Capacity profile in order control spro

hi
in order control of pm spro
capacity profile-field
i fnd generally people left it bank
can i manintain the all the capacity(man) of maintenace in profile
and put it here
so capacity avalabilty check for manpower i can do
this is what i know
if iam wrong please correct me and also give some idea how to use this field
thank you

1. In Capacity tab page, use
Other Formula - SAP008 (Proj: Reqtmns in Prcng). This relates to the internal Calculation of Available Capacity by system.
2. Overload - in Percentage
eg) Available Capacity of the Work Center is 100 mhrs. If you set Overload as 10%, the work center can be loaded with 110 mhrs. That means, in Maintenance Order the Work Center can be loaded 110 mhrs per day. If the Capacity requirement Crosses 110 mhrs, sysytem will throw message according to the IMG setting.
3. If we set the Indicator Relevant to finite scheduling,
we will have the flexibility to continue with MO processing even though the Work Center is Over loaded (If you have this option, during the pop up meesage by system at the time of overloading, we can manually adjust the Capacity and proceed with the process)
4. Can be used by several Operations -
Capacity of Work Center id 100 mhrs. Capacity requirement for One Operation in an Order is 50 mhrs. In this case, if you have not selected the "Can be used " option, remaining 50mhrs can not be utilized for the whole day by any other Operation. So it ie advisable to enable this option, so that maximum utilzation can be done.
5. Long Term Planning -
As the name indicates, it is basically to plan the Capacity Requirements/assignments in long term.
eg) Planning of Spares, Man power in a Maintenance Plan
Hope this will solve ur clarification.
Regards
Sam

Similar Messages

  • COMAC - COHV: manage object profile for order information system

    Hi,
    when you carry out an collective availability check from transaction COHV or COMAC, it is possible to select a layout or a profile. The layout can be defined within the transaction.
    What about the profile ? I can't find how to create a new profile in the  customizing for order information system.
    In standard the profiles are:
    000001 standard profile
    000002 pick list
    000003 collective availability check
    000004 documented goods movements
    Do you have any idea where the profiles can be maintained ?
    Many thanks
    Regards

    Hi,
    Go to SPRO > Production >Shop Floor Control > Information System>Define Profile for Order Information System.
    Hope this helps
    Regards
    Ali

  • Status Profile - Sales Order Change

    Hi,
    I have a issue regarding Status Profile in Sales Order.
    I have a sales order with two status - 
    Awaiting Approval ( Initial at the time of creation of Sales Order )
    Approved ( Approval by HOD after creation )
    No changes has to be done in Sales Order once approved, if any changes to be done then, needs resetting of the status to initial.
    How to control the same.
    I have checked the transactional control in user status but change sales order control is not there.
    Can be controlled through user exit then how can it be be done.... User Exit name and brief logic of possible.
    Regards
    SD Consultant.

    Hi
    You can use MV45AFZZ include to find appropriate User exit for your requirement with the help of your ABAPer.
    USEREXIT_SAVE_DOCUMENT would be suitable to you.
    User status are maintained at JEST table, so you can write code to activate status 1 and deactivate status 2 if sales order changed.

  • DBM Order Control configuration steps..

    Hi All,
    We have got a requirement and need to create new Events/Actions etc in Order Control.
    Since I am new to DBM, I need some guidance to configure actions etc under Order Control.
    I am trying to search on net but not getting some comprehensive document.
    If someone has any document or link having config steps etc ,pls share with me.
    Regards,
    SB

    Hi,
    all information you need should be found in Steffens post
    INFO - General DBM Cookbooks / Consulting Notes / Guides / etc.
    BR
    Robert

  • Table name and  BAPI to view/modify APO Resource capacity profile data

    Please advise the table where the data of APO resource capacity profile stores and BAPI which help to extract and modify the break duration and utlization rate for a resource.
    Steps to view APO resource capacity data
    1. Use transaction /SAPAPO/RES01 and enter as below
    Resource <Resource Name>
    Location XXXX
    Planning Version 000
    2. On the display screen, click button "Capacity Profile" to view the
    data of start, end, break duration and utilizaiton %.
    Appreciate your help!!

    Hi Kurt,
               You can use the below tables/views in which Resource and Capacity Profile related data is stored.
    Tables:
    /SAPAPO/RES_INTQ - Resource Capacity Intervals
    /SAPAPO/RES_INTV - Resource Capacity Intervals
    /SAPAPO/RESCAP - Capacity Profile: Resource Time Capacity
    /SAPAPO/RESDIM - Dimensions and Capacity of a Resource
    /SAPAPO/RESDOWN - Resource Downtime
    /SAPAPO/RESDOWNT - Resource Downtime
    /SAPAPO/RESKEY - Reset Key for Resource to UID
    Views:
    /SAPAPO/V_RESVER- Resource Capacity Variants
    /SAPAPO/VRESINTQ - Resource Interval of Available Capacity Quantity Model
    /SAPAPO/VRESINTR - Resource Interval of Available Capacity Rate Model
    BAPIs available to read:
    BAPI_RSSRVAPS_GETCAPAPRO - Read Resource Capacities Profile
    BAPI_RSSRVAPS_REQUESTCAPAPRO - Query: Selection of Capacities for Resource and Result Transfer
    BAPI_RSSRVAPS_GETLIST - Selection of Resources
    I hope this will help you to get the data which you want to read.
    Regards,
    Saurabh

  • Why we create settlement profile. What master data must exist in sap before creating settlement profile for order.

    Why we create settlement profile. What master data must exist in sap before creating settlement profile for order.

    As mentioned above, settlement is to post the cost to cost centers or any possible receivers as per the settlement profile. PM / Service orders, WBS elements, etc., can be temporary cost bearers from which cost should be settled to some permanent receivers.
    Cost elements / Cost element groups should be available as Master data before configuring settlement profile.
    To answer your latest query, there are 2 type of cost centers.
    Sender Cost Center - Against this, labor / internal activity price will be maintained in KP26. This cost center will be maintained in PM / PP work centers. While creating PM / PP orders, one of the work centers & activity types will be mentioned. Based on the KP26 entry for the combination of Activity type & Sender cost center, price will be picked & calculated according to work hours / labor hours maintained in PM / PP orders.
    Receiver Cost Center - Receiver cost center is the department / location cost center to which cost should be settled. Only receiver cost center will be maintained in settlement profile. Sender cost centers will be picked up automatically from work center.

  • MTO Sales order controlling with valuated stock

    Hi,
    In SAP MTO with sales order controlling (sales order is cost object) with valuated stock, how to make settlement rule set to sales order so that costs will flow from production order to sales order .
    Can anybody advise me in this.
    Regards
    Rajesh A

    Hi Rajesh,
    I'm new to Engineer To Order (ETO) and Make To Order (MTO) Product Costing and my client like to implement ETO and MTO product costing with Project Systems(PS) integration.
    If you worked on these proccess? please can you guide me how to design the process or could you please forward me design and configuration documents....my client is discrete manufacturing industry.
    Thanks,
    Rau

  • Hide the Investment profile in WBS - Control Tab

    Hi,
    Our project has four level of WBS elements. The fourth wbs element  would have investment profile attached to it and would be relevant for AuC and settlement.
    I request you experts to suggest how should I grey out the Investment Profile in WBS Control Tab, so that no one would by mistake enter a Investment profile, in only top 3 wbs elements.
    Thank you
    KAP

    T Code OPUK- Field selection for WBS elements.
    Double click on the field Investment profile (PRPS-IMPRF), position the cursor on level field and click on new value button. Mention the level 1,2 and 3 and select the radio button 'Invis' (Invisible). Save.
    With this Investment profile field will not be displayed at level 1-3 but would be visible at level 4.
    Regards
    Sreenivas

  • APO - capacity profile time capacity for resources

    Dear all,
    I have a problem which I hope can be resolved by one of you ...
    In APO, it is possible to add downtimes for resources using transaction /SAPAPO/RES01 ... After adding this, we can click on "capacity profile" and then we see the time capacity of a resource with all downtimes per shift (with capacity variant) ... I would like to use this time capacity in a program, so it would be interesting to have this information on DDIC-level ... I am looking for some days now, but I don't find which tables to read or which BAPI / function to use ?
    Does anyone know how I can find this data ?
    Thanks in advance for the assistance !
    Greetz,
    Kurt.

    Hi Kurt,
               You can use the below tables/views in which Resource and Capacity Profile related data is stored.
    Tables:
    /SAPAPO/RES_INTQ - Resource Capacity Intervals
    /SAPAPO/RES_INTV - Resource Capacity Intervals
    /SAPAPO/RESCAP - Capacity Profile: Resource Time Capacity
    /SAPAPO/RESDIM - Dimensions and Capacity of a Resource
    /SAPAPO/RESDOWN - Resource Downtime
    /SAPAPO/RESDOWNT - Resource Downtime
    /SAPAPO/RESKEY - Reset Key for Resource to UID
    Views:
    /SAPAPO/V_RESVER- Resource Capacity Variants
    /SAPAPO/VRESINTQ - Resource Interval of Available Capacity Quantity Model
    /SAPAPO/VRESINTR - Resource Interval of Available Capacity Rate Model
    BAPIs available to read:
    BAPI_RSSRVAPS_GETCAPAPRO - Read Resource Capacities Profile
    BAPI_RSSRVAPS_REQUESTCAPAPRO - Query: Selection of Capacities for Resource and Result Transfer
    BAPI_RSSRVAPS_GETLIST - Selection of Resources
    I hope this will help you to get the data which you want to read.
    Regards,
    Saurabh

  • Difference between calendar used in capacity profile & factory calendar?

    Hello experts
    I am trying to check available capacities in planning book & found some ambiguities.
    In /SAPAPO/RES01, factory calendar maintained in the resource is say Z1, but in the same page, the capacity profile tab uses a different calendar.Say in Z1, if X/X/XXXX is a working day, the one present inside capacity profile considers it as a holiday & the  available capacity doesn't reflect in planning book.
    In ECC, the plant where this work center is defined follows calendar Z1.
    So my doubt is which calendar the capacity profile follows & how to ensure that it follows the same factory calendar Z1?
    Regards
    Soum

    Hello Soumyajit,
    few things you can check,
    Plant and work center calender assignment should be same, Plant has precedent over WC
    Check if in CFC9 you have correct change transfer mode set for resource.
    Once calender updated in ECC, use program RSIMPCUST to rebuild the tables for factory calendars in APO and then run /SAPAPO/CRES_CREATE_LC_RES to extend the resource in LC
    also run /SAPAPO/TIMESTREAM_UPDATE for any time stream update.
    This will update capacity profile as well resource capacity in planning book/ planning board.
    Hope this info will help you,
    Thanks,
    Rajiv

  • Rough Cut Capacity Profile

    Hello All,
    I want to ask about Rough Cut Capacity Profile and how to analyse it in MC82 t-code,
    I have made RCCP using MC35 for a Product Group X, where i use 2000 ton for the base qty
    After that, i use MC82 t-code and than I enter the production line for just 1 month, for example i enter production value for June 2010, but for April,May and June still blank
    The Problem is when i choose View --> Capacity Situation --> Rough Cut Planning --> Show, to analyse the capacity requirement,
    I get that the Capacity Rqmnt value is not only in June, but also in May, Why it has to divide the calculation for 2 month? , because i just entry the production line for June, so i expect that the capacity rqmnt value is just appear in June
    and How to calculate the formula for capacity rqmnt in MC82 ?
    Regards,
    Marufat

    Hello All,
    Is there anyone who can help me?
    Please, I really need to solve this problem
    Regards,
    Marufat

  • First order control system for proportion​al valves

    I am working on a proportional valve control program. We have four gas lines and it is desired to send four different gases through a combustion chamber sequentially. The close time for each valve is determined by the pressure measurement inside the combustion chamber. For instance, firstly, we let the nitrogen gas flows to the chamber, and the pressure inside the of it reaches 5 bars, we closed the nitrogen valve, and open the argon gas valve, and hold it opened until the pressure is reached at 15 bars inside the chamber and so on.
    I was thinking on utilizing PID for control of these valves, however, one author from my institute said that you can not do this with a PID program, you can do that with a  first order control system. Because in the system,  it is not allowable to gases exceed their set points (set pressure values). PID controls the system with osilations around set point and after it provides the set value, but in this case, we are not allowed to exceed the set point (we may reach the set point slowly and asymptotically, but never exceed it).
    I have not background on controlling hence I need your help. Could I do that with Labview? Is there a first order system control module in Control & Simulation Toolkit? And also where can I find examples, tutorials, etc. -if there are- about first order system controlling? Thanks in advance.
    Egemen

    what you are trying to do can be done with PID, but you would need to tune it to avoid overshot. But, most importantly, the use of the closed-loop PID will guarantee that your system will follow the setpoint, which can be a ramp going from the 0 to 100 % of the valve. The ramp on setpoint is a typical control technique to avoid overshoot of the system.
    Now, if you look in the PID palette under Control and Simulation, you will see the function called "Lead-Lag". This function is a 'first order' system and you can define a pole and a zero for your system. If your objective is just make the change smooth, you can make the Lead-Lag to work as a "Lag" (make the lead zero) and apply to your system. here is an example:
    C:\Program Files (x86)\National Instruments\LabVIEW 2014\examples\control\PID\Simulation - Lead-Lag.vi
    If you need something more complicated than Lead-Lag, than I would you advice to use the LabVIEW Control Design and Simulation Module. There you can really develop more advanced controllers, like higher order filters or Model Predictive Control. But this also requires you to have a better knowledge of control theory...
    Barp - Control and Simulation Group - LabVIEW R&D - National Instruments

  • BAPI for extracting Capacity profile from resources

    Hi,
    I have a requirement of extracting the capacity profile from resources.
    Is there any BAPI etc that can be used?
    Thanks in advance,
    Zeeshan.

    Thanks Nandha,
    The BAPI is not returning any values. Probably i am not calling with the right parameters. is it possible to send some more details on the necessary parameters? a screen shot would be great.
    Regards,
    Zeeshan.

  • SAP Profile Parameters which controls the [ Background Jobs ]

    Hi,
    Is there any SAP Profile Parameters which controls the [ Background Jobs ] getting executed.
    Also I would like to know especially if there are any Timeout Parameters for Background jobs getting executed in the ABAP System.
    Thanks in advance.
    Regards,
    L Raghunahth

    Hi
    Thanks for your reply..
    based on your reply , I searched and found a parameter called rdisp/max_wprun_time
    The description given for the parameter is "Maximum work process run time"
    Do you have any idea about what is this parameter for ?
    Thanks again
    Best Regards
    L Raghunahth

  • Resource capacity profile extension

    Hi Experts
    I want to put the resource utilisation in Capacity profile(Resource master data).
    In my capacity profile, it is showing upto Mar,2009 and i want to do the planning from April, 2009 to Mar, 2010. Please tell me how to extend my capcity profile upto mar, 2010.
    Regards
    Guru

    Hi
    You need to change planning paramet in Genral Tab of resourse master . You can maintain the period using the range -days to +days
    regards

Maybe you are looking for