Change Request for records in table

Dear all,
I want to create a Change Request to include all the records in my Z table, by using the SM30,
I don't want to change record by record, as the table includes hundreds of record.
Could any body tell me?
Best Regads,
Jack

Hi Jack,
Including Table Entries in a Transport Request   
Enter a transport request.
Select the table entries you wish to transport.
Assign the selected table entries to the transport request using the Include in request function.
This marks the entries for inclusion in the transport request.
Save your changes.
The selected table entries are added to the transport request.
You can display all table entries which are either marked for inclusion or already included in the transport request by choosing Choose ® All in request.
You can display all table entries which are not included in the transport request by choosing Choose ® All not in request.
Regards,
Deepak Kori

Similar Messages

  • How do I AUTOMATICALLY generate Transport request for a Z table data?

    Hello friends,
    I would like to automatically create/generate a transport request for a Z table every time I change, add or delete data in that table.
    Currently, every time I modify data in the Z table, I need to go and manually create a transport request and then indicate keys for the row(s) which were modified. I find this a tedious, time consuming, and error prone process.
    So I would like to automate this process. That is to say, the transport request is generated for the rows that I modified. The same way as is done when you change a program. It automatically prompts you for a transport request thingy.
    Any ideas?
    Your help is greatly appreciated.

    You need to make the table contents transportable by creating a "table maintenance generator" in SE11 under Utilities -> Table maintenance generator.
    In that screen for the section "Dialog data transport Details" the "Standard Recording Routine" option should be selected.
    Then only will the system ask for Transport request when entering data through the generated maintenance view in SM30.
    Also change the "delivery class' in the table attributes to 'C' - Customizing table

  • Usage of Company code field in the Change Request for Company

    Hi,
    Would like to know the usage of - Company code field in the UI for Change request for Company.
    1. If a new Company is created, can i assign the company code directly in the UI, will the assignment also replicated to backend in this case?
    2. In case of new Company creation, is it possible for multiple company code assignments?
    3. Is it possible to to pick the existing Company from the F4 list in the CR and assign the company code in the CR? How about the replication work in this case?
    Please share your comments, Thank you.

    Thanks Sanjay.
    Just to summarize and a bit more specific, here is my understanding:
    1. (a). You have mentioned that we can assign new company code also - does this mean i can select            a company code which is not in the F4 list? In such case, how will be the assignment                   replicated? It should ideally create a company code in the backend before the assignment is           processed.
        (b). Usually, if a new company code is created in backend, i need to load that in to MDG tables                 such that it will be active in MDG F4 list, for Company assignments in the Change request.
    2.      Understood
    3.      In the Change request, if i pick existing company from F4 values and edit company related data,          it will be replicated accordingly.
             In the same CR, if i give some value in the company code data, the replication will result in one          more assignment added to the company, so as on date, SAP has given the option of only                    additional assignments to the existing assignments.

  • How to set a change pointer for a perticular table?

    Hi,
    Please let me know how to set a change pointer for a perticular table.

    what do you mean by 'change pointer'? normally this idiom is used for sending ÍDOCs from one system/client/org-unit to another ...
    do you generally want to record changes to a specific table? then set parameter rec/client using RZ10 for your instance profiles and restart the instances in order for the parameter to take effect.
    set the table to 'record all changes' using SE11.
    you might re-consider if the table has a lot of  data and is accessed very often for performance-resons.
    change protocols can be evaluated using tx, SCU3.

  • This is regarding creation of change pointers for a particular table?

    Hi to all,
    Here is my requirement,
    How to create change pointers for a given table.
    i know that change pointers record changes of master data at field level......
    here now i have to create change pointers for a given table..
    how to do this,......\
    regards,
    swami

    Configuration steps :
    BD53 -> create reduced message type (use MATMAS as your reference for material master records). Select tables
    BD52 -> specify fields to track (use fieldname KEY for new entries)
    BD50 -> activate change pointers for new reduced message type
    BD61 -> activate change ponter generally (only if not already done) Make sure if this is not already active that you deselect the default enteries in BD50 for the message types you don't care about
    The view BDCPV will now contain change pointer entries for the master data that has change or been created
    Use function modules
    CHANGE_POINTERS_READ                - read new unprocessed change pointers
    CHANGE_POINTERS_STATUS_WRITE - mark change pointers as processed
    Hope it helps.
    Chang

  • Create a change request for multiple customers from spreadsheet

    Hello Experts,
    1.We have a spreadsheet with 100's of Customer data maintained in it , can we create a change request by downloading data from spreadsheet directly instead of manually entering the data in the CR. Also can we create a single change request for multiple Create customers.
    2.Can we create CR's automatically , lets say we have 100's of customer data loaded into MDG hub by Data Services using DEBMAS Idoc , can this create automatic CR's , is this possible.
    Thanks.

    Dear Collins,
    1.We have a spreadsheet with 100's of Customer data maintained in it , can we create a change request by downloading data from spreadsheet directly instead of manually entering the data in the CR. Also can we create a single change request for multiple Create customers.
    Answer:there are various options are available in MDG to process multiple material as shown below
    you can down load the customers using file down load funcationality and same change,upload the customers using the file Upload process.
    you can create a single CR for muntiple customers options are shown below.
    2..Can we create CR's automatically , lets say we have 100's of customer data loaded into MDG hub by Data Services using DEBMAS Idoc , can this create automatic CR's , is this possible.
    Answer:Yes you can create CR automatically using DTIMPORT tcode and some configuration needs to be done further reading go to the link SAP Master Data Governance - SAP Library
    regards
    shankar

  • Change documents for customer Z table - serious help wanted

    Hi all,
    I am no beginner and I don't expect any comments from beginners.
    Situation: My customer wants to replace the material valuation transactions MRN1 MRN2 MRN3 due to bad performance and locking problems with own developed programs.
    The valuation results will be stored in a customer Z-Table on a monthly base. For auditing and transparency purposes, this Z-table has to get a change object and the update routines will have to write change documents.
    Due to the expected size of the new Z-table, it is not advisable to simply switsch on table logging.
    In this huge project (and in none I participated!) nobody ever implemented the change document process for a Z-table. <b>BUT EVERYBODY CAN TELL YOU THI IS NO PROBLEM AT ALL.</b>
    I read some documentation at SAP and serached for threads or blogs here. I could not find anything desribing that in depth.
    So before I start, I'd be happy to get some hints from people who created own change documents and implemented the process. Links to documentation and other helpful pages are also welcome.
    If I can keep the process simple, I'd like to create a BLOG on this - because I think, in the future it will get more and more difficult to pass the auditing process with undocumented features and uncontrolled table changes.
    TIA.
    Regards,
    Clemens

    Hi,
    Please check this thread.
    http://www.sapdevelopment.co.uk/tips/changedoc/cd_createch.htm
    Once you create your change document object using generate update pgm option then  please check the WRITE document fm.
    I have done this long back i am updating CDHDR and CDPOS for 2 table YATT and YATTPLANTS. Here YATT have single record (header table) and YATTPLANTS have multiple records (item table)
    function yatt_write_document           .
      call function 'CHANGEDOCUMENT_OPEN'
        exporting
          objectclass             = 'YATT           '
          objectid                = objectid
          planned_change_number   = planned_change_number
          planned_or_real_changes = planned_or_real_changes
        exceptions
          sequence_invalid        = 1
          others                  = 2.
      case sy-subrc.
        when 0.                                   "ok.
        when 1. message a600 with 'SEQUENCE INVALID'.
        when 2. message a600 with 'OPEN ERROR'.
      endcase.
    if upd_yctc                           ne space.
       call function 'CHANGEDOCUMENT_SINGLE_CASE'
         exporting
           tablename              = 'YATT                          '
           workarea_old           = o_yatt
           workarea_new           = n_yatt
            change_indicator       = upd_yattc
            docu_delete            = 'X'
         exceptions
           nametab_error          = 1
           open_missing           = 2
           position_insert_failed = 3
           others                 = 4.
        case sy-subrc.
          when 0.                                "ok.
          when 1. message a600 with 'NAMETAB-ERROR'.
          when 2. message a600 with 'OPEN MISSING'.
          when 3. message a600 with 'INSERT ERROR'.
          when 4. message a600 with 'SINGLE ERROR'.
        endcase.
      endif.
      if upd_yctcauthplnts                  ne space.
        call function 'CHANGEDOCUMENT_MULTIPLE_CASE'
          exporting
            tablename              = 'YATTPLANTS                 '
            change_indicator       = upd_yattplants
            docu_delete            = 'X'
          tables
            table_old              = yyattplants
            table_new              = xyattplants
         exceptions
           nametab_error          = 1
           open_missing           = 2
           position_insert_failed = 3
           others                 = 4.
        case sy-subrc.
          when 0.                                "ok.
          when 1. message a600 with 'NAMETAB-ERROR'.
          when 2. message a600 with 'OPEN MISSING'.
          when 3. message a600 with 'INSERT ERROR'.
          when 4. message a600 with 'MULTIPLE ERROR'.
        endcase.
      endif.
      call function 'CHANGEDOCUMENT_CLOSE'
        exporting
          objectclass             = 'YATT           '
          objectid                = objectid
          date_of_change          = udate
          time_of_change          = utime
          tcode                   = tcode
          username                = username
          object_change_indicator = object_change_indicator
          no_change_pointers      = no_change_pointers
        exceptions
          header_insert_failed    = 1
          object_invalid          = 2
          open_missing            = 3
          no_position_inserted    = 4
          others                  = 5.
      case sy-subrc.
        when 0.                                   "ok.
        when 1. message a600 with 'INSERT HEADER FAILED'.
        when 2. message a600 with 'OBJECT INVALID'.
        when 3. message a600 with 'OPEN MISSING'.
    *    WHEN 4. MESSAGE A600 WITH 'NO_POSITION_INSERTED'.
    * do not abort, if positions are not inserted!!!
        when 5. message a600 with 'CLOSE ERROR'.
      endcase.
    endfunction.

  • IDOC trigger using Z change pointers for standard SAP table

    For IDOC trigger, is using custom change pointers on standard SAP master data tables, a good idea? A seasoned abaper told me "it will mess with the standard" and further told to go with scheduled job.
    So, for example, say that my data for table T001K is updated via transports in PRD and I need to transfer this updated data via IDOC to an external system. Since there is no standard message type for this data, I will create a new one. Further, I will create a new change pointer for table T001K (it already has six fields with their data elements activated for Change Documents). Then I link the message type and the new change pointer. And so on an so forth. I have followed the procedure given here:SAP Tips: A to Z of Custom Change Pointer
    Now, the question is, will this be a good idea to capture data and trigger IDOC? Or a batch program with calls to standard FM to read CDHRD/CDPOS be a more suitable option.
    I need to know if a near instantaneous data transfer (and an effecient one as far as the system performance and reliability is concerned) can be acheived. If there is any other way of doing this, I am not aware of it!
    Any one has any input/experience on this?

    Hi Viktor,
    I think the batch program approach would be a good solution as the by this way you are taking matter into your own hands rather giving control to the SAP framework because you may have to test out the other approach as to how the standard SAP framework is behaving for custom change pointers.
    Thanks,
    Ravi

  • Creating a custom change document for a standard table field

    Hi
    Is it possible to create a change document for a field in a standard table?
    I have searched the forum and only found threads about creating change document to a custom table.
    Will the creation of change documents to a standard SAP table be a modification?
    Thanks.
    Regards
    Sowbhagya.L

    Yes it will be a modification on standard table, but you can always create change document for any field by assigning it to custom change object.
    Regards,
    Krishna.

  • Change documents for a Z table

    Hi,
    We have a Ztable with 4 fields, Due to some business reasons.. . We have given access to users for changing the contents of the table. Now For audit purpose Customer wants to track the changes made to the table. I came know that this can be achieved by using the change documents concept. I am little confused in using this concept. After clicking on the generate update program, system will ask us to give an include name and functiona group. After giving these two system will create include object as <change document object>_write_document. This Include inturn calls some more includes like F<K4>CDC,F<K4>CDT,F<K4>CDF,F<K4>CDV.
    Here my questions are
    1. Wher do we need to write our owncoding for capturing the changes?
    2. is it possible to share the sample code starting from the First Include <changedocument>_Write_Document to ending.
    3. Does this change document functionality will be called automoatically when we use Transaction SM30(Table maintainance) for changing the contents of the tables?
    4. What is the difference between single case and Multiple case. My scenario falls into single/Multiple?
    Awaiiting for all the expert responses
    Thanks and Best Regards
    Jagadeesh Ambati

    Hi Srinivas,
    you can activate in DDIC that your entry changes will be logged.
    Go to SE11 -> Your Tablenname -> CHANGE
    Button TechnicalSettings -> Activate checkbox Log data changes.
    From now on any chenge will be logged in table DBTABLOG.
    Kind Regards
    Henner

  • Multiple Change Requests for project cycle

    I have a question.. if we have multiple chane requests/documents for a project cycle , how will the project cycle proceed??
    i have two CRs for my implementation cycle , now how should i proceed my implementation cycle, since all the changes are of type SDMJ and i want all my changes to be imported to PRD together??
    Please help

    Hello,
    i had the same problem few weeks ago. I couldn't find the Change request Tab in Solar_project_admin
    I fixed it by following : SAP note : 802793
    The note explain how to re assign the client to manage change request management.
    We folow the note, then the missing tab appear
    Regards

  • How to find the workflow for Change Request for the PO's

    Hi All,
    We have a PO which is pending and we can't receipt it again nor make payment on this. After checking the Approval history for that PO we found that the change request has been made. The change request was to change the amount to be paid to R39196 instead of R58237.00. We don't know where to check the workflow for the change request to identify the cause.
    what i need to know is how to find the workflow for that change request? The other workflows can be checked using the po_header_id for the PO's but i am confused with the change request workflow
    Your input will be highly appreciated.
    Thanks in advance
    Rgds,
    Sonia

    For 11.5.10.2 run this query to determine the keys to search on:
    Select wf_item_type, wf_item_key from APPS.po_change_requests where document_type = 'PO' and Document_num = 'put-PO-number-here'
    Then use the keys returned by the query to look up the Workflow in
    Workflow Administrator Web Applications / Administrator Workflow / Status Monitor
    Search using the results returned in fields "Type Internal Name" and "Item Key" in Status Monitor
    The query for change requests on a specific Requisition would be:
    Select wf_item_type, wf_item_key from APPS.po_change_requests where document_type = 'REQ' and Document_num = 'put-Req-number-here'

  • Error in creating Transport Request for a view table

    Hello all,
    I have an ECC IDES 6.0 system named EC1 and another one which is ECC EhP4 IDES named EA1 which I have just installed.
    One of my requesters has a view table named ZVAITM_TBLE in EC1 and she wants it to be transported to EA1.
    So I created a workbench transport in SE10 and included the following:
    PgmID = R3TR
    Obj = VDAT
    Object name = ZVAITM_TBLE
    But when I press enter, I encountered the following error:
    No object definition exists for Customizing object ZVAITM_TBLE
    Message no. TK427
    Diagnosis
    The Customizing object R3TR VDAT ZVAITM_TBLE is not defined in the tables of the Change and Transport System.
    This means that you cannot use the Transport Organizer to edit it.
    System Response
    The function terminates.
    Procedure
    First check whether the name of the object is correct. Then you (or the system administrator) should check the object definition, to ensure that the object was created correctly (transaction SOBJ).
    If the object does not exist, then create it or delete it from the request/task.
    I am new to transports so I have no idea how to proceed.
    Please advise.
    Thanks a lot!
    Cha Cha

    Hello Cha,
    Kindly open this custom table using SM30 and try creating a transport request from there.
    Regards
    Vivek

  • How to change colors for record working time calendar

    Hi,
    I would like to change the colors in the calendar displayed in record working time based on some conditions.
    How do i do that is there any BADI associated with that
    Thanks
    Bala Duvvuri

    Hi Bala ,
    Yes its possible to change that .
    You need to implement BADI for this ..
    BADI name : "PT_ABS_REQ"
    In the BADI "PT_ABS_REQ"   interface "IF_EX_PT_ABS_REQ" you can find the method
    "SET_CALENDAR_COLOR" in that you can set the colure for the Absent type ......
    Adjust Colors of Calendar and Team Calendar
    Functionality
    You can use this method to change the colors in the team calendar.
    In the standard system, the different statuses for requests have different colors. You can use this method to differentiate the colors of requests depending on the following aspects:
    Status of requests (status)
    Action that an employee has executed: new request, delete, change (UIA operation)
    Subtype of absence (SUBTY)
    Full-day or partial-day absence (BEGMT, where BEGMT = 0 signifies a full-day absence)
    Application mode ( mode). You specify the application mode in the Select Employees for the Team Calendar IMG activity.
    Color Display of Status of Leave Requests(COLORS_ACTIVE). You specify this status in the Specify How Leave Is Displayed and Default Values IMG activity.
    Available Colors
    You have a choice of 16 colors. The 16 colors are hard coded, that is, you cannot change them or add other ones.
    The available colors are stored with their RGB value as constants of the CL_PT_REQ_CONST class. Use these constants if you want to change the colors.
    Notes
    If you change the colors in the team calendar, you should also adapt the legend accordingly. You can use the Adjust Legend for Calendar and Team Calendar method to do so.
    Hope this work!!!

  • Creating the spool request for the internal table data

    Hi..
    I am little confused with the function module used for creating the spool request.
    well...I am practicing the ALV report and sending the that report to the spool.
    I  ve used the FM SLVC_TABLE_PS_TO_SPOOL.
    this is the way i defined the internal table.
    Data:
    begin of imat occurs 0,
    matnr like marav-matnr,
    maktx like marav-maktx,
    matkl like marav-matkl,                     
    ntgew like marav-ntgew,
    gewei like marav-gewei,
    end of imat.
    data i_lines type sy-tfill
    and i declared..
    describe table imat lines i_lines.
    then i given the value for i_file_length as i_lines in the export paramet of the FM SLVC_TABLE_PS_TO_SPOOL.
    CALL FUNCTION 'SLVC_TABLE_PS_TO_SPOOL'
        EXPORTING
          i_file_length            = i_lines
       IMPORTING
         E_SPOOLID                = spoolid
        tables
          it_textdata              = imat
    when i executed it shows the list and wen going back it shows the runtime error as
    CALL_FUNCTION_CONFLICT_LENG  - Type conflict when calling a function module (field length).
    please provide me some solutions.
    thanks in advance.
    etienne.

    Hi satyajit,
    Thanks for your response....but the fields in my internal table "IMAT" is not compatible with the structure LVC_S_1022 as it has it componenrt - LINE.
    so how can i define my internal table IMAT as type lvc_s_1022 as you suggested.
    thanks in advance.
    etienne.