I have raised a sales Order and shipping point is determined in that order. But while creating Outbound delivery i decided to send it through different Shipping Point.
Can anyone please let me know how to change the Shipping Point at creating Outbound delivery.
NOTE: I DONT HAVE AUTHORIZATION TO MAKE CHANGES IN THE SALES ORDER.

hi,
you cannot have delivery for an item having a different shipping point at delivery than is proposed at the sales order level.
the copy control rountines between order to delivery ensure this.
However if there is a business requirement like this wherein you may need to change the shipping point, take the required authorization to do so, than thinking of any customization.
regards
sadhu kishore

Similar Messages

  • Sales order change allows shipping point | plant combination - not possible

    A sales order was created and all lines defaulted to the correct shipping point for the plants.
    Subsequently, one line's shipping point was changed to a shipping point not possible for the plant, i.e, no assignment exists for the shipping point and plant.  There were no checks to validate the change.  Thus, the sales order was saved with the bad shipping point for the plant (non-WM).
    The delivery was created with two lines for plant (WM) and one line for plant (non-WM).
    The solution was to manually delete the non-WM plant line from the delivery and.  Next, correct the plant (non-WM) to the WM managed plant and create a new delivery.
    Why did SAP allow the order to save with bad shipping point - plant combination.
    Thank you in advance for your assistance.
    lotjjon

    Why did SAP allow the order to save with bad shipping point - plant combination
    Definitely, standard SAP won't allow you to change the shipping point unless, it is assigned in OVL2 as already pointed out.  Check whether this issue is there for all plants / shippint points or only in that document, this issue has happened. 
    G. Lakshmipathi

  • In STO Process How can i Change the shipping point manually

    Hi,
    I need clarification in STO process, shipping point determined automatically based on ovl2 setting like Shipping condition from customer master loading group from material master plant in the line item.(here the shipping point is1000.)
    In my scenario it picking correctly shipping point(1000) even i have maintained manually shipping point(1200) in ovl2 but when i am creating STO document UB change shipping point at item level in shipping tab system allowing the manual shipping point (1200) but when i enter or save the document system overwrite 1200 to 1000,system consider only automatic determination  in shipping point (1000)
    Can you please help why i am not able to change the manually shipping point 1200( even i maintained  in ovl2 manually shipping point 1200)

    Sending a calendar to another country is not supported in many jurisdictions - as it can lead to extra charges for the receiver. As I have no idea what country you are in you can select your country from this list
    http://store.apple.com/us/help/print_products/routing
    And find out if it's supported in your country and to your chosen destination.
    Regards
    TD

  • Change Shipping Point in STO in Transaction code ME27 / ME22

    Hi Experts,
                      I want to change Shipping point in Transaction ME27 Is it possible i want to change default shipping point with manual shipping point ?
                      Is it possible ?
                       Please help...
    Thanks & Regards,
    Tom

    Thanks for your reply
    I have configured multiple shipping point in same plant
    shipping condition - Loading group - Plant - Prop Ship  Point - Manual shipping point
      03  -                        006      -                  xx      -                  x      -                           y
    In me22 - Item shipping data i am not able to change prop shipping point with manual
    Please help me to solve this problem
    Thanks & Regards,
    TOM
    Edited by: tomsoulsurfer on May 18, 2009 1:37 PM
    Edited by: tomsoulsurfer on May 18, 2009 1:38 PM

  • Sales office to shipping point in VA01

    Hello,
    We've tried to create a new Sales Organization with a new Sales Office in SAP system, but got following problem in VA01:
    In VA01 first screen you can choose them ok. But in sales order items Shipping Point/Receiving Point is automatically sales organization and NOT the sales office. You can't change the shipping point manually either, VA01 says "Shipping point is not defined for this transaction".
    We've tried SPRO configuration but haven't found anything that helps, any ideas?
    Thanks in advance,
    Tom

    Dear Tom,
         I dont think the new sales organization is the cause of your issue to determine shipping point in VA01 line items.
    Because Neighter Sales organization nor sales office doesnt have any direct assignemnt with shipping Point.
    Shipping Point determination is based on :
    Shipping Conditions ( which will be copied either from  Sales doc type or Customer master of the sold to party)
    Loading Group ( will be taken from MMR-Sales/Plant general tab)
    Delivering Plant ( taken from: Customer Material Info record or Customer Master record / Material Master record) .
    Coming to your issue: as per your post,
    Whether you want the system should determine Shipping Point based on either sales org or sales office? Ist so-Please confirm. But in std its not provided.

  • Shipping point in STO defined upon storage location

    Hello, all
    On stock transport order I want to set up shipping point in a way that it is determined regarding to storage location I have entered in header of STO.
    Storage location is saved in field EKKO-ZZLGORT (tab Customer data). Now I need solution how to determine or overwrite shipping point when entering items.
    For example:
    . if storage location is 100, shipping point should be AAAA
    . if storage location is 200, shipping point should be BBBB
    I know that shipping point is determined according to combination of Plant-Shipping conditions-Loading group. And it works this way now.
    Is it possible to do this via customizing ? If user-exit is needed please specify which and what must be modified. I'm not a programmer but I know business process. Will get help of programmer if needed.
    I'm looking for this solution because I want to prevent that VL10b puts Stock transport orders with different storage location in header on same delivery.
    Thanx in advance,
    RJ

    Hi,
    You should be able to use METHOD if_ex_me_process_po_cust~process_item to change the shipping point. We've created a customer table in which we've set the corresponding plant, SLOC and shipping point combination which is read during execution of the BADI.
    You can also use METHOD if_ex_le_shp_delivery_proc~save_document_prepare for changing the shipping point in the delivery.
    We've used above for return items. We're on 6.0 as well and for all non return items, standard customizing is available, but not for returns.
    Hope this helps.
    MdZ

  • Shipping point in sales order

    Hi ll,
    I have crearted a sales order, and i want to change the shipping point, but each time i change the shipping point it keeps going back to its original shipping point.  how can i change this?
    were is the shipping point held?

    Dear SAPing SAP,
    you are not able to change the shipping point in the sales order due to shipping point determination settings in OVL2 transaction.
    If you want to change the shipping point manually in the sales order you need to maintain that shipping point as manual shipping point in the OVL2 transactuion.
    Please go to OVL2 transaction here you enter the shipping point which you want to enter manually in the sales order ,in the colomun Manual shipping point -MShPt with the combination of
    Shipping conditions (Customer master)Loading group(Material master)Plant-->Proposed shipping point + MShPt.
    Now you can able to enter the shipping point manually in the sales order system will accept.
    I hope it will help you,
    Regards,
    Murali.

  • Help in Shipping point.

    I have a scenario... we are selling water and soda. It is shown like the materials is received here at our plant and sold from here.. but in most cases it is taken directly from the manufacturer and supplied to customers
    So, my client wanst to know which batch has gone from our stock and from manufacturer
    If I maintain difefrent shipping point, is it fine? will it have any implications on MM?
    when I enter sales order, i dont know from where is is going to be shipped. say half from system determined shipping point
    I created a delivery with that. Now rest shud be from other shipping point. I have maintained it als oin OVL2
    But without editing sales order, when I try creating with other Shipping point system is showing "Delivery not possible"
    If I change the shipping point in sales order, it works. But person sitting in plant cant edit sales order
    Any idea?
    Regards,
    Anbu

    Hello Anbu,
    A similar thread is active right nnow in the forum.
    See, in Sales Order for each line item you can have only one Shipping point (you can change this shipping point based on Manual Shipping Point defined in OVL2). But the bottom line is that in one line item there can be only one Shipping point & this Shipping Point Cannot be change at Delivery Level.
    I understand that your Plant person will not have authorization to change Sales Order, but there is no other option.
    The solution can be:
    Create a Sales Order with two line Item of same material. Maintain different Shipping Points for each of the line items.
    Now the Plant person can create Delivery for each Shipping Point based on Actual Quantity dispatches.
    The balance quanty in Sales Order can be closed by person having Sales Order change Authorization.
    Example:
    Say you have to deliver 100 Tons of Material A to Customer.
    In Sales Order create two line Item with Quantities like this:
    Line Item 1 Material A 70 Tons - Shipping Point 1
    Line Item 2 Material A 70 Tons - Shipping Point 2
    Now the PLant person can deliver like this:
    Line Item 1 - 45 Tons
    Line Item 2 - 55 Tons.
    The balance quantity in Sales Order can be closed once quantity of 100 tons is Delivered to Customer by entering Reason for Rejection.
    Hope this Helps,
    Thanks,
    Jignesh Mehta

  • Shipping point determination in stock transfer order,

    Hi, experts,
                            I have one problem regarding stock transfer note, In my business scenario, product wise SR no use for excise invoice, So, i had maintain no range as per shipping point wise, But , when i have create stock transfer order, at a time system take default shipping point , as per shipping point determination, But i want to different shipping point in this stock transfer order, but i can not change shipping point in stock transfer order, Can u give me any solution of this problem,
    T.code - Use - ME27
    Order type - UB
    Regards:
    Happy

    First create a STO with a Plant as per your Requirement by maintaining the same Plant in the Material.Also maintain the same Plant in determining the Shipping Point Determination.
    Otherwise to change the Shipping Point Manually is not a good habit by the Users.
    Best Regards,
    Ankur

  • Different shipping point for returns delivery

    How do i assign a different shipping point for returns delivery when the material was actually shipped from another shipping point?

    Hi Salag,
    As our expert suggested by using 2 shipping point you can create delivery. Delivery will create based on single shipping point.
    In you scenario if you want to ship the return goods with different shipping point then go with new configuration.
    For Normal sales order OR maintain the shipping condition 01 in the respective sales document type OR
    For  returns order maintain the shipping condition 02 in the respective sales document type RE.
    When comes to shipping point determination shipping point will determine based on
       Order:        SC Loading Group Plant -- Proposed S.P -- Manual S.poimt
        OR    :        01 0001AAAA -
    >     XXXX             --- YYYY
        RE     :        020001AAAA -
    >    YYYY
    If you don't want to go with different SC then manually change the Shipping Point in Returns sales order before creating delivery.
    I hope it reaches to ur requirement. revert in case of any query..
    Regards
    Durga Sana

  • How to change the format in shipping point

    Hiii.. When we define shipping point, how to change the format from hours to days for entering loading time & pick pack time.
    Regards,
    Jay

    When you maintain working times in define shipping point, the time is maintained in HRS. This is called precise scheduling.
    If u do not mainatin the workin times field (blank) then the time is maintained in days. This is daily scheduling.
    Vishal

  • Modify shipping point in sales order create/change

    Hi,
    I want to modify/overwrite shipping point value while create sales order and change sales order. Is there any user exit or BADI available to fullfill this requirement.
    Thank you.
    -Pallavi

    Hi Palavi,
    You can modify or overwrite shipping point value while create Sales order or change Sales order. For this you have to modify field  VBAP-VSTEL in the FORM userexit_move_field_to_vbap of include MV45AFZZ.
    Regards
    Dillip

  • Transport shipping point address change

    Hi All,
    I have to change shipping point address in production. I have tried changing shipping point address in Dev system but it could not generate transport request. Please guide me the way to transport shipping point address change from Dev to Production.
    Thanks & Regards
    Ashok Reddt

    Usually TR are created by Basis team, if you don't know the process who is suppose to create TR, ask your manager to get the same.
    Once after you are given the TR then save the changes in the TR.
    Once done the changes in development system, you need to test it in test system( Quality client) then you need to request for User to test(UAT). After confirming the changes by User then you need to move these changes to Production.
    But some times  for some clients will do testing both in Development as well as Quality client.depends on client process. But testing is mandatory.
    The above process usually followed by most of the clients.Check your client process exactly how it is followed then proceed further.
    Please let me know if you need any further help.
    Srinu.

  • Shipping Point Change .SO

    Hi all
    Can you help us. We have placed salesorder to plant SE03 with some dien articles.
    Somehow the system then puts in shippingpoint 2 instead of 21
    which it should be and I can not change shipping point when I try. These orders are shipped from Germany (SE03) and configuration is made in Sweden so these order should not be visible for Finland (SE11) at all.
    What can be done?
    Best regards'
    Ram

    Hi ,
    Thanks , Can u pl brief me bit more clear .
    Pl let me know the IMG Path.....
    Best regards'
    Ram.

  • Shipping point address Change :

    I was changing the street address of shipping point . I got the below error "The region DE is not defined for country DE" . And not allowing me to change the street address. -
    Please suggest.

    This error means that region DE is not defined for country DE (Germany). Germany has regions 1-16. They don;t have DE as region  in standard system.
    Please check the address. Per German standards & SAP standards DE cannnot be a region in Germany. So your address is incorrect.
    But if you want to create a new region then you can in SPRO.
    Hope this helps !

Maybe you are looking for

  • Dbms_xmlgen: write emp content to xml file

    Hi. I have the following procedure to write the content of the emp table in xml to a file: CREATE OR REPLACE PROCEDURE BSP_DBMSXMLGEN IS v_ctx DBMS_XMLGen.ctxHandle; v_file Utl_File.File_Type; v_xml CLOB; v_more BOOLEAN := TRUE; l_exception varchar2(

  • Problems in c:out tag.

    hi all, i a JSP page i have added code like this on body onload.           <c:if test="${not empty rgnToDate}" >                document.getElementById("rgnToDate").value = '<c:out value="${rgnToDate}" />';           </c:if>     so in referenceData()

  • Time Machine Oldest/Latest backup field is blank "--"

    Hello, In Time Machine under the Oldest and Latest Backup fields all it says is "--". It is also the same in the quickmenu. It used to work perfectly fine but it now it is blank, when I go into time machine all the dates/backups are there including t

  • Porting Java Sources to other languages

    well, I know I might be in the wrong place with this, but since the subforum's theme is somewhat related to my question, I'll try to get an answer here. Along with the upcoming hype around AJAX (http://en.wikipedia.org/wiki/AJAX) I see the need for a

  • PHP code initiating a BPEL Process

    Thanks to Ross Ackland, we have an example of PHP calling BPEL. We are working on integrating it into the build as a sample. Between now and then here is the PHP code snippet! <?php ** Using PHP Soap - Requires PHP Version 5 ** See: http://au.php.net