we have changed our cost component structure to account for an externally procured material; for that we created new cost component ( EXTERNAL SERVICES ) and a new G/L assigned to map the cost.
Now we are facing two issues;
- when i run ck11n, i get messae "cost component struture does not match with itemization".
- when i use ck13n to see previously saved cost estimates; i found that system has updated all of them with " EXTERNAL SERVICES " cost.
Plz guide me regarding my error.
Regards,
M. Tayyab Aslam

Hi Aslam,
1. When you have completed the Cost Component Structure configuration and do a Costing Run / Cost Estimate in CK11N, you saved it.
Now, you changed the Cost Component Structure. That means, shuffling of Cost Element mapping has happened among the Cost Components.
So, when you try to do the Cost Estimate again, the system will look into the already saved Cost Estimate and compares the Cost Estimate which being done at present.
So, do delete the previously saved Cost Estimate and run again.
2. When you say that even for a Material for which there is no utilisation of External Services, this Component is getting updated with some value, then you can check in the "Itemization View" whether this Cost Element is agianst Material / Activity. That means, this GL must have been assigned wrongly some where else also either in MM Automatic Account Assignemnt (if it is showing against Material) or in Operation (if it shown against Activity).
Pls revert back for further explanation...
Srikanth Munnaluri

Similar Messages

  • How to change material component for a Purchase Order?

    How to change material component for a Purchase Order?
    I need FM .
    PLEASE help

    Dear ,
    Create PO with item category L....There in Item detail you will get tab for material.
    There click in component Button, it will take you to the component screen there you can assign and deassign components.
    Hope this helps.
    Regards
    Utsav

  • Automatic change of component in bom

    After certain perion of time if i need to change a component in bom automatically ..is this possible..?
    if yes pls help  guru.....

    In mateial mastr in MRP4 there is a section i.e
    Discontinued Part (Under this)
    Discont in
    eff out
    follow-up mtl
    similarly there is in bom cso2 in
    select the component component & click the button item icon or F7
    u get the button disconti data
    here i need to linkage material master & bom .
    here i reqd help how to linkage & create a folow up grp & discont grp.

  • How to change the component styles (inside panelFormLayout.)

    Hello friends,
    Can anyone help me, How to change the component styles where components (af:inputtext) inside af:panelFormLayout.
    i changed all of the components one by one style, inlinestyle .. from the inspector. By result is nothing.
    how to extend blafplus-rich and override some of the components style?
    thanks for your helps

    thanks alright but i want to learn again after this.
    Which component has a content or border or how can i find list components attributes for change style?
    For example i want to change document content pane, what will i write to css. i am little knowledge about css.
    Thanks for help

  • Mass change in component Scrap % in BOM

    Hi Guru,
    Can someone explain me the process of mass change in component scrap % in BOM ? I have to make zero coponent scrap % in BOM for all materials.

    Dear Vikash,
    Check with t-code CEWB
    for this you need to define work area in OP77
    Regards
    Madhu

  • Changing Query Component's criteria items at runtime

    Hi All,
    As per my requirement i am changing query component's criteria items on some user input.
    So initially there were 9 components on query panel form and after user input it will become 7. I programatically used to set this two component's UI Hint as setVisible(false).
    Its working fine but if user input some value in to be removed 2 components it throws an null pointer exception.
    I understood the problem which is:-
    On query form if user input any value it used to persist. for same framework used to store this user entered value somewhere and after refresh it apply this value to the relevant components.
    Since two of the component are missing after refresh. it throws a null pointer exception as it tried to call setValue() method on removed component which is not there.
    After refresh the query panel form is rendered as per defined by QueryDescriptor object.
    Is there any way we can update this QueryDescriptor object with the changes...????

    Hi Simran,
    Yes, it is possible with the help of store procedure. In SQL Server there is a IF-Else Conditional block, which you can use inside store procedure. Create a SP with 2 additional parameter something like FlagReadAgain and KeyField. Pass the flag always as True or False. For the Key field pass the record key which you want to read again if you are passing the Flag as True else pass it as 0 or whatever.
    In the procedure check if the value of flag is True -> If yes, Read the entry with key name specified in where part.
    In the else part put the query which you are using for the normal flow.
    IF (FlagReadAgain) = TRUE
    BEGIN
       SELECT EmpName, EmpAddress
       FROM Employee
       WHERE EmpID = 'E001'
    END
    ELSE
       BEGIN
         SELECT EmpName, EmpAddress
         FROM Employee
         WHERE Status = 'N'
       END
    You may also use the approach which Srini mentioned. Create an application to restore any value to intial stage so that it can be picked up by XI when it poll again.
    Choose any approach which you like.
    Regards,
    Jitender Chauhan

  • Satellite S3000: how to change a component on the motherboard?

    How do you open the case of this laptop/notebook?
    I need to change a component on the motherboard.
    I get to the stage where all the screws on the base are off, and it seems like all that remains for access into the casing for the 'system board' motherboard is that MAYBE the strip on the front, just below the screen, should be removed.
    Is this so? What do I need to do at this stage?
    It's urgent that I get to do this in the next few hours.

    I dont know what components you want to change on the motherboard but I dont think that its a good idea. :O
    However, I dont think that you will find any officials manual how to do anything on this unit. I think only the service partner can receive such documents.
    I have found in the net this site:
    http://www.irisvista.com/tech/laptops/Toshiba-Satellite-1200/take-apart-laptop-1.htm
    It describes how to open and remove all parts from the Satellite 1200. I know its not a Sat 3000 but you can detect roughly how to do it.
    But you know if you have not experience you shouldnt do or remove anything ;)

  • Prevent changes in Component of a maintenance orders

    Hi Experts,
    I have two questions:
    1. Is it possible to restrain and changes to Component line items (Materials) in maintenance order once it's released except for allowing deletion of the material?
    2. Is it possible to make the filed "Item Category" as Display right when entering the materials in a maintenance order to prevent users from the changing the IC which is defaulted from Material Master?
    Once I set it as Display it only takes an effect once we enter a material number and press enter but if a user changes the IC before that the system allows it.
    Please help

    Hi,
    For question 1:- Use User exit PPCO0023 : Check Changes to Order Components
    For question 2 :-  In our project we have used use exit CNEX0013 Order: Cust. enhancement: Default item category comp. assgmt to populate item category once material no is entered & grey out the field ..
    pls check the above user exits ..
    regrds
    pushpa

  • Error while changing the component quantity

    Hi Experts,
    I facing an issue, while changing the component quantity of the process order. Parent material have fixed lot size and the componenets maintained as fixed quantity in BOM. When I try to change the quantity of the components in process order, it showing an message "Please re-explode the BOM, since the component quanities are changed.
    Why am getting this message?
    Regards,
    Sureshbabu G.

    Hi
    As Mr Reddy said, there is a fixed quantity indicator ticked in the BOM, therefore you are getting that error. Please remove the tick in BOM in the item details besides the quantity field and then try changing the quantites while confirming.
    Chandra

  • Disable for adding or changing in Component or Operation Tab

    Dear Expert,
             Module PM ::: I got an requirment form customer that they need to disable the field for adding or changing in Component or Operation Tab after maintenace order has a status as REL. Could you please find out the solution for me?
    Thank you in advance
    Gamez

    Hi,
          1. U may try to LOCK the Maintenance Order for changes once its status is release , so u should do changes via User exit :-
    IWO10002  -> PM maintenance order: Customer check for order release
    U can read status using FM STATUS_READ
    2. U can also check if BADI :- IWO1_SCREEN_MODIFY Field Content and Display Modification is helpful for ur case ..
    regrds
    pushpa

  • How do I change a component in an existing design?

    I have an existing design created in V11.0 Multisim/Ultiboard. I want to change a single component to replace a transistor in a D2PAK to a part in a DPAK.
    I edited the component in my users library to use the DPAK footprint.
    I transferred (Transfer to Ultiboard 11.0) the revised design to Ultiboard. All components and traces were ripped off the board and the board outline was deleted. All that is left is a board outline rectangle with lots of components scattered around it.
    This happens if I transfer from Multisim to Ultiboard, or if I open the ewnet file from Ultiboard.
    The documentation/help says nothing about modifying existing designs.
    How do I make changes to existing boards without having to start over from scratch?
    PRH
    Solved!
    Go to Solution.

    Don't transfer to Ultiboard - this basically creates a new design - what you want to do is forward annotate only (which will only update the design).
    Optionally you can transfer the UB Netlist only and reimport from Ultiboard.
    Regards,
    Pat N

  • Change logical component  for upgraded satellite

    Hello.
    After upgrading a satellite system from 4.6C to ECC6, I would like to to change the Logical component in SMSY accordingly. But cannot find an easy way to do that. I would like to keep the actual monitor, alert and reactions configuration in the current solution, and just update the Logical Component.
    Actually I am afraid that I have to cancel the system, and recreate it under the new component missing all the settings.
    Does anybody know if there is a non destructive way? I'm working with a 3.2 Solman.
    Thanks a lot, kind regards,
    Dino

    Try manually setting it, or change the leading product from R/3 to ECC

  • How do I remove the extra space when I manually changed a component ?

    Hi,
    I have changed a , lets say 10cm² component to 2cm² component by hand. Now I am stuck with some 8cm² extra space where I can not place any other component in.
    I know I have changed it in the passed but I can't figure out how I did it.
    Any suggestions?
    Regards,
    Stieve

    Hello Stieve,
    Can you share an example of what you did?
    Kind Regards,
    Thierry C - Applications Engineering Specialist Northern European Region - National Instruments
    CLD, CTA
    If someone helped you, let them know. Mark as solved and/or give a kudo.

  • Problem changing displayed component smoothly

    I have the following problem that I cannot resolve.
    Background : I have two display components which my app must alternate between showing. One is a JScrollPane holding a JTextPane, the other a canvas. The canvas in turn holds an animation. In my first attempt I construct a JPanel which (when it is time to change display) just remove the scrollpane and add the canvas, starting the animation thread and then call revalidate(). It works, but this solution is not smooth enough, it took more than one second before the the animation is displayed properly. To solve this I was thinking of putting the two components into a JTabbedPane component, and then just let the app change the tab index. However, I dont want the tabs available in the JTabbedPane, since changing the display is controlled by the app, not by user interaction. In fact, I dont want the tabs visible at all.
    So, how do I solve this? Is using a JTabbedPane, but somehow disabling the tabs possible, or does anyone know a better solution?
    Thanks !

    Hi,
    You're problem might be due to your use of the Canvas (which in Swing is called a heavyweight (=bad) component).
    JPanel is lightweight and you're trying to add a heavyweight component to a lightweight one - which is Bad, bad, bad. Simply make your component extend not Canvas but either java.awt.Component or java.awt.Container.

  • Changes to component not reflected after transport

    We recently modified the  BT115QIT_SLSQ assignment block to rearrange some of the fields and column headers and also add in some newer standard fields. When transported up to quality, we noticed that only some of the changes came in, but others did not. Looking at the setup in the component workbench, it looks identical to the setup in DEV and we didn't receive any errors on the transport. I do  notice the View Navigation tab is now gone in quality and we were getting a "Error in runtime repository' error when we opened up the component in quality which has disappeared all of a sudden. The changes that do come in work fine.
    I tried to do a comparison between the repository.xml files between the 2 environments but they are identical. This was verified using WinMerge, a file comparison utility.
    What else could be causing the changes to the component to not reflect correctly or for that View Navigation tab to be missing?

    Hi James,
    When u transport the Enhanced component to Quality/Prod system the SICF node for that component in SICF transaction will be deactive in the target system, Activate the SICF node for all the enhanced components by right clicking in the SICF transaction manually in the Quality system, this will remove the 'Error in runtime repository' error.
    If you have added the custom fields through UI configuration tool, go to the personalize option for the view/component, select 'Reset to default' option.
    Regards,
    S Reddy

Maybe you are looking for