Hi,
My client is a machine industry having both MTS and MTO scenarios.
For example letu2019s consider a material u201CAu201D which is manufactured with 12345 components and u201CAu201D is a finished material. My customer directly sells this to customer which will be MTS scenario.
But sometimes customer will ask the material u201CAu201D with modifications like he needs 12356 i.e. in place of u201C4u201D component he needs u201C6u201D.
So please suggest a better process to map the same in SAP SD

Hi,
  In this case also you can follow the same procedure,sales order will be created by the customer requirement and then moved to the production,here if the material all ready produced then they will change the parts as per the order requirement,if not they will produce as per the requirement.
With my knowledge i am giving you the suggestion,please correct me if i am wrong.  
Thanks
Ram

Similar Messages

  • How to change component / actual used material during MIGO for Suncontract

    Hi
    We have below scenario, need your expert help...
    1) As per BoM Material A- is produced from Mat B.
    2) Sub-contact Order is created with Mat A and Mat B is sent to Vendor with Mov type 541.
    3) In few cases Mat A can be produced with Mat C / mat D etc
    4) Now at the time of MIGO..we will come to know that which mat is used .
    Question: -  Can I change component material at the time of MIGO. I mean can change component material from Mat-B  to Mat C etc.

    Hello Rajesh,
    You need to change the component in Purchase order (ME22N). there is not separate table for this.
    - Go to ME22N transaction
    - Select the line item for final product
    - Go to Material tab and click on "Component" at rightside
    - Add new material number here
    - You can keep old material or delete it.
    Hope this helps.
    Regards
    Arif Mansuri
    Reward if answer is helpful

  • Can a finished material be a component

    Hi gurus,
    Can a finished material be a component in BOM of some other material.
    Regards
    Kaisar

    Hi,
    In process industry, there are scenarios where FERT material from one plant is being used as a component of the other FERT material.
    For eg.
    Scenario is there is one compay manufacturing Vitamin A, plants located in this org are A1, A2.
    Plant A1: Fert is Hydroxenine
    Plant A2: Fert is Vitamin A 
    For plant A1,  FERT is Hydroxeine, but this same material is
    used as a component in plant A2.
    This is the actual process scenario used in process industry, as mentined by shiva setting for this is maintained in SAP. Thanks Shiva for this update.
    Regards,
    Avinash.

  • Serial number status of semi finished material.

    Hi Gurus,
    I have a serialized finished product.
    I have a serialized semi finished material as a component of that finished product.
    After issuing the semifinished to the production order of the finished product, the serial number status of the semifinished item becomes AVL.
    I dont want the semifinished serial number to be reused once it is issued to a production order and the finished material from that production order is delivered .
    Help me in acheiving this.
    Thanks in advance.
    Regards,
    Gowrisankar.p

    Hi Gowri Shankar,
    You should maintain a User Status Profile for the Serial Number Profile, (Through Equipment Category).
    Once the Semi finished Material with a particular Serial Number is Issued for a production order. The status should change to Say " Used". Then this Serial Number cannot be assigned again to a new Semifinished Goods.
    User Status profile should be defined in transaction BS02.
    Thanks And Regards,
    Balasubramanian.

  • Extrusion Sales price based on multiple parameters of the Finished Material

    Hi Gurus,
    Scenario: Extrusion Industry- Finished Material price to be calculated, based on the following parameters:
    1. Basic Price of the Finished Material
    2. Alloy Market Price
    3. Temper Price
    4. Type of Finish based Price
    5. Length ordered based price
    A. Customer wants the Sale Price of the Finished Material to be sum of 12345.
    B. Customer wants to Change the Basic price for few Customers.
    C. Customer wants to Change the Sale Price of the Finished Material based on the Market fluctuations with respect to the Alloy used in the production of the Finished Material.
    How to address, this type of Scenario ? Those who have come across similar scenarios in Extrusion Industry can share their experiences ?
    Do we need to go with Variant Pricing ? If so, do we need to go with KMAT or FERT ?
    Thanks & Regards
    Sreekanth

    hi,
    1. Basic Price of the Finished Material
       Kondition xxx1  Access : 1. Kunnr / Matnr   ex      ( B )
                                                 2. Matnr
    2. Alloy Market Price
        Kondition xxx2    Access : alloy - price
                                    with formula over the weight of the Material
    3. Temper Price
        Kondition xxx3
    4. Type of Finish based Price
        Kondition xxx4
    5. Length ordered based price
        Kondition xxx5    with Formula over the length
    6. Summ of 1 - 5
    7. xxx6 Manual Price   with exclusion of xxx1 to xxx5      for C - manual Price
    or
       xxx7 Rabatof sum 6   for the scenario c -- for scenario c, there is to less information, what there should be done.
    so far, i dont see a reason for variant pricing.
    hans

  • Automatic change of component in bom

    After certain perion of time if i need to change a component in bom automatically ..is this possible..?
    if yes pls help  guru.....

    In mateial mastr in MRP4 there is a section i.e
    Discontinued Part (Under this)
    Discont in
    eff out
    follow-up mtl
    similarly there is in bom cso2 in
    select the component component & click the button item icon or F7
    u get the button disconti data
    here i need to linkage material master & bom .
    here i reqd help how to linkage & create a folow up grp & discont grp.

  • Prevent changes in Component of a maintenance orders

    Hi Experts,
    I have two questions:
    1. Is it possible to restrain and changes to Component line items (Materials) in maintenance order once it's released except for allowing deletion of the material?
    2. Is it possible to make the filed "Item Category" as Display right when entering the materials in a maintenance order to prevent users from the changing the IC which is defaulted from Material Master?
    Once I set it as Display it only takes an effect once we enter a material number and press enter but if a user changes the IC before that the system allows it.
    Please help

    Hi,
    For question 1:- Use User exit PPCO0023 : Check Changes to Order Components
    For question 2 :-  In our project we have used use exit CNEX0013 Order: Cust. enhancement: Default item category comp. assgmt to populate item category once material no is entered & grey out the field ..
    pls check the above user exits ..
    regrds
    pushpa

  • Error while changing the component quantity

    Hi Experts,
    I facing an issue, while changing the component quantity of the process order. Parent material have fixed lot size and the componenets maintained as fixed quantity in BOM. When I try to change the quantity of the components in process order, it showing an message "Please re-explode the BOM, since the component quanities are changed.
    Why am getting this message?
    Regards,
    Sureshbabu G.

    Hi
    As Mr Reddy said, there is a fixed quantity indicator ticked in the BOM, therefore you are getting that error. Please remove the tick in BOM in the item details besides the quantity field and then try changing the quantites while confirming.
    Chandra

  • Change Release price of FERT material

    Dear friends,
    I m trying to change the price of a finish material thro' MR21.
    This material is having a marked cost estimate for the current month.
    I have use t_code CK40n to find the cost of the material.
    All steps are completely done up to the release of the cost to material master.
    But the cost of the material came out to be 261.33 rupees. My client certainly cannot sell this material for 261.33 rupees. He wants to change the cost to Rs. 265, but the system is giving an error, that the material is already having a released cost.
    The procedure to change the cost of the material is also given, it says
    "You can set the price of a marked cost estimate through the radio button 'Default Planned Prices' and release it by saving." But I m unable to find this radio button.
    Your help is really appreciated.
    Thanks for the assistance.

    I suggest you to take CO help for this. As per my knowledge we cannot update standard prize from MR21if this is released for the same period (only moving average prize uopdate is possible) . As you have run the cost and already released in the same period, you need to reverse/cancel this and run the fresh cost estimate.
    Regards
    Tajuddin

  • Price control "V" for Finished Material

    Hi,
    In implementation project i have created ZFIN for finished material type.And given Price control "S". But as per client reqirement i have to change that " S" into "V".
    Is there any effect for those material which already have been valuated with price control "S"? Can i proceed?

    hi
    generally the valuation is kept S for finished goods
    as the price is updated from production and not from sales, so u cant keep the MAP as the production cost varies as per the change in cost of raw material
    i think u should tell this to ur client
    either if u want to change  the price control from S to V
    You can make this change at any time. The moving average price (which until now has been updated for informational purposes only) replaces the standard price and is used for valuation from now on.
    read this
    http://help.sap.com/saphelp_47x200/helpdata/en/47/60ff6249f011d1894c0000e829fbbd/content.htm
    http://www.sap-img.com/materials/price-control-v-or-s-in-material-type.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/47/60ff0749f011d1894c0000e829fbbd/content.htm
    regards
    KI

  • How can I change the name of a Materialized View?

    How can I change the name of a Materialized View?

    Oracle permitted renaming the snapshot in the earlier versions of 8i. However, it does not permit renaming the materialized view in 9i or 10g.
    SQL> rename mymatview to mymatview2;
    rename mymatview to mymatview2
    ERROR at line 1:
    ORA-32318: cannot rename a materialized view
    SQL> disconnect
    Disconnected from Oracle Database 10g Enterprise Edition Release 10.1.0.2.0 - 64bit Production
    With the Partitioning, Oracle Label Security, OLAP and Data Mining options
    SQL> rename mymatview to mymatview2;
    rename mymatview to mymatview2
    ERROR at line 1:
    ORA-32318: cannot rename a materialized view
    SQL> disconnect
    Disconnected from Oracle9i Enterprise Edition Release 9.2.0.3.0 - 64bit Production
    With the Partitioning option
    JServer Release 9.2.0.3.0 - Production

  • Serial Number Error in YMFBF confirmation for semi-finished material.

    Dear Experts,
    We are having repetitive manufacturing scenario,while confirming the Semi-finished material ( X) in YMFBF Screen, after POST with Correction and Saving the Confirmation. Error Applied....
    "Only the 0 serial numbers entered instead of 1.
    Message no. IO304
    Diagnosis
    There is a serial number obligation, so the number of serial numbers must equal the number of serial numbers in the material document.
    You can post the operation only if you entered the correct number of serial numbers previously.
    System Response
    Depending on the context in which the error arises, the system continues processing, or the required function cannot be performed.
    Procedure
    You have the following options, for example:
    Check that the serial numbers are entered fully.
    If necessary, display an error log.
    If necessary, contact your system administrator.
    Please give some solution for this,
    Thanks,
    Babarkhan

    thread is closed from my side.

  • Finish material is not showing at the time of confirmation

    Dear all ,
    Finish material is not showing in the goods movement tab .So that movement type 101 is not possible at the prod ord confirmation .
    Goods movement is accepting in mb31.
    So plz suggest me

    Abhay,
    I think you are asking for Auto GR,whereby upon confirmation GR will happen automatically in the background
    Required Setting
    In the routing ,to the last operation assign PP03(Auto GR-Std SAP) as the control key instead of PP01
    After that while doing confirmation for last operation in CO11N,there if you click the goods movement tab you will be able to see the finish material with movmnt type 101
    Hope the above is clear
    Reward points if useful n close the thread
    Regards,
    SVP

  • Change the inspection stock of material in qm only

    Hi All,
    Error I am getting while doing a Goods Movement is "change the inspection stock of material in qm only". Let me explain you what exactly happend.
    We moved transports, some how moved transports deleted the existing Inspection types in Production system. So there were no inspection types available in the system untill we send another transport. During the period of the transport  in transit Goods reciept agains the Purchase order is done. So inspection lots were not generated. So now inspection types exist due to another transport.
    So Users complained about the inspectiion lots.
    I told them to reverse the Goods reciept documents and do the Goods recipt again so that inspection lots get generated.
    When they are trying to do 102 Mvt Type they are getting the error.
    I was even trying to use 321 Mvt Type, still Unsussesful.
    I tried de-activating the Inspection typem but system throwing an error "Quality stock exist".
    Is there a way to Move stock from Quality to Unrestricted?
    How to generate an Inspection lot for the existing stock to move the stock from  quality to unrestricted?
    QA01 inspection lot creation, i dont see the purchase order field. Is there any possibility of adding purchase order to the inspection lot?
    Thanks,
    Quantum.

    hi ,
    How to generate an Inspection lot for the existing stock to move the stock from quality to unrestricted?
    activate  0800 inspection type in material master, its basically for stock which is in qulity and does not have a inspection lot.
    regards
    satish

  • Change the valuation class of material [Stock transport order scenario]

    Dears,
    Client would like to change the valuation class of material.
    There is no open Purchase order/Process order/Purchase requistion and stock in plant.
    Scenario- One Stock transport order is created.
    For same goods issue (351-issuing plant) and goods receipt (101-receiving plant) is done.
    When we are going to change the valuation class of said material, message is "purchase order is open
    and it shows the no of STO [for which receipt and issue is done]"
    To resolve this issue we had first delete the STO line item no(ME22N). Then change the valuation class.
    (this allows). and then undelete the STO line item. Through this we can change the valuation class of material.
    Please advise in such business process that this is right way or there may be other option.
    Thanks & Regards
    Rajan

    rajanshah219,
    Here's my take on how to fix:
    *Manually change Config TCode OMT4 - change message MM 326 & 327 to type "W"   (if open order exists...now you can enter through warning messages)
    *If inventory exists, then issue out of stock to a cost center
    *Change valuation class
    *Put stock back into inventory (reverse to that same cost center)  Note issue out and reverse back into inventory must happen in the same posting period.
    **Valuation class should be changed as expected
    **Manually change config  TCode OMT4 - change message MM 326 & 327 back to type "E"
    Thanks,
    Jason

Maybe you are looking for

  • HOW TO USE  BAPI_INCOMINGINVOICE_PARK

    HI ALL;      I WANT TO USE   BAPI_INCOMINGINVOICE_PARK  FOR T-CODE MIR7. IS THERE ANY BODY COULD GIVE SOME EXAMPLES ? THANKS A LOT.

  • Trigger Compilation Errors after Full Import with Datapump

    Hello All, We did a full import with Oracle Datapump, and encountered some errors related to triggers: ORA-39082: Object type TRIGGER:"CONVERT3"."CUBCNVT_AUDIT_RESET" created with compilation warnings ORA-39082: Object type TRIGGER:"CONVERT3"."CUBCNV

  • The configuration assistants emca and netca exits (redhat8, pentium IV)

    The assistants just exits when I try to configure listeners and a (new) repository. I'm using redhat 8, oracle8i and pentium IV. Any suggestions?

  • Unable to get access to workspace

    Hi, The group sponsor has tried to add me to this group, but we get the following error message: "You have been invited to become a member of a Group hosted by Oracle BeehiveOnline. The details are: Group Name: Oracle_AC_ISV_ASFU Group Purpose:T�ss�

  • Using the cookie cutter tool

    I am having trouble cropping a photo with the cookie cutter tool. When I drag a shape over my photo, my photo disappears, leaving the gray/white checkerboard. Any advice?