Change of Material Type in Plants

Dear Guru's,
Good Day.
I've two plant Codes Plant A and Plant B with one company code.
Plant A Procures a Material(ABC) from an Vendor. Material type for ABC is maintained as ROH(Raw material).
Plant B produces Material(ABC) inhouse and does STO to Plant A.
I've extended the Material (ABC) from Plant A to Plant B.
Now,  I need to Change the material Type for ABC in Plant B as Finished Goods(FERT), which is not Possible by transaction MMAM.
I need to Change the Valuation Class and Price control for mateiral ABC in plant B.
With Regards,
Siddharth

Hi There
Steps in Split valuation
1. Define the valuation category Globally
2. Define the Valuation types Globally
3. which valuation types belong to which valuation category
4. Define the Vlauation category/Valauation type locally- Per Plant
Ref the below links for Split valuation config
http://www.sap-basis-abap.com/mm/step-by-step-procedure-of-configuring-split-valuation.htm
http://www.sap-img.com/mm025.htm
Thanks
Senthil

Similar Messages

  • Material type to plant assignment

    Hi all,
    where in SPRO, we can assign material type to plant??
    Regards,
    Aisha Ishrat
    ICI Pakistan Ltd.

    Hi,
    We assign Material type to Valuation area which is either Company code or Plant.
    This will be assigned in Quantity & Value updation for that Particular Material type.
    Path is
    SPRO-Logistics genMaterial masterBasic settings-Material types--Define attributes for Material types.
    Here select the Material type and then select the quantity & Value updating.
    You will find all the valuation area there select your valuation area(Plant) and select the check box which means the quantity & Value will be updated with respect to this material type whenever you do any goods movement or any changes to the material which is created based on that material type
    rgds
    Chidanand

  • Error while Change of material Type

    Hi,
            I have one material  and the same material is present in our 3 company code and plant,  the materila TYpe is HALB  anf I want   to change it to  FG  but while changing with MMAM  first it was giving error that valuated stock is avalable then  I have issue the material  now my stock is zero  but  still it giving error that  many PO exist  and Porduction order exist,  for the HALB valuation class is 2000  and for FG it is  3000,
    How this probelm can be solve.
    regards,
       zafar

    Hi,
    While changing the Material Type, following points needs to be confirmed :-
    1. There should be no stock against the materials. If there will be any stock against the materials, then u will have to nullify the stock for the materials.
    2. There should be no open documents against the materials like PO, PR etc. In case if any open documents, same needs to be closed.
    3. Also there should be no open reservation order against the materials.

  • Change of Material Type via MMAM

    Hi All,
    May I ask what are the other prerequisites in changing the Material type?
    What I know is stocks must be zeroed out, Open POs must be closed (is it the open POs only? or all POs with the specified material?) ,and OLD and NEW Material type should have the same Value and Quantity Updating setup.
    I tried changing one material by it reflects an existing Delivery for the said material, I checked the DR and found that it was already received - although its Shipment Cost hasn't been transferred. What should be done with these DRs?
    Thanks a lot.
    =)

    Hello
    The following are the checks the System made :                                                                               
    The POs will need to be flagged for deletion and/or the production          
    orders will need to be archived, in order to change the material type       
    for the material.                                                                               
    The value and quantity updating must be identical for the old and new       
    material types in order to allow a material type change.                    
    Review note 160970.                                                         
    If you do not want to flag the deletion flag of the PO line item for        
    the material, please use note 160970.                                       
    Note 160970 is only for material types where the quantity and value         
    updating is similar (txn OMS2 configuration) .                              
    Please refer to the Online documentation:-                                  
        Logistics - General                                                     
        -> Logistics Basic Data                                                 
           -> Material Master                                                   
              -> Material Master Records                                        
                 -> Material Types                                              
                    -> Changing a Material Type                                                                               
    If the material is already in stock, or if reservations or purchasing       
    documents exist for it, the following conditions must also be met:                                                                               
    o Quantities and values of the material of the new material type          
        must be updated in exactly the same way in all plants as quantities     
        and values of the material of the old material type.                    
    Please take note that the account category reference must be the same       
    for both the new and old material types and the stock values for the        
    materials with the new material type must be updated in the same G/L        
    account as the stock values for materials with the old material type.       
    Regards,
    Mauro

  • Change the material type

    Dear All,
    i have changed the material type "FERT" to "ROH" wrongly and then , i am trying to reverse it . but the system give the error"material type can't be changed . and its give some PO number and line item also. for all those PO's are STO PO's. this All   the PO has been created  last year and GR/ IR also completed. could you please explain , why the system doesn't give any error while changing the material type FERT to ROH.
    Rgt
    KT

    Hi,
    Check whether this is helpfull,
    Following are the pre-requisites for changing a Material type :
    1. No PR , PO should exist
    2 No Stock should exist .
    OR
    1. Account Category refernce assigned for both the material type should be same so tht the accounting determination wrt to material type is not effected .
    Hoep that was helpfull..
    Thanks & regards
    Vicky

  • Change the Material type & Material industries

    Hi Expert,
                      I have created one material code. Suppose that Material Code is " XYZ"
    Material code : "XYZ"
    Material Type : FERT
    Industry sector: Chemical industries
    I want to Change material type & Industry sector.
    Please help me how i change the  Material type & Industry sector.
    Best Regards
    Shashi Singh

    Hi
    I want to Change material type & Industry sector.
    Changing the material type for a material is possible as it has been well explained by other friends
    It is because a semifinished goods  one material type  can become a finished goods another material type
    Changing the industry sector is not possible at all
    Once industry sector is assigned to a material you cant change it at all
    Regards
    Raja

  • Change of material Type

    Hello to all,
    I have one question. We are doing implementation with SAP R/3 version ECC 6.0. First let me explain the scenario. The scenario is Intercompany sale. We have two Statergic Business Units e.g. 'A' & 'B' . One SBU ('A') isues PO for manufacturing Press Tool to other SBU ('B') for which it will be SO. . ETS is operated through Project System Module for which Tool is a FERT (Finished product). Now 'B' manufactures the tool and delivers & sales it to 'A'  with the material type as FERT whereas for 'A'  it is FHMI (Production resource tool). The problem is that both the Statergic business units are operated through SAP with same client.
    Kindly provide the soluion. Please feel free to ask any furthur clarification required.
    Thanks in advance
    Sudhir

    Hi,
    If you want to change the material type, you can try in T.code: MMAM
    But in your scenario, u just go for BOM in T.CODE: CS01( example: in a finished products how many parts are there).You can have PO for parts and SO for finished products.
    Hope this will help.
    Regards,
    Biju K

  • Changing standard material types

    Hello All,
    We are using ECC 6.0
    I want to change few settings for standard materials types like FERT, HALB, ROH and HAWA.
    For example Standard FERT does not have Purchasing view enabled but I enabled it.
    Will these settings be reset when we go for upgrade in future?
    Thanks
    George

    Hi,
    You can change settings related to std config, depending upon your clients requirement using T code OMS2. In that case once you make changes in std config then all materials are created with purchasing view.
    But it will reset after you upgrade your system in future as these are standard SAP settings.
    As our collegue mentioned it is better to create another material type instaed of changing std material type.
    Hope this will resolve your issue.
    Best Regards,
    Avinash.

  • Reg change of material type

    Dear Guys,
                      how do i change a material type after it is created in material master...?

    Hi,
    Material Type can be changed using transaction MMAM
    Menu: - Logistics > Material Management > Material Master > Material > Change Material Type
    Refer following link for the same;
    [HOWTO change the Materials Type of a material master|http://www.sap123.com/showthread.php?t=21]

  • Changes of Material type

    Hello All.
    I have created a Material master and by mistake i have put wrong Material type, so now can i change that material type for that material master.
    please suggest.
    Regards,
    Vishal

    Hi,
    Before changing material type check whether any stock is there for that material also check open purchasing & sales docs. If you are changing the material type use T.code MMAM once you change the material type valuation class of the  material  also changes.
    Regards
    Ravi shankar.
    Edited by: Ravi Shankar H N on Oct 8, 2008 11:02 AM

  • How to clear the PPC balance to change the material type?

    Dear experts,
    Our customer need to change some material type (valuation class as well) from semi-finished product to purchase part. It uses Product Cost Collector for semi-finished/finished product and never makes settlement for any PCC.
    To change the material type through MMAM requires zero stock and cleared PCC balance. So we removed the stock of the semi-finished product and settled the PCC for every month of this year.
    Since the products could have entry this year and last year, even if we settled their balances of this year, it still can not be changed the material type.
    And we do not know how to settle the PCC balance of last year because only one field YEAR can be entered on screen KK87/CO88. If I enter settleme period 11, posting period 12 and fiscal year 2007, system will give error "Period 12 is not allowed".
    But we happend to find one product has no entry this year but has balance value of last year. Its material type can be changed w/o any errors, which seems last year balance has no impact material type change. I get confused.
    Can any one advise whether I'm wrong and where?

    Hi Sharan,
    Matl Povided to Vendor stock will appear in Subcontracting scenario.
    If at all you have given some material to a subcontractor , this will be consumed automaticaly when you will recieve the ordered material from subcontractor.that is 543 movement will take place in the backgroung when u do the GR.
    In case if u need to clear the stock u can do 542 and take the stock back to unrestricted.
    Edited by: Donsandy on Jan 21, 2009 6:19 PM

  • Shall v maintain price control  for material type with plant specific ?

    Hai Guru,
                       In OMS2, we change HALB price control [valuation] as V or S.  whether shall v maintain this for plant specific.?
    Kindly guide
    With Regards
    Swetha

    Hi
    if you do not make the indicator Price control manadatory active then you can have different price indicator for each plant. However thsi indicator is never done plant specific. If you wish to have plant specific then you may have to have a new material type and again you need to control the MM01 creation for that particular plant by means of Authorisation control which is littel involved also but can be done.
    Regards

  • MMAM - change material type

    When we try to change the material type of a material we often get the following "error" messages:
    The material type cannot be changed.  The reasons for this are:
    stock already exists in the following plants
    purchase orders exists
    We want to change the material type automatically (via program) but then we need to catch these errors ---> so we need a workaround to be able to change the material type.
    Can anyone help us with this workaround ---> any known program/function/... for this issue?
    Kind regards,
    Lieselot

    I don't want to create a way around these issues.  I just want to put these actions into a program so we don't need to do them manually. 
    Kind regards,
    Lieselot

  • Change material Type - 'MMA'

    I am trying to Change Material Type using T-code - 'MMAM'.But Message is coming PO already exist.
    Problem is tat we have already created GIN for the PO & Reversed the GIN also,but still PO is not getting release to Change any data.It is giving error,that GIN already exist.
    I want to Change the MAterial Type.How can i do that.??
    Viru.

    Please note that both the new material type and the old material type must have the      
    same characteristics eg. quantity based material management is one of   
    the characteristic. The R/3 Online Help provides a very good explanation 
    on all the pre-requisites before you can change a material type.        
    (Logistics Gen>Logistics Basic Data > LO Managing Material Master Data >
    Material Master Record > Material Type > Change Material Type)          
    Please check if you have set the deletion flag for any PO's as              
    these need to be physically deleted for MMAM to work. You will also         
    need to check if there are ANY open items for this order. The purchase      
    orders need to be ARCHIVED. You should complete the invoice receipt for     
    this position BEFORE you set the deletion flag in the purchase order.       
    Also, if the material is already in stock, or if reservations or           
    purchasing documents exist for it, the following conditions must also be   
    met:                                                                       
    >The stock values of the material of the new material type must be         
    updated in the same G/L account as the stock values of the material of    
    the old material type.                                                                               
    >Quantities and values of the material of the new material type must be    
    updated in exactly the same way in all plants as quantities and values    
    of the material of the old material type.                                                                               
    >If there is a transfer requirement for the material and if quantities     
    of the material exist, the new material type must also allow the          
    material data to be maintained from the Warehouse Management view.

  • How to change Material Type

    Hi All,
    I have created new material type as ZINS ( Insurance spares ).
    Now,I have to change ZSPR ( Spares) material to ZINS material type.
    In system there are no liabilities for this material.But ,I am getting following error while executing T-code :-MMAM.
    Error :- " Change Material Type
    The material type cannot be changed.
    The reasons for this are:
    QM inspection data exists for the material. In this inspection data,
    it is defined that a plan is required for the inspection. However,
    inspection plans are not allowed for the new material type.
        Plant
        1100
        6001
    Task lists already exist for specific TL types for the material
    The new material type does not allow assignment of task lists for these TL types "
    I want to know is there any settings required while creating new material type in quality module,as this error seems to be related to Quality module.
    Please help,as this is very much urgent.
    Thanks.
    With Best Regards,
    Rajesh

    Hi Vivek and Murali,
    Thanks for your answers.
    In my question ,I mentioned that,
    In system there are no liabilities for this material.I want to know is there any settings required while creating new material type in quality module,as this error seems to be related to Quality module.
    I got answer,while creating new material type it was not assigned to in quality module.I need to assign the task list type ‘Q’ to the new Material type.
    I have done configuartion as follows, ( Path: SPRO -> Quality management -> Quality Planning -> Inspection planning -> Assign Task List Type to Material types).
    Once again thanks for your help and support.
    Regards,
    Rajesh

Maybe you are looking for

  • Sync with outlook (calendar problem)

    I used to sync and everything was all right, but now (I don't know after what) everything syncs but my calendar. I use microsoft outlook 2003 and all my app.s are up to date. Now, contacts are syncing but not calendar. any ideas? I am going insane...

  • Planning in distributed environment

    Would like to know with following environment how planning works... Lets say Shared services and Essbase are installed in Machine 1. These 2 are commonly used for multiple planning instances Planning instance 1 is in Machine 2 with locale US Planning

  • MIS report extraction for P&L and B/S  t codes

    Hi MIS report required from SAP for the following: 1. Profit & loss acct (consolidated , plant and segment wise) 2. Balance sheet we havn't configured FSV at production yet, so without this is it possible? Edited by: barnabasjh on Jul 7, 2010 12:50 P

  • Mass 'check-out'

    We wish to check out entire folders and subdirectories of files. How is this done programmatically. (We prefer using PLSQL to alter the database tables, over JAVA, right now). Naturally, this implies that we want to check the files back in batch-wise

  • Can one make a template with live links?

    I have a simple .htm file with 5 links going out, created with image map tool. I'm going to create 80 similar pages, but different names, titles etc. Is there a way to have a template with live links retained? (inserting a new jpeg image map each tim