Dear Expert,
I've done production order for multiplication last year with expected quantity 22.000 kg. This year we received from subcontractor 50.000 kg. Would you be so kind and advice the best way to updated this? It's allow to go to CO02 and change quantity from 22000 to 50000? I afraid because in component overview the component will change according to new qty but has to be the same. The GI 261 on this component was done last year
Thanks in advance,
doti_781

Hi,
If you do not want the quantity to be changed, then tick the check box of Fixed Qty for each component, this will ensure that the qty will not increase or decrease when the header qty is changed.
Hope it clarifies your query.
Regards,
Vivek

Similar Messages

  • Change Alternative Item Quantity in Production  Order BOM

    Hi Gurus,
    I woould like to ask how can I make the Alternative item quantity to become editable. As of now, the system will calculate the percentage in the BOM and default it in the Production order.
    Now I have a requirement that in the Production order Change, the user can change the quantity of the Alternative Item based on the situation with out changing the BOM. Just change in the production order. What settings do i need to change?
    Thanks,
    Raymond

    Hi,
    Can you let us know why you want the user to make the changes manually ?
    Not in front of the system at the moment, but just do an Av. Check to see if you're able to get the switch if the stock situation has changed for the alternative items.
    Based on what i know, the field will not be editable & there is no specific setting to make it editable.
    Regards,
    Vivek

  • How to get change date in Production Order ?

    Dear Friends,
    I want to know it, how to get change date in Production Order "Administration-TAB".
    F1-Help, It is displayed with "Change date for Order Master". and Structure table "CAUFVD".
    But, CAUFVD is not Transp. Table.
    Which table should I read ?
    Thanks in advance
    Yamazaki-H

    Dear Friend
    Thank you for an answer.
    It was settled.
    Best regards.

  • Table of list status changes of the production orders

    Dear.
    In which table the system store the list status changes of every production order ?
    Thanks.

    Hi,
    First go to CAUFV table input the production order get the object number
    Input this object number in JEST table and get the system status
    Input the system status in TJ02T table ,u will get the production order status

  • Change Component in Production Order

    Hi!
    I have to change materials in Production Order components before saving. Does anyone know a BADI or user-exit that i can use? I have tried so far BADI WORKORDER_UPDATE and user-exits PPCO0001 and PPCO0008 but none of them can be used for this.
    Regards,
    Zoltan

    Hi
    check the following exits related to production Order
                                                                                    CCOWB001            Customer exit for modifying menu entries                         
    COIB0001            Customer Exit for As-Built Assignment Tool                       
    COZF0001            Change purchase req. for externally processed operation          
    COZF0002            Change purchase req. for externally procured component           
    PPCO0001            Application development: PP orders                               
    PPCO0002            Check exit for setting delete mark / deletion indicator          
    PPCO0003            Check exit for order changes from sales order                    
    PPCO0004            Sort and processing exit: Mass processing orders                 
    PPCO0005            Storage location/backflushing when order is created              
    PPCO0006            Enhancement to specify defaults for fields in order header       
    PPCO0007            Exit when saving production order                                
    PPCO0008            Enhancement in the adding and changing of components             
    PPCO0009            Enhancement in goods movements for prod. process order           
    PPCO0010            Enhancement in make-to-order production - Unit of measure        
    PPCO0012            Production Order: Display/Change Order Header Data               
    PPCO0013            Change priorities of selection crit. for batch determination     
    PPCO0015            Additional check for document links from BOMs                    
    PPCO0016            Additional check for document links from master data             
    PPCO0017            Additional check for online processing of document links         
    PPCO0018            Check for changes to production order header                     
    PPCO0019            Checks for changes to order operations                           
    PPCO0021            Release Control for Automatic Batch Determination                
    PPCO0022            Determination of Production Memo                                 
    PPCO0023            Checks Changes to Order Components                               
    STATTEXT            Modification exit for formatting status text lines               
    Regards
    Anji

  • Track changes to Quantity in Production Order

    Question.
    Is there a way to track changes made to the quantity field in the Production Order. I can only find changes the order status, not to the order, or any other field for that matter.
    I also checked tables CDHDR/CDPOS but no change is recorded there either.
    Is this a missing feature?

    Fernando Garcia ,
    Try using ORDer chnage management for your production orders. I am not sure if order qty change is tracked there.
    Thanks,
    Ram

  • User Exit for Changing Quantity in Process Order , COR1, COR2

    Hi All,
    Can anyone point me towards the light in User exit related to COR1 and COR2.After the Creation of Process order  while saving i need to write a code that rounds off the quantity values.
    I tried to change the values in the below user exits but i was not succesfull.
    CCOWB001            Customer exit for modifying menu entries
    COIB0001            Customer Exit for As-Built Assignment Tool
    COZF0001            Change purchase req. for externally processed operation
    COZF0002            Change purchase req. for externally procured component
    PPCO0001            Application development: PP orders
    PPCO0002            Check exit for setting delete mark / deletion indicator
    PPCO0003            Check exit for order changes from sales order
    PPCO0004            Sort and processing exit: Mass processing orders
    PPCO0005            Storage location/backflushing when order is created
    PPCO0006            Enhancement to specify defaults for fields in order header
    PPCO0007            Exit when saving production order
    PPCO0008            Enhancement in the adding and changing of components
    PPCO0009            Enhancement in goods movements for prod. process order
    PPCO0010            Enhancement in make-to-order production - Unit of measure
    PPCO0012            Production Order: Display/Change Order Header Data
    PPCO0013            Change priorities of selection crit. for batch determination
    PPCO0015            Additional check for document links from BOMs
    PPCO0016            Additional check for document links from master data
    PPCO0017            Additional check for online processing of document links
    PPCO0018            Check for changes to production order header
    PPCO0019            Checks for changes to order operations
    PPCO0021            Release Control for Automatic Batch Determination
    PPCO0022            Determination of Production Memo
    PPCO0023            Checks Changes to Order Components
    STATTEXT            Modification exit for formatting status text lines
    Reason was the data related tp materials was not accesble at this point and residing in resb internal table .
    Any suggestions ? Ideas  ?
    Thanks in advance,
    Gowri

    Hi,
      Try with BADI <b>WORKORDER_UPDATE</b>.
    Regards

  • Issue about requirement quantity in production order

    Hello:
    Requirement quantity shows negative number when I am creating production order, as I checked its BOM it is ok,what's wrong?

    Allen,
    Check in CS03 in the item level details of that component for Co-Product check box activation. Also check in BOM whether its maintained in negative quantity. This component would also be defined with Co-product check box in MRP views.
    If the above are not true then manually someone would have changed., so would suggest you to just try creating a production order manually to check.
    Regards,
    Prasobh

  • Change BOM and Production Order

    Hello Expert,
    I have recuuring problem, hope you can lean help to me. Can you explain to me why this happen?
    we have change a component BOM in CS02, first we create change number in CC01. with effective date for 30.09.2008.
    In BOM 6083, there exist a component 10020379. we want this component to be deleted on 30.09.2008 and be replace with a new component material 10060530 effective on the date 30.09.2008. that was the new set up of the BOM of material 6083 (at this date august).
    Today (27.08.2008) we create a production order for material 6083, relesed it and when we will look at the PO Component Overview of our created PO both BOM component material 10020379 and 10060530 was present both backflushed was tick. but 10060530 component has zero req. qty compared to 10020379 it has a value on req. qty.
    why that even we create the PO in August replacement material 10060530 was exploded and included in PO since this material will be effective on 30.09.2008?
    and when we confirmed the PO via CO11N, we have a COGI error for the replacement material 10060530 "Enter Storage Location"?
    How all this happen Guru?.
    Thanks and more Power

    Hi,
    in this scenario, you can control the BOM explosion better with Revision Levels.
    say you have created the Revision Level with CC11, using the same change master which is effective from 30.08.2008.
    Every time, when you create an Order, system will pick the latest/relevant Revision level.
    If you create an Order on 01.01.2009, suppose there is a chanege again to your BOM, still at the time of confirmation/backflush system will explode the BOM as on 30.08.2008.
    Hope this helps..
    Regards,
    Siva

  • Report of List of all status changes for various production orders at a tim

    Hi,
    Can I have a standard report which shows the dates of each and every status (user & system) of a production order.
    I need to have a report for a list of productio orders at a time.
    If we go to CO03, header menu, status changes option is there, but it only caters for single production order.
    Table JCDS is available to know the dates but I need a standard one rather than a Z development.
    Or you can guide me any function module.
    Thanks,
    Kumar

    Hello,
    You will get the details of status in following table.
    JEST - for object status
    JSTO - Status Profile
    TJ02T - to Decode the status Number
    as the status data you will get from JEST is in very typical form you have to use TJ02T to find the exact status
    AM

  • Find the table name for Delivery quantity in production order

    Hi,
    Pls can you tell me what is table name for delivered quantity field in General tab for that production order number.
    With Regards,
    P.Arunkumar.

    Hi
    You can find it GR qty via following 2 Tables.
    Table AFPO Order item
    Field WEMNG - Gr Qty
              Or
    Table AUFM
    Field SHKZG (Debit Credit Indicator ) Select Debit Indicator - S
    Field KZBEW Movement type ind.- Selct F Goods movement for production order.
    Regards,
    Dhaval

  • Committed Quantity in Production Order

    when we do the availability check in production order Transaction co02 we get a screen which shows Reqmts Quantity and Committed Quantity. I just need to know in which Table these quantities are getting stored

    Not sure you asking about, but give a try to look at OITW table...

  • Control cost and control quantity in production order cost analysis

    Hi,
    When I checked the WIP value, I found there are two field, control cost and control quantity, in the cost analysis of production order which has some relationship with WIP calculation. But I do not know where the control cost from and by what the control quantity is controlled. Could anyone who know advise please?
    Regards

    Anyone who can help please?

  • Allows to change quantity in sales order lesser that already billed

    Dear All,
    I am new to SD and I have encountered an issue. Please help me finding a solution. The details are given below:
    1. I have a sales order with 1 line item with quantity 5
    2. I bill the sales order for quantity 4
    3. Someone goes and change the quantity in sales order to 2 which is wrong because an invoice of 4 has already been raised.
    4. System gives a information message telling that an invoice has already been raised for quantity 4 but the person ignores and saves the sales order.
    I would like system to display an error message and stop the person from saving the sales order in this scenario.
    Kindly let me know where can I make the changes in configuration to achieve the same.
    Regards,
    Rajesh

    Hi Rajesh,
    Thats why the above solution has not worked. The above solution is for delivery related orders.
    I have tried the same scenerio as yours, I mean the order related Billing and Once the billing is done then I again open the order and tried to change the quantity.
    System give me the red error
    For item 000010, the following has already been invoiced:                   3 PC
    Message no. V1518
    That was the error Rajesh, As per my understanding we cant customize V1 Messages. These are hard coded in the progam.
    Please contact to your ABAPer and ask him/her to analyse the process in Debuging mode.
    One more interesting thing I have found
    My credit memo request already billed for 3 quantities
    When I am tring to decrese the quantity, it gives me red error V1518.
    But when I increase the quantity its give me same error V1518 but only as information, after enter it accept.
    I think it really needs technical analysis.
    Hope this helps,
    Regards,
    MT
    Edited by: M T on Mar 1, 2010 6:44 PM

  • Component quantity in production order

    Hi,
    For my finished product component quantity in BOM is 1.386 for the base quantity 100.When am creating the production order for 100 in my component overview of  production order screen it is showing component quanitity as 2 instead of 1.386.
    Since am not using any rounding value,rounding profile and scrap nad upto 3 decimals allowed in CUNI for particular UOM.
    Thanks
    P.Srinivasan
    Edited by: srinivasan ponnurangam on Dec 23, 2011 12:33 AM
    Edited by: srinivasan ponnurangam on Dec 23, 2011 12:35 AM

    As I understand even if production order screen it is showing component quanitity as 2 instead of 1.386 ,Internally it is stored as 1.386 only.
    So as per knowledge it should not affect anything.
    Refer Note 931971 - Decimal places in stocks and stock postings
    Also refer
    Problem with item/component quantity in BOM

Maybe you are looking for

  • Export and Import of Roles and Privileges

    Hi, We're nearing the end of our development phase and are now preparing for initial load in our QA / Test environment. Is there a way to export the Roles and Privilege metadata from one environment to import them into the other. The Staging guide st

  • Stopwatch - doesn't freeze, but goes into "power save"

    What am I missing? I have started using my iPod's stopwatch to time my daily walks -- and, lately, after walking a bit, I look down and the screen is black. I press a key to bring it back to life, and the stopwatch has STOPPED. What good is that? I r

  • What app do I need to replace adobe

    When I go to watch a video or tv program it tells me I need adobe, but I know u can't down load it on iPads so what other program/app do I use? I did buy photon app but that doesn't seem to be working!

  • Upgrading Fifth generation iPod to software version 1.2.1

    the latest software version for the fifth-gen iPod has been out for a while now, but i havent been able to upgade it because itunes keeps on telling me that "the iPod cannot be updated because it contains files that are in use by another application.

  • Sending e-mail alerts in Microsoft Project 2010

    I'm using Microsoft Project 2010 in creating my project. While adding my tasks I want to be able to send an e-mail alert to my resources indicating a task is coming up or the task is overdue. What do I have to do?