Change delivery date in schedule line
High gurus,
I need some help. How is it possible to change the delivery date in a schedule line generate by APO ?
Thanks.
Hi Thanks for your reply.
But the Tcode that you have mentioned appears to be in the SCM system and it calls an External Procurement Relationships report. My requirement is as follows:
I have a date generated based on the Route Schedule id (VL51, VL52) and I need to sync this date with the Goods issue date of the Sales Order created. So whenever a sales order is created with the schedule line dates, i need to modify the dates generated by the system with my dates like I will have to call a FM or a BAPI by passing the new GI date and get the new set of dates and populate them on the Sales Order schedule lines screen.
This scenario will happen for a GATP (Global Available to Promise) where by the ECC system does a remote call to the APO system to get the new dates. I will have to modify these dates with a new set of dates created either using a FM or a BAPI and populate them again on to the screen
Thanks,
Susanth Kumar
Similar Messages
-
Changing delivey dates on schedule line level in Purchase order in IS AFS
Hi,
I want to know if there is any standard transaction or enhancements to change the delivery dates in purchase order on schedule line level in IS AFS scenario on mass.
Thanks,
KumarHi Antony,
Thanks for the reply.But the transaction MASS is not enhanced for changing delivery dates in schedule line level in IS AFS.
Thanks,
Kumar -
Delivery dates in schedule lines is not changing in sales order
Dear all,
delivery dates in schedule lines on line item in sales order is not changing.delivery dates are different in schedule line of partial qtys.i have to do same delivery date on all schedule lines.
Regards,
PraveenHi Praveen
1. Schedule Line dates can be changed manually or by doing an availability check only.
2. In case if you change the delivery date in the header it will not change automatically in the line item level.
3. You need to do it manually only.
kindly let me know more details.
reg
dsk -
Issue with delivery date in schedule line ??
Dear Members,
I have created a sales order on 05/18/2009.I am getting delv date on schedule line as 06/12/2009, due to this problem, I am unable to create a delv. What should I do now ?/
I have checked the availbility of material and material is available on 05/18/2009.
Also Checked on config of order type in V0V8 T-code, and lead time in not maintained.
please let me know, where should I check.
Thank you.
Madhuhello, friend.
on the schedule lines tab, try changing the date to the present and see if delivery can be confirmed. another way is to run the "check item availability" functionality in the sales order.
on the document header, check what date is being proposed for "Requested Delivery Date". this date could be proposed based on settings for the document type. but since you indicated that there was no lead time maintained, you will have to check lead times in:
1. the shipping point (deliveries processing, picking, packing, etc.)
2. in the MRP views of the material master
3. transportation lead times (routes, etc.)
4. if externally procured, purchasing lead times
hope this helped you.
regards. -
How to compare delivery date in schedule lines and PGI in outbound delivery
Hi,
I want to create a report to monitor and compare different dates in sales and delivery process.
One of my key figure is the comparison between date confirmed to the customer, that I can find in the schedule line of the sales order, and the actual goods issue date from the outbound delivery.
But I can't succeed in making the link between delivery and schedule lines, means between LIKP and VBEP.
Would you have any idea?
Thank you.It seems there's no exact (table) connection / link between delivery item and schedule line item.
Those who were searching for this thing (link / connection between delivery item and schedule line) were recommended to use FM "RV_SCHEDULE_CHECK_DELIVERIES".
This FM calculates the delivered quantity for each schedule line, so it makes link between the delivery item and schedule lines - however if you check the code it's quite sophisticated...
(if you put a breakpoint in the FM and display a SO in VA03, you can check how the parameters have to be populated with data).
Schedule Line and Delivery Link
Edited by: Csaba Szommer on Aug 5, 2011 12:03 AM -
Default category of delivery date in schedule lines
Hi,
When i enter transaction ME38, select an item and click on delivery schedule to input schedule lines,
by default i can see 'M' in field category of delivery date.
'M' is displayed in all the records, whether a sch line exists or not.
In another system of mine, when i try to enter sch lines thru ME38, by default all records show blank in category of delivery date.
I want to change the default category of delivery date as 'D' or want to keep it blank , but not 'M'.
How can i change this???
Regards,
Sneha
Points will be awarded for helpful answers *Hi w1n,
following is the setting in my system.
EN C 5 Calendar format
EN D 1 Day format
EN K 2 Planning calender
EN M 3 MONTH FORMAT
EN P 4 Period format
EN W 2 Week Format
Still it is showing me M as default in all the lines.
M 06.2008 32 R01.06.2008
M 06.2008 24 R01.06.2008
M 06.2008 24 R01.06.2008
M
M
M
Can u pls help me out ???
Regards, -
Printing last delivery date in schedule lines for sales order
Hi!
We should create a sales order with more then one schedule line. This schedule lines are only for internal use (only to plan our production) and not for printing on the sales order paper. Only the last line is the real delivery date which should be printed on the sales order paper. Now I'm searching for a solution to print only this schedule line.
Have anyone a good idea?
Thanks
MarkusHi,
Select <required fields> from VBEP
into table <itab>
where vbeln = <order number>.
sort itab by posnr etenr descending.
read table itab into wa index 1.
contents of work area will have the last schedule line details of order.
Regards
Vinod -
Delivery Date in Schedule Line
Hi,
The issue is:
There is a 1 hour time gap between the System time & the local time.
Say the PRD system date & time is 01.01.2011 23:30 & the local date & time is 02.01.2011 00:30.
I have a scenario where there are 2 similar MTO sales orders.
Sales order 1: Create SO with date & time 01.01.2011 22:30 & the schedule line for the item gets the GI date as 01.01.2011 as expected.
Sales Order 2: Create SO with date & time as 01.01.2011 23:30, then the schedule line for the item gets the GI date as 02.01.2011.
I am not sure if the time difference could be the reason for picking up the different GI dates eventhough both the orders were created on the same day 01.01.2011.
Please let me know if i am missing something here.
thanks & regards
NarainFor shipping point or route pick pack time, load time, transit time may be maintained totally 1 hr. Hence when you create the order at 23:30 the delivery date comes to next day.
or
Shift time may be maintend.
Please check the both. -
Delivery date in scheduling lines
Hi all,
I am using FM 'SD_SALESDOCUMENT_CHANGE' and passing all the desired fields, when passing fields for shceduling lines date is coming from header or somewhere else.
Please suggest me in which field i have to put entry so that scheduling lines will show my dates.
Regards,
Gaurav.Hi,
Pass the data in structure field ORDER_SCHEDULES_IN-REQ_DATE.
Edit : Also pass 'X' into structure field ORDER_SCHEDULES_INX-REQ_DATE.
Regards
Vinod
Edited by: Vinod Kumar on Jul 20, 2010 3:59 PM -
Delivery item per schedule line
Hi all,
Thank you for viewing my posting, I have the requirement as following:
I have two SD schedule agreements, there are several schedule lines on JIT delivery Scheudle tab for each schedule agreement, these two schedule agreement are for same customer, have different material.
What I want is:
When I create delivery for these two schedule agreements in VL10A, these two schedule agreements are combined into one delivery note, but the delivery item per schedule line on the delivery note.
E.g.
one schedule agreement has 5 schedule lines
the other has 4 schedule lines
After I create delivery for these two delivery notes in VL10A, there should be 9 items on delivery notes, one item per schedule line.
Do you have idea on this? I do not want to combine several schedule line into one delivery item.
Thanks!
Alex LuDear Alex,
You try these copy control settings between Scheduling agreement and delivery document.
Go to VTLA transaction select your document types
First you go header level settings here you can find the check box field called Copy item number check this then try.
If it is not full fill your requirement then go in to the item details here you can find the copying Routine maintenace field Item Data Under Data transfer Tab,this field will have 101 item Routine as per the standard,you take ABAPer help you copy this routine then change according to your requirement then assign new routine here.
I hope this will help you,
Regards,
Murali. -
Change Delivery date in Sales Order
Hi all
I want to change Request Delivery Date in Sales Order. But when I changed Request Delivery Date system appear" The default date is not copied into existing schedule lines"
And Delivery Date didn't change.Could you tell me how to change Delivery Date ?
I setup Request Delivery Date - September 21th but Availability Date is September 19th. Could you tell me how to setup loading time, picking time, packing time ?
Thank and Best regards,
ThangHi,
When you change the Request Delivery Date, it automatically changes the schedule line date of all the materials, but by default does not change the schedule line date of the ordered material.
So just check the ordered material schedule line date and change it manually in the order.
Similarly maintain the same date in all the resp fieldsi in the delivery, wherever you see the date.
Regards,
Siddharth. -
Split delivery for each schedule line
Hi,
We have a requirement to split deliveries for each schedule line in the order.
For example: I have an order with one line item which has 2 schedule lines. If the schedule line date on one is 01/29 & the other is on 01/31, and the delivery due list VL10A is run with a range 01/29 - 01/31, it picks both the schedule line & combines them into one delivery.
Is there a way by which we can force them to create 2 different deliveries (as it would if the delivery due list was run for each day at a time).
We created a data transfer routine (deliveries), and populating ZUKRL with schedule line date & that doesnt solve the problem since the routine is triggered once for each sales order line and not for schedule lines.
SAP reverted back that this is standard SAP behaviour to cumulate all due schedule lines into one delivery, but I would like to know if anyone has any other solution ?
Thanks in advance!First of all you have to use VL10E to create deliveries, since it creates one delivery item for each schedule line.
Then play with your own delivery role copied from standard profile 0201:
you can trigger 3 different flags to reach your goal:
Cumul. Rule: Rule for calculation of quantity to be delivered
There is a field that contains a cumulated quantity in delivery lists
with item or schedule line views. The quantity at which the list line
(document item or schedule line) is delivered is defined in this field
when it is selected and the delivery process is started in the
background. The value is a default and can be changed by manually
processing the delivery list on the item or schedule line level.
SplitSchedLine: Rule for creating one delivery item per schedule line
In a delivery list in item view with multiple schedule lines, you can
decide for the same document item whether you want to generate one
delivery item per schedule line or whether you want to deliver the
cumulated quantity of the last schedule lines selected.
LimitSchedLine: Allow constraints on schedule line level
You can use this indicator to limit selection o
delivery when
o Delivery due date and/or
o Planned goods issue date and/or
o Route schedule
does not fall within selection range.
This should help you to solve your problem.
pls. reward points if helpful
Regards
Roberto -
How to get the Delivery date in PO line Item in SAPScript
Hi Gurus,
I am working on PO Script (MEDRUCK). I copied the Standard to a Z form. ZMM_MEDRUCK, Now I need to print the the Header text at the end of MAIN window. I put Iem number along with the other line Item informmation like stanadrd PO Script MEDRUCK. I also want to show the delivey date with line Item, so Itried to use EKET-EINDT but it is returning the delivery date of last line item, means while printing the first line and other information it is showing the delivery date of the last line item, I tried with the PEKPO-EINDT it is also not working.
Can any body suggest me how i can get the delivery date for the respective line Item ?
Regards
Sonyactually your are picking up the correct data from Table EKET (EKET-EINDT) but your are printing that in item data loop for EKET might have already executed in your script and the header of that internal table consist the last entry of the table so for that. Fetch the delivery date explicite from the Table EKET when your in item level processing and print that.
For Example u can use this code.
To print you have write the this code in Script item level printing window "MAIN" window
Following perform is called to get the line item delivery date in PO
{/: PERFORM GET_DEL_DATE IN PROGRAM ZPerform_prog
/: USING &EKPO-EBELN&
/: USING &EKPO-EBELP&
/: CHANGING &DEL_DATE&
/: ENDPERFORM}
{* Dellivery date &DEL_DATE& }
write the below code in the Z program "ZPerform_prog"
{ FORM get_del_date TABLES in_par STRUCTURE itcsy
out_par STRUCTURE itcsy.
READ TABLE in_par WITH KEY 'EKPO-EBELN'.
CHECK sy-subrc = 0.
$_po_no = in_par-value.
READ TABLE in_par WITH KEY 'EKPO-EBELP'.
CHECK sy-subrc = 0.
$_po_line = in_par-value.
SELECT *
FROM eket UP TO 1 ROWS WHERE ebeln EQ $_po_no AND ebelp EQ $_po_line.
$_del_date = eket-eindt.
CALL FUNCTION 'CONVERT_DATE_TO_EXTERNAL'
EXPORTING
date_internal = eket-eindt
IMPORTING
date_external = $_del_date
EXCEPTIONS
date_internal_is_invalid = 1
OTHERS = 2.
READ TABLE out_par WITH KEY 'DEL_DATE'.
CHECK sy-subrc EQ 0.
out_par-value = $_del_date.
MODIFY out_par
INDEX sy-tabix.
CLEAR : $_po_no , $_po_line ,$_del_date.
ENDSELECT.
ENDFORM. "GET_DEL_DATE } -
Delivery Status at Schedule Line level.
Hi All,
I have to retrieve some data on the basis of Schedule line for which delivery is not complete. Please find below the requirement.
I am having one sales order with one line item which having two schedule line. For one schedule line confirmed qty is 1K and for other 2k. For first line item deliver qty is also 1k.
I want to know how to check the delivery status for schedule line counter so I will get the idea that for first schedule line qty is delivered and for second not.
Thanks
PiyushUse the function module
CALL FUNCTION 'RV_SCHEDULE_CHECK_DELIVERIES'
EXPORTING
fbeleg = wa_vbap-vbeln
fposnr = wa_vbap-posnr
FVERRECHNUNG = ' '
FS073_ALT = ' '
IF_NO_SORT = ' '
TABLES
fvbfa = fvbfa
fvbup = fvbup
fxvbep = it_vbepvb
FVBLB =
fvbap = fvbap
EXCEPTIONS
FEHLER_BEI_LESEN_FVBUP = 1
FEHLER_BEI_LESEN_FXVBEP = 2
OTHERS = 3
IF sy-subrc <> 0.
MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
ENDIF.
loop the internal table it_vbepvb.
get the open qty in that schedule line
MOVE wa_vbepvb-olfmng_flt TO wa_itab-openqty.
IF wa_vbepvb-bmeng EQ wa_itab-openqty.
check that with the schedule line confirmed qty wa_vbepvb-bmeng
If delivery is avaliable the open qty will not be equal to confirmed qty. -
Need to check PO Posting date at schedule line and material document level
HI All,
I am facing an issue to reconciliation data with ECC.
Issue :
we have a PO,item,schedule line with delivery date, scheduled qty and quantity received from EKET table
we have PO,item,Material document,movement type,posting date with quantity received from EKBE table
the standard extractor 2LIS_02_SGR is providing data at
PO,item,schedule line,material document,movement,posting date
as if now we are using this extractor to get the posting date at schedule line level.
can some one let me know how exacty the EKET and EKBE table are joined ???Hi,
The data for the datasource 2lis_02_sgr can be compared in ECC using ME80FN transaction.
Please check the below Link for all the details reragrding 2LIS_02_SGR datasource.
[http://help.sap.com/saphelp_dm40/helpdata/en/69/063f3f2615e07fe10000000a114084/content.htm]
Hope this helps..
Thanks,
Nagarjuna
Maybe you are looking for
-
How to make clone of active directory security group
Hi i am having one Security group in AD, i want to make copy or clone of that group with same members in different name in AD. Anybody help me out...
-
Can't load properties from file in webapp
I've got a bean that I use to read a properties file. from the JSP page, I use <%@ page import="com.buildrequest.Login" %> <jsp:useBean id="buildproperties" scope="page" class="com.buildrequest.BuildProperties" /> <jsp:setProperty name="buildproperti
-
RM887- change rem profile regarding generation of postprocessing records.
Hi, While doing MFBF (GR GI) I am getting error "change rem profile regarding generation of postprocessing records" Message No RM887. I am using same REM profile for many other materials for which MFBF is working fine. There are no COGI errors pendin
-
Styles are missing when publishing to ePub in RoboHelp 9
Good afternoon, We are developing content for Android Tablets and have learned the customary format that we used is, well, unusable. A few posts suggest that ePub is really the only way to go with Android Tablet Help. http://blogs.adobe.com/techcomm/
-
Hello When running payment engine I have the follwoing message Error code -100 (missing field) = VAT Number of Business Partner 'QMA SARL' must be defined; I believe I must inform the text field called VATREGNUM but I am not able to see this field on