How do i change a standard hierarchy for profit centers which is already assigned in 0kE5.
Currently there are no transaction data in the system.However the profit centers are already assigned to the standard hierarchy ABC.
We now want to change the standard hierarchy to DEF.
Is this possible?
Thanks & Regards,
Rajeshwari

Hello Murali,
Thanks for the Quick reply.
We  did try using the transaction KCH4 and delete the profit centers/profit center groups assigned to it.
However we get the following message for the same:
This function is not allowed in the standard hierarchy
Message no. OH 040
Diagnosis
You are directly processing the standard hierarchy (cost centers, business processes). The following actions are invalid for individual values:
Inserting groups that already contain values
Removing/deleting groups that already contain values
You are processing the profit center standard hierarchy or any other alternative hierarchies that contain parts of the standard hierarchy. The following actions are then invalid for individual values:
Delete
Insert
Reassign (delete and insert)
Removing groups that already contain values
Inserting groups that already contain values
Procedure
Undo the change you wanted to make.
Hence we are unable to even remove the profit center groups within the group ABC.
Is there any other way?
Thanks & regards,
Rajeshwari

Similar Messages

  • How to make changes to profit center standard hierarchy?

    Hello!
    I have to make changes in standard profit center hierarchy. Should I make the changes in IMG or Sap Easy access -screen? If I make changes in IMG, could you please tell me the right path where can I find it?
    Another question, if some profit center is in the wrong place in stardard hierarchy and I want to transfer it to another place (under other node for example), how is this done? Should I delete this profit center first (I tried delete but it wasn't possible..) or can I just transfer the profit center?
    Thanks!
    Points will be given!=)

    Hi,
    in the IMG you can maintain the profit center standard hierarchy via TA KCH4. The path is:
    -> Controlling
    -> Profit Center Accounting
       -> Master Data
        -> Maintain Standard Hierarchy
    The transport of the profit center standard hierarchy is done via TA 0KEQ,  (this is relevant for both KCH5N and KCH4).
    IMG Path:
    -> Controlling
    -> Profit Center Accounting
      -> Tools
       -> Transport Customizing Settings
    Hope I understood you correctly.
    Regards
    Karl

  • Profit Center Standard Hierarchy  in Production Server

    Dear All
    I have done Controlling Area Settings for Profit Centers via TCode: 0KE5. I have made Profit Center Standard Hierarchy in Development server. The same Standard hierarchy is available in Quality sever but it is unavaliable in Production server.
    Please guide me.
    Thanks & Regards
    Kanwaljit

    Hi,
    You should check if the transport with the relevant configuration has passed to Produciton. Anyway, you can create new one via 0KEQ transaction.
    Regards,
    Eli

  • Profit center Standard Hierarchy

    Hello Gurus
    I  Defined  the Profit center group in KCH1 but i can not able to Define the standard hierarchy in KCH4  when i was define the standard hierarchy  while system shows some message
    This function is not allowed in the standard hierarchy
    Message no. OH040
    can anybody give the Valuable inputs my issue my client year ending process is going on
    Regards
    venkat

    Hi,
    Via KCH1 you create alternative profit centre groups. If you want to define standard hierarchy, you have to create it in KCH4 (or 0KE5).
    Regards,
    Eli

  • How to read profit center standard hierarchy Remote

    Dear all,
    Could anybody please tell me how to read the standard hierachy of profit centers
    using RFC module(s) for a certain controlling area?
    I found lots of classes and modules in the standard dialogs but nothing remote enabled :-(.
    Thanks in advance,
    Marcel

    Hi Marcel,
    It's due to the order of appearance; let's say you have the following:
    Group1
    Group11
    Group111
    Group112
    Group12
    Then, the table will show
    Group1 0
    Group11 1
    Group111 2
    Group112 2
    Group12 1
    So, the connection is defined: you know that Group 111 is assigned to Group11, because it's level is 2 and the first group above it with level 1 is Group11. The same is with values by the order of appearance as you know for each group the quantity of the values.
    Regards,
    Eli

  • What is the T-Code for creating Cost center - profit center standard hierar

    Hi,
    What is the T-Code for creating Cost center - profit center standard hierarchy.Please provide me the T-codes.
    Thanks

    Hi Supriya,
    Create / Change Cost Center Standard Hierarchy - OKEON
    Display Cost Center Standard Hierarchy - OKENN
    Create Profit Center Standard Hierarchy - KCH1
    Change Profit Center Standard Hierarchy - KCH5N
    Display Profit Center Standard Hierarchy - KCH6N
    Srikanth Munnaluri

  • Function module to find the top node in the Profit Center standard hierarch

    Hi,
    Please let me know the function modules/Tables to do the following.
    1. To find the Top node in the Profit center standard hierarchy which is displayed via KCH6N Transaction.
    2. To read/retrieve standard hierarchy displayed in KCH6N Transaction.
    Thanks in Advance,
    Madhuri.

    Hi Madhuri ,
    have a look @<b>SETLEAF</b> or SET* in se11 , u can get the Top Node by putting the Logic like this
    ex: i am searching for Top Node of A3
    <b>select setname from setleaf where  valfrom eq 'A3'.</b>and for that selected setname u have to do one more
    loop.
    <b>select setname from setleaf where  valfrom eq 'A2'.</b>
    then only u will net Node A1.
    this is a sample code only , dont check F2.
    let me know if u want more inputs of Set Ids.
    regards
    prabhu
    [email protected]
    NjoySAP

  • Transport cost center standard hierarchy & profit center herarchy

    Dear All,
    Pls guide how to transport cost center standard hierarchy, cost center groups, profit center hierarchy and profit center groups from config client to production?
    Regards
    Komal

    Hi,
    For CO data go to OKE6 transaction and create a change request.
    For PCA, go to 0KEQ and do the same.
    Regards,
    Eli

  • Using BADI for changing the Profit Center in FI Document during MIRO

    Hi,
    We have an requirement of changing the profit center in FI/CO Document while doing MIRO which is different than the one which is posted at the time MIGO.The system is not allowing us to do this and the field profit center during MIRO is not changeble mode and the business requirement is to change this through any SAP enhancements or program.
    How can I do this ?
    Is there is any standard BADI or User Exit is available for this.
    Pleease help me in this and will give valuable points.

    Hey,
    Use the BADI INVOICE_UPDATE and try with this. Otherwise you try to create Enhancement point to implement your code.
    Note: Inside BADI we can't change the runtime value. So, try to use enhancement point.
    Rewert back for any clarification.
    Regards,
    Saravanan M

  • Changing of profit center group assigned to one profit center

    Hi,
    Profit Center Group "SMBA-CIN" was erroneously assigned to Profit center PSC021100. I tried to change the profit center group and assigned "SMBA-MALL via Tcode KE52".  After that, I viewed the profit center hierarchy, and found out that PSC021100 now exists in the 2 profit center groups.
    Why is it that PSC021100 exists in the 2 profit center groups?  How can I correct this? Said profit center should exist in SMBA-MALL only.
    Thank you very much for the help.

    Hi,
    Here's the result.
    Ambiguity check for group SMBA SM City Batangas (SMBA) 20090513
    Groups which occur more than once:
    Set Name                 Description
    Path for Set             Description                                   Level
      List contains no data
    Values occuring more than once:
    Overlapping Area                Set Name                 Asl  Asl   Description
      PSC021100 - PSC021100  SMBA-CIN                 001        SMBA-Cinema
      PSC021100 - PSC021100  SMBA-MALL              001        SMBA-Mall
      PSC021200 - PSC021200  SMBA-CIN                 005        SMBA-Cinema
      PSC021200 - PSC021200  SMBA-MALL              002        SMBA-Mall

  • Change in Profit center of Material Document

    Dear SAP
    I have made a outbond delivery with movement 601 and corresponding material document is being created with accounting entries. but here profit center got wrong and when I am changing profit center through SAP Edit (Changed in MSEG,LIKP,BSEG).
    But the the MIGO Display and MB5B report are showing the earlier profit center.
    How and where we can change the profit center so that it gets corrected

    Hello
    As per standards, you can't change account assignment for a document after you have posted the material document. It is advised to reverse the material document and then do the neccessary corrections in the preceeding documents and then post the material document again. So, even though you have changed same may not help.
    If you still want further information, consult FICO consultant on this.
    Thanks & Regards
    JP

  • How to manage change of profit center in Material master?

    The material master of a number of materials were populated with wrong profit center. Transactions were also posted for a few years. Now we want to change the profit centers for some of the materials. These materials have inventory balances and is set for on line transfer to PCA. If we run 1KEH data is duplicated.
    What is the best way to manage this change?

    Hi Mr.Sanjay,
    Good Morning to you,
    Regarding your thread the best and easy way to change the profit center is goto MM02 and give the material code and enter and goto Sales: General/plant and in down you can see the Profit Center XXXXX now you change it to YYYYY and save it. So, from now onwards what ever the postings you do the system will show the values in YYYYY - Profit center.
    Hope you can solve your thread & for further clarrification feel free to ask me.
    Best Regards,
    SAPUK.

  • How to change the Profit Center in Sales Order

    Hi Gurus,
    Previously they setted the profit center (YB999) in sales order, now i want to change the profit center and need to give the amount into this profit center 100500.
    So, could you guide me how to change the profit center in sales order.
    Thank you for your replies.....
    Thanks & Regards,
    Chandrababu.B
    Edited by: Chandrababu Naidu on May 25, 2011 12:44 PM

    Hi
    If this SO is processed partially - i.e. transactions happened - You cant change it
    You can use ABAP and change it in Debug mode, but not advisable... Better to short close the SO and open a new SO for Balance qty
    br, Ajay M
    Edited by: Ajay Maheshwari on May 25, 2011 5:10 PM

  • Change the Profit Center in Sales Order line item's Account assignment tab

    Hi Gurus,
    I need to change the Profit Center at Sales order Line item in Account Assignment Tab. Currently  The Profit center is coming from Material Master for the Line Item's Material as default but I have to change / overwrite  that.
    Can any body provide me how can i achive that means
    Any User exits, substitution or any thing ?
    I tried MV45AFZZ but i am not able to find out the right place where I can change COBL-PRCTR.
    Sony

    Hi
    There is perform which moves the values to VBAP field.
    This PRCTR field is stored in VBAP (i.e., SO line item table)
    USEREXIT_MOVE_FIELD_TO_VBAP
    Hope it works.
    VVR

  • Profit center wise hierarchy

    hiiiii...
    by which t.code we can see the profit center wise hierarchy?
    Thanks & Regards
    Rekha Sharma

    HI
    KCH6N