Capacity Plan for Partially Confirmed Order

Hi Guys
Can any one please guide me on Capacity Planning (CM29) how to:
1. Plan to plan a partial order. Or in other terms: how to plan a part order in wk1 and rest in wk2
2. If the process order is partially confirmed, then how should supervisor re-schedule it again for later date!
3. Ideally what should be followed:
  a. Schedule the Planned Order on CM29 and then Convert them to Process Order , OR
  b. Convert the Planned Order and then Schedule the Process Order on the CM29 screen
Thanks in advance
-Rahul

Hi Mehdi,
Once order status is PCNF you cannot create lot with inspection type as 03. You need to reverse all the confirmations/Goods issue and activate 03 inspection type in material master, maintain MIC related data in routing and do Read Master data. Then system will create inspection lot.
For 03 inspection type manually inspection lot cannot be created. Once order is released inspection lot will be automatically created by system.
Thanks & Regards,
Ramagiri

Similar Messages

  • Workforce Planning for Partially Confirmed Activities

    Hi All,
    I have recently configured Workforce planning for one of the clients, and it has been working as per the requirement. Here, I have configured Workforce Planning profile and Scheduling parameters of Network. So, once a Project and a Network is created, User plans Personnel for this Network's activity using CMP2. Also, CATS profile is maintained in such a way that Worklist shows the Planned hours and accordingly a person can book Time against it.
    Now, the problem arises after a Personnel assigned to an activity books the Timesheet. Once a Person books time against this particular Activity, it gets disappeared from CMP2 screen. Now, practical implications are that, suppose that person goes for a leave or leaves the organization and PM wants to assign another person for the same Activity (which is partially confirmed).
    How can we address this issue - to perform workforce planning for Partially Confirmed activities?
    Any pointers to User Exits, BADIs, BAPIs or SAP Notes are highly appreciated.

    Hi Sanjeev,
    Thanks for your feedback.
    In CMP2, we are already checking the activity work hours. According to that only we are adding resource, then checking that resource's availability and then assigning work.
    As an example, activity work duration is from 20.08.2014 to 30.09.2014. I assigned a resource A from 20.08.2014 to 30.09.2014 for 8 hours because he is available in that duration.
    Now, the real problem comes when this resource is suddenly unavailable (due to any reason) and PM comes to know about this on 07.09.2014. Resource A has already booked Timesheet for the duration he has worked (20.08 to 06.09). So activity is PCNF.
    So PM wants to reduce the Work assignment for Resource A from 30.09.2014 to 06.09.2014 and assign Resource B from 07.09.2014 to 30.09.2014, but he is unable to get this activity in CMP2 view because it is PCNF. Here PM can only see activities of same project which are in REL status.
    So how can I enable this PCNF activity in CMP2 view.
    If there is any IMG activity settings, then let me know.
    If this is standard behavior and can be done through User Exit/BADI/BAPI then also let me know.
    Message was edited by: Aditya Kotak

  • Capacity Planning for all Sales Order Items

    Sir,
    A Sales Order have 4 different line items & need to produce on single work center.
    In schedule line of sales order requirement dates are given priority wise.
    After running the MRP I have observed that for all schedule lines, all planned ordered are starting on same date & time on the given capacity.
    I need to level it manually.
    Here I have few Question.
    1) Can Capacities are Scheduled as per priority given in SO automatically.
    2) Can revised availability dates will be reflected in SO.
    3) Which reports will be useful for understanding consolidated availability date of material for given sales order/s.
    Regards

    Dear ,
    To answer the question for Capacity requirement planning on sales order I would say that MRP does  only materials planning based on demand and reciept  but never does Capacity Requirement Plannig .MRP generates Planned Order  and susequently , production order can be genreted and farther you can carry out capacity requirement planning based on the work cente available capacity , requirement and load for those MTO orders .
    But there are SAP business suit like APO-SNP APO PPDS which carriy our details scheduleing and caapcity check based on the demand situation : Sales Order ,Independent Order  and does capcaity vaialbality chek for those demands while planning .
    Now , here is the answer of your question :
    1) Can Capacities are Scheduled as per priority given in SO automatically. : Not possible  through  SAP MRP but in APO-PPDS, APO-SNP-CTM , Herustic model .
    2) Can revised availability dates will be reflected in SO. : It can be reflected as per the ATP chekc , Replishmenet Lead  Time and re-scheduling horizon maintained in OPPQ-Carry all overall plant parametres.
    3) Which reports will be useful for understanding consolidated availability date of material for given sales order/s. : You can check through MD04/MD05 or in sales order -Availaibility check -Schedule Line -Availaibility date .
    Hope your are clear about the requirememt .
    Regards
    JH
    Edited by: Jiaul Haque on Jun 5, 2010 1:59 PM
    Edited by: Jiaul Haque on Jun 5, 2010 1:59 PM

  • Report for mass interruption of partially confirmed orders in PPDS?

    Hi gurus,
    our client has a lot of partially confirmed orders in the past, and this is giving us problems with the optimizer.
    Is there a report for mass interruption of this orders?
    We can do it one by one in the DS planning board, but there are too many!
    would appreciate any help,
    Pablo

    Hi Pablo,
    I would suggest you can close the partially confirmed orders at R/3 itself
    so that it will update in APO via CIF.
    There is delivery complete indicator in R/3 production/process order which
    upon checking will close the order.
    Regards
    R. Senthil Mareeswaran.

  • In process inspection for partial confirmation of production order

    Hi QM Guru,
    how i will do in process inspection for partial confirmation of production oder
    Senior is this  I have maintain inspection type 03 in finish material u2026..suppose production order quantity 20 kg..there are 2 operationu202610 and 20.. I have maintained MIC on operation 20u2026after release the production order  lot are generatingu2026but when they confirm operation 10 they do partial confirmation for 10 kgu2026.then again when do confirmation 20..they checku2026for quality resultu2026
    Then I do the result record ok of 10 kgu2026then they confirm 20 operationu2026.
    Now. again he do the confirmation of rest production order 10 kg..opration 10 ok..but in operation 20..system does not check for qualityu2026..
    Again I want to do the quality inspection of 10kg on 20 operationu2026
    How I will do. kindly suggest me
    Regards
    Aqueel

    Hello
    I think that the process can be mapped in one of these ways:
    - according to what you describe this is closer to a good receipt inspection and not to in-process inspection, as the trigger for the inspection is the GR and not the release of the order. So, why dont you give a chance to a 04 inspection type, with inspection lot creation for every GR ? Check the indictor in MM02, QM view for "04" inspection, and uncheck the "Stock in quality", so you dont get caught by the stock in quality and resembles in process "Non-stock relevant" inspection
    - alternatively you can define the use of inspection points ? So you are adding new results as new confirmations are made. Disadvantage: you can only give one usage decision to the inspection Lot, irrespective of the number of samples you have analyzed.
    Regards

  • BAPI for Partial Confirmation CO11N

    Dear Gurus,
    REG : BAPI
    How to get the actual activites for partial confirmation of qty
    we have tried some bapis like for getting activites we have used
    bapi_prodordconf_get_tt_prop
    but in this bapi it is calculating total qty i.e, order qty not for the yeild qty.
    I need to get the yeild qty planned activites
    Tks
    Murali

    Hi,
    Check the Bapis
    BAPI_PRODORDCONF_CREATE_TT 
    BAPI_PRODORDCONF_CREATE_HDR
    Regards,
    Raj.

  • Capacity planning and schedulng production order based on availabe capacity

    Hi Gurus,
    I am trying to use capacity planning, when the production order is created it takes the order start date as the requirement date. Then when i do he capaity check it says capaity not available. After finite scheduling again it proposes to shift operations by certain days.
    I need the capity to be check in MRP and the palled orders to have start dates based on aviable capity, currenty all the palled orders are starting on the requirement date irresptive of avaiabe capaity. I tried using finite scheduling option in MD02 still it does not take in to account exsting production orders for giving dates of the planned orders.
    Regards
    Abhi

    Dear Abhishek,
    1) This is Std SAP of MRP, only material Av check will be carried out in MRP & create procurement
    Proposals
    2) Capacities will not Checked  ( consider ) in MRP in Std R/3
    3) Your Need can be only met through APO
    Regards
    Madhu

  • Constraint capacity planning for Un-Routed items in ASCP

    Hi All,
    Is there any possibility to create constraint capacity planning for items which do not have routings in ASCP?
    I tried by setting Bill of Resources (BOR) in Aggregatin tabbed region in Plan option. But i could not get an expected result. Kindly help me out in this.
    regards,
    Murlai R
    Edited by: user10942922 on Mar 27, 2009 9:30 AM

    Dear ,
    To answer the question for Capacity requirement planning on sales order I would say that MRP does  only materials planning based on demand and reciept  but never does Capacity Requirement Plannig .MRP generates Planned Order  and susequently , production order can be genreted and farther you can carry out capacity requirement planning based on the work cente available capacity , requirement and load for those MTO orders .
    But there are SAP business suit like APO-SNP APO PPDS which carriy our details scheduleing and caapcity check based on the demand situation : Sales Order ,Independent Order  and does capcaity vaialbality chek for those demands while planning .
    Now , here is the answer of your question :
    1) Can Capacities are Scheduled as per priority given in SO automatically. : Not possible  through  SAP MRP but in APO-PPDS, APO-SNP-CTM , Herustic model .
    2) Can revised availability dates will be reflected in SO. : It can be reflected as per the ATP chekc , Replishmenet Lead  Time and re-scheduling horizon maintained in OPPQ-Carry all overall plant parametres.
    3) Which reports will be useful for understanding consolidated availability date of material for given sales order/s. : You can check through MD04/MD05 or in sales order -Availaibility check -Schedule Line -Availaibility date .
    Hope your are clear about the requirememt .
    Regards
    JH
    Edited by: Jiaul Haque on Jun 5, 2010 1:59 PM
    Edited by: Jiaul Haque on Jun 5, 2010 1:59 PM

  • Capacity Planning for External Procurement Material

    Hi, I have the following requirements.
    MRP Scheduling is getting executed material level (material no, plant) with scheduling type 2 which means lead time scheduling using MD02 Transaction Code. This is works fine for the Inhouse Product. In order to achieve lead time the functional team has maintained the necessary routing/workcenter configs.
    The business needs the same functionality "Capacity requirements calculation" for the external procurement material. Business is willing to maintain routing/workcenter config.
    Currently standard program (MD02) is not considering the Capacity planning for the external Procurement material.
    Could you please suggest is it can be controlled through programming.
    Kindly suggest the function modules for Capacity Planning - materialwise, plantwise.
    Please suggest.
    Thanks
    Giri

    Hi Giri
        I think the requirement is not mentioned clearly. Capacity is required only if the material is assembled/produced in house.
    Anyway try this. Set the Procurement type to X in the MRP views in material master. You might have to define your custom material type so that it does not force the procurement type to F. Try the feature called "Quota arrangement". The idea is to define the material in such a way that it can be procured externally or produced in house. With quota arrangement you can say what % has to be bought and what % to be produced in house. If it is produced in house then you can have capacity requirements.
    Regards
    Pragnesh

  • Capacity Planning for Workflow Manager

    Some information is available regarding highly available Workflow Manager implementations but I cannot find any information regarding when or how you should perform capacity planning for the workflow manager.
    A few questions are jumping out at me.
    When would we want/need a dedicated Workflow Manager server? (I can understand if this was shared between multiple farms this may be a benefit but what about from a pure capacity perspective).
    Are there any case studies or documentation that we can use as a baseline estimation for capacity for the workflow manager?
    Generally speaking for a small/medium farm deployment is it expected that this service also run on the application server?
    certifications MCITP, MCTS, MCPD | blog
    http://corypeters.net | twitter
    @cory_peters

    That would really depend on what kind of workflows are being run and the traffic being generated by the users. If you have long and complex workflows, you will need multiple nodes in the farm to handle.
    Our tests with very simple workflows on a 16-core 16GB machine with SQL Server on a diff machine showed that it could handle 400 incoming messages per second and 65 workflow executed per second. Now if you have complex workflows, it may slow down further.
    If you have one msg per user per second - it may mean 400 users handled per second. But I wouldn't make that conclusion - u must test your farms against your scale needs and accordingly plan your farm capacity
    Hope this helps
    Ravi Sekhar

  • Capacity planning for DB, pctfree pctuser

    What is segment, pctfree, pctused ? want to clear my concepts...
    Secondly how we can do capacity planning for Database growth?

    The simplest and most accurate approach is
    - Create the schema
    - Load it with a representative amount of data (i.e. 1-2% of the expected data volume)
    - Measure the amount of disk required
    - Multiply by an appropriate factor to determine the eventual size
    You can also do back of the envelope calculations, taking the average row size of your larger tables, multiplying by the expected number of rows, then adding an appropriate multiplier. Probably in the neighborhood of 2 to account for indexes, empty space in the table, etc., but this is very application specific.
    Justin

  • Capacity Planning for OBIEE

    Hi,
    I am looking for some information on how to do capacity planning for obiee imlpementation. Any pointers would be much appreciated.
    -Thanks

    Check out this document:
    http://www.peakindicators.com/media_pi/BI+EE+Architectures+and+Sizing.pdf
    regards
    John
    http://obiee101.blogspot.com/

  • Capacity Planning for Hyper-V individual host and Cluster

    Hi Experts
    I need to know some basic idea about Capacity planning for Hyper-V which requires Capacity Planning for Hyper-V individual host and Cluster.
    I got attached info on websites but still not clear. Can someone link me to an effective website or help me to calculate the required sizing. W
    Regards Suman B. Singh

    Hi,
    You might want to check out these websites:
    http://www.microsoft.com/en-us/download/details.aspx?id=39057
    http://technet.microsoft.com/en-us/library/dd277865(v=office.12).aspx
    http://technet.microsoft.com/en-us/solutionaccelerators/dd537570.aspx
    Cheers
    Andrew

  • Can anybody give me the formula for Database capacity planning for 10gR2?

    Hi ,
    I want to learn how to make database capacity planning for production in 10gR2. Here i need any formula to plan the capacity.
    Can anybody help me?
    Regards
    Rajesh

    hi,
    There is no perfect world. There is no perfect application. If I am permitted to say, there is no perfect CAPACITY PLANNING. In this world, we strive hard to achieve near PERFECTION
    DISK SPACE ESTIMATED FOR THE DATABASE(RDBMS) ONLY
    ESTIMATES ARE BASED ON ASSUMPTIONS, SAMPLING, STATISTICS
    ESTIMATES CAN NOT QUANTIFY DISK SPACE REQUIREMENTS IN REAL TIME
    ACTUALS ALWAYS VARY FROM ESTIMATES.
    so ther is no particular formula to plan capacity planning.
    or post your rquirements for the DB and wait for some reply
    regards,
    Deepak

  • Bandwith Capacity Planning for 100 user SSL VPN Facility

    What are things we should conisde while doing the  bandwidth capacity planning for SSL VPN Facility for 100 users  ?       

    Hi Surya,
    This is not an easy question, since there are so many things to consider that I may miss some of them.
    1- In case you are planning to use an ASA, check this to find the ideal throughput for you:
             Compare Models
    2- What type of traffic? TCP or UDP?
         If TCP
              Make sure you avoid fragmentation, adjust the MSS value if necessary.
         If UDP
              If fragmentation must happen, then set the DF bit to clear to allow it.
    3- Make sure the clients always negotiate DTLS (which is by default).
    As mentioned in the document above:
    "Maximum throughput measured under ideal test conditions.
    VPN throughput and sessions count depend on the ASA device configuration and VPN traffic patterns. These elements should be taken into consideration as part of your capacity planning."
    Thanks.
    Portu.
    Please rate any post you find useful.

Maybe you are looking for

  • My External Drive...with ALL myTunes Library, is now a paperweight!

    I HAD a Seagate External hard drive that I'd partitioned to hold my iTunes library. It is now totally dysfunctional, and according to the Seagate technicians, valuable only as a paperweight. I still have all my music on my iPod, but what do I do to "

  • What does Firewall do?

    Hello everyone! I have been receiving BBM boradcasts from friends asking to Enable Firewall saying that it will prevent the network provider from accessing our phone and viewing our photos. Could someone pls explain the function of the firewall and i

  • No Login for GWMonitor on Linux?

    I installed gwmonitor on SLES and unlike the Windows version I do not see a section for authentication to the gwmonitoring URLS. Can someone help me locate that? We certainly want authentication to our monitoring service. Thanks, Lee

  • Excisable Finished Goods Stock Transfer (India specific)

    Hi Gurus, Is it possible to handle the stock transfer of Finished Goods from one excisable (manufacturing) plant to another excisable (manufacturing) plant in SAP CIN? If yes, can you please advise the steps? Looking forward to your expert advise. Re

  • Can`t access songs

    I deleted the mp3 files from my computer due to lack of space but now I don`t have anything in my ipod library, even though I can play the songs from the ipod when connected to itunes. Is there a way I can re-join my ipod data to my itunes library wi