CATS hours against Activity Type

Hi,
I have one scenario, where,
1: The entered hours by employees to be captured against Activity type,and should be considered as Cost.
2: The final billed hours to be captured against the WBS elements as a revenue.
Example: Employee enters 5 hrs initially, which is approved as 4 hrs and sent for billing. The 5 hrs need to be captured against the activity type and 4 hrs to be captured as revenue.
My question is how to achieve this as CATS would capture and retain 4 hrs after approval. The CATS record only shows 4hrs after approval process and changes done.
So how this can be captured ?
Regards,
Ayesha

Hi,
Check if any field is there for Un-approved times ?
if you want to show the recroded time entries of employee, go for additional fields and configure there. check with ABAPer they can help you.
Best Regards.

Similar Messages

  • CATS Problem with Activity types, it takes the first 6 digits of PERNR

    Hello Gurus!
    I have configured cats and maintained infotype 0315. When i go to CAT2, i dont see any default values on the screen from 315. When i try to call the cost center and activity type,. enter the times and hit enter, it hits an error saying: Activity type 001131is invalid for 00113199. It doesnt speak abt the activity type i assigned, it probably takes the first 6 digits of personal number as the activity type and throws an error.
    Please help me what to do with this... its very urgent..
    Points granted..
    Thanks,
    Soniya Singh

    Which version of SAP are u using. I don't see any message with your description in the message class.
          I think the values on CATS are only defaulted when u give the WBS element and hrs and press ENTER. Try this and u should be able to get the values defaulted from 315 assuming you have set the default values in CAC1 and also please check the settings in the Initial screen of CAT2 if any other values are getting defaulted in Persons tab and also check ur activity type has the valid Controlling area.
    Edited by: Madhu Gudur on Feb 21, 2008 5:58 AM

  • Confirmation of activity type in Process order -Impact in FI.

    Dear All,
    On doing a confirmation of a activity type for a process/ Production order - values get posted to secondary cost element which has been assigned to a acitivity type.  This means only a impact in controlling but not in FI
    How woould the booking happens in FI ?is it not required to book in FI, if yes, why.
    Please suggest.
    Thanks.

    Hi Daya
    1. You can calculate activity price for plan in KSPI and for actual KSII for respective CCtr and activity type...but some times people manually update price at KP26 directly which in my opinion is not right way because price is either more or less than the real calculation in KSPI and KSII...
    2. However in your case price is directly updated in KP26 against activity type..when confirmation is done in order this rate * activity qty is your value posted in order level and at the same time respective CCtr is also credited by this amount which you can see in CCtr report
       Example:  CCtr  XXXX01
                       Activity type 999999
                       Sec cost Element for activity type 999999 (43 cat)
        Suppose you have booked FI entries for some expenses like Salary in F-02/FB50...against CCtr XXXX01   So your CCtr XXXX01 is debited by Salary amount and this amount will be absorbed in product through activity for which you need  activity price and confirmation.
        FI entry is booked your expense in GL a/c Salary and same time debited your CCtr through CE salary....Now when you charging this expense in product through prod order you are doing it through confirmation of activity qty which in turn calculating value by taking price from KP26 and qty from confirmation.
    Kamal

  • Activity Type with no dollars.

    We have a situation where we would like to charge hours quantity to a project but we don't want to pull any dollars into the project based on the hours.  The dollars will be charged directly off Vendor Invoices.  I thought that using Category 4 Activity Types could accomplish this zero charge but we ran into problems not being able to allocate Cat. 4 Activity Type.  Does anyone know how to get hours charged into a project without pulling in dollars as well.  You help would be apreciated.

    Here is what I have ocnfigured:
    Activity "CONLAB" for contract labor is set up with the following fields populated-
    Activity Unit = H 
    CCtr categories  =  8
    AtypCategory = 4
    Every thing else is blank.  When I attempt to set this up on the project I get the following error message -
    Activity CONLAB cannot be allocated to 2009
          Message No KL008
    Diagnosis
         Activity type CONLAB was planned in fiscal year 2009 as non-allocatable.  That means other objects cannot input any activity through this activity type.
    System Response
         No activity input can be posted
    Procedure
         Choose an activity type.
    We need to plan these statistical hours but it's not letting us track them in the Project.  I sure hope someone has an idea on how to fix this.

  • CAT2 - How can I see the rate assigned to an activity type?

    In transaction CAT2, there is a column named ActTyp (Activity type). How can I see the rate assigned to this activity type (example: 50$/hour pour activity type Project management) ?
    Thanks,
    Julien

    Hi Julien,
    plz goto KP26 and enter the acitvity type and cost center of the work center and check the price ..
    regrds
    pushpa

  • Activity Type ---------------kp26 --------------------Suggest

    Hi all
    can any one give good suggestion ..
    my client is asking activity type planning not fixed
    we have 4 activity type
    1) Labour -K.G
    2) Labour -Inch
    3) Machine Hour-
    4) Labour Cost Area
    But main problem
    when we plan in KP26
    There is plan in labour wise
    because one labour is taking some amount
    other labour is taking another amount like 
    pls suggest me
    it is very urgent
    where can plan

    HI Supriya,
    You plan activity-dependent primary costs as follows on a cost center(s)/cost center group:
    By cost element(s)/cost element group
    Based on the activity type(s)/activity type group
    This means that you can plan a fixed amount and a variable amount for your primary costs. Variable costs are the costs incurred in producing a given activity, proportional to the quantity of activity produced. You can calculate target costs based on the costs split and the operating rate (actual activity quantity related to the plan activity quantity). Target costs for costs planned by value are comprised of:
    Plan fixed costs
    Plan variable costs adapted to the actual operating level (= target costs of the actual operating level)
    Example:
    To produce 1000 hours of activity type FST, costs of $400,000 are required. This amount represents the variable costs. The portion of fixed costs, $200,000, is incurred irrespective of the activity quantity.
    For activity-dependent costs, which are planned based on quantity, the following formulas apply:
    Variable target quantity = Variable plan quantity X Operating rate
    Fixed target costs = Fixed target quantity X Fixed price
    + Variable target quantity X Fixed price
    + Fixed target quantity X Variable price
    Variable target costs = Variable target quantity X Variable price
    If useful give me points.
    Venkat

  • What are the difference between Activity types & SKFs

    Dear Friends
    Can any body help me regarding, what are the main differences between Activity Types & Statistical Key Figures(SKFs).
    Thanks, in Advance

    Hi Prabhakar,
    Both are used as tracing figures. The major difference is that Activity type has price on its own and its gets summed up at the time of allocation. The sum figures debited to the receiving cost object and credited to sending cost object. Activity type cannot stand alone.
    But it is not the case with SKF. SKF are only used as tracing factors and do not have price unlike activity type.
    Example
    In the case of activity allocation of Labour hours, the activity type of Labour with price shall be used.
    In the case of statistical figure, take the example of Canteen expenses and its allocation between the Cost objects on the basis of head count of each cost object. :
    Hope this answers to your query!

  • CATS INTEGRATION WITH PP AND PM MODULE ( TO FIND ACTUAL MANPOWER COSTING THROUGH ACTIVITY TYPE)

    Hi Experts,
    We have a scenario like, Client wants to track the actual manpower costing through activity type ( Ex: How much hours an employee worked on a particular work center to produce an “X” product, So that his actual cost should be loaded on that product.
    We have employee ( 1. Staff 2. Worker 3. Contract labor employee and apprentice from third party roll and staff and worker we plan to go with negative time management and for contract labor and apprentice will go with through cats.
    Since we are not going to run the payroll for contract labor employee and apprentice, we just maintaining the employee data as a group ( Ex: Group A,B,C etc.. Each group consists 20 or 30 employees, According to system each group as one employee and according to us each group consists as 20 or 30 employee.
    The Activity type as well cost center will be created by Co module, the same will be assigned in info type 0315, but still i want more input from experts on the same, since i am new to cross application time sheet configuration, could any one help me out to find the actual manpower costing in a better way.
    Regards,
    Prem

    Hi Experts,
    Can any one please reply on the same.
    How to arrive the exact manpower costing through activity type ?..
    Regards,
    Prem

  • In CATS,  where can I assign "Activity type to default Time sheet",

    Hi gurus,
    In CATS,  where can I assignt Activity type to Default time sheet.  Please help me asap.
    If any cats doc.  available plz share with me.
    Thanks in advance,
    Sadana.

    If you have defined activity types then you can define them with the right price in KP27 for each costcenter.
    the costcenter is connected with the personelnumber.. in infotype 315 you can define which is the default activitytype for each person.
    if you have only 1 activitytype you can also programm the user exit to fill it in by default
    see EXIT_SAPLCATS_002 to implement a fixed activitytype for whole cats
    kind regards
    arthur de smidt

  • CATS billing thru PS | internal Order, WBS, Activity Type

    Hi,
    I am a HCM consultant, therefore I have zero knowledge in PS/SD.
    Currently I am working on a task, where I need to create the bill on the CATS data (Time Sheet Data: HCM). I want to know how the CATS data is transferred to WBS, and how the billing of the same is done in PS the WBS element and Activity Type. I ll be transfering the time data to Internal Order (I dont know how to assign these internal orders to WBS elements) and in Activity type I ll be storing the rates of the activities/tasks. Now on the basis of these Internal type, WBS and Activity type, How can I generate a bill in PS? (We are inactivate in SD module).
    A more clear explanation would be better as said, am new to PS..
    regards
    Tahir

    HI Tahir,
    wbs and internal order is the object where we can book time via time sheet so clear here when you are booking time in CAT2 transaction then time sheet ask it's receiver object that would be either wbs nor I/O. once you have done this activity, then need to transfer it to object area like PS CS CO HR PayRoll
    such transaction path is below in CATS
    CAT2
    Time Sheet: Maintain Times
    CAT2_ISCR
    CATS: Maintain Times (Init. Screen)
    CAT3
    Time Sheet: Display Times
    CAT3_ISCR
    CATS: Display Times (Initial Screen)
    CAT4
    CATS: Approve Data
    CAT5
    Data Transfer CATS -> PS
    CAT6
    Transfer External -> Time Management
    CAT7
    CATS: Transfer Data to CO
    CAT8
    Time Sheet: Document Display
    CAT9
    Data Transfer CATS -> PM/CS
    i m telling you in PS area next take help from SD guys
    Regards,
    Sanjeev

  • Pre-populate the Public Holiday hours in CATS with A/A Type

    Hi Experts
    Please let me know if there is anyway for us to pre-populate the Public Holiday hours in CATS with A/A Type for all employees. 
    Our Client would like automatically populate Holiday hours with A/A type 2000 in CATS for all eligible employees, based on whatever amount of hours they are scheduled to work on the specified days. 
    Basicall client dont want employee to enter A/A with Public Holiday Hours, they want it to be automatically exist in CATS timesheet
    If you have any other ideas about how to accomplish this please let me know.
    Regards,
    Koutilya A.K

    Hello Koutilya,
    I got the same requirement as yours. Can you please suggest me how to achieve this one.
    Thanks,
    R V Narayana.

  • CAT 2 : activity type

    Hi
    Please tell how  to add "Rest Day" in Activity Type List for employees rendering
    24 hrs work: country grouping 48(Philippines) in CAT 2
    Regards
    Ritu

    hi,
    have the client implemented plant maintenance (PM)?
    actually the the activity types are defined in PM.

  • CO substitution for sender activity type

    Is it possible to substitute the sender activity type during a KB21N activity allocation?  I attempted to do this at the line item level (callup point 1) by changing field COBL-LSTAR but the substitution was not reflected in the controlling document.  I later found note 392273 which states that this isn't possible at the line item level...  "In activity allocation (KB21, KB21N) or in the reposting of an activity allocation (KB65), the system prevents a substitution of the sender."
    Is there another way to substitute the sender activity type?
    Thanks
    Jeff

    Hi,
    For booking of time sheet through CATS, it requires mandatory fields.
    Cost center
    Activity type
    CO object(internal order, n/w or activity, WBS, SO, Cost center)
    For booking the time sheet through CATS:-
    - rates should be maintained in cost center w.r.t activity type.
    - personnel number with the responsible cost center.
    - data entry profile.
    Also whenever we are booking the time sheet, we are booking the hours against some of the activity performed in business such as project management, erection, commisioning etc. So that we can check the cost on the project related to various business activity.
    Thanks & regards,
    KK

  • Please suggest where I have to maintain activity type in employee master

    Hi,
    Goodevening to you.
    Can I maintain Activity Type to an Employee.
    My client is having Time Sheet entries through CATS and would like to have actual hours booked against projects as well as activity type.  Each activity type will have a different rate.  Please suggest where I have to maintain activity type in employee master.
    Regards,
    Rahul

    Hi,
    I have got the answer.  We can maintain activity type in 315 info type.
    Regards,
    Rahul

  • Actual activity price does not exist for cost center / activity type

    Hi,
    We are trying to upload the time sheet related data(number of hours an employee workred on a project) ect from Non SAP to SAP.
    We have used a customized program and have loaded the data from se38.
    All this HR data will be saved in CAT2
    Later we transfer the time related data into SAP FI/CO using CAT7.
    +When  tested  with a couple of employees time sheets, they got uploaded in SE38 proerly and when transfered it through CAT7 it was properly taking the hour*rate is cost and was reflecting in the respective cost element.
    For a few time sheets in SE38 we were getting an error saying that the cost center(100501)/ activity type(EAT001) does not exist for 2010.
    Hence we have taken, FY 2010, the cost centes and activity types in KP26 and have given the planned Activity as 1. No planned cost in KP06.
    We have run the price calculation forr the FY 2010.
    Then we were able to uplaod the time sheets, but when we tried to transfer the data through CAT7, it throws an error saying no activity price exist for cost center 100501/ activity type EAT001. If I ignore the warning an proceed, no amount is being calculated.
    When uploaded employee time sheets before, all the cost were getting claculated and were entering into  the respective cost elements, but now no amounts are being calculated and it is taking Zero.
    When checked the previous years data i.e, 2009 all amounts are fine, in KSII I can see the activity quantity filled with some numbers in 2009, where from are they comming? I have checked KBk6 nothing was mentioned.
    PLease assit
    Regards,
    shilpa

    Hi
    I never used CAT* though, but the error means that you need to maintain a activity price in KBK6 (Actual price)
    Regards
    Ajay M

Maybe you are looking for

  • Apple TV (1st Gen) no longer appears in iTunes 10.

    Hi there, my Apple TV (1st Gen) no longer appears in itunes 10. I have looked at as many of the forums as I can and I have followed all the advice to reset Apple TV, router and PC. No joy. I have then restored Apple TV, uninstalled and reinstalled it

  • Can a 10.5.8 bootable clone be used as a startup disk in 10.6.8

    For the very experienced users and experts. We have a mbp bootable clone with 10.5.8 and want to use this as a backup startup disk on a mba with 10.6.8.  We understand that it is generally not possible to startup a bootable clone that has a different

  • Warning message in logs..

    Hi All, How do i remove this warning from my server log???? why does this occur??? 15:28:22,687 WARN [loggerI18N] [com.arjuna.ats.internal.jta.recovery.xarecovery1] Local XARecoveryModule.xaRecovery got XA exception javax.transaction.xa.XAExcepti on,

  • BI Query with Hierarchy in VC does not get correct values

    Hello Gurus, I am building a model in VC for Performance Score card using Query as data service. I have  the following problem. When I execute query in BEx with Hierachy_node variable , it is getting correct values, but the same is getting incorrect

  • Comparing incoming file name having timestamp with system time.

    Hi, The scenario is File to FIle. i have to read the incoming file name which will be having time stamp. compare the time stamp with the system time . if the difference in time is within specified time then send the file to target location,else send