Capacity planning ( CM01 ) across Plants

Hi all
I have a scenario where a material can be manufactured across Plants as an example
Plant1 - Work Center ( WC 1)
Plant 2 - WC2
Plant 3 - WC3
I want to look at capacity across all the 3 work centers at a group level so that if WC1 is overloaded then I can shift my production to WC 2. I want to use a 'pooled' capacity concept. If I use Work center heirarcy then I am restricted to creating a heirarcy at a Plant level.
Is there a way I can pool capacity of work centers in different plants into one pooled capacity?
thanks a bunch

Hello
1)Using CM50 you will get details capacity load irrespective of plant,just u have to enter the work center  and execute it will display the work center wise capacity detail
2)Using CM21 transaction enter only work center and execute it will display the planning table with order number details on which date work center is loaded. So manually u can allowcate the operation to the particular work center
I think this will be helpfull to u

Similar Messages

  • Plant Maintenance: Capacity planning CM01/ CM07

    Hi
    In capacity planning CM01, the standard sap shows all the maintenance orders which have system status created. But we would like to look at onlly the released pm order in the standard overview list and detailed capacity list. Please let me know if there is way we can configure it.
    Thanks

    Hi Nayan202,
    You could configure desired "selection set" T.code "CSM1" and then assign this to appropriate "Selection Profile" under initial set.
    Hope this helps.
    Shahnawaz

  • Maintenance Work Center : Capacity Planning CM01

    Hello Gurus,
    We are using T-code CM01 to determine the Requirements / RemAvailCap of the Maintenance Work Orders in a given Maintenance Work Center.
    After executing CM01, the detail capacity list contains Not Scheduled orders( CRTD )and  capacity of these not Released orders also taking into consider.
    How to restrict CM01 Order selection based on the work order System status or User status ?
    I found below discussions on SCN but couldn't get precise answere.
    Plant Maintenance: Capacity planning CM01/ CM07
    Configuring profiles in CAPACITY PLANNING (CM07)
    Please help.
    Thanks in Advance
    Ashok M

    There are a few ways:
    Create a new status profile via BS42 and assign the REL status only (see image 1). Then in the CM01 display screen, use menu path: Planning->Selection->Order and enter the status profile created above (see image 2)
    Create a new selection combination via OAP0. In the CM01 display screen, use menu path: Planning->Selection->Combination and enter the selection combination created above (see image 3)
    The above settings can then be defaulted via the various capacity planning profiles.

  • Capacity planning CM01 not displaying PM Order capacity

    Hi experts,
    I have created one order with the work center and defined operations...... but i am not able to see the CAPACITY REQUIREMENTS in the capacity planning (CM01)............
    Please suggest me what should  i do for this.............

    Hi Maheswaran,
    Thanks for the information , in configuration "Capacity Requirement Planning" have been maintained and now i am getting the CAPACITY REQUIREMENTS and CAP. LOAD also .........................but there is one problem i.e. when i am seeing the capacity planning (CM01) , IT IS NOT SHOWING THE VALUES ON THE DAY WHICH IS WORKING actually according to factory calendar FRIDAY and SATURDAY are holiday, but it is showing the value on SATURDAY and not showing the value on THURSDAY that is today........Please see the screen shot also......
    what should i do.......

  • OPU5 settings and Capacity planning-CM01

    Hi All,
    I have a confusion while configuring the settings for scheduling for planned orders in REM environment PE order type, when i select the scheduling and capacity requirements in DS section system shows me capacity requirements in CM01,CM50 reports  and also DS tab in planned order but when i deselect the same check boxes there si no data in CM01, CM02 or CM50,
    If I need to generate the CM01, etc reports in REM environment , then do i need to select DS check boxes also?
    My OPU5 settings are as attached in this case CM01 reports are fine.
    Regards,
    Anupam Sharma

    Hi Anupam,
    Screen shot is missing. Rate based scheduling is fine for REM.
    Create a "Run schedule" planned order and schedule it via rate-based scheduling.
    In transaction OPU5, choose order type PE and the plant you use.
    Choose "Details" and in the field "Scheduling level", set "1 Via rate-based scheduling" and save the change.
    For more information on this visit the following links
    http://help.sap.com/saphelp_47x200/helpdata/en/8a/a58a864adc11d189740000e8322d00/frameset.htm
    Levels of Scheduling - Planning Process - SAP Library
    Regards,
    R.Brahmankar

  • Capacity Planning CM01 Question?

    We have a production order schedule for a workcenter over 3 Days.
    The workcenter capacity is 15.74 HR
    When i run CM01 without any Qty confirmed.
    Day 1 has Requirements as 14.24 HR
    Day 2 has 15.7HR
    Day 3 has 15.7 HR
    After i did a confirmation for Qty 1000.
    Day 1 has 13.28 HR
    Day 2 has 14.67 HR
    Day 3 has 14.67 HR
    My questions is why would capacities for Day 2 and Day 3 reduce. All the hours should have been consumed from Day 1 ?

    Please check your order. It must have been scheduled over >= 3 days. Thereby adding capacity requirement over 3 days.
    When you confirm the order, where confirmed order quantity is equivalent to 3 days of your capacity. Thus system reduces the capacity requirement from 1st Day and subsequently from next days also.
    Thanks

  • Capacity Planning CM01

    Hello Experts,
    The required hours of a production order are the actual hours and not the remaining hours. So if the order has 8 hours and there is already 6 hours booked, I want to see the remaining 2 hours and not the complete 8 hours. How to do that? I have tried a lot off things but donu2019t get the result that I want?
    Mukesh

    Not clear how you have booked 6 hours out of 8. You mean dispatched? Ot they are in different operations and you have dispatched the first ? Or you have confirmed 6 hours as partial confirmation in an operation having 8 hours as planned time ?

  • CM01 / capacity planning / generate graphic automatically ?

    Hello experts,
    we have implemented the capacity planning for our production.
    The processes are working fine.
    But I've got the following requirement to solve:
    Is it possible to generate the graphical views from CM01 every day automatically in background jobs and send them to printers or email-accounts (nice to have)?
    Thanks a lot for your answers.
    Regards
    Markus

    Dear,
    Yes it is possible to generate the graphical views from CM01go toGraphic--standard overview.
    But automatic in background it is not possible.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Maintaining work center list in Capacity Planning: Selection List in CM01

    Hi,
    Where can find the config route in SPRO for maintain work center into the Capacity Planning: Selection List in CM01?
    Thanks a lot!
    Min

    Mandy,
    Couple of combinations you should check,
    1. First try to identify "Selection Profile" which is used. In "CM01" go to menu Planning->Profiles->Selection Profile.
    2.Check the defination of this profile using transaction "OPA2". Here you need to look for "Work center Set" which is assigned.
    3. Now look at the defination of the workcenter set using transaction "CMS3", here is were we define as how the list is to be fetched.
    Hope this helps....Reward your points and close the thread if so,
    Regards,
    Prasobh

  • Planning Capacity using CM01 and CM07 transaction

    Hi,
    there are two kinds of sales order in our company: the "confirmed" order sales and the "not confirmed" order sales. The both we need to plan in PS and need use the factory capacity. But when we need to analyze the capacity planning of these projects, it's interesting if we can separates both types of projects, the "confirmed" and the "not confirmed project". And we have to change the projects from "not confirmed" to "confirmed" when a costumers really confirmed a sale. The input in CM07 transaction that I use is the work center.
    I think this case is very common in the companies since there are situations that it's necessary to use the factory forces even a order sales is not confirmed but probably is going to. Than we need to change this project to "confirmed" and is going to show us in CM07 as a confirmed project.
    Thanks,
    Tiago

    Try this function module,
    CLOI_WC_CAPACITY_READ  Similarly
    Please search in SE37 using f4 by giving the capacity in the description field and search.
    there are many function modules are listed for capacity related one , then try  giving your input value and find the output you are expecting...
    Thanks.

  • Capacity Leveling vs. Plant Maintenance

    What is the difference between Capacity Leveling Planning Tables (CM21, 22, 27,28,31,23) and Plant Maintenance Planning Tables (CM33, 34, 30, 24)? 
    In what type of scenario would I want to use either one?  What would the end result of utilizing these tables be?

    Hi
    Mark the control key for generating capacity requirement.
    Give the formula SAP008 in Work Center Capacity Tab.
    Use CM01 to check Capacity Planning
    Use CM22 for Capcity Levelling.
    Explore these options
    Regards
    KG

  • Capacity Planning & levelling

    Hi all,
    Pls help me with the below situation
    I have three machine
    1.IMM-01: Injection molding machine
    2.IMM-02
    3. IMM-03
    I usually get the customer requirment through mail.
    Based on the tentative plan & current stock we need to make monthly  capacity plan for each machin & its occupancy load should not exceed 85%. Based on the Customer req I need to plan the machine which is having lesser occupancy.
    I need to get the details in single sheet (Monthly capacity plan)
    Available hr: 744
    Days :31 days
    IMM-01
    Material              Cycle time/sec      Planned Qty nos     Capacity %
    Front Cover-1    75                            20000                    ???
    Front Cover-2    75                            20000                    ???
    Front Cover-3    85                            20000                    ???
    IMM-02
    Material              Cycle time/sec      Planned Qty nos     Capacity %
    Back Cover-1    75                            20000                    ???
    Back Cover-2    75                            20000                    ???
    Back Cover-3    85                            20000                    ???
    IMM-03
    Material              Cycle time/sec      Planned Qty nos     Capacity %
    Side Cover- 1    75                            20000                    ???
    Side Cover- 2    75                            20000                    ???
    Side Cover- 3    85                            20000                    ???
    Thanks & regards
    Subbu.

    Dear
    I assume that you have Capacity Requirement Planning set up in place .
    You can check the Work Centre capacity overload  or capacity analsisy in CM05/CM01 day wise /week wise all those set up .
    Please enter work centre , plant code -Hit standrad view -goto general option -setting -select periods Day .By default it will come  as week .Or you can execute and then choose Profile -Option Profile -Select SAPB010 day wise .Like wise you can analise the caapctiy situation .
    Capacity level in spossble throuh CM21-Work Centre wise Graphaical View -Select the operationj against planned order -Hit dispatch button at the top -if you have available capacity on the required date , time , then those operation will be dispatched and also you will recieve the Scehduling Log.
    I think you should try this frist in sandbox to simulate the business requirement based on your CRP set up.
    You can also use call function  : CBP_EXC_WC_CAPACITY_REQUEST'  for   available capacity of a work center and use CY01_DISPATCHING_OPR_DATES_CHK  for dispatch
    refer my earlier thread : Capacity Leveling of Work Center
    Hope this helps
    Regards
    JH
    refer my earlier post rekated to this :

  • Machine capacity planning and efficency

    Dear Guru,
    I have number of machines and i want there individual capacity and efficency can we see that by any report or any tcode to see all capacity of machine.What is capacity leveling.
    Is thee any configuration for capacity planning.
    Thanks in advance

    Hi, the following configuration steps involved in the capacity planning: SPRO --> IMG --> PRODUCTION --> CAPACITY REQUIREMENT PLANNING Capacity Requirements Planning: 1) Define time units 2) Define Capacity Category 3) Set up Capacity Planner. 4) Define parameters 5) Define Standard value key. 6) Define Move time matrix. 7) Define Setup matrix. 8) Define Control Key. 9) Define Shift Sequence. 10) Define Key for performance efficiency rate. 11) Define Formula parameters. 12) Specify Scheduling type. 13) Set up Production scheduler group 14) Select Automatically. 15) Define Scheduling parameters for Production orders 16) Define Scheduling parameters for networks. 17) Define Reduction Strategies planned/ production orders. 18) Define Reduction Strategies for network/process orders. 19) Define Control Profile. 20) Define Selection profile. 21) Define time profile. 22) Define Evaluation profile. 23) Define Strategy Profile. You can follow these above configuration steps in capacity planning Yes you need to active your all work center for the finite scheduling at the bottom of capacity view. Use all standard SAP configurations, Capacity Leveling Profile. Define time profile in OPD2. Define the strategy profile in OPDB Define the Overall profiles in OPD0. Then only you need to to active your all work center for the finite scheduling at the bottom of capacity view in work center.(CR02) Then run MRP with scheduling- 2 Lead time scheduling and capacity planning.(MD02) You will get your capacity requirement in CM01, or CM25/CM21. In rem you can use MF50. -
    OR refer below steps Capacity Planning Evaluation: Use this procedure to Evaluate the Capacity of a Work Center (Resource). The same transaction will be used for finding out the Capacity Overload on the Work Center Select Logistics -> Production -> Capacity Planning -> Evaluation ->Work Center View ->Load and go to the Capacity Planning Selection screen (CM01) Through capacity planning : Standard overview :System will show week wise overload in Red Color. If there is no overload then system will show in the normal color. Date wise Capacity can be overviewed. If there were capacity overload, system would show with Red Color indication and Percentage overload can be viewed. Through capacity planning : Standard overview: Details: Date wise, planned process order wise capacity requirement. Through capacity planning : Standard overview: Graphical: Yellow Color indicates capacity lying un-used. Red Color Bars is the indication for Capacity Overload and Blue Color Bars indicate for Capacity available Use this procedure to Level / Schedule the Capacity of a Work Center Capacity Planning - Levelling/Scheduling: Select Logistics ->Production->Capacity Planning -> Levelling -> Work Center View and go to the Planning Table (Graphical) screen (CM21) Key Points u2022 This would be used for Shop floor production scheduling u2022 Capacity Scheduling is mandatory for correct results of Master Production Schedule and Material Requirement Planning For settings: Define formulas for resources: (OP54) IMG -> Production Planning For Process Industries -> Master Data ->Resource->Capacity requirements planning->Formulas for resources->Define formulas for resources. For formula parameters for Resource/workcentre:(OP51) IMG -> Production Planning For Process Industries -> Master Data ->Resource->Capacity requirements planning->Formulas for resources->Define formula parameters for resources-> Standard Value u2013 Define Parameters (OP7B) IMG -> Production Planning For Process Industries -> Master Data ->Resource-> General Data -> Standard value -> Define Parameters Define standard value key(OP19) IMG -> Production Planning For Process Industries -> Master Data ->Resource-> General Data -> Standard value -> Define Standard Value First configure the below settings in the capacity Planning. 1) Define time units Path : SPRO ->Production-> Capacity Requirements planning ->Master Data-> Define Time units (OPCF) 2) Define Capacity Category Path : SPRO ->Production ->Capacity Requirements planning->Master Data-> Capacity Data ->Define Capacity category. 3) Set up Capacity Planner. Path : SPRO ->Production ->Capacity Requirements planning -> Master Data->Capacity Data -> Set up Capacity Planner 4) Define parameters Path : SPRO->Production ->Capacity Requirements planning -> Master Data ->Work Center Data->Standard value ->Define Parameters (OP7B) 5)Define Move time matrix. Path : SPRO -> Production-> Capacity Requirements Planning -> Master Data-> Work Center Data -> Define Move time Matrix (OPCN) 6) Define Setup matrix. Path : SPRO -> Production ->Capacity Requirements Planning -> Master Data -> Routing data -> Define Setup Time Matrix 7)Define Control Key. Path : SPRO-> Production-> Capacity Requirements Planning -> Master Data ->Routing data -> Define Control Key(OPCG) 8) Define Shift Sequence. Path : SPRO -> Production-> Capacity Requirements Planning -> Operations -> Define Shift Sequences (OP4A) 9) Define Key for performance efficiency rate. Path : SPRO-> Production -> Capacity Requirements Planning -> Operations-> Available Capacity-> Define Key Performance Efficiency Rate (OPDU) 11) Specify Scheduling type. Path : SPRO ->Production ->Capacity requirements Planning->Operations->Scheduling ->Specify Scheduling Type (OPJN) 12) Set up Production scheduler group. Path : SPRO ->Production->Capacity requirements Planning -> Operations -> Scheduling -> Set up Production Scheduler Group (OPCH) 13) Select Automatically. Path : SPRO -> Production -> Capacity Requirements Planning ->Operations->Scheduling ->Task List Type-> Select Automatically (OPJF) 14) Define Scheduling parameters for Production orders. Path : SPRO -> Production ->Capacity Requirements Planning-> Operations->Scheduling -> Define Scheduling Parameters for Production orders (OPU3) 15) Define Reduction Strategies planned/ production orders. Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies->Define reduction strategies planned-/production order 16) Define Reduction Strategies for network/process orders. Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies-> Define reduction strategies for network/process order 17) Define Selection profile. Spro->Production->Capacity requirements Planning->Evalution->Profiles-> Define selection profiles Hope clear to u. Regards Alok

  • Constraint capacity planning for Un-Routed items in ASCP

    Hi All,
    Is there any possibility to create constraint capacity planning for items which do not have routings in ASCP?
    I tried by setting Bill of Resources (BOR) in Aggregatin tabbed region in Plan option. But i could not get an expected result. Kindly help me out in this.
    regards,
    Murlai R
    Edited by: user10942922 on Mar 27, 2009 9:30 AM

    Dear ,
    To answer the question for Capacity requirement planning on sales order I would say that MRP does  only materials planning based on demand and reciept  but never does Capacity Requirement Plannig .MRP generates Planned Order  and susequently , production order can be genreted and farther you can carry out capacity requirement planning based on the work cente available capacity , requirement and load for those MTO orders .
    But there are SAP business suit like APO-SNP APO PPDS which carriy our details scheduleing and caapcity check based on the demand situation : Sales Order ,Independent Order  and does capcaity vaialbality chek for those demands while planning .
    Now , here is the answer of your question :
    1) Can Capacities are Scheduled as per priority given in SO automatically. : Not possible  through  SAP MRP but in APO-PPDS, APO-SNP-CTM , Herustic model .
    2) Can revised availability dates will be reflected in SO. : It can be reflected as per the ATP chekc , Replishmenet Lead  Time and re-scheduling horizon maintained in OPPQ-Carry all overall plant parametres.
    3) Which reports will be useful for understanding consolidated availability date of material for given sales order/s. : You can check through MD04/MD05 or in sales order -Availaibility check -Schedule Line -Availaibility date .
    Hope your are clear about the requirememt .
    Regards
    JH
    Edited by: Jiaul Haque on Jun 5, 2010 1:59 PM
    Edited by: Jiaul Haque on Jun 5, 2010 1:59 PM

  • Any std report in Capacity Planning showing only dispatched orders/opns ?

    Hi CRP gurus:
    Does SAP has any standard report/transaction in Capacity Planning that shows (or has a selection for showing) only "dispatched" orders/opns ?
    - Chetan

    Chetan,
    Use transaction COOIS. In this choose Operations, System status as DSPT at operation level, enter plant and execute. You will get only orders and the operations which are dispatched in this plant.
    You can navigate to the capacity planning table from the selected records through order change.
    Hope this is ok with you,...reward points..and close.
    Regards
    Ram

Maybe you are looking for

  • KDE. network manager "No agents were available for this request"

    I think there might be a bug with the networkmanagement plasmoid. Not sure if this is the right place to post it, or if maybe I should take this to the KDE forms¿?? Anyway, took me quite a while to reproduce this, but it seems that with WPA wireless

  • HT4623 I can't restore my iphone 4. I keep getting a error message.

    I keep trying to restore and update my iphone4.  It extracts files and prepares for restore, then it gives me an unknown error message. And my iphone won't let me do anything until I connect to itunes. What can I do?

  • Re-installation advice, please

    Hi all. After installing CS4, shortly after its introduction, everything went well, sort of. The GPU feature wouldn't work with my older graphics card, I think. At least it wasn't one of the tested/supported cards. Then, my D drive (storage and scrat

  • Need a Secure Reliable connection Using IDSL and dsl routers

    I need to get a fast secure remote connection to my database. I am using oracle 8i database and the 6i developer for my applications. I need to connect to from remote sites to my office using my internet dsl router. I managed to do this using the web

  • 'GetInfo' file does not work!

    Hey Folks, I have a strange problem... I have just migrated on a PPC-G5 from an Intel processor Mac (I have used the migration assistant utility) and the 'GetInfo' file doesn't work. I cannot have access to any file informations. The most surprising