Cenvat CLEARING account in Stock transfer order

Hi
Please tell way to clear Cenavt CLEARING   account in intra company stock transfer order(Within same company code).We  will not post any MIRO against the STO.
Thanx
Mani

Hi,
1. Create a Subtransaction type for STO in the receiving plant.
2. Copy the GRPO excise transaction type and change the clearing account
3. suggest the user to enter the sub transaction type manually during excise invoice capturing (when the material is received from the other plant only).
4. If you need some validations to avoid user entry mistakes, please take the help of ABAPer and incorporate some validations while capturing excise Invoice like checking whether the PO referred is Intra company or normal. etc...
For manual clearing, approach your fellow FICO consultant.
Regards,
Girish

Similar Messages

  • Stock transfer order accounting entries

    Dear all,
    In intracompany stock transfer order(within same companycode) please let me know how account determination happens and what are the settings of account determination.

    hi,
    This process used to transfer goods between plants using Stock transport order with Delivery order. Before doing this function the Material must be maintained in both supplying and receiving plants. And in sales organization data 1 screen the delivering plant must be maintained. This process has the following stages.
    Creation of stock transport order (STO) at receiving plant (T code u2013 ME21N)
    Transfer posting of Material to Material (T Code MB1B)
    Creation of Replenishment order (Outbound delivery order) at Supplying plant with reference to the Stock transport order(STO) (T code u2013 VL10B)
    Changing of the Replenishment order delivery .i.e. Goods issue at supplying plant (T code u2013 VL02N)
    Goods Receipt at receiving plant (T Code MIGO)
    SOURCE : SOME OTHER WEB SITE
    please check the above
    balajia

  • Stock transfer order invoice accounting entries

    Hi,
    In stock transfer order  billing  we need to show the accounting document in which the receiving plant is debited  towards the stock transfer price and supplying plant is credited  .to achive this what setting is required to be done and where.
    Regards,,
    Rohit

    hi,
    This process used to transfer goods between plants using Stock transport order with Delivery order. Before doing this function the Material must be maintained in both supplying and receiving plants. And in sales organization data 1 screen the delivering plant must be maintained. This process has the following stages.
    Creation of stock transport order (STO) at receiving plant (T code u2013 ME21N)
    Transfer posting of Material to Material (T Code MB1B)
    Creation of Replenishment order (Outbound delivery order) at Supplying plant with reference to the Stock transport order(STO) (T code u2013 VL10B)
    Changing of the Replenishment order delivery .i.e. Goods issue at supplying plant (T code u2013 VL02N)
    Goods Receipt at receiving plant (T Code MIGO)
    SOURCE : SOME OTHER WEB SITE
    please check the above
    balajia

  • Stock transfer orders

    Hi Experts,
    Can i know what is stock tranfer order?
    how to create stock transfer oreders.

    Dear Raghavendra,
    Whenever you need to transfer the materials from one plant to another plant belonging to one company or belonging to two company code stock transfer order is raised by the delivering company.
    STO:
    Transfer of goods from one location to another location,it may be between plants within the same company code or in different company code's plants.
    within the company code, bet plants, receiving plant will raise the STO in Supplying/issuing plant-ME21n,
    Supplying plant will deliver the goods to receiving plants , then we need to pick n post the Goods Issue-VL02n, nw when we can observe that the STO qty will be added into receiving plant and reduced in Delievering plant.
    To do this, we need do prior customizatin in SPRO-IMG,-material should be created in both plants( receiving & Supplying)
    -maintaing the stock only in supplying plant
    -create a dummy customer in supplying plant's sales area(if u have one sales area, create in tat comp code n sales area)
    -Assign this customer number to receiving plant's details along with the sales area,
    -Assign the STO doc type(UB) to Supplying plant, along with checking rule
    -Assign the Del type (NL/NLCC) to Supplying n receiving plant.
    You create a STO from MM route i.e., ME21N and then enter the details of the supplying,receiving plant and the materials.Once you complete the STO,then it goes for a delivery followed by an intercompany invoice.
    Remember that the Material should be there in BOTH supplying and receving plant.
    Internal Procurement (Stock Transfer With Delivery):
    In a company, goods movements do not only occur in the form of goods receipts and goods issues. Depending on the organization of the company (for example, decentralized storage) and its sales policy, internal stock transfers might also be necessary.
    The stock transfer with delivery is a plant to plant scenario. You are posting a goods issue in plant BP02 and a goods receipt in plant BP01.
    This type of stock transfer can only be carried out from unrestricted-use stock of the issuing plant to unrestricted-use stock of the receiving plant.
    You post the placement into storage at the receiving plant in a second step. Only then is the event completed and the transferred quantity part of unrestricted-use stock.
    Functions:
    Creating a Planned Independent Requirement
    Creating a stock transport order in plant BP01
    Generating a delivery in plant BP02
    Picking of the material and posting the goods issue in the delivering plant
    Posting the goods receipt in the receiving plant
    Note: The quantity posted from stock is first of all managed as stock in transit of the receiving plant. Only once the goods receipt has been posted is the quantity posted to the unrestricted-use stock of the receiving plant. This enables the quantity "on the road" to be monitored.
    The transfer posting is valuated at the valuation price of the material in the issuing plant.
    Delivery costs can be entered in the stock transport order.
    Internal Procurement (Stock Transfer without Delivery):
    The cross-plant, internal procurement of materials can be carried out within one company code (intercompany) or by using several company codes (cross company). This process can be dealt with using standard functions such as material requirements planning, purchase requisition, stock transport order, transportation planning and the handling of internal deliveries.
    The following functions are provided to support the Internal Stock Transfer without Delivery:
    Create Stock Transport Order
    Post goods issue for stock transport order
    Post goods receipt for stock transport order
    Note: Quantity "on the road" can be monitored
    Delivery costs can be entered in the stock transport order
    Internal Procurement (Cross-Company Stock Transfer):
    You post a stock transfer from company code to company code the same way as you post a stock transfer from plant to plant, except that both plants belong to different company codes.
    During the stock transfer, two accounting documents are created in addition to the material document:
    -An accounting document for the removal from storage at the issuing company code
    -An accounting document for the placement into storage at the receiving company code
    The stock posting is offset against a company code clearing account.
    To display the value of the cross-company-code stock in transit with a report, choose Environment à Stock à Stock in transit Cc.
    The following functions are provided to support the cross company stock transfer:
    Create sales order to customer
    Run single-level MRP
    Creating a purchase order
    Creating delivery
    Picking and post goods issue
    Posting goods receipt
    Create inter-company billing document
    Invoice receipt
    Create delivery, picking and post goods issue to customer
    Billing
    Notes: The issuing plant enters a delivery for the stock transport order and a billing document. This is an inter-company billing document (billing type YBIV). Pricing takes place as normal.
    When the goods arrive, the receiving plant posts a goods receipt for the purchase order. The unrestricted-use stock increases and an accounting document is created.
    The invoice is checked with reference to the purchase order.
    Stock transport order processing in receiving plant
    Delivery processing in supplying plant Picking batch determination in delivery Goods issue processing in the supplying plant Billing processing in supplying plant
    Goods receipt processing in receiving plant Invoice verification processing in receiving plant Purchase order monitor processing in receiving plant
    Stock Transport Order:
    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b911d43ad11d189410000e829fbbd/content.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b917843ad11d189410000e829fbbd/content.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/4d/2b918543ad11d189410000e829fbbd/content.htm
    Regards,
    Naveen.

  • Open Qty is not copied in Delivery for Stock Transfer Order

    Hi,
    In the Stock Transfer Order process, Once the STO Order is created, I am creating delivery in the transaction VL10B or VL10G.
    When I am clicking the background button Delivery gets generated. Then when i am going in the transaction VL02N and increasing the delivery Quantity which is more than STO order quantity, the system is accepting it. But i want the system to throw an error message if the delivery quantity is more than the order qauntity. For this I have made the following settings.
    In the Transaction Code 0VLP, i have selected B in Check Over Delivery field. But still it is not throwing an error.
    The reason for the same may be, the system is not copying the Open Delivery Qty from the STO Order (Which normally happens in Sale Order to Delivery process, bcos of Copy Control). This field has 0 value. So the system is not able check for over delivery.
    If I get this value in the delivery then it should be working fine and the sytem will throw an error for over delivery.
    Can you please suggest me a way to get this open qty value in delivery for STO order or suggest me some other option to check for over delivery in STO.
    Regards
    Vijay

    Dear Friend,
    If I can understand you clearly.
    to achieve your task the best way you can sit with your abaper and configure a routine and assign the same to T-code OVLK delivery type customizing :
    In the Item requirement : Generally it is 202
    reward points if helpful,
    regards,
    Amlan

  • Proforma invoice not created for stock transfer order

    Hi Experts
    while creating a proforma invoice for stock transfer order between the plants we are not able to create proforma invoice , the process is replenishment delivery is created and Wm is also done and the billing with reference to delivery and the item category is relevant for billing with value J, and below is the message i get whilw creating invoice
         Technical data
             Tech. data details
              Client                                
              Group Number
              Sales Document Number                
              Item Number of the SD Document         000010
              Schedule Line Number                   0001
              Counter in Control Tables              00
              Message Identification                 00
              System Message Number                  001
              Output Type                            E
              Message Variable 01
              Message Variable 02
              Message Variable 03
              Message Variable 04
              Group Type                             F
    No biliing documents generated
    Please suggest.
    Thanks

    This explanation is not in detail and hence I am not clear about your configuration settings. 
    First go to IMG Logistics-General => Tax on Goods Movements => India => Business Transactions => Outgoing Excise Invoices => Assign Billing Types to Delivery Types.
    There ensure that you have assigned the billing type JEX (assuming that you are using the standard) to your delivery type NL.
    Perhaps, you can also try with "D" for your item category in Billing Relevance field but I am not sure this will solve your issue.  Try in development client.
    thanks
    G. Lakshmipathi

  • STO Stock Transfer Order with HU (Handling Units) - Error Hugeneral 319

    Hello,
    We implemented a Stock Transfer Order process with the following details:
    MM side
    - PO is type NB, supplier is F_8001;
    - In table T001W, supplier F_8001 is assigned to plant 80GP;
    - WERKS = 40TV and LGORT = 41P in all PO items;
    - In each item, the shipping tab is filled with NLCC as delivery type and customer C_4000 (this customer corresponds to plant 40TV in table T001W). The sales area is also defined as the sales area to be used in the sales order that will be created in plant 80GP;
    SD side
    - Sales order is created automatically for customer C_4000;
    - In plant 80GP we have a HU managed stloc (32P). In this stloc we have a HU with the exact contents of the sales order. This HU has X in the HU storage loc field;
    - We created the outbound delivery and chose our HU. From this moment the HU storage loc field changed to D and the HU was assigned to the delivery;
    Now for the problem:
    When we click Post Goods Issue button, we get the following error for each item:
    HUGENERAL 319 - HU item contains different data than the stock posting
    The HU contents are exactly what we need to ship, so we do not understand this error. We need this HU to be transfered to stloc 41P in plant 40TV (this stloc is also HU managed). Any clues?
    Thanks in advance,
    Joã

    Hi,
    Have you checked your HU material and material to packed both having stock in Inventory.
    Even check the table HUMSEG is correctly updated or not.
    check this table correctly Hu assignd to you material and created materil document or not.
    check for for material master clearly for both material like plant, storage location, batch etc..
    Ask your MM consultant to check all entry is correct in material master and delivery or not.
    Regards
    Karthik.

  • Stock Transfer Order two step process

    Hi!
    we are following stock transfer order in two step process along with WM
    we are using movement types 641 & 101.
    Now our client rerquiement is : when goods issue is posting in supply plant ( movement type 641), the accounting entry should be Goods in Transit A/C dr TO Stock Account Cr.
    when goods receipt is posting in receiving plant the accounting entry should be : Stock Account a/c dr to Goods in Transit A/C, if there are price differences it will be posted to price difference accounts ( both have price control "S").
    how can we acheive this.
    Now only at the time of 641 or 101 we posting the accounting document as: Stock A/C dr ( receiving plant) to Stock A/C Cr ( issuing plant) and price difference.
    regs,
    ramesh

    we can a report in MB5T, but there you cannot find value of the stock, only quantity of stock, as in STO, there will not be any price, that is the problem.
    regs,
    ramesh

  • Planning Strategies 10 and 40 with Stock Transfer Orders for consuming PIRs

    Hello,
    I have the following situation in a Client:
    One Production Plant (1000)
    There exist various Plants  to sell products.
    The production Plan (PIRs) I create in Plant 1000 (MD61). Monthly buckets.
    The planiing strategy I want to use is 40  or maybe 10 (both to Stock).
    Consumption of the materials in plant 1000 is via:
    1. Stock transfer orders to other plants (with Shipping funcionality)   (about 80% of the shipping form plant 1000)
    2. Sales Ordes with shipping   (10%)
    3. Transfer postings from one plant to another (303 - 305 movement type) (10%)
    How can I make sure that all these outgoing movements from plant 1000 do consume my forecast? Is this standard funcionality.
    Thanks for any reply,
    Aart

    Hello Mario,
    Thanks for your answer. I looked at the note but Im not sure it does apply in our situation.
    Let me explain our situation maybe more clearly:
    I want to create a monthly Forecast (MD61) with PIRs for Production Plant 1000. (Planining strategy 10)
    The stock created in plant 1000, on the basis of this forecast is consumed during the month by:
    1. Stock Transfer Orders (from plant 1000 to plant X) - (for 95%)
    2. Sales orders (directly) (5%)
    The STOs should not be on top of the PIR but should be part of the PIR.
    For your information, the stock which is moved from plant 1000 to plant X via STOs, is sold at plant X (not directly at plant 1000).
    this stock sold monthly at plant X however, is considered withing the forecast!
    I hope this clarifies  our situation a bit more.
    Thanks for any anwer,
    Bye
    Aart

  • Sp.Procurement  key  40 stock transfer order.

    Hi Friends,
    I am facing typical probelm in post go live stage of the project .
    Scenario : 2 plants say 'A ' & 'B'  both are producing product 'x'. this product contains dependent componenets 'y' it is onle produced in plant A.
    Hence sp.procurement key 40 (stock transfer order) is maintained in plant B for component y .
    MRP  runs monthly once.
    Storage location stock excluded from MRP run
    Pur req cretaed in in nplant B and planned order in palnt A.
    Pur req converted in to  number Purchase orders (PO items) partialy.daily arround 20 Purchase orders are created,
    Now th problem is while carring out MRP  run for next month system considers the open PO items while caluclating requiremnt of y
    My requirement is that system should not consider open  PO , it should give gross requiremnt of Y depending upon PIR ;s of x.
    Stratgey 11 is mainatined for x in both plants
    Regards
    Sandeep

    Hi
    You have to run total planning & configure scope of planning.
    accordingly run MRP not for single plant.
    Further please follow the following link which is self explanatory.
    http://help.sap.com/erp2005_ehp_02/helpdata/en/f4/7d3f9344af11d182b40000e829fbfe/frameset.htm
    In the above link it is clearly explained as to what procure ment types to be maintained.
    Pl. follow the same.
    Also run MRP for scope of planning.
    Regards
    YMREDDY

  • Stock transfer order excise

    Dear Experts,
    Can i know wt are the special things comes in stock transfer order excise  compare to domestic excise process?
    i know abt domestic excise invoice process.. pls let me knoe the process of stock transfer order-for excise --
    Regards
    ishikesh

    Do the following steps for STO Customizing:-
    1. Create a customer master record for the issuing plant.
    2. Create a vendor master record for the issuing plant, and enter customer account number in the Customer field on the Control screen.
    3. Repeat steps 1 and 2 for the receiving plant.
    4. Assign the plants to the customer master record in Customizing for Materials Management (MM), by choosing Purchasing <Purchase Order < Set Up Stock Transport Order< Plants.
    The Process Flow would be as follows :-
    Create a stock transport order, following the standard procedure, and send the order to the issuing plant.
    Issuing plant has processes your order, and when it is ready to ship,the storeperson at the issuing plant issues the goods using a transfer posting. The excise clerk there creates an excise invoice.The excise supervisor verifies and posts the excise invoice.It then sends the goods to you, together with the excise invoice.
    Once the goods arrive, you follow the standard procedure for incoming excise invoices:
    The excise clerk captures the excise invoice, using the stock transport order as the reference document. The storeperson enters the goods receipt, again using the stock transport order as the reference document.Alternatively, you can first enter the goods receipt and then capture the excise invoice.
    The excise supervisor then posts the excise invoice.
    Best Regards,
    Ankur

  • Stock Transfer Order Scenario

    Dear Gurus
    This is regarding Stock Transfer Order.
    I am transfering the Stock from One Plant to Another in Same Co Code.
    MAterial-1 Which is Processed in Plant-1 and is sent to Plant-2.
    After Processing and sending it to Plant-2.
    My Client wants that in Plant-1 80 % Profit should be shown and in Plant-2 after Processing 20% Profit in accounting documents should be shown on the final delivery of the Material.
    For Eg: Material-1 is Manufactured in Plant-1 and packing is done in Plant-2
    Manuf Cost in Plant-1 is 80 Rs and Packing Cost is Rs-20 ,Profit in Plant-1 should be 80% and Profit in Plant-2 should be 20%.
    Please Guide us how it can be done.
    Regards
    Shailesh

    Hi Shilesh,
    Are you doing costing for the material? If so i believe the profits can be distributed when u do the costing run. Pls check with finance team as well.
    If you want to do pricing config for stock tranport order, you can copy the std pric proc (RM2000) and modify as per requirement.
    Cheers
    Arun.

  • Credit management in stock transfer order

    Hi experts,
    For export billing scierio
    we are doing stock transfer order from our main plant to ship yard( dock plant) with excise invoice , and doing final invoice in SD when actual shipment is made from dock yard.
    Our requirment is to have a credit mangement check when material is getting transfered from main plant to dockyard through Stock transfer order ( UB) . Can any one help me regarding this.
    Regards,
    KC Choudhury

    Hello KC Choudhary,
    I have seen that your business process consists on a Purchase Order and a Delivery but with no Sales Order (VA01). Unfortunately I regret to tell you that in the standard it is mandatory to have a sales order if you want to perform a
    correct credit check in the delivery. There are several data needed from the sales order which are not available in the delivery. All the data for the delivery should come from the sales order (like the payer -> credit account). If there is no sales order, these data is not available and therefore no credit check can be performed. A credit check in delivery without related sales order is not possible in the standard system. There is no userexit availabe to achieve this functionality either.
    Regards,
    Raghavendra YN

  • Stock Transfer Order Between plants

    Hello Everybody,
    Can someone tell me the steps and configuration involved in STO between 2 plants?
    Please help me .
    Thanks,
    Sneha.
    Please dont post basic and repeated questions.  Do search in the forum
    Edited by: Lakshmipathi on Feb 26, 2009 2:23 PM

    Hi Read this fully and configure accordinngly
    Configure Inter company Stock Transport Order
    Material should exist in both the plants (Delivering & Ordering),
    Internal customer should be assigned to the ordering plant ( MM -> Purchasing -> Purchase Order -> Setup stock transport order -> assign the internal customer to the ordering plant and assign the Sales area of the internal customer.
    Assign its Sales area to the delivering plant
    Assign the document type and Delivery type NB and NLCC
    Assign the Supplying plant --> Receiving Plant --> NB
    Take the delivering plant and assign the sales area.
    Vendor master has to be created and assign the supply source (Delivering Plant).
    Create a purchase order ME21N ---> Save
    Delivery VL10 G ---> Calculation rule (appropriate) --> Assign the purchase order number here and execute.
    Select the Delivery creation line and do the back ground process.
    Start the log display and see the delivery document number by the documents button
    Goto VL02N --> do picking and PGI --> Then do the MIGO with respect to the delivery document.
    Billing (Intercompany pricing conditions should be set).
    AND
    1. Customer No. for the Goods Receiving Plant - OMGN
    2. Availability Check- Checking Rule (if necessary) - OMGN
    3. Assign a Delivery Type for the Delivering Plant - OMGN (for Stock Transport Orders, NLCC)
    4. PO type (which i believe you have done) - OMGN
    5. Assign Vendor No. to the Supplying Plant (done) - VK02
    6. Assign Customer No. to the Purchasing Plant for the Inter-Company Invoice (but you need to assign this to the Sales Organization pre-assigned to the Purchasing Plant),
    IMG-SD-Billing-Inter Company Billing-Define Internal Customer No. by Sales Org
    ***and by the way for the Invoice to work between Cross-Company Plants, you need also to have a Sales Org for the Supplying Plant and a Pricing Determination Procedure
    INTERCOMPANY PRICING:
    PI01 Inter company: fixed amount per material unit
    PI02 Inter company: percentage of the net invoice amount
    These condition types specify that the price charged by the delivering plant to the sales organization is shown as a statistical value in the sales order and an effective charge in the internal invoice.
    The condition records you create and maintain for inter company billing are the same kind of records that you create for pricing in general.
    IV01 Inter-company Price ERLOS Revenue
    IV02 Inter-company % ERLOS Revenue
    STO:
    STO CONFIG:
    The following steps have to be followed in order to configure stock transport order between two plants.
    1. Create a vendor for the Company code of the receiving plant using account group 0007 via T-Code XK01.
    2. In the purchasing data view assign the supplying plant and the schema group
    3. Create customer with the sales area of the vendor.
    4. The shipping conditions, the delivering plant and the transportation zone determine the route in the STO.
    5. In the pricing procedure determination relevant to the STO assign document pricing procedure and customer pricing procedure to get the pricing in the invoice.
    6. Maintain condition records for pricing condition.
    7. Maintain carrier as a partner in the customer master.
    8. In OMGN select the supplying plant and assign the company code and sales area. Similarly select the receiving plant and assign the company code and sales area (The company code to which the plant is assigned to).
    9. Assign the delivery type and checking rule to the document type.
    10. And finally, assign the purchasing document type to the supplying plant and the receiving plant.
    11. Create the STO using T-Code ME 21N and save.
    12. Check for release strategy if any and release using T-Code ME 28.
    13. Create delivery in background using VL10G.
    14. If delivery is created, it is an indication of correct configuration and master data creation.
    Stock transfer between two plants in different company codes is known as inter company stock transfer.
    Material shoud be maintained in both supplying and receiving plant MM01
    Sotck should maintain only in supplying plant MB1C
    Create receving plant as a customer in suplying plants company code and sales area XD01
    Assign this customer number in receving plant detials OMGN
    Assign supplying sales area in supplying plant details OMGN
    Assign delivery tupe NB for in combination of supplying/ receving plants.
    Create STO ME21N
    As it is normal there in the item details wer should get shipping date i.e customer number
    Go for Delivery VL10B
    Shipping point *****
    Select PO go for execute
    then select the delivery then go for delvy ............create delvy,,,, delvy nubmer generated.
    Goods Issue VL02
    Delvy doc **********
    Click on picking
    enter the picking qty
    Click on PGI
    in the mean time check in the PO history you will get the details
    Goods receipt MIGO
    Stock overview the stock will be updated....
    P.O Order types and Delivery Types
    STO: - Stock Transfer Order
    Stock Transfer between Two Plants with One Company code.
    The Purchase Order Type is Used in this case is "UB",
    And the Delivery Type Used here is "NL"
    STPO:- Stock Transfer Purchase Order
    Stock Transfer Purchase Orders Between Two Plants with Two Different Company Codes.
    The Purchase Order Type is Used in this case is "NB",
    And the Delivery Type Used here is "NLCC".
    INTRA COMPANY STO.
    1. There should be two plants in the given company code for intra STO to
    happen.
    2. Assign Purchasing org of the ordering to the supplying plant.
    3. Create a customer in the supplying sales area.
    4. Assign the customer to the ordering sales area.
    5. IMG > MM > Purchasing > PO > Setup STO > Define shipping data for plants
    here go to supplying plant and mention its own sales area.
    6. In the ordering plant assign the customer created in the supplying sales area
    and also the supplying sales area.
    7. Maintain checking rule as 01.
    8. Assign the delivery type NL supplying plant checking rule and PO Doc type
    UB.
    9. Assign document type UB supplying plant and ordering plant then decide up
    on either 1 step or 2 steps.
    10. Create PO with doc type UB.
    11. Go to VL10B give the PO No. and enter, select the line item and click back
    ground. (Where Del. Will be created in the back ground)
    12. Go to VL02N for picking and PGI.
    13. If 1 step no need of doing MIGO else for 2 steps do MIGO.

  • Stock Transfer order & PIR

    I am using strategy 10 and sales order is consuming PIR but stock transfer order is not consuming PIR.
    Do I need to maintain any settings in customization.
    thnks
    SD

    Dear ,
    Why STO should consume PIR when you are using Stratgey 10 ?
    However, PIR is still at planning level. STO is stock transfer after finishin the production.
    The only way to consume PIR by stock transfer is maintain minimum stock levels in warehouse and do the gross requirments planning. However, the STO is not directly consumed.
    Basically , it is nothing but your requirement  and depends on the stratgey you defined in MRP3.
    Consuming the PIR, it is fully depends on strategy what you have used in material master of FERT.
    If used 40, sale order will consume PIR.
    For 10, when goods delivery PIR will erase.
    For 11, when goods receipt.
    For 20 , no PIR.
    For Stock transport purpose we are not creating any PIR.
    Hope this is clear
    regards