Capacity Planning Fields - CM01

Hi guys,
I need help on getting some information from SAP.
I have a request for a report that need the Availability Capacity for Machines.
This information can be found in T-Code CM01.
See below the result of the transaction:
Week Requirements AvailCap. CapLoad RemAvailCap Unit
23.2009 0.00 67.86 0 % 67.86 H
24.2009 0.00 105.30 0 % 105.30 H
25.2009 0.00 105.30 0 % 105.30 H
26.2009 0.00 105.30 0 % 105.30 H
27.2009 0.00 105.30 0 % 105.30 H
28.2009 0.00 105.30 0 % 105.30 H
29.2009 0.00 105.30 0 % 105.30 H
30.2009 0.00 105.30 0 % 105.30 H
31.2009 0.00 105.30 0 % 105.30 H
Total >>> 0.00 910.26 0 % 910.26 H
The field I need is the one that says AvailCap.
I have debuged the program lots of times... have found a bunch of function modules but can't figure out how this is calculated.
Can any one help? Pleeeeeeeeeeeease!
Have any of you used this before?
Thanks a lot and regards,
Fernanda

Hi,
The available capacity can be find from the work center.
In CR03 transaction enter the work center & plant. Goto the capacity tab page & click the capacity header (displayed in the bottom). Now click intervals & shift button.
Now check the valid from & To dates & then select the required date range & see the value displayed in the capacity column. For Eg: if for a day the working hours is 8 Hr & capacity utitlisation is 100 % & Number of individual capcity is 1, then the avaialable capacity is 8 hours per day & for a week of 5 working day the available capacity will be 40 hours.
In number of individual capacity is 2 then the available capacity will be 80 Hrs.
Regards,
Senthilkumar

Similar Messages

  • OPU5 settings and Capacity planning-CM01

    Hi All,
    I have a confusion while configuring the settings for scheduling for planned orders in REM environment PE order type, when i select the scheduling and capacity requirements in DS section system shows me capacity requirements in CM01,CM50 reports  and also DS tab in planned order but when i deselect the same check boxes there si no data in CM01, CM02 or CM50,
    If I need to generate the CM01, etc reports in REM environment , then do i need to select DS check boxes also?
    My OPU5 settings are as attached in this case CM01 reports are fine.
    Regards,
    Anupam Sharma

    Hi Anupam,
    Screen shot is missing. Rate based scheduling is fine for REM.
    Create a "Run schedule" planned order and schedule it via rate-based scheduling.
    In transaction OPU5, choose order type PE and the plant you use.
    Choose "Details" and in the field "Scheduling level", set "1 Via rate-based scheduling" and save the change.
    For more information on this visit the following links
    http://help.sap.com/saphelp_47x200/helpdata/en/8a/a58a864adc11d189740000e8322d00/frameset.htm
    Levels of Scheduling - Planning Process - SAP Library
    Regards,
    R.Brahmankar

  • Plant Maintenance: Capacity planning CM01/ CM07

    Hi
    In capacity planning CM01, the standard sap shows all the maintenance orders which have system status created. But we would like to look at onlly the released pm order in the standard overview list and detailed capacity list. Please let me know if there is way we can configure it.
    Thanks

    Hi Nayan202,
    You could configure desired "selection set" T.code "CSM1" and then assign this to appropriate "Selection Profile" under initial set.
    Hope this helps.
    Shahnawaz

  • Maintenance Work Center : Capacity Planning CM01

    Hello Gurus,
    We are using T-code CM01 to determine the Requirements / RemAvailCap of the Maintenance Work Orders in a given Maintenance Work Center.
    After executing CM01, the detail capacity list contains Not Scheduled orders( CRTD )and  capacity of these not Released orders also taking into consider.
    How to restrict CM01 Order selection based on the work order System status or User status ?
    I found below discussions on SCN but couldn't get precise answere.
    Plant Maintenance: Capacity planning CM01/ CM07
    Configuring profiles in CAPACITY PLANNING (CM07)
    Please help.
    Thanks in Advance
    Ashok M

    There are a few ways:
    Create a new status profile via BS42 and assign the REL status only (see image 1). Then in the CM01 display screen, use menu path: Planning->Selection->Order and enter the status profile created above (see image 2)
    Create a new selection combination via OAP0. In the CM01 display screen, use menu path: Planning->Selection->Combination and enter the selection combination created above (see image 3)
    The above settings can then be defaulted via the various capacity planning profiles.

  • CM01 / capacity planning / generate graphic automatically ?

    Hello experts,
    we have implemented the capacity planning for our production.
    The processes are working fine.
    But I've got the following requirement to solve:
    Is it possible to generate the graphical views from CM01 every day automatically in background jobs and send them to printers or email-accounts (nice to have)?
    Thanks a lot for your answers.
    Regards
    Markus

    Dear,
    Yes it is possible to generate the graphical views from CM01go toGraphic--standard overview.
    But automatic in background it is not possible.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Maintaining work center list in Capacity Planning: Selection List in CM01

    Hi,
    Where can find the config route in SPRO for maintain work center into the Capacity Planning: Selection List in CM01?
    Thanks a lot!
    Min

    Mandy,
    Couple of combinations you should check,
    1. First try to identify "Selection Profile" which is used. In "CM01" go to menu Planning->Profiles->Selection Profile.
    2.Check the defination of this profile using transaction "OPA2". Here you need to look for "Work center Set" which is assigned.
    3. Now look at the defination of the workcenter set using transaction "CMS3", here is were we define as how the list is to be fetched.
    Hope this helps....Reward your points and close the thread if so,
    Regards,
    Prasobh

  • Capacity planning CM01 not displaying PM Order capacity

    Hi experts,
    I have created one order with the work center and defined operations...... but i am not able to see the CAPACITY REQUIREMENTS in the capacity planning (CM01)............
    Please suggest me what should  i do for this.............

    Hi Maheswaran,
    Thanks for the information , in configuration "Capacity Requirement Planning" have been maintained and now i am getting the CAPACITY REQUIREMENTS and CAP. LOAD also .........................but there is one problem i.e. when i am seeing the capacity planning (CM01) , IT IS NOT SHOWING THE VALUES ON THE DAY WHICH IS WORKING actually according to factory calendar FRIDAY and SATURDAY are holiday, but it is showing the value on SATURDAY and not showing the value on THURSDAY that is today........Please see the screen shot also......
    what should i do.......

  • Capacity planning: detailed capacity list

    Hi,
    How to save layout of capacity planning: detailed capacity list (CM01) after choosing fields in report?
    Rex

    Can you please step on how to save the capaciity list?

  • Machine capacity planning and efficency

    Dear Guru,
    I have number of machines and i want there individual capacity and efficency can we see that by any report or any tcode to see all capacity of machine.What is capacity leveling.
    Is thee any configuration for capacity planning.
    Thanks in advance

    Hi, the following configuration steps involved in the capacity planning: SPRO --> IMG --> PRODUCTION --> CAPACITY REQUIREMENT PLANNING Capacity Requirements Planning: 1) Define time units 2) Define Capacity Category 3) Set up Capacity Planner. 4) Define parameters 5) Define Standard value key. 6) Define Move time matrix. 7) Define Setup matrix. 8) Define Control Key. 9) Define Shift Sequence. 10) Define Key for performance efficiency rate. 11) Define Formula parameters. 12) Specify Scheduling type. 13) Set up Production scheduler group 14) Select Automatically. 15) Define Scheduling parameters for Production orders 16) Define Scheduling parameters for networks. 17) Define Reduction Strategies planned/ production orders. 18) Define Reduction Strategies for network/process orders. 19) Define Control Profile. 20) Define Selection profile. 21) Define time profile. 22) Define Evaluation profile. 23) Define Strategy Profile. You can follow these above configuration steps in capacity planning Yes you need to active your all work center for the finite scheduling at the bottom of capacity view. Use all standard SAP configurations, Capacity Leveling Profile. Define time profile in OPD2. Define the strategy profile in OPDB Define the Overall profiles in OPD0. Then only you need to to active your all work center for the finite scheduling at the bottom of capacity view in work center.(CR02) Then run MRP with scheduling- 2 Lead time scheduling and capacity planning.(MD02) You will get your capacity requirement in CM01, or CM25/CM21. In rem you can use MF50. -
    OR refer below steps Capacity Planning Evaluation: Use this procedure to Evaluate the Capacity of a Work Center (Resource). The same transaction will be used for finding out the Capacity Overload on the Work Center Select Logistics -> Production -> Capacity Planning -> Evaluation ->Work Center View ->Load and go to the Capacity Planning Selection screen (CM01) Through capacity planning : Standard overview :System will show week wise overload in Red Color. If there is no overload then system will show in the normal color. Date wise Capacity can be overviewed. If there were capacity overload, system would show with Red Color indication and Percentage overload can be viewed. Through capacity planning : Standard overview: Details: Date wise, planned process order wise capacity requirement. Through capacity planning : Standard overview: Graphical: Yellow Color indicates capacity lying un-used. Red Color Bars is the indication for Capacity Overload and Blue Color Bars indicate for Capacity available Use this procedure to Level / Schedule the Capacity of a Work Center Capacity Planning - Levelling/Scheduling: Select Logistics ->Production->Capacity Planning -> Levelling -> Work Center View and go to the Planning Table (Graphical) screen (CM21) Key Points u2022 This would be used for Shop floor production scheduling u2022 Capacity Scheduling is mandatory for correct results of Master Production Schedule and Material Requirement Planning For settings: Define formulas for resources: (OP54) IMG -> Production Planning For Process Industries -> Master Data ->Resource->Capacity requirements planning->Formulas for resources->Define formulas for resources. For formula parameters for Resource/workcentre:(OP51) IMG -> Production Planning For Process Industries -> Master Data ->Resource->Capacity requirements planning->Formulas for resources->Define formula parameters for resources-> Standard Value u2013 Define Parameters (OP7B) IMG -> Production Planning For Process Industries -> Master Data ->Resource-> General Data -> Standard value -> Define Parameters Define standard value key(OP19) IMG -> Production Planning For Process Industries -> Master Data ->Resource-> General Data -> Standard value -> Define Standard Value First configure the below settings in the capacity Planning. 1) Define time units Path : SPRO ->Production-> Capacity Requirements planning ->Master Data-> Define Time units (OPCF) 2) Define Capacity Category Path : SPRO ->Production ->Capacity Requirements planning->Master Data-> Capacity Data ->Define Capacity category. 3) Set up Capacity Planner. Path : SPRO ->Production ->Capacity Requirements planning -> Master Data->Capacity Data -> Set up Capacity Planner 4) Define parameters Path : SPRO->Production ->Capacity Requirements planning -> Master Data ->Work Center Data->Standard value ->Define Parameters (OP7B) 5)Define Move time matrix. Path : SPRO -> Production-> Capacity Requirements Planning -> Master Data-> Work Center Data -> Define Move time Matrix (OPCN) 6) Define Setup matrix. Path : SPRO -> Production ->Capacity Requirements Planning -> Master Data -> Routing data -> Define Setup Time Matrix 7)Define Control Key. Path : SPRO-> Production-> Capacity Requirements Planning -> Master Data ->Routing data -> Define Control Key(OPCG) 8) Define Shift Sequence. Path : SPRO -> Production-> Capacity Requirements Planning -> Operations -> Define Shift Sequences (OP4A) 9) Define Key for performance efficiency rate. Path : SPRO-> Production -> Capacity Requirements Planning -> Operations-> Available Capacity-> Define Key Performance Efficiency Rate (OPDU) 11) Specify Scheduling type. Path : SPRO ->Production ->Capacity requirements Planning->Operations->Scheduling ->Specify Scheduling Type (OPJN) 12) Set up Production scheduler group. Path : SPRO ->Production->Capacity requirements Planning -> Operations -> Scheduling -> Set up Production Scheduler Group (OPCH) 13) Select Automatically. Path : SPRO -> Production -> Capacity Requirements Planning ->Operations->Scheduling ->Task List Type-> Select Automatically (OPJF) 14) Define Scheduling parameters for Production orders. Path : SPRO -> Production ->Capacity Requirements Planning-> Operations->Scheduling -> Define Scheduling Parameters for Production orders (OPU3) 15) Define Reduction Strategies planned/ production orders. Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies->Define reduction strategies planned-/production order 16) Define Reduction Strategies for network/process orders. Spro-> Production->Capacity reqirements planning->operations->Scheduling->Reduction strategies-> Define reduction strategies for network/process order 17) Define Selection profile. Spro->Production->Capacity requirements Planning->Evalution->Profiles-> Define selection profiles Hope clear to u. Regards Alok

  • Any good table for Capacity Planning?

    HI all,
    Is there any table for capacity planning?
    we want to do some development to get capacity requirements data for each work center, don't like using CM01.
    Thanks!
    Harvey

    Dear
    Please find below SAP tables for CRP :
    CRHD         Workcenter Header Data
    CRCA         Workcenter Capacity Allocation
    CRCO         Workcenter Cost Center Assignment
    CRHH          Hierarchy Header
    CRHS           Hierarchy Structure
    CRTX          Workcenter Text
    KAKO         Capacity Header
    KAZY          Intervals of Capacity
    Regards
    JH

  • Tables for capacity planning?

    HI all,
    Is there any table for capacity planning?
    we want to do some development to get capacity requirements data for each work center, don't like using CM01.
    Thanks!
    Harvey

    >
    harvey wu wrote:
    > HI all,
    >
    > Is there any table for capacity planning?
    > we want to do some development to get capacity requirements data for each work center, don't like using CM01.
    > Thanks!
    >
    > Harvey
    Hi Harvey,
    Kindly check if the Below tables satisfy ur requriement
    KBED      Capacity Requirements Records
    KBEZ      Add. data for table KBED (for indiv. capacities/sp
    KBKO      Header Record for Capacity Requirements
    Reg
    Dsk

  • Capacity planning at Planned order level

    Dear All,
                      In my current scenario i'm able to see load of process orders against the workcenter in CM01. My requirement is to do capacity levelling at the planned order level.
             I have created Production version also & attached to the planned order. Still in CM01  no load or planned order is shown on workcenter.
    when i convert it into process order then it shows load / process order.
    pl.let me know how i can do the capacity planning at planned order level.
    Thanx & regards,
    dev

    Hi,
                       In MD12 when click on Go to > Capacity Levelling >
    Error Message : No work centers with capacity requirements were found
    I have given formula : SAP006 in capacity & Relevant to finite schedulling indicator is also active.
    what may be the cause ?
    thanx & regards,
    dev

  • Capacity planning issue

    Dear all
    My customer has two actor types: project managers PM and 7 work center managers WCM, with strong antithesis: PM looks at project quality and productivity; WCM looks at his resources capacity planning.
    Every PM defines wbs basic start / finish dates with appropriate, large and comfortable time lag. Into this time lag, during the capacity planning, the WCMs can set definitive activity start / finish dates, by their needs (and with user status communicates to PM the happened choice) .
    The generic project is composed of more wbs elements and 7 networks: all activities of a generic network are assigned to only one work center. Every lowest wbs element has only one activity.
    Every PM plans dates (large and comfortable) and efforts on network activities; schedules via bottom up and copies wbs scheduled dates on basic dates. After, CP sets the top down scenario and save the project. In IMG, network profile, the type of checking during top-down time scheduling is u201CEu201D:  exit with error (transaction code OPUU).
    Every WCM using transaction code CM01 doesnu2019t see the WBS constrains. So doesnu2019t know the wbs dates range. Moreover the WCMs donu2019t like a dashboard like CM01 because it is not user friendly. They prefer a graphical dashboard. 
    My personal idea to resolve this issue is use transaction code CM21 or similar with the display of wbs time lag. Is it possible?
    Is there anyone who could help me, please? I am also interested in other technical solution.
    Thanks in advance.
    Salvo50

    Venky,
    1) Sales order when enter in the system can perform the capacity availability check ?
    Not in ECC/R/3.  However, in APO this is possible.
    2) The delivery dates & confirmation in the sales order is on what basis?
    Depends on how you have configured your availability check.  There are a number of possibilities.  Many companies confirm MTS orders to Total Replenishment Lead time in the Material master.  Other companies leave the orders unconfirmed until Planning has created supply elements (production orders).  
    As far as the delivery date is concerned, it can also start with the confirmed material availability date as calculated by ATP, and then additionally schedule in the warehouse pick-pack-load times, and route transit time (the time it takes to move the shipment from your loading dock to the customer's location.
    In 'Assemble to order' (a special version of Make To Order) it is possible to confirm to the scheduling time of the supporting Finished goods production orders combined with the availability of the components of the FG production order.
    In R/3, some companies will confirm the MTS sales order to a date that is farther into the future than the actual estimated process time including capacity backlog.  Then, they run MRP to create planned orders.  Then, they run Capacity leveling.  Then, they run BackOrderProcessing (rescheduling) of the sales orders to re-confirm to the planned or production orders that have been capacity leveled.  In this way, Sales orders are indirectly confirmed to capacity.
    Consult with your local SD and PP ATP experts to discover the options available.
    Rgds,
    DB49
    Edited by: Dogboy49 on Jan 6, 2010 10:37 PM

  • Capacity planning requirement by individual capacity wise

    Is it possible to get the report of capacity planning requirement by individual capacity wise. (Individual capacities assigned to work center).
    I have checked Tcodes CM01 to CM07, but unable to get the same.

    Hi
    What i understand from your query is you want Individual capacities to work center means  report as per capacity category wise..
    In CM01  go to  menu select Planning->selection-> capacity category wise enter your capacity category, slection list window will appear, click Detailed Capacity List...
    Regards,
    MSH

  • Capacity Consumption in SNP Capacity Planning Book

    Hi,
    Can someone let me know how the Capacity Consumption KF(9ACACON)  is calculated in the SNP Capacity Planning Book.
    No macor is associated with the KF. But when i load the data in specific to a resource it gives me some value in the Capacity Consumption KF.
    Is there any option to identify the calculation logic of this KF ?
    Regards
    BVN

    Hi
    There is no formula as such, it depends on the master data settings in your resource. In transaction /sapapo/res01 you can display the Capacity but how exactly depends on what type of resource you are using and how the capacity is calculated, basically you can have:
    Time-Continuous capacity
    PP/DS Bucket Capacity
    SNP Bucket Capacity
    And they can also have different values!
    For the SNP View it should be using the SNP Bucket Capacity, so if you click on this tab in your resource master data it should have a field "Bucket Definition" which can either be from Continuos Capacity or be maintained separately. If you click the button "Bucket Capacity" it should show you the current values you have.
    If it is from Cont Capacity then click that tab and see the start, end and break times there.
    To add a little confusion, you may also have several variants of capacity, the active variant is on the General Data tab, this is the capacity variant that should show up as standard capacity in your planning book.
    There is more to it all than this but hopefully that should help answer your qeustion.
    Regards
    Ian