Capacity Planning - CM07

Dear PP Gurus,
I am using CM07 to view the work center for the capacity planning. My requirements load for  12 months.
How come the planned order on July onwards is schedule all to June?
It is supposed to load according to the month for the orders, but is not and the earlier months capacity is not fully utilised?
Need you expertise on this.
Appreciate the assistance
Thanks & Regards
Pooja

Hi Abhijeet,
You can use profile SAPPISAFRU - IS Confirmation and then after double clicking the particluar line item you can chose confirmed quantity in the field display.
Otherwise you can use the transaction CN41 for actual work done or CN48n for confirmation line item display.

Similar Messages

  • Configuring profiles in CAPACITY PLANNING (CM07)

    We need to configure a profile in CM07 which should be similar to CM01 but only should pick up released orders (PM orders) and instead of 9 weeks we need data for 11 weeks. These are the major two differences that we need. Can you please let me know the steps to do it.
    Your help would be really helpful and appreciated.

    Hi,
    Regarding selection of data of 11 Weeks than 9 Weeks you can do the same using Option Profile using T.Code: OPA3 in customisation where in you can mention Start and End Date.
    Path SPRO - Production - Capacity Requirements Planning - Evaluvation - Profiles - Define options profile.
    You need to assign the new Option Profile in Overall Profile (OPA6).
    Regarding selection of only released orders I will check and confirm.
    With best regards
    Shankar.

  • Maintenance Work Center : Capacity Planning CM01

    Hello Gurus,
    We are using T-code CM01 to determine the Requirements / RemAvailCap of the Maintenance Work Orders in a given Maintenance Work Center.
    After executing CM01, the detail capacity list contains Not Scheduled orders( CRTD )and  capacity of these not Released orders also taking into consider.
    How to restrict CM01 Order selection based on the work order System status or User status ?
    I found below discussions on SCN but couldn't get precise answere.
    Plant Maintenance: Capacity planning CM01/ CM07
    Configuring profiles in CAPACITY PLANNING (CM07)
    Please help.
    Thanks in Advance
    Ashok M

    There are a few ways:
    Create a new status profile via BS42 and assign the REL status only (see image 1). Then in the CM01 display screen, use menu path: Planning->Selection->Order and enter the status profile created above (see image 2)
    Create a new selection combination via OAP0. In the CM01 display screen, use menu path: Planning->Selection->Combination and enter the selection combination created above (see image 3)
    The above settings can then be defaulted via the various capacity planning profiles.

  • Plant Maintenance: Capacity planning CM01/ CM07

    Hi
    In capacity planning CM01, the standard sap shows all the maintenance orders which have system status created. But we would like to look at onlly the released pm order in the standard overview list and detailed capacity list. Please let me know if there is way we can configure it.
    Thanks

    Hi Nayan202,
    You could configure desired "selection set" T.code "CSM1" and then assign this to appropriate "Selection Profile" under initial set.
    Hope this helps.
    Shahnawaz

  • Setting needed for Capacity Planning.

    Hi PP Gurus,
    I want to know what setting we have to do for capacity planning.
    what I know is:
    1. W/C should be set for finite scheduling.
    2. In scheduling parameters for process order tick "Generate capacity Requirement".
    This both setting are made in my scenario, but it is'nt loading the work center fot that week.
    Any other setting nedded?
    Thanks, in advance.

    Dear ,
    You need to have following set up at basic level frist before you perfomr the capacity requirement planning  :
    1.In OPKP-Define Production Scheduling parameter -Availability check -Confirm Capacity and also Finite Scheduling chekc box ticked .
    2.In OPU3/OPU5-Define Scheduling Parametesr -you should mark the following
    1.Automatic Scheduling check box should be marked
    2.Scheduling Log check box should be marked -generate in case there is a scheduling error due to capacity over load .
    3.Scedulinga and Generate Capcity should be ticked .
    3.In OPJK Imaintain check capacity with SAPSFCG013 overall profile and set indicator -1 -Release Order -by user decision if capacity is insufficient
    4.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
    5.Routing - enter the values for the standard values. Use control key with scheduling and CRP activated .
    6. OPD0 and have the following set up  : Overall profile : SFAPSFC015 --Inside the over all profile I have the following set up
    1.Selection Profile -SAPSFCS013 SFC: Order view, standard overview
    2.Control Profile : SAP___C004 : Gen Capacity Availability Check for 1.5 months
    3.Time Profile : SAP___Z006 : Gen Capacity Availability Check for 1.5 months
    4.Evalution Profile : SAPSFCA013 : Gen Capacity Availability Chek =3.0D
    5.Strategy Profile : SAPSFCVER1-Gen Capacity availability Check
    6.Period Profile : SAP___P001 -Weekly period
    7.List Profile : SAPSFCI001-Production Planing
    Check all of them in place .Then you can go ahead with Capacity Req.Planning -Evalution and Leveling -CM21/CM22/CM05/CM07  etc.
    Refere the below theread for farther reference :
    Capacity problem in production order
    capacity planning
    Hope this will be useful .
    Regards
    JH

  • Capacity planning requirement by individual capacity wise

    Is it possible to get the report of capacity planning requirement by individual capacity wise. (Individual capacities assigned to work center).
    I have checked Tcodes CM01 to CM07, but unable to get the same.

    Hi
    What i understand from your query is you want Individual capacities to work center means  report as per capacity category wise..
    In CM01  go to  menu select Planning->selection-> capacity category wise enter your capacity category, slection list window will appear, click Detailed Capacity List...
    Regards,
    MSH

  • Shiftwise capacity planning

    Dear friends,
    My client requirement is to do capacity planning shiftwise. As far as I know capacity planning can be done up to day. I have assigned shift and intervals in workcenter capacities but when I check the capacity load I can view  (CM01 transaction) only Period,daywise,Factory calendar,Week,month, etc.
    Kindly give your valuable sggestions
    Thanks
    Arun

    HI Andrew,
    We are using ECC 6.0 and looking for Shiftwise Capacity report similar to CM07. Is any functionality available in ECC 6.0? We are planning to extend CM07 to have shiftwise report, what are your suggestions for that?
    Thanks in advance.
    Regards,
    Devang Shah

  • Capacity planning Long-term planning CM38

    Hi,
    I am using Long-term planning scenario. I have created 12 PIRs for 12 months from January 2010 to December 2010. I executed MRP in MS01 in Lead scheduling Mode.
    There are 12 planned orders created for the 12 PIRs for the months Jan to Dec-2010. When I see the planned orders in MS04 the satrt and finish date for the planned orders are showing in respective months beginning.
    But when I check capacity in transaction CM38, all the 12 planned order for Jan to December months are displayed in the month of  January itself instead of the respective months from Jan to December and the work center is overloaded 199%.
    Please suggest to solve this issue.
    thanks and regards
    Murugesan

    Hi,
    In customization for Capacity Planning you can define you own selection profiles to work with. You may specify further selection criteria in selection profile and enhance query speed from database. Slection profiles are assigned to overall profiles and overall profiles can be called by CM07 transaction. CM38 is also working over an overall profile which you may learn from SAP help. This can also be changed.
    Also check OPC5 to limit max data for selection which might be useful.
    Regards.

  • Operations are not getting despatched in capacity planning table

    Hi Experts,
    I am using capacity planning table (Graphical) to level the capacities and sequence the process orders. The start date of my orders are very well in future and sufficient capacities also is available in resources. But when I go to CM25 and select one order and click on despatch, system is not despatching it. This is the case for almost all the overall profiles.
    The surprising factor is, this function was working fine earlier without any issues. I havent done any changes in configs which will affect capacity planning.
    What can be the reason for this? Any thoughts please?.
    One more thing. Is there any option to avoid the capacity planning step if Iam using R/3 and manage it by some other way?
    Appreciate your earlier reply
    Thanks & Regards
    Prathib

    Most likely you didnt define the rowsource key properly. Please look under <install>/errors folder for any file there.
    Also, please read the documentation. There is information there about how to troubleshoot a loading problem. Please always read the documentation and we would appreciate feedback on the documentation.
    http://download.oracle.com/docs/cd/E17236_01/epm.1112/iop_user_guide/frameset.htm?launch.html

  • Machine capacity planning and efficency

    Dear Guru,
    I have number of machines and i want there individual capacity and efficency can we see that by any report or any tcode to see all capacity of machine.What is capacity leveling.
    Is thee any configuration for capacity planning.
    Thanks in advance

    Hi, the following configuration steps involved in the capacity planning: SPRO --> IMG --> PRODUCTION --> CAPACITY REQUIREMENT PLANNING Capacity Requirements Planning: 1) Define time units 2) Define Capacity Category 3) Set up Capacity Planner. 4) Define parameters 5) Define Standard value key. 6) Define Move time matrix. 7) Define Setup matrix. 8) Define Control Key. 9) Define Shift Sequence. 10) Define Key for performance efficiency rate. 11) Define Formula parameters. 12) Specify Scheduling type. 13) Set up Production scheduler group 14) Select Automatically. 15) Define Scheduling parameters for Production orders 16) Define Scheduling parameters for networks. 17) Define Reduction Strategies planned/ production orders. 18) Define Reduction Strategies for network/process orders. 19) Define Control Profile. 20) Define Selection profile. 21) Define time profile. 22) Define Evaluation profile. 23) Define Strategy Profile. You can follow these above configuration steps in capacity planning Yes you need to active your all work center for the finite scheduling at the bottom of capacity view. Use all standard SAP configurations, Capacity Leveling Profile. Define time profile in OPD2. Define the strategy profile in OPDB Define the Overall profiles in OPD0. Then only you need to to active your all work center for the finite scheduling at the bottom of capacity view in work center.(CR02) Then run MRP with scheduling- 2 Lead time scheduling and capacity planning.(MD02) You will get your capacity requirement in CM01, or CM25/CM21. In rem you can use MF50. -
    OR refer below steps Capacity Planning Evaluation: Use this procedure to Evaluate the Capacity of a Work Center (Resource). The same transaction will be used for finding out the Capacity Overload on the Work Center Select Logistics -> Production -> Capacity Planning -> Evaluation ->Work Center View ->Load and go to the Capacity Planning Selection screen (CM01) Through capacity planning : Standard overview :System will show week wise overload in Red Color. If there is no overload then system will show in the normal color. Date wise Capacity can be overviewed. If there were capacity overload, system would show with Red Color indication and Percentage overload can be viewed. Through capacity planning : Standard overview: Details: Date wise, planned process order wise capacity requirement. Through capacity planning : Standard overview: Graphical: Yellow Color indicates capacity lying un-used. Red Color Bars is the indication for Capacity Overload and Blue Color Bars indicate for Capacity available Use this procedure to Level / Schedule the Capacity of a Work Center Capacity Planning - Levelling/Scheduling: Select Logistics ->Production->Capacity Planning -> Levelling -> Work Center View and go to the Planning Table (Graphical) screen (CM21) Key Points u2022 This would be used for Shop floor production scheduling u2022 Capacity Scheduling is mandatory for correct results of Master Production Schedule and Material Requirement Planning For settings: Define formulas for resources: (OP54) IMG -> Production Planning For Process Industries -> Master Data ->Resource->Capacity requirements planning->Formulas for resources->Define formulas for resources. For formula parameters for Resource/workcentre:(OP51) IMG -> Production Planning For Process Industries -> Master Data ->Resource->Capacity requirements planning->Formulas for resources->Define formula parameters for resources-> Standard Value u2013 Define Parameters (OP7B) IMG -> Production Planning For Process Industries -> Master Data ->Resource-> General Data -> Standard value -> Define Parameters Define standard value key(OP19) IMG -> Production Planning For Process Industries -> Master Data ->Resource-> General Data -> Standard value -> Define Standard Value First configure the below settings in the capacity Planning. 1) Define time units Path : SPRO ->Production-> Capacity Requirements planning ->Master Data-> Define Time units (OPCF) 2) Define Capacity Category Path : SPRO ->Production ->Capacity Requirements planning->Master Data-> Capacity Data ->Define Capacity category. 3) Set up Capacity Planner. Path : SPRO ->Production ->Capacity Requirements planning -> Master Data->Capacity Data -> Set up Capacity Planner 4) Define parameters Path : SPRO->Production ->Capacity Requirements planning -> Master Data ->Work Center Data->Standard value ->Define Parameters (OP7B) 5)Define Move time matrix. Path : SPRO -> Production-> Capacity Requirements Planning -> Master Data-> Work Center Data -> Define Move time Matrix (OPCN) 6) Define Setup matrix. Path : SPRO -> Production ->Capacity Requirements Planning -> Master Data -> Routing data -> Define Setup Time Matrix 7)Define Control Key. Path : SPRO-> Production-> Capacity Requirements Planning -> Master Data ->Routing data -> Define Control Key(OPCG) 8) Define Shift Sequence. Path : SPRO -> Production-> Capacity Requirements Planning -> Operations -> Define Shift Sequences (OP4A) 9) Define Key for performance efficiency rate. Path : SPRO-> Production -> Capacity Requirements Planning -> Operations-> Available Capacity-> Define Key Performance Efficiency Rate (OPDU) 11) Specify Scheduling type. Path : SPRO ->Production ->Capacity requirements Planning->Operations->Scheduling ->Specify Scheduling Type (OPJN) 12) Set up Production scheduler group. Path : SPRO ->Production->Capacity requirements Planning -> Operations -> Scheduling -> Set up Production Scheduler Group (OPCH) 13) Select Automatically. Path : SPRO -> Production -> Capacity Requirements Planning ->Operations->Scheduling ->Task List Type-> Select Automatically (OPJF) 14) Define Scheduling parameters for Production orders. Path : SPRO -> Production ->Capacity Requirements Planning-> Operations->Scheduling -> Define Scheduling Parameters for Production orders (OPU3) 15) Define Reduction Strategies planned/ production orders. Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies->Define reduction strategies planned-/production order 16) Define Reduction Strategies for network/process orders. Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies-> Define reduction strategies for network/process order 17) Define Selection profile. Spro->Production->Capacity requirements Planning->Evalution->Profiles-> Define selection profiles Hope clear to u. Regards Alok

  • Capacity planning and schedulng production order based on availabe capacity

    Hi Gurus,
    I am trying to use capacity planning, when the production order is created it takes the order start date as the requirement date. Then when i do he capaity check it says capaity not available. After finite scheduling again it proposes to shift operations by certain days.
    I need the capity to be check in MRP and the palled orders to have start dates based on aviable capity, currenty all the palled orders are starting on the requirement date irresptive of avaiabe capaity. I tried using finite scheduling option in MD02 still it does not take in to account exsting production orders for giving dates of the planned orders.
    Regards
    Abhi

    Dear Abhishek,
    1) This is Std SAP of MRP, only material Av check will be carried out in MRP & create procurement
    Proposals
    2) Capacities will not Checked  ( consider ) in MRP in Std R/3
    3) Your Need can be only met through APO
    Regards
    Madhu

  • Bandwidth Utilization Avg or Max for capacity Planning best practice

    Hello All - This is a conceptual or Non-Cisco product question. Hope you can help me to get this best industry practice
    I am doing a Capacity planning for the WAN Link Bandwidth. To study the last month bandwidth utilization in the MRTG graph, i am seeing  two values
    Average
    Maximum.
    To measure how much bandwidth my remote location is using which value i have to use. Average or Max?
    Average is always low eg. 20% to 30%
    Maximum is continuous 100% for 3 hour in 3 different intervals in a day and become 60% in rest of the day
    What is the best practice followed in the networking industry to derive the upgrade size of the bandwidth by using the Utilization graph
    regards,
    SAIRAM

    Hello.
    It makes no sense to use average during whole day (or a month), as you do the capacity management to avoid business impact due to link utilization; and average does not help you to catch is the end-users experience any performance issues.
    Typically your capacity management algorithm/thresholds are dependent on traffic patterns. As theses are really different cases if you run SAP+VoIP vs. youtube+Outlook. If you have any business critical traffic, you need to deploy QoS (unless you are allowed to increase link bandwidth infinitely).
    So, I would recommend to use 95-percentile of maximum values on 5-15 minutes interval (your algorithm/thresholds will be really sensitive to pooling interval, so choose it carefully). After to collect baseline (for a month or so)  - go and ask users about their experience and try to correlate poor experience with traffic bursts. This would help you to define thresholds for link upgrade triggers.
    PS: proactive capacity management includes link planning for new sites and their impact on existing links (in HQ and other spoke).
    PS2: also I would recommend to separately track utilization during business hours (business traffic) and non-business (service or backup traffic).

  • How to go about capacity planning for storage ?

    Hi Experts,
    How to go about Capacity Planning? For  instance if clients wants to upgrade to new server and new storage and asks us how much additional storage do you need for next 5 years, how can calculate the amount of storage.
    I don't have any baseline info about the server of past years. Where can I start and any scripts you guys use for doing capacity planning?
    Appreciate your help.
    Thank you.
    Sam

    Please see this link:
    SQLAuthority News – Storage and SQL Server Capacity Planning and configuration...
    T-SQL Articles
    T-SQL e-book by TechNet Wiki Community
    T-SQL blog

  • Planned order splitting during capacity planning

    Hello,
    anybody plese help me during the capacity planning in T.code.CM31 i want to split a planned order and want to assign alternative sequence. how can i do this and the capacity should be reschedule automatically to my requirement date. i am using backward scheduling.
    plese suggest immediately
    Thanks and reagards
    Bhakta

    Dear Bhakta
    MRP does not perfom any Capacity Requirement Planning .While  you are executing MRP with Lead Time Scheduling , MRP proposes Planned Order Dates based on the Routing Operation Timing not based on the Work Centre available Capacity because in SAP Std R/3 we did not have scope to check the finite scheduling and capacity requirement chek .MRP assume that Work Centre has infinite available capacity .
    In MRP run , it will give you Detail scheduling of the Operation in Planned Order -Detail Scheduling tab  and copied the routing , BOM as master data .When you convert that Planned order to Production order , it will copy the Routing details based on the Order Type denpendt Parameters -OPL8-Routing -Alternative sequnce  and Automatic selection -3 option
    Thats why we have Capacity Requirement Planning  for Detail Capcity check and production order scheduling  .
    Note : Earlier to my first  reply , please note that you have option in CM21  enter sequence number  at order level which may applicable to you .CM21-Work Centre -exectute -Select the Order from order pool -Goto Order -Sequence number maintainence
    This number( sequence number operation /order )  that can be assigned to production orders or planned orders at the level of the task list header and is therefore valid for all the operations in an order.
    Hope this is clear .Revert if you nees farther help
    Regards
    JH
    Edited by: Jiaul Haque on Jul 5, 2010 3:32 PM
    Edited by: Jiaul Haque on Jul 5, 2010 4:01 PM

  • How to use parallel sequence in capacity planning.

    How we can use parallel seq in capacity planning?we have two machines which can be run parallel for production ,now how  to distribute capacity load? suppose for the production of 100 km,we required 1000 min when it is produced through only one machine.Now if 2 machines are used simultaneously we required 500 min.How to see this in capacity planning?

    Dear,
    For calculating Available capacity you have options like minimum capacity, normal capacity and maximum capacity. You can select this option in work center-capacity tab for individual capacity category.
    With parallel sequence and with both machines you can select maximum capacity option and plan your capacity.
    Hope this is helpful.
    Regards,
    Prasad