information lives?  I can find the production capacity information in table KBEZ, but it appears that there is no planned order info there.
    Thanks,
    Matthew Bruckner

Maybe you are looking for

  • Download data from ALV to excel issue

    Hi All, Could you please tell me if there has any restriction on ALV grid data download to excel? I've a report contains 68 columns and about 500 rows, I want to download the data using the standard menu list->export->save to local file. but after I

  • Faulty line for over a month now but BT says it is...

    Has anyone got any suggestions, please?  I reported a faulty line on 22nd April - it had an increasing amount noise on it (which it has had for ages but had become unbearable) including clicking, and my broadband kept dropping.  I had done all the us

  • Error in Script Logic

    Hi All, For the below code i am getting error. any alternate way to resolve this issue. *WHEN P_ACCT *IS "EXTSALES", "ICSALES" *REC(FACTOR=1.5,P_ACCT="UPSIDEFACTOR") *ENDWHEN *COMMIT Error LINE:3 multi-member specified for dimension "3" *IS How to re

  • Problem with select many rows in table

    1. I have af:table 2. In my bean I get the selected rows with DCIteratorBinding countriesIterator = ADFUtils.findIterator("FigureTypesViewIterator"); RowKeySet rowSet = this.getRichTable().getSelectedRowKeys(); Iterator rowSetIterator = rowSet.iterat

  • How to split up an album

    i downloaded some songs and they ended up in the same album but i want them seperated