Cash forecast (FF7B) from IM / PS applications, and internal orders as well

Hi,
Does anyone know how to use transaction FF7B (cash forecast), with IM and PS applications?
I have several options:
1) from IM application, I would like to use the capitalize date and another field(s) that will contain the terms of payment; then I would like to be able to forecast my payments 1 year in advance and monthly (according to the terms of payment: 20% the 1st of june, 50% the 1st of october,...). Does SAP enable to do so in its standard? Which field(s) should I use in the investment line item to enter my terms of payment?
2) Same question for PS application or from internal orders, which fields should I use to have a date and terms of payment so that I can have a report of my payment forecast with transaction FF7B?
As you would have understood, I would like to have several levels of payment forecasts: at IM level, at PS level, then engaged with purchase orders/requests (standard SAP) and invoices (standard SAP).
Thanks for your ideas/help...
Ronan

Hi Ronan,
FF7B allows you to pick up itesm from the SD and MM module and show it in the Liquidity Forecast report.  So for example, if you have Sales Orders with a delivery date of say November 1, 2010 and the customer has terms Net/30, then this amount will show up as a Receivable on Dec.1, 2010. Similarly if the delivery is spread over a one year period with 1/12th being delivered every month, then the Liq. Forecast will show them accordingly in each month starting from December 2010.
In your case you want to show items appearing in IM and PS. I am not familiar with these modules, but I am sure there will be a way to capture them and show them items in the Liquidity Forecast. May be if you can give some detail about the items which you want to see in the FF7B report, I might be able to guide you.
Kalyan

Similar Messages

  • How do I play audio from my headphone jack and internal speakers?

    How do I play audio from my headphone jack and internal speakers at the same time ? I have a splitter for my audio jack so that when i connect up my second monitor I can have it so it also plays audio as well as anything else i have connected into the jack but how do i let the internal speakers emit sound at the same time?

    Hello,
    If you mean the internal speakers in your Mac, you can't play audio through them at the same time you have anything plugged into the headphone jack. When you plug something into the headphone jack, it disconnects the internal speakers.

  • Report showing total costs pr. cost center and internal order..

    Hi FI Gurus,
    Do any of you know a standard report, which can display G/L, Company code, Period, total cost in local currency, cost center and internal order. The report should be at summarizational levet (not line items) and we should be able to sum costs at cost center and internal order.
    Finally we should also be able to transfer the report to BI via an extractor etc.
    Thanks for you help
    Pernille

    Hi,
    Cost Centre vise Report you can take from KSB1
    Internal Order Vise Report you can take fro KOB1
    Regards,
    Sridhar Sha

  • Usage of Cost Centers, Profit Centers and Internal Orders

    Hello everyone,
    i have perhaps for some of you a simple question but it bothers me alot.
    Imagine we are using Cost centers and Internal Orders. For them we create statistical key figures using transaction KB31N.
    Now we are installing SAP BI and want to create a report which would be generated acording to cost centers but with statistical key figures.
    The question would be how to make a connection between cost centers orders and those stat.key.figs?
    In our case the economists say that we are using this kind of scenario:
    Dist.chanel ->
    Sender: Cost center, Cost element
    Receiver: Int.Order
    and Stat key fig.
    This is the only place where we have a connection between thos objects. Is there other way how to connect them. perhaps using profit centers?
    If somebody didnt understand it, maybe ill try to explain it a bit better
    Reagards
    Laurynas Prikockis

    Hi Laurynas,
    Pls try to understand the concept as explained hereunder...
    Cost Element:
    Primary Cost Element : Replication of GL to bring costs into CO module when they are posted in FI 
                                       module
    Secondary Cost Elements: Carriers of costs between two Cost Objects (when we want to transfer the
                                            cost from Cost Centers to Internal Orders, vice versa and more, we create
                                            Secondary Cost Elements to carry the costs and transfer them to the 
                                            reciever objects from sender objects)
    Cost Center: It is a Cost Object, maintained on long-term basis, where we can capture the costs (Ex:
                        Marketing Cost Center)
    Internal Order: It is also a Cost Object, maintained on shor-term basis, where we can capture the costs
                         (Ex: Internal Order for Special Marketing Campaign). Ultimately, whatever the costs
                          posted to this Internal Order, will get settled to Marketing Cost Center.
    Staitistical Key Figure: It is used as a basis for allocation of certain expenses (Simple example would
                                      be, Total rent paid for office is $100000 per month. This cost has to go to
                                      different Cost Centers like Finance and Accounts, Marketing, Purchase Dept
                                      etc on the basis of "Area Occupied". So, We will define "Area Occupied" as a 
                                      Statistical Key Figure in our system.
                                     Now, when the Rent amount is posted in FI, it wil reach a Virtual Cost Center
                                     (An "Allocation Cost Center" with name "Rent" to be created under your
                                     Controlling Area) "Rent". From there, it has to reach the other Cost Centers (lie
                                     F&A etc as explained above) on the basis of Area Occupied (SKF Created
                                     for "area occupied")
    For this, you need enter the Area Occupied values (Ex:Sq Ft) in KB31N and you need to create an Allocation Cycle (Distribution / Assessment) where in you will select "Area Occupied" (SKF) as your Receiver Tracing Factor.
    I hope I am clear, don't hesitate to revert back for more explanation...
    Srikanth Munnaluri
    Edited by: Srikanth Munnaluri on Mar 3, 2009 7:26 PM

  • Profit center field and internal order field in sales order

    Hello all,
    I am unable to find the settings for profit center field and internal order field in sales order account assignment tab screen. kindly let me know the path and configuration settings.
    Thanks in advance
    Regards
    srinivas

    Hi Srinivas
    If you want to assign the profit center then make sure that the Profit center is assigned in MMR->Sales orgn 1 view . 
    But to assign the Profit center in MMR also you need to configure the Profit center first for your Material in your company code with the help of FI/CO consultants and then assign then the profit center will flow from MMR to sales order  item data->account assignment tab
    Regards
    Srinath

  • Difference between WBS element and internal order?

    What is the main difference between WBS element number and internal order number?
    Points will be given!

    Hi,
    WBS:
    The work breakdown structure (WBS) is a model of the project that organizes project tasks into a hierarchy.
    It is the functional basis for further planning steps in a project, for example, for process planning, cost planning, scheduling, capacity planning or costing, as well as project control.
    It gives you a clear picture of the project and facilitates the coordination and implementation of the project from a management standpoint.
    It shows the work involved in a project.
    check this link also
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/a9/8a853488601e33e10000009b38f83b/frameset.htm
    Internal order:
    Internal orders are normally used to plan, collect, and settle the costs of internal jobs and tasks. The SAP system enables you to monitor your internal orders throughout their entire life-cycle; from initial creation, through the planning and posting of all the actual costs, to the final settlement and archiving:
    check this link also
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/a9/ab7f68414111d182b10000e829fbfe/frameset.htm
    if this helps,please assign points.
    Thanks,
    Rau

  • PO and internal order

    Hello i have a question concerning PO and Internal Orders.
    I have created some Internal Orders and i have made a PO for assets with this internal order (internalorder1)
    Now i have authorised a user with another internal order number.(internalorder2)
    Can i somehow prevent a user to release POs for internal orders according to the authorised internal order.(internalorder2)
    Maybe the authorization object k_order the field co_action???

    If you use TCode SU24 to look at the authorization object checking for the object K_ORDER you will see that this object is not checked for TCodes ME21, ME21N, ME22, ME22N, ME23, or ME23N.  This is probably why you can still use any internal order whether you have it in your profile or not.  You might be able to add the authorization object to these to the MM_E Materials Management: Purchasing class.  I think you can use TCode SU21 to maintain these objects, but you need to check with your Basis/Security personnel.
    As a test you can use SU24 to look at object M_BEST_EKO Purchasing Organization in Purchase Order.  You will find that it is checked in pretty much every PO creation or change TCode (ME21, ME21N, ME22, ME22N, ME23, ME23N, ME24, ME25, ME26, ME27, ME28, ME29N).
    Regards
    Edited by: Paul Shrewsbury on May 11, 2009 2:32 PM

  • Wbs no and internal order no

    How do i get the WBS no and INTERNAL ORDER NO
    in the same report what is the link between these two tables

    Hi,
    Go to T.Code: FB00 and maintain G/L account items fast entry Layout SAP02 now  you will get WBS
    Regards
    Viswa

  • What is link between SD and Internal order

    hi sap garus
    can baby explain the link between Sd and internal Orders.
    advance thanks
    suresh

    Hi,
    What link exactly do you have in mind? You can assign a sales order to internal order, if that's your question.
    Regards,
    Eli

  • How can I call Adobe Reader from inside my Application and prevent operator to access Open/save opt

    Can Anyone help to find a way?
    http://answers.acrobatusers.com/How-call-Adobe-Reader-inside-application-avoid-operator-op en-save-doc-q13487.aspx
    From inside my application that run on an Automation PC, under Windows O.S, I want to call Adobe Reader using a shell command to open up an PDF Document containing some informations.
    Shell command like these
    "C:\Program Files\Adobe\Reader 10.0\Reader\AcroRd32.exe" /A "<options>" "C:\mydoc.pdf"
    or
    cmd  /c "C:\mydoc.pdf"
    Operator is using a touchscreen.
    I want to prevent user to access any option that can give him acces to filesystem (Open/save/save as).
    I want also to prevent any change/add information to PDF document
    Thank you in advance for the time you will spend for me.

    You can use the Installation Tuner for Reader to customize the UI elements provided to the user.  Details on the Adobe web site.

  • PR are created automatically from MRP without Demand and Sales Order

    Hi experts,
    I used Tcode ME5A to display PR list and i see some Perchasing Requisitions created from MRP. I checked Demand by tcode MD61 and Sale Order or Delivery Order by MD04 but i see nothing.
    I don't know how can it happens. Pls give me the way to check it.
    Thank you,

    if you dont see any reason, then the reason may not be present anymore.
    E.g. the sales order got deleted.
    In this case the next MRP run will automatically remove the requisition.
    What are your settings in material master MRP view?  maybe you are below safety stock or reorder point.
    you have to look into the requistion, what item category does it have, what accounting category. Only there you can see if the PR is related to sales order or any other order.

  • Microphone delay / echo / audio bounce from mono plug microphone and internal microphone

    hi everyone... i have been trying for months to figure out how to banish the echo /delay from my g6 laptop!i have a g6 with 4gb ram and an i7-3632qm cpu @ 2.20ghz!i have uninstalled audio drivers.. reinstalled the idt audio driver.. reset..refreshed.. troubleshoot recording devices..troubleshoot playback devices.. gone between hp forums and windows forums.. tested youtube remedies.. changed quality of audio from cd quality to studio quality.. changed o.s from 7 to 8.. to 8.1... to 10... turned off "listen too" button then adjusted secondary control for hd audio.. !!i even tried looking into older audio drivers with no luck!!if i cant fix this any chance hp would do a recall?i love this laptop and it served me well as a video dj.. but now im getting back into recording.. i am devasted and stuck in the middle of the ocean in a row boat with no paddle!!!glug glug!!!thanx in advance...!!!

    I have just sent you a private message. If you are not sure how to check your forum messages, this post has instructions.

  • Production Order and Internal Order for each item of the sales order

    Hi
       I am developing Make To Order Report where I have to display the MTO Line Items and non MTO Line Items. For non MTO Line Items I have to display Internal order with Planned and Actual Costs and also Production Order with Planned and Actual Costs. Could anybody tell how to get the Internal order no and production order with Planned and Actual costs for each line item for a sales order.
    Thanks
    Naga

    Hi,
    You can get the Production orders, Planned orders, Internal orders generated for Sales order item from AFPO table (use fields KDAUF-Sales order number & KDPOS-Sales order item). Then to identify the order type use order category (AUTYP) from table AUFK.
    Once you have the Production/internal order, you can ge the cost from COSS and COSP table. Use the object number from AUFK to get the cost entries from COSS & COSP.
    You can use the following sample code as reference.
    Hope this is helps.. (Don't forget to mark it... )
    Form GET_COSTS                                                       *
    Get the material cost, labour hours and the labour cost for the      *
    sales order material.                                                *
    There are no interface parameters to be passed to this subroutine.   *
    FORM GET_COSTS.
      DATA V_OBJNR LIKE AUFK-OBJNR.
    DATA v_menge LIKE vbap-kwmeng.
      SELECT SINGLE OBJNR
        INTO V_OBJNR
        FROM AUFK
       WHERE AUFNR EQ AFPO-AUFNR.
      SELECT * FROM COSS
       WHERE OBJNR EQ V_OBJNR
         AND WRTTP IN ('01', '04'). " p_wrttp. "Labour Cost ( Plan, Actual)
        PERFORM GET_VALUES_FROM_COSS.
      ENDSELECT.
      SELECT * FROM COSP
       WHERE OBJNR EQ V_OBJNR
         AND WRTTP IN ('01', '04')         " p_wrttp
         AND KSTAR NE '0000510033'. " EQ p_kstar2.      "Material Cost
        PERFORM GET_VALUE_FROM_COSP.
      ENDSELECT.
    Get the unit cost of the production order by dividing the production
    cost by the order quantity. The result will be multiplied by the
    GL posting qunatity (Delivery quantity) to get the production cost
    for the quantity being deluivered.
      IF NOT AFPO-PSMNG IS INITIAL.
        OUT_REC-LABOUR_HOURS_ACT = OUT_REC-LABOUR_HOURS_ACT / AFPO-PSMNG.
        OUT_REC-ADDNL_LABOUR_HOURS_ACT =
                          OUT_REC-ADDNL_LABOUR_HOURS_ACT / AFPO-PSMNG.
        OUT_REC-LABOUR_HOURS_PLN = OUT_REC-LABOUR_HOURS_PLN / AFPO-PSMNG.
        OUT_REC-ADDNL_LABOUR_HOURS_PLN =
                         OUT_REC-ADDNL_LABOUR_HOURS_PLN / AFPO-PSMNG.
        OUT_REC-LABOUR_COST_ACT = OUT_REC-LABOUR_COST_ACT / AFPO-PSMNG.
        OUT_REC-ADDNL_LABOUR_COST_ACT =
                         OUT_REC-ADDNL_LABOUR_COST_ACT / AFPO-PSMNG.
        OUT_REC-LABOUR_COST_PLN = OUT_REC-LABOUR_COST_PLN / AFPO-PSMNG.
        OUT_REC-ADDNL_LABOUR_COST_PLN =
                         OUT_REC-ADDNL_LABOUR_COST_PLN / AFPO-PSMNG.
        OUT_REC-MATERIAL_COST_ACT = OUT_REC-MATERIAL_COST_ACT / AFPO-PSMNG.
        OUT_REC-ADDNL_MATERIAL_COST_ACT =
                         OUT_REC-ADDNL_MATERIAL_COST_ACT / AFPO-PSMNG.
        OUT_REC-MATERIAL_COST_PLN = OUT_REC-MATERIAL_COST_PLN / AFPO-PSMNG.
        OUT_REC-ADDNL_MATERIAL_COST_PLN =
                         OUT_REC-ADDNL_MATERIAL_COST_PLN / AFPO-PSMNG.
      ENDIF.
    Multiply the calculated Unit Production costs with the GL quantity to
    get the actual production cost of the quantity delivered.
    Calculation for Labour Hours
      OUT_REC-LABOUR_HOURS_ACT = OUT_REC-LABOUR_HOURS_ACT *
                                 OUT_REC-QUANTITY.
      OUT_REC-ADDNL_LABOUR_HOURS_ACT = OUT_REC-ADDNL_LABOUR_HOURS_ACT *
                                 OUT_REC-QUANTITY.
      OUT_REC-LABOUR_HOURS_PLN = OUT_REC-LABOUR_HOURS_PLN *
                                 OUT_REC-QUANTITY.
      OUT_REC-ADDNL_LABOUR_HOURS_PLN = OUT_REC-ADDNL_LABOUR_HOURS_PLN *
                                 OUT_REC-QUANTITY.
    Calculation for Material Cost
      OUT_REC-MATERIAL_COST_ACT = OUT_REC-MATERIAL_COST_ACT *
                                  OUT_REC-QUANTITY.
      OUT_REC-ADDNL_MATERIAL_COST_ACT =
          OUT_REC-ADDNL_MATERIAL_COST_ACT * OUT_REC-QUANTITY.
      OUT_REC-MATERIAL_COST_PLN = OUT_REC-MATERIAL_COST_PLN *
                                  OUT_REC-QUANTITY.
      OUT_REC-ADDNL_MATERIAL_COST_PLN =
          OUT_REC-ADDNL_MATERIAL_COST_PLN * OUT_REC-QUANTITY.
    Calculation for Labour cost
      OUT_REC-LABOUR_COST_ACT   = OUT_REC-LABOUR_COST_ACT *
                                   OUT_REC-QUANTITY.
      OUT_REC-ADDNL_LABOUR_COST_ACT = OUT_REC-ADDNL_LABOUR_COST_ACT *
                                  OUT_REC-QUANTITY.
      OUT_REC-LABOUR_COST_PLN   = OUT_REC-LABOUR_COST_PLN *
                                  OUT_REC-QUANTITY.
      OUT_REC-ADDNL_LABOUR_COST_PLN = OUT_REC-ADDNL_LABOUR_COST_PLN *
                                  OUT_REC-QUANTITY.
    Get the planned material cost from the total of the planned cost of
    the component materials in the production order confirmations.
      SELECT BWART MENGE MATNR SHKZG FROM AUFM
        INTO (AUFM-BWART, AUFM-MENGE, AUFM-MATNR, AUFM-SHKZG)
       WHERE AUFNR EQ AFPO-AUFNR.
        CHECK AUFM-BWART NE '101'.
        READ TABLE I_MBEW WITH KEY MATNR = AUFM-MATNR
                                   BWKEY = AFPO-DWERK.
        IF SY-SUBRC NE 0.
          SELECT MATNR BWKEY ZPLPR LPLPR PEINH
            FROM MBEW
            INTO I_MBEW
           WHERE MATNR EQ AUFM-MATNR
             AND BWKEY EQ AFPO-DWERK.
            APPEND I_MBEW.
          ENDSELECT.
        ENDIF.
        IF SY-SUBRC EQ 0.
          IF I_MBEW-ZPLPR NE 0.
            IF AUFM-SHKZG EQ 'H'.
              OUT_REC-PLANNED_MATERIAL_COST =
              OUT_REC-PLANNED_MATERIAL_COST +
                           ( I_MBEW-ZPLPR * AUFM-MENGE / I_MBEW-PEINH ).
            ELSE.
              OUT_REC-PLANNED_MATERIAL_COST =
              OUT_REC-PLANNED_MATERIAL_COST -
                           ( I_MBEW-ZPLPR * AUFM-MENGE / I_MBEW-PEINH ).
            ENDIF.
          ELSEIF I_MBEW-LPLPR NE 0.
            IF AUFM-SHKZG EQ 'H'.
              OUT_REC-CURRENT_MATERIAL_COST =
              OUT_REC-CURRENT_MATERIAL_COST +
                           ( I_MBEW-LPLPR * AUFM-MENGE / I_MBEW-PEINH ).
            ELSE.
              OUT_REC-CURRENT_MATERIAL_COST =
              OUT_REC-CURRENT_MATERIAL_COST -
                           ( I_MBEW-LPLPR * AUFM-MENGE / I_MBEW-PEINH ).
            ENDIF.
          ENDIF.
        ENDIF.
      ENDSELECT.
    Get the Future material cost per Unit by deviding the calculated
    Future material cost above with the goods reciept quantity to, then
    multiply the unit cost with the GL quantity to get the Future material
    Cost for the Quantity delivered. (Quantity in the entery from GLPCA
    Table).
      IF NOT AFPO-WEMNG IS INITIAL.
        OUT_REC-PLANNED_MATERIAL_COST =
           OUT_REC-PLANNED_MATERIAL_COST / AFPO-WEMNG * OUT_REC-QUANTITY.
        OUT_REC-CURRENT_MATERIAL_COST =
           OUT_REC-CURRENT_MATERIAL_COST / AFPO-WEMNG * OUT_REC-QUANTITY.
      ENDIF.
    ENDFORM.                               " GET_COSTS
    Form GET_VALUE_FROM_COSP                                             *
    Get the Material cost from COSP table.                               *
    There are no interface parameters to be passed to this subroutine.   *
    FORM GET_VALUE_FROM_COSP.
      FIELD-SYMBOLS: <FS> TYPE ANY.
      DATA: V_COMPONENT TYPE I.
    Cummulate the posting values of all the 16 period buckets as to get
    total production order cost. This is to handle the aprtial posting of
    prodction order values in diffrent periods.
      V_COMPONENT = 15.
      DO 16 TIMES.
        ADD 1 TO V_COMPONENT.
        ASSIGN COMPONENT V_COMPONENT OF STRUCTURE COSP TO <FS>.
        IF COSP-WRTTP EQ '04' AND COSP-KSTAR EQ P_KSTAR2.
          ADD <FS> TO OUT_REC-MATERIAL_COST_ACT.
        ELSEIF COSP-WRTTP EQ '04'.
          ADD <FS> TO OUT_REC-ADDNL_MATERIAL_COST_ACT.
        ELSEIF COSP-WRTTP EQ '01' AND COSP-KSTAR EQ P_KSTAR2.
          ADD <FS> TO OUT_REC-MATERIAL_COST_PLN.
        ELSEIF COSP-WRTTP EQ '01'.
          ADD <FS> TO OUT_REC-ADDNL_MATERIAL_COST_PLN.
        ENDIF.
      ENDDO.
    ENDFORM.                               " GET_VALUE_FROM_COSP
    Form GET_VALUES_FROM_COSS                                            *
    Get the Labour cost and Labour hours from the COSS table.            *
    There are no interface parameters to be passed to this subroutine.   *
    FORM GET_VALUES_FROM_COSS.
      FIELD-SYMBOLS: <FS1> TYPE ANY,
                     <FS2> TYPE ANY.
      DATA: V_COMPONENT1 TYPE I,
            V_COMPONENT2 TYPE I.
    Cummulate the posting values of all the 16 period buckets as to get
    total production order cost. This is to handle the aprtial posting of
    prodction order values in diffrent periods.
      V_COMPONENT1 = 15.
      V_COMPONENT2 = 111.
      DO 16 TIMES.
        ADD 1 TO: V_COMPONENT1, V_COMPONENT2.
        ASSIGN COMPONENT V_COMPONENT1 OF STRUCTURE COSS TO <FS1>.
        ASSIGN COMPONENT V_COMPONENT2 OF STRUCTURE COSS TO <FS2>.
        IF COSS-WRTTP EQ '04' AND COSS-KSTAR EQ P_KSTAR1.
          ADD <FS1> TO OUT_REC-LABOUR_COST_ACT.
          ADD <FS2> TO OUT_REC-LABOUR_HOURS_ACT.
        ELSEIF COSS-WRTTP EQ '04'.
          ADD <FS1> TO OUT_REC-ADDNL_LABOUR_COST_ACT.
          ADD <FS2> TO OUT_REC-ADDNL_LABOUR_HOURS_ACT.
        ELSEIF COSS-WRTTP EQ '01' AND COSS-KSTAR EQ P_KSTAR1.
          ADD <FS1> TO OUT_REC-LABOUR_COST_PLN.
          ADD <FS2> TO OUT_REC-LABOUR_HOURS_PLN.
        ELSEIF COSS-WRTTP EQ '01'.
          ADD <FS1> TO OUT_REC-ADDNL_LABOUR_COST_PLN.
          ADD <FS2> TO OUT_REC-ADDNL_LABOUR_HOURS_PLN.
        ENDIF.
      ENDDO.
    ENDFORM.                               " GET_VALUES_FROM_COSS

  • CATS and internal orders

    we are trying to use Co internal orders to collect costs based on the input in cats.
    Does any one have a detailed document to accomplish that.
    Also what modifications need to be done to the cat2 screen to update the internal order
    Thank you

    I don't think you need to make any thing specific. But you make few general settings in the data entry profile for using CAT2 - Time sheet entry. Check the SPRO nodes mentioned below:
    In below node you mention general settings,Time settings, worklists etc.,
    Cross-Application Components>Time Sheet>Specific Settings for CATS regular>CATS regular>Record Working Time>Set Up Data Entry Profiles
    Use T code CAC2 you make the Field selection settings like what fields should appear in CAT2 screen and if any field entry is to be made mandatory before you save the entries.
    Regards
    Sreenivas

  • Project stock "Q" and Internal order

    Hy,
    we are trying to use the Project stock indicator ("Q") for make-to-order ; the Project stock seems to work properly.
    We are also trying to insert the "Internal order"  and we modified the "Q" account assignement category to add the 'internal order'.
    In the Purchase order we insert a 'real' internal order and a 'statistic' wbs.
    When we make the good receipt we have only a CO posting to the 'statistic' wbs but do not have any CO posting to the 'real' internal order.
    Can someone help me to solve this point?
    thanks in  advance.
    Mario

    Hi Gianmario,
    What you can try is to change the consumption posting indicator in the account assignment category from P to V. But I am not sure how the system then behaves in combination with special stock Q.
    Regards,
    Kay