Dear Experts
I am trying to carry forward the budget of the Investment program from FY 2010 to FY 2011. I have used IM27 for copying the program structure and Internal Orders. The Budget Values, Commitments of IO has been carried forward but I am not able to carry forward the budget at the Position ID and NODE Level.
Kindly help.
Vikash

Hello,
You can run the BPCARRY01 program to copy the most recent budget structure to a target year. In doing so, you no longer have to maintain BS elements that already exist.
You execute the program, under Accounting - Public Sector Management  - Funds Management - Master Data - Budget Structure - Former Budgeting  -Transfer from Previous Year. This is, as Eli said, FM9Z.
Helene

Similar Messages

  • FMJ2 - Carry forward with budget Line

    Hello,
    I have done a carry forward FMJ2 and everything works perfectly. However the client let me know that they also want the budget line associated to the commitments to be carry forwarded.
    When I try that, the system gives me error FMAVC005.
    In "Define basic stting for carry forward" I have "Carry forward with document chain".
    In "Enter default settings" I have flaged "Carry forward budget for commitement allowed" and also the other 2 (Commitemnt and residual).
    Any idea about this topic.
    Please let me know.
    Regards,

    Hello,
    Avalability control is activated and I ma working with BCS Budget.
    In 2013 I have introduce my budget FMBB (Budget line). Then I have created a reserve agaisnt this budget line.
    When I try to do the carry forward the budget line is not carry forward and so the reserve in 2014 is trying to consume a budget line that do not exist.
    Please find a document with the images of the customizng and the 4th one with the result of the budget in 2014 but without the availability control (I get a negative ammount).
    Regards,
    Daniel

  • Down payment Carried Forward: Negative budget

    Hello,
    I have a downpayment of 8 euros in year X related to a PO. I carry forwarded the PO to year X+1.
    In year X+1 I have received an invoice of 7 and so the system automatically:
    Invoice 7
    Invoice -8
    Downpayment -8
    Payment 8
    That means that the budget is negative in year X+1. Any solution for that? If I check "Activate the conversion of bank clearing" in the settings of the Payment Transfer it would be the same?
    Please let us know.
    Regards

    Hi Mar,
    I had seen this SAP note before posting thread.
    I have some doubts in regard to implementing above note which are as follows:
    1. In update profile Down payment request & Down payment is marked for statistical update then why it is impacting funds
    2. SAP Note says that it is a modification & SAP will withdraw support after implementation of note. What are the changes take place once note is implemented:
          a. Whether I would not be able to make down payment against purchase order line item?
          b. If i can not make payment then this note is of no use as i want to track down payment against purchase order.
          c. If i can make the down payment against purchase order, will it not impact purchase order history?
                                                                                    OR
          d. this change will only impact fund management & down payment document will not impact fund management
    Thanks

  • Investment management - budget carry forward

    HI Experts,
    When ever I am running transaction code CJCO in update run, I get a message saying " Update run possible only in closed fiscal year". If I tick the green check, it runs for a while. I am not sure if it actually carrying forward the budget or not.
    I have gone through the program description  which says " You can use this program to carry unused budget from a closed fiscal year forward to the next year"
    I have closed year 2008 using IM27_close. I am not sure if this is the correct or not. Projects were created in fiscal year 2008. Fiscal year 2008 for in this case is from June 07 to May08.
    Can you please guide me as to what are the steps to be performed for year end closing of IM and at the same time is it ok to ignore the message and continue to process it.
    Please help me in this regard.
    Thanks in advance.
    regards
    Pawan

    this depends mainly on your cut over strategy -
    are you converting existing projects?
    Is the historical postings also being converted - most likely not
    if not then what happens to costing of projects  - ie are you converting partial complete projects, if so without historical data how you will analyse the project costs etc for whole projects
    what if you have projects over say 5 yrs - do you want to roll over budgets from say 2003?
    my advise would be to allow all the financial trial balance conversion take care of the project P&L
    you should only convert active projects with structures to be used form 1/1/09
    create z tables for any data required for historical puposes for the drill down from standard reports or use statistical postings to build the historical data only for the converted projects

  • Budget carry forward

    Dear Experts,
    I have doubt regarding the budget carry forward.
    I'm using PS with Investment Management.
    Now I need to carry forward the budget from 2008-09 to 2009-10 fiscal year.
    I have the following transactions:
    IM:
    IM27 - Open New Approval Year
    IM27_CLOSE - Closing Old Approval Year
    IMCAOV - Budget Carry forward
    PS:
    CJCO - Budget Carry forward
    CJCF - Commitment Carry forward
    Can any one please tell me what is the hierarchy for the above transactions?
    Do I need to carry CJCO, CJCF and then IM27, IM_CLOSE & IMCAOV? or first I need to carry out for IM and then do for PS?
    What is the flow? Please advise me on the above.
    Thanks in Advice,
    Regards,
    Praveen.

    hi
    Do the following steps:
    PS:
    CJCO - Budget Carry forward
    CJCF - Commitment Carry forward
    IM:
    IM27 - Open New Approval Year
    IM27_CLOSE - Closing Old Approval Year
    IMCAOV - Budget Carry forward

  • Carry forward of residual budget to next fiscal year

    Hi all,
    We are trying to implement Funds Management.  As part of year end closing, we need to carry forward residual budget of a particular budget type which i have created by using program FMMPCOVR.  However, the standard SAP residual key figure does not seem to be providing the correct figures to carry forward.  It throws out all budget types, and all entered budgets, not taking into account the consumed budgets as well.  I have thus created a new key figure which is simliar to the standard key figure, but change the budget type under the "budgeting data" tab to restrict to only the budget type I'm interested in.  It is still not working though, results are the same.  I'm not sure if I have created the key figure correctly.  Can someone please advise?
    Simlilarly, I have also tried to restrict the Funds to carry forward by only selecting a particular fund type by indicating in the "Restriction of FM Account Assignments" on the selection screen of FMMPCOVR.  The filter doesn't seem to be working either.  It throws out all funds of all fund types.  Can someone please adivise on this too? 
    Regards,
    maz

    Thanks Farhad...
    May I ask how did you manage to do some validation in the budget workbench?  Is there any user exit/badi that we can implement?  We wanted to do some validation on the Fund and Fund Center values which users will enter, to prevent them from entering the wrong combination.  In our business requirements, for every Fund entered in the budget workbench, users can only enter a particular group/range of Fund Centers.  Currently, the system allows free entry of any Fund and Fund Center combination.
    We are using Funds Management ECC 6.00.
    Regards,
    maz

  • Budget carry forward problem

    Guys,
    When i try to carry forward my budget for internal orders in KOCO i am getting this error. I am trying to carry forward budget of 2008. We are testing are year end steps. How does the system determine which fiscal year is closed? i have closed the fiscal year in asset accounting and was able to open year 2009.
    Why can i not carry forward budget to 2009.
    Update run only possible for closed financial years
    Message no. BP595
    Diagnosis
    You have tried to close the current fiscal year or a future fiscal year in a production run.
    Since the process cannot be reversed, you may only close a fiscal year which has elapsed.
    System Response
    Processing automatically takes place in test mode.
    Procedure
    Start the transaction again for a fiscal year which has elapsed.

    Some closing steps you can not do in the Future.
    In some case to test the fical year closing you have to change the CPU date from the server.
    An other option is to test it from 2007 to 2008
    There are some work arrouds you can found then on SAP notes, I think you can't to close the fiscal year for asset accounting to in the future
    Paul

  • Wrongly carried forward budget (KOCO) want to return.

    Hi,
    I have by mistake carry forward the budget for a internal order to wrong year, like; a order created in 2008 and i wanted to carry forward the budget to 2009 but done to 2010.
    We need to have the budget corrected to the value. I have tried with entering several transactions like budget adjustment KO22, KO24 and KO26, but the budget is still not correct. Currently the internal order is closed, but the budget needs to be corrected for it to be able to get used in the future properly.
    Please suggest if I can correct the budget which is wrongly carried forward to wrong year?
    Regards,

    Any Input?

  • Budget Carry forward report

    Hi,
    i am working for one of the client where they have carried forward the budget for some of the internal orders and for the rest of the internal orders budget is yet to be carried forward.
    is there any report whereby i can find out for which internal orders budget has been carried forward to the next year & for which internal order budget carry forward is still pending
    Regards
    Jyotsna

    Hi Jyotsna
    I dont there is any such report... Ideal way would be to run KOCO... Create a Variant and execute for all the Orders(A to ZZZZZ or 1 to 99999999)... Those orders where Budget is already carried forward, will automatically get exlcluded
    br, Ajay M

  • Reverse of Carry forward Budget ( CJCO )

    Dear All,
    I have an urgent requirement.
    User has carry forwarded the budget (CJCO) in next fiscal year, and now they want to reverse it.
    Can anyone tell me the process of it.?
    And one more thing, if anyone can tell me, how system calculates carry forward budget?
    Thanking you in advance.
    Regards,
    M P

    I don't believe there is a Reverse Function for this
    You can however run CJCO again and again and it will correct the Budget carried forward for example if additional actual costs have been posted in the old year since the last run.
    See OSS note 1048588 for calculation of Budget Carry Forward
    Hope this helps
    Steve

  • Funds Management-Budget Carry Forward

    Hi,
    I was doing testing for open item commitment carry forward along with Budget (FMJ2). In the selection screen, there is a drop down for Availability Control,  When I  Select Check and execute..
    1) I get errror message.. Budget "Annual Budget Exceeded by ......" . This message shld not appear as budget from CY is to be transffered to New Year.
    2) Then I executed FMJ2 again but this time I in Availability Control.. I selected Update without check.. this time there was no error and I could post it. But here the problem is when i see the report for Year 2009 (new year)FMRP_RW_BUDCON - Budget Control System (BCS) -> Budget -> Overview of Budget Consumption , Consumable bugdet  is 0, Current bugdet has value carried forward, available budget is in negative.
    I have release strategy for budget, but not for budget type carried forward.
    What could be the problem...How shld I solve this???
    Thanks & Regards,
    Jyoti

    Hi ELi,
    I have checked the table BUVALTPRO, automatic release is checked for carry forward process.
    Why I m not using release for this:
    1) IN FMJ2, I would like to choose Availaibility control as check, if I do this i'll get error message as release is done after I do carry forward.
    2) Budget is already released for open items in old year, so it would not make sense to release it again.
    3) Now, I have activated consistency check for Negative budget, so when I execute FMJ2, it does not allow me post even if I choose update wihout check and I get the message : "The current budget for budget type CFWD is negative"
    Does it has anything to do with
    IMG/PSM/FM Govt/Closing Operations/Closing operation for BCS/Set Up Automatic Budget Postings After Fiscal Year Change -
    what's d use of this?
    Thanks & Regards,
    Jyoti

  • How to release investment program  budget

    Hi expert:
            We distribute original  budget  in investment program using Tcode Im32,  but our customer  require to release
    original  budget ,  because  two position require to approve this budget.  
             We use Tcode Im52 to distribute budget to project,  our customer also approve this operation. but i donot know
    whether the system provide standand release function.
            how to  realize this two functions?     thank you

    You are distributing  budget from Investment prog.  to project.
    In IM there is not concept of Budget release. If you want to control your budget at Release  ( which is called Active budget control ) you have to does the same in PS.
    Your flow would be like that
    IM32 :Change origional Prog. budget
    IM52 : Budget distribution from Prog to measue i.e. Project/ WBS.
    CJ32: Change release Budget. ( so, sys will check budget against this release budget ) 
    For using Release budget funcation you have to activate avalability control in your Budget profile (OPS9 txn ) for the Release & assign that budget profile to budget profile.
    Refer this online material
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/c4/5dbfa8e7cc11d496eb0000e835339d/frameset.htm
    Regards
    Nitin

  • Balance carried forward for New GL

    Hi Expert,
    I would like understand about the balance carried forward for AP and AR in the New GL.
    When executing the program in test run mode, user will download the balances and try to tie to the recon accts in trial balance. The openning balance generated by the program should tie to the last fiscal year closing balance. But apparently, it is not. There is a difference. And after checking, the difference seem to the opening balance that aready exist in the new FY.
    So, when executing the carried forward program, is the system transferring only the difference ? New posting or items not yet carried forward ?
    Thanks.
    Angel.

    Hi,
    FAGLGVTR - Balance Carryforward (New)  for GL carry forward
    F.07 - Balance Carryforward for AR/AP carry forward
    When you execute these programs system will carryforward all closing balance to subsequent year opening balance.  Any postings happened in previous year will dynamically carried forward to subsequent year after executing this program.  If you find any mismatch, you can again execute this program.  It will not create any impact.
    Hope this clarifies your doubt.
    Best Regards,
    Madhu

  • Year end closing (Balance carried forward

    Hi
    Please help.  Our company did not do a year close on debtors and vendors.  I realised it now with certain debtors, that their closing balance (June 2006) do not agree to the opening balance (July 2006).
    Can one do a closing on the sub-ledger (Debtors & Vendors) as well as for the GL.  What affects will it be having on our books or is it save to do it.

    Hi Theo,
    There is probably nothing much you can do to bring the balances to what it should have been by end of June as some debtors would probably have paid amount owed before June 2006 and you may have paid some Creditors too.
    Your best bet is to still go ahead and carry out the year end closure of all the various <b>sub-ledgers</b> that has not been done. Once you've completed this, you may then want to embark on a reconciliation process to determine the exact balances as at June 2006 by analysing all payments received from Debtors to see which ones relates to prior 30 June 2006 and adding these back to get the correct figures as at end of June 2006. You would have to do the same for all Vendor payments you have made.
    Just to be sure you have not left out anything from your year-end processes, the following would be very useful and handy as a guide. (Though some of them may not be applicable to your organisation)
    1. <b>CJCF</b> - Carry Forward Commitments For WBS Elements
    2. <b>CJCO</b> - Carry Forward Budgets For WBS Elements
    3. <b>IM27</b> - Carry Forward IM Budget
    4. <b>F.07</b> - Execute AP/AR Carry Forward
    5. <b>ABST2</b> - Reconcile FI-AA Ledger
    6. <b>AJRW</b> - AM Fiscal Year Change
    7. <b>OAAQ</b> - Check Last Fiscal Year Closed
    8. <b>AJAB</b> - AM Year End Closing
    9. <b>F.16</b> - Execute FI Year-End Roll-Over
    10. <b>FS10N</b> - Check G/L Opening Balances
    11. <b>GJ10</b> - Execute JVA Year-End Roll-Over
    12. <b>GVTR</b> - Execute Special Purpose Ledger Year-End Roll-Over
    13. <b>2KES</b> - Profit Center:Carry Forward of Actual Balance
    14. <b>OKP1</b> - Close All Periods in Old Fiscal Year For CO
    15. <b>KSCF</b> - Cost Centers Carry Forward
    16. <b>KOCF</b> - Internal Orders Carry Forward
    I hope the above helps.
    Thanks and Regards,
    Jacob
    <b>PS:</b> Do not forget to award the points

  • Distribution of Budget to Investment Measures

    Hi,
    I finished the budgeting of Investment Program through IM32. When I try to distribute this budget to Investment Measure through IM52, the system says that no Investment Meeasures are available. I am surprised to see this mesage.
    Please help.
    regards
    Pratap.V

    Hi friends,
    I will explain in detail the process which I followed.
    1) Creation of Inv Program Definition
    2) Creation of Inv Program Structure
    3) Creation of Appropriation request
    4) Approval of the App request
    5) Creation of Project and release of App request
    6) Create WBS
    7) Cost Planning of WBS thru CJ40
    8) Transfer of Plan values to from WBS to Inv Program
    9) Budgeting of Inv Program
    10) Distributing Budget to Measures
    While doing the 10th step, the system says that no measure are available. Please try to help me out.
    regards
    Pratap.V

Maybe you are looking for

  • How do I set twice monthly events based on the week number

    Greetings all. I can't seem to navigate this help system, so hopefully I'm not reasking something that's already been asked. But I have a problem with iCal that I just can't figure out of find an answer to. I need to create a twice monthly event, but

  • Can't connect LINKSYS router to DSL modem

    I'm trying to set up a WRT54GS2 Linksys router with a D-Link DSL-2320b modem.  Have a Westell 6100 modem that is going bad, so I bought the D-Link to replace it. Originally had a D-Link router connected with the Westell, but the router overheats ofte

  • How do I upgrade to OS X Mountain Lion for free?

    How do I upgrade to OS X Mountain Lion for free? I just bought a new Mac Book Pro 5 days ago with OS X Lion. The Apple store said I could download the new OS for free by entering the receipt # and total amount of the purchase.  I don't know where to

  • URL iview issue for intranet sites

    Hi Guys, I am creating a simple url iview for one of our Sharepoint site. when I preview the iview it works fine. but when I assign it to some Role, it doesn't load. "Page cann't be displayed" error comes. Some prefix with the text  "res://ieframe.dl

  • Acrobat 8.1.0 Delete Not Visable

    Hello. I have cloned my old hard drive to a new large capacity hard drive. The delete fuction now does not work. I have just reinstalled the Acrobat 8.1.0 software and still the delete function is greyed out. Before cloning all functions worked. Any