Change documents for planned order

HI ,
My issue is that My client is creating planned orders manually. He is changing them if required( like quantity or dates) . Now he is asking that he require change documents relating to change he has done to the planned order. He wants to mention the reason behind the change in SAP.
Please help me to resolve this issue
Thanks in advance
vinay

Dear,
Planned order is a tempapry object...cannot have a change document for that.
Once production order is created in Std SAP planned order is deleted..what will you do with change number against the pklanned order reference...
Please advice your client to use production order if required.
If you want to have that you need to change the SAP std code
Edited by: Rajesha Vittal on Feb 8, 2008 4:16 PM

Similar Messages

  • Change document for internal orders - RKAUFTRAG

    I am trying to trigger a workflow event using change document RKAUFTRAG (internal order).  It works when I change the internal order, but not when I CREATE an internal order.  Any help?

    Hi Kenneth,
    I am facing the same problem for object class RKAUFTRAG, for creation i am not getting the data.
    please let me know the user-exit.
    it will realy helpful for me.
    with regards,
    Debdutta Dey

  • Change Documents for Sales Order (VA03)

    Hello,
    Is it possible to track changes to the text (VA03 - Header Detail - Text Tab) from a Sales Order by using change documents?
    Thanks in advance for your help,
    CL

    I don't think that is possible. These are getting stored in Longtext (ie STXH & STXL) by retrieving this also we need to use fm READ_TEXT.
    and also in change document table CDPOS fields VALUE_NEW & VALUE_OLD have length limit of 254.

  • Change document for Maintenance Order Basic Start date

    Hi Gurus,
    I want to trace the changes to MO basic start date. But the change document indicator for MO Basic start date is not enabled.
    Is there anyother option to trace the changes to MO Basic start date??
    Thanks,
    Prabhu.

    Prabhu,
    Not all fields are tracked for changes.
    In the past we have developed some functionality to add these missing fields to the change documents.
    In this case you could utilise IWO10009 (at save event) to save the change documents.
    PeteA

  • Change Document - for purchase order

    Hi all,
    when i make some changes in the purchase order(ME22N) it is stored in the table CDPOS but when i change the delivery address field this alone is not stored. what may be the reason? and how to do it?
    can anyone help me in this?
    helpfull answers will be rewarded with points..
    Thanks,
    Murali.

    Saquib,
    No, this is not directly linked to the customer or vendor master. What happens is, during PO creation the delivery address is picked up from the address of the plant, but that can be updated via both BAPI and transaction.Each time this address gets changed, SAP generates a new ADRNR and store that address in ADRC.
    This might help you in future in case you face such situation. I faced this only a few months and that's why I remeber this so clearly.
    Murali,
    Please award points and close the thread if it helped you.

  • How to create or update 'change document' for crm order

    Hi all,
       i want to create or update change document records via program . And which method could be used (FM or ...) ?
      I find there is a fm 'CRM_ORDER_WRITE_DOCUMENT' . But seems not available?
      any good idea ?
    BR.

    Hello
    You can refer to FM:CRM_ORDER_CHANGE_DOCS_CREATE. In this FM, the change documents are set.
    But I don't recommend to create or change standard change document by your own logic because of view of the internal control. Changing the change document by user own logic has possibility to make the falsification.
    Regards,
    Masayuki

  • User exit/ badi needed for planned order create/change,collective ATP check

    Dear All,
    I'm looking for a user exit/ badi which can be used for planned orders at the stage of
    mass collective availability check (COMAC tcode) update; or at some other relevant stages of mass update of planned orders.
    I need after collective availability check to perform the following:
    1) to copy date from "total comitment" field on header tab of planned order and paste it (replace old date) to order finish date on header screen
    then
    2) to start a scheduling.
    Very appreciate your help.
    Best Regards,
    Andrey
    Edited by: Andrey Kruglov on Apr 15, 2010 3:06 PM
    Edited by: Andrey Kruglov on Apr 15, 2010 3:07 PM

    Dear,
    Use the BAPI : BAPI_PLANNEDORDER_CHANGE
    Or use the function module MD_SET_ACTION_PLAF for Schedule planned order.
    and the transaction MDAC Execute action for planned order
    This function module includes the following actions:
    Explode BOM
    Explode BOM, check availability
    Check availability, only explode BOM in the case of a requirement
    Check availability, do not explode BOM
    Reset availability
    Change planned order data
    Schedule planned order
    Delete planned order
    Assign the key for the respective action control to the materials in the material master (MRP 4 view).
    Please refer this thread,
    Re: MDVP for collective orders
    Regards,
    R.Brahmankar

  • How to config History Log Changes Document for Mkt Plan/CPG/TP?

    Working in SAP 4.0...
    Dear Expert,
    I want to save the document changes for Marketing Plan, Campaign and Trade Promotion.
    How to config the document changes, since the information that recorded not complete.
    Please help....
    BR,
    Robin

    Hello Robin,
    In  CRM 4.0 follow the below path:
    SPRO --> Customer Relationship Management --> Marketing --> Marketing Planning and Campaign Management --> General Settings --> Edit Categories for Change Documents
    Then maintain the entry for application as MKT for each entry, then under object type: CPG, CPT, MPL, MPT, TPM, TPT  and then Check box the entry under change document for all the entries.
    If you want to display the change log history use report : CRM_MKTPL_CD_DISPLAY in CRM 4.0
    Thanks & Regards
    Raja Pamireddy
    CRM Marketing Forum Moderator

  • Changing MRP controller for planned order

    Hello experts,
    Is there any way the planner could change the MRP controller of a planned order within MD12 ? We are using ver 4.7 and this field is not enabled. Currently the planners are creating prod orders much in advance and are looking to move to a process where they firm planned order. We are using project stock planning structure so more that one planner may create orders for the same material. So when one planner review the material planning for one project he would firm the planned order and assign it to him for leater conversion.
    Note: I the config I didn't saw any field selection control for planned orders.
    Thank you in advance for sharing your wisdom.
    Francois Paquet BPA
    aeronautive industrie

    Francois,
    Very interesting question. However I never had to change those fields in either planned or prodcution orders.
    Both orders master data fileds are disabled.
    However since your are working with project orders ( or netwrok orders ) system would be giving you specific planner order hard tied to the project order ( similar to Made to order scenario).
    Planner could use MD51 ( project planning ) & MD4C ( option for Netwrok or WBS element ) for monitoring progress of his /her order.
    This way planners do not have to go by MRP controller data.
    Hope this provides some new thoughts.
    Thanks,
    Ram

  • Creation of Reservation for planned order

    Hi Team,
    Is it possible to create reservation for planned orders after MRP run?
    My opinion was the reservation can only be created with reference to production order after MRP. The reservation can not be created with reference to planne dorders after MRP run because planned orders are intermident document which will not exist in the system always. The planned order details will not be available in the system once it get converted into production order.
    How the reservation will be processed which was created with reference to planned order after converting the planned order to production order?
    Kindly need ur guidance.
    Thanks
    psk

    Dear PSK,
    In a typical discrete manufacturing setup production orders are the promised receipt for which reservations gets generated as
    soon a production order is created.But only if the order is released goods movements can be posted against the reservation
    details through MIGO/MB1A for 261 movement.
    It's not required to create any reservation at the planned order level or which may not help you in any means to your business.
    But however in a REM scenario MF60 is used to create stock transfer reservations for 311 movement where planned orders
    are used for production backflush.To explain in detail even without any planned orders you can do a stock transfer reservation
    for a production quantity.
    Check and revert back.
    Regards
    Mangalraj.S

  • How to implement Change pointers for Purchase order - ME22N - Custom Fields

    Hi Experts,
    Can you please tell me how to implement - Change Pointer for Custom fields in IDOC.
    I am working on IDOC - For purchase order - acknowledgements - in custom screen/tab in ME22N.
    Everything is working fine according to my requirement.
    All i need to know is the process of - Creating/Change - Change pointers for Custom fields.
    1.How to implement change pointers for custom fields.
    2.Can we maintain - Change Document - for custom fields at data element level?
    P.S. - I have browsed many previous - forums before posting a new discussion.
    please share your inputs...
    explaining how to create/implement - change pointers for custom fields will help me .
    Regards,
    Karthik Rali.

    Hi,
    To maintain Change Document for custom field:
    1. Check if "Change document" checkbox is set in data element.
    2. Find Change Document Object for transaction.
       You can use SQL trace - ST05.
       Look there for line with table CDHDR and statement insert values
       (for example for transaction KA02 Change Document Object is KSTAR)
    3. Regenerate update program for this Change Document Object in transaction SCDO
    Change documents for z-fields schould be generated.
    I am not sure about change pointers but they are configured somehow in BD61 and BD50.

  • Changes documents for BOM and Routing

    How Can I find the change documents for a BOM and routing?

    Change Documents For BOM
    CS80 - Material BOM
    CV80 - Document Structure
    IB80 - Equipment BOM
    IB81 - Functional Location BOM
    CS81 - Standard BOM
    CS82 - Order BOM
    CS83 - WBS BOM
    Change Documents for Routings
    CA60 - Task List Changes
    CA61 - Routing
    CA62 - Reference Operation Set
    CA63 - Rate Routing
    CA64 - Reference Rate Routing
    Hope the above may help you.

  • Logs or change history of planned orders

    Hi,
    Would like to ask if you know a transaction code that will display the logs or changes made for a planned orders.  If there is a transaction code also that would display the username of the person who deleted or changed the planned order. 
    Thank you.
    -Lyncel

    Hi,
    For Planned order change -  Check with  Table PLAF and below fields
    User 
    Time Stamp - This will give the last change date on  which planned order has changed( For EX today  20,080,506)
    However u cannot view the details of  deleted planend order. Because Planned order is temp object only, once u delete, it will be deleted from PLAF table
    Pradeep

  • Change Documents for the table EKET

    Hi ,
    We create a purchase order from ME21N . We do have some data for delivery schedule for the data .
    This delivery schedule data gets stored in tabe EKET . When this PO is processed from V_V2 the dates
    in the  delivery schedule are overwritten and he new values will be even in the table EKET .  When I follow  
    the navigation  Environment -> Item Changes  I dont see the changes documents for these fate fields . I did
    debug through the FM   EINKBELEG_WRITE_DOCUMENT to see but it looks like it is not captuirng the fields .
    Now my requirement is to find where the change documents can be found for the date changes in the delivery
    schedule tab in the PO .  The fields of interest are  :
    EKET-SFLDT , EKET-DAT01, EKET-MBDAT , EKET-LDDAT , EKET-WADAT .
    I tried for some OSS notes too, but in vain . Can anyone please help to find out how we find the changes documents for these fields .
    <b>Also please tell me if there are any OSS notes which explain us to extend the table EKET .</b>
    Thanks and Regards ,
    Varun  .

    HI ,
    I did check the table CDHDR and CDPOS and also the change document is checked for the data element but no change documents are stored in CDHDR and CDPOS .
    <b>Did anyone ever extend the tabke EKET ? Any OSS notes available for this .</b>
    Regards ,
    Varun .
    Message was edited by: varun sonu

  • Change Log for Production Order

    Hello Gurus,
    I have a requirement where the production order scheduled finish date should not be changed in the BW reporting though it changes in the R/3.
    For the same. I need to know if there is any way i can get to know if there were any changes to the scheduled finish date (GLTRS). I checked the CDPOS and CDHDR, but did not find any entries for these changes..
    Please let me know if you have any details on where the change documents history would be maintained.
    Best Regards
    Avinash

    Please check the Order and Click on the Status, then go to extras and check the change documents for all.
    this will display all the changes against the order, with dates and user names.
    From this try to get the report developed.
    Or get the status of Order status from JEST table.
    Hope this helps you.