Change Factory Calender assigned to Plant

Dear All,
Currently I have assigned Calender 01 (05 days working) to a plant. Now I want to switch to Calender 02 (All Days Working) & want to assign the same to Plant.
What will be the implications in system transactions if I change calender assigned to plant ?
Please share your views if already caome across such situation.
Regards,
Rakesh

No as such change. after assigning the new factory calendar, when you will run MRP they the exixting orders will be re-scheduled. Since you are changing from 5 working days to 7 working days , no such problem in SAP you will find. But the reverse may create change the planning scenario.
Go ahead.
Warning: The new factory calendar should have the same valid start date as of before. Otherwise if any pending PR/PO exists in the system which are pending will create a lot of problem and hampered in MRP. I have faced the issue once upon a time.
Don't forget to give point if the purpose is solved.
Thanks
Krishna

Similar Messages

  • Factory Calender assigned to Plant & resource/Work center

    Hello,
    If we have assigned the Factory Calender "XX" which has 5 working day(Monday to Friday) with no Special rules & no Holiday Calender to Plant & "YY" Factory Calender to Work center which has 365 days working with no no Special rules & no Holiday Calender.Now, when MRP creates Planned Orders for FERT material It did not create it on Weekends(i.e. on Saturday & Sunday) though the factory calender assigned is  "YY" (which has 365 days working )in work center.Why?
    Actually it should have consider the Work center assigned Calender for Capacity planning & Schedulling purpose.
    If I assign the Factory Calender "YY"  to plant then it will create the procurement proposal on weekends which is not acceptable to external procurement MRP Controller as plant office works only 5 days.
    Please guide.

    Dear
    Goto CR02/03 , select the Capacity tabe "hat" and u will fined there is tabe "Available Capacity " .U have to maintain the Active version ok.
    Basically , the active version is used for scheduling and capacity planning. If you have not entered an active version, the standard available capacity is used, even if an available capacity version has been entered.
    At the same u have to check out the below requirement :
    you must maintain the following data in the capacity header:
    1.The grouping, that defines which shift sequences and shift definitions can be used to maintain the available capacity
    2.The number of the active version of available capacity
    3.The base unit of measure of the available capacity
    3.The factory calendar, that is the basis of the available capacity-Workcentre
    If you do not enter a factory calendar , the system uses the default calendar for the plant.
    I hope in your case , u have the shift sequence of 5 work days for the calander you have assinged in work centre .
    Please check all those n come back .
    Reward points if usefull.
    Regards
    Jia

  • How to extend factory calender to a plant ?

    Hi Ranga:
    How to extend factory calender to a plant ? ( Tcode: SCAL, The calender is not client specific)
    I check marked US factory calender, where after can you tell how to extend factory calender to plant
    Note: I am using IDES ( International Demonstration & Education System)
    Thanks

    Hi Sandeep,
    you need to use the following path
    Go to SPRO>ENTERPRISE STRUCTURE->DEFINITION> LOG GENERAL>DEFINE COPY,DELETE AND CHECK PLANT>DEFINE PLANT
    Here you need to assign the factory calendar. The assignment in work center will only applicable for capacity not for MRP and others.
    <b>For information how to create a factory calendar</b>
    Pl follow the steps
    1.Go to SCAL transaction
    2.there will be three options.
    Click first public holidays and go in change mode.
    Click create and create your holidays there and save.(Generally fixed date will be used in the pop up)
    3.Now click Holiday calendar and go in change mode.
    Click create and give holdiay cal id and description.
    Click assign public holiday and add your holidays one by one and save
    Now holiday cal is created.
    4.Now come out and choose fact calendar and go in change mode
    Click create and give Factory calendar id and description, and validity period.
    Give the holiday calendar ID.
    If you want to give special rule like any of the specific date/ day is the holiday or work day (which is different from holiday calendar you can define)
    and save.
    5.You have to assign factory calendar to PLANT
    Go to SPRO>ENTERPRISE STRUCTURE->DEFINITION> LOG GENERAL>DEFINE COPY,DELETE AND CHECK PLANT>DEFINE PLANT
    Choose your plant and go to details-
    You have to define factory calendar there
    Hope this will help you
    Regards
    Ranga

  • Urgent    how to change factory calender to normal calender  in bw report

    Hi
    how to change factory calender to normal calender  in bw report give me step by step
    prasanth.k

    Prasanth,
    the calenders are maintained in the source system and not in BW - if you have to change the calendar coming into BW - do the needful change for the related transaction in the source system.
    Arun

  • Wrong factory calendar assignment to plant

    Hi,
    We define new plant in customizing and assign a factory calendar  ( table T001W ).
    I have wrongly assigned a factory calendar BE to German plant in customizing system and moved to changes to production system. Now I want to change this factory calendar from BE to DE in customizing, but the field is greyed out.
    Kindly advice.
    Regards,
    Abhijit

    Abhijit k wrote:
    Hi,
    > We define new plant in customizing and assign a factory calendar  ( table T001W ).
    > I have wrongly assigned a factory calendar BE to German plant in customizing system and moved to changes to production system. Now I want to change this factory calendar from BE to DE in customizing, but the field is greyed out.
    >
    > Kindly advice.
    >
    > Regards,
    > Abhijit
    Hi,
    Open Enterprise Structure-Define, copy-Logistics - General-delete, check plant-Define Plant-select your plant and open in detail view-click on Table view from your header and select Displaay-changes.Now you can see your factory calender as editable.
    Thanks

  • Error at the time change factory calender (scal) validity period

    Dear Experts
    When I tried to change the factory calender Valid period with t code scal Fr. Year 1996 to Year 2011, it probe me the message "Please enter validity area between years 1995 - 2010." and I wasn't allow to save.
    Pls advise how to solve the above problem.
    Thanks.
    BK GAIKWAD

    hi
    your issue is clear that the factory or plant cllendar is defined for only 5 years 2005 to 2010
    NOTE: pleaase contact your HR or FICO consultants for this issue & dont change any thing in PRD then you will be responsible for it
    hope this clears your issue.
    balajia

  • Planning Calender Assignment to Plant

    hello experts
    wee have maintained 7 planning calender to plant 0020, the same client wants to maintain to the plant 0010,
    pleazse let me know the procedure and implications and impact of this assinment .
    please suggest me earliest.

    7 planning calenders maintained earlier, its not by me, now, customer is asking me to maintain same 7 calenders to plant 0010,
    screen shot attached for ref, dta from table T439g
    0020 ES1 1 - 999 04.01.2006 29.12.2020 19.10.2006
    0020 ES2 1 - 999 02.01.2006 30.12.2020 19.10.2006
    0020 ES3 1 - 999 28.03.2007 23.12.2020 26.03.2007
    0020 ES4 1 - 999 04.01.2010 20.08.2020 10.09.2010
    0020 ES5 6 V 999 18.09.2006 30.12.2020 19.10.2006
    0020 QP1 1 + 900 04.01.2010 17.05.2020 03.11.2010
    0020 QP2 1 + 900 04.01.2010 21.05.2020 03.11.2010

  • Factory calender issue

    Hi all,
    Here goes a problem with factory calender in project systems.
    The Project performed by the client are flexible. in some projects they work considering sunday as holiday and in some cases they work on  sundays.
    we have only one plant assigned to the projects which has only one factory calender assigned. e.g plant 1000 to factory calender F1(considering sunday as holiday)
    when i create a new project if i change the factory calender at project definition to F2(considering sunday as working) and then if i go futher creating activities. system will still take the default factory calender assigned to plant i.e F1 and not F2.. the factory calender F2 can be seen in project definition, wbs element and activities.
    but when i change dates at network header level and try to schedule.. system is considering factory calender F1.
    can anyone pls tell me how to solve this problem.
    thanks in advance,
    steve

    Please go to work centre ---&#61664; capacity ---&#61664; assign required calendar there.
    As in the activity calendar will be picked up from work centre

  • Activities happening on holidays even though th factory calender is maintai

    hi all,
    we are creating a sales document
    the factory calender assigned to the plant and shipping point are 5 day week calenders
    but the activities like loading date, goods issue date are falling on weekends i.e. saturday and sunday.
    in the calender weekends are specified as holidays
    thanks in advance for help.
    harini

    Hi Harani,
    check the assignment of factory calender to the Shipping point , sales organisation in enterprise structure ,
    assign the relevant calender to get the correct dates
    Hope this helps
    Thanks
    Akasha

  • Change of factory calender

    Hi All,
    I have come across a scenario wherein the factory calender are different in the plant and the shipping point. If i change the calender of shipping point on PRD what will be the implications of this ? What all aspects do i need to watch out for ? There is a PP integration in this plant too.
    Thanks in advance.
    Regards,
    Saurabh Diwakar

    hello again.
    since calendars are cross client, prashant has a point.  apparently it wouldn't make a difference whether you do this is PRD or DEV.  you will see the changes in any environment within the global setting.
    thanks for the correction.
    regards.
    p.s.
    but shouldn't the assignment of the calendar to the shipping pt be done in DEV?
    Edited by: jonathan yap on Mar 25, 2008 8:29 PM
    Edited by: jonathan yap on Mar 25, 2008 8:30 PM

  • Factory calender for plant

    Dear Experts,
    What is the T-code and how to set factory calender for a specific plant.
    Regards,

    Hi,
    Either you can use SCAL t-code or go to SPRO --> SAP Netweaver --> General Setting --> Maintain Calendar. Once Factory Calendar is maintained. Then go to OX10 and assign factory calendar to specific plant.
    Regards,
    Gaurav Mehra

  • Tables for plant , factory calender & calender validity period

    In which tables we find the data of plant , facory calender & calender validity period.If anybody knows please tell.

    I want the combination of plant , factory calender  & validity period tables to extract the data.In TFACD table we don't get plant & validity details to know exactly what was done during configuration.

  • Change the ML assignment to a plant

    What are the things to be taken while assigning a plant with a new Material Ledger?  Is there any specific OSS note to take care of the same?
    Thanks and Regards,
    Bhuvaneswari.S

    In the intro of the "Change Apple ID" is written:
    "You can change your Apple ID to any other email address you control, as long as it's not already in use as an Apple ID."
    That's my problem, it's al ready in use of an other Apple ID.

  • Invalid factory calender error in creating subcontrating po

    hello all,
    during creation of subcontracting po,system shows the error message "invalid factory calender error".
    i have checked the assignment in oy05.seems ok.
    pls provide some input.
    regards
    sumit simran.

    Hi,
    Please check the path.
    IMG>Enterprise Structure>Definition>Logistics - General>Define, copy, delete, check plant-->Define Plant.
    Here you can find the which factory calender is assigned to your plant.
    Then go to  Tcode SCAL ,  select the Holiday calender and edit it . Double click on your holiday calender   and change it  i.e valid From year to To year. Go back , select the factory calender and edit it ,  give  valid From year to To year.
    Thanks.

  • Problem in Factory Calender

    Hi,
    When creating the sales order the system shows the messege" Date 05.02.2009 occurs after the end of factory calendar IN from plant X".
    So when i tried to change the validity period for factory calender IN to 2009, then the system again showing the messege "Please enter validity area between years 2007 - 2007"-The validity period specified for the factory calendar exceeds that of the selected public holiday calendar.
    So how can i change the Year in Factory Calender.
    Regards
    JYOTI

    Hi,
    under SAP Netweaver - General Setting - Maintain Calendar check which holday calendar is assigned to your factory calendar IN. In the secons step change the validity for your holiday calendar.

Maybe you are looking for

  • Technical competition team needs Labview Developer

    The KC Space Pirates are a team in NASAs Beamed power competition. We are looking into using Labview to automate aiming a high power laser. I am looking for an experienced Labview developer to help with the project. There is no pay if we don't win. I

  • Isight noise

    Whenever i try to record a video in imovie using the isight it makes a very fast beeping noise that gets recorded through the microphone right next to it. Thus making my sound have a constant beeping noise in it. Is there something im doing wrong or

  • Final Cut 10.1 - Crashes when Colour Correcting.

    Every time i try to do colour correction in FCP 10.1 i receive this error message and have no choice but to quit FCP - "The application detected an error that prevents changes from being saved. To avoid losing your work, quit Final Cut Pro." I am abl

  • [Solved] Named Bind Variables at Runtime - SQL WHERE clause issue

    Hey 'all, I've been having this issue today with a Search page using Named Bind Variables at Runtime for the search parameters for the WHERE clause in the view objects SQL. I've got everything working except for a clearing method which I've created s

  • Oracle revoke issue

    Hi ALL, When we revoke a user permission say: REVOKE CREATE TABLE,      ALTER TABLESPACE,      UNLIMITED TABLESPACE,      FORCE TRANSACTION      FROM temp_user;/ Its sets the tablespace value to zero for the all the tablespace for which the temp_user