Change Resources in a Process order operation

Hello
Is there any way to change a resource in a process order operation?, I have 5 machines, but sometimes I use the machine1 and machine2 to produce the material A, but if i dont have capacity to produce or if one machine is not working, I could use another machines. I know i could use products versions, but if I do thar, there will be a lot of convinations.
Thank you in advance.

Dear Saly,
as correctly said by Caetano in standard SAP the only tool to change work center in production orders is in leveling activity through CM21 (graphics or tabelar - CM21 , CM22).
In this strument (CM21) according to customizing setting in strategy profile (belonging to overall profile)
you can change resource through drag / drop method or (with special setting in strategy profile)  insering manually a new resourse.
As alternative tool is possible to create a custom report and change work center using a BI custom using a filter tool present in the production order after go to operation details. Unfortunaltely in the standard SAP there isn't a bapi/fm (released by SAP)  to change work center in production order.
Let me know if i've been useful for you.
Daniele

Similar Messages

  • Process Order operation scheduling duration calculation

    Hi
    We have following formula has been maintained for processing time calculation in resource.
    Machine * ( Operation quantity / Base quantity / Operation splits ) + Setup + Change-over
    As per above formula for following procee order qty and time, SAP caulates time.
    Opeartion qty - 100,
    Base qty - 100,
    Op split - 1
    Machine - 0.5 hrs (30 Mins)
    Processing time calculated as 30 mins (.5hrs)
    When I schedule the process order with same resource for same qty and machine time, processing time is calculated as 33 mins. We dont have maintained any floats in scheduling margin key in material master. We dont have any wait times also.
    Can you please let us know why process order operation is having 3 mins tolerance? Any idea where such settings has been maintained?
    Any pointers will be helpful.
    Edited by: nilesh sankpal on Dec 8, 2011 5:47 AM

    Hi Mangalraj,
    Thanks for your reply.
    We have not maintained ay reduction levels in OPUZ for plant and order type combination.
    In resource, we have 2 hrs break time and total operating time is 18.50 hrs.
    I got following SAP help link for calculation of duration for processing time.
    http://help.sap.com/saphelp_46c/helpdata/en/b1/c04387439a11d189410000e829fbbd/content.htm
    Is processing time is calculated based on following formula.
    Processing time u2013 Calculated Processing time * (1+ (Length of break / Operating time)
    Can you please correct my understanding here?
    Thanks in advance.
    Nilesh

  • Resource selection in process order

    Dear Experts,
                         I have a scenario where I want to group similar resources under specific resource types and finally arrive at a situation where if I try to change the resource in an order from the drop-down menu in the resource field, it only shows those particular resources which belong to the same category. Can anybody suggest a way to map this ?
                        Thanx in anticipation.
    Regards
    Sm.

    Hi
    This can be achieved by using Work center class type 019.
    For example if you have manual lathe machine and automatic lathe machine which can be used to do the same the operaion. Then the resource can be selected after creating the process order based on availability.
    1. Create a class type 019 and assign the required characteristics of the work center.
    2. Create a resource using CRC1 and Goto Extras-->Clasification and assign the class created.
    3. Create Recipe.
    4. Select the operation in the recipe and  click on the resource selection criteria radio button in the bottom menu and mention the selection criteria.
    5. Create a process order and if more than one work center is satifying the criteria mentioned in the recipe then you can change the resouce in process order by cliking execute resource selection.
    Regards
    S.Senthil

  • Process order operation information

    Dear Experts,
    I want to know the name of table from where I can get information of process order no., process order status and the operations which are still to be confirmed for the order. I think I will have to create a view by using two tables but let me know which tables should I refer.
    Thanks in advance.
    Prashant

    Dear
    Find below the SAP tabel  for your report requirement :
    Order tables :
    AUFK Process  order headers
    AFKO Order header data PP orders
    AFPO Order item
    AFVC Order operations
    AFVV Quantities/dates/values in the operation
    AFVU User fields of the operation
    AFFL Work order sequence
    AFFH PRT assignment data for the work order(routing)
    JSTO Status profile
    JEST Object status
    AFRU Order completion confirmations
    Process Order operation tabel :
    PLAS Task list - selection of operations/activities
    PLFH Task list - production resources/tools
    PLFL Task list - sequences
    Order and Operaton syetm Status :  SAP Table and field  : JEST-OBJNR 
    1.Orders/Operation  with status CRTD : JEST-STAT = I0001 .
    2.Orders/operation  with status REL/PREL : JEST-STAT = I0002 /I0042
    3. Orders with status MSPT  : JEST-STAT = I0004
    4. Orders with status PRC  : JEST-STAT = I0016
    5. Orders with status DLV/PDLV  : JEST-STAT = I0012
    6. Orders/operation  with status CNF/PCNF  : JEST-STAT = I0009/I0010
    7. Orders with status GMPS  : JEST-STAT = I0026
    8. Orders with status TECO : JEST-STAT = I0045
    9. . Orders with status DLFL : JEST-STAT = I0076
    Hope this will help you to include required table in your BI report
    Regards
    JH
    Edited by: Jiaul Haque on Jun 3, 2010 9:12 AM

  • Changing material number when Process Order is released

    Hello,
    We have a scenario in which the material number of a process order may need to be changed after the process order is released.  We will have both in process and post production inspection types assigned to this order, and both inspection lots are created at process order release.  We also will have a batch number created at process order release. 
    When recording test results in the inspection lot before a process order has been confirmed, the users may identify that the material number should be different.  We would like a way to be able to either change the material number in the process order (and inspection lots).  We know this involves a lot of updates (master data changes to the existing process order and inspection lots).  Currently, there is no way to transfer information to a new material number without receiving product in and performing a usage decision in the post production inspection lot to transfer to a new material number. 
    The client has implemented all modules, except PP (which we are in the process of now).  We know that Variant Configuration would have been the right solution for this, but this is not an option since MM is already implemented. 
    If you have any suggestions, please reply. 
    Thanks in advance.

    Hi Prasobh,
    The exact scenario is as follows:
    1. A semi finished good will be used as a component to produce the finished good.
    2. This semi finished good will have treatments added to it, and quality inspection will be performed as treatments are added. 
    3. Inspections will occur several times as treatments are added.  If during one of these inspections, material is out of spec, and the blend should be transferred to another material number, we need to be able to change to another material number.  To have a customization where material number is changed in all of the relevant PP and QM tables seems risky. 
    This is why we can't really use material classification.  We also do not have the option to use VC bc the MM module is already implemented. 
    Thanks.

  • FM or BAPI to Modify or Delete Process Order Operations (COR2)

    Hi Experts,
    As a part of Process Order Migration, we have a requirement where in we need to pass the confirmation quantity of the Old Process Order number to the Unloading point field (ABLAD) in the Process Order Operation details and set that operation as marked for deletion.
    Please suggest if you have come across similar scenarios.
    Thanks in advance,
    Anand

    Hi Anand
    Try This BAPI_PRODORD_SET_DELETION_FLAG and it will work for your requirement.
    Thanks,
    Adil

  • User Status Profile for Process Order Operations

    Hello Experts.
    I have a need to set up a User Status at the Process Order Operation level that will prevent operation confirmation when the status is Active .
    I have been successful at the following:
       --- Created a new Status Profile (transaction BS02),
       --- Creating a u201CHoldu201D status,
       --- Defined the Influence on Business Transactions,
       --- Set the allowed Object Types for the profile.
       --- In an individual Process Order operation, I can now select the Status Profile, and set the Hold status, and it functions correctly.
    My problem is that I canu2019t figure out how to set my new profile as a default for Process Order Operations.  For Production Orders, this is done in the IMG definition for the Order Type (transaction OPJH), updating field T003O-VRG_STSMA.  However the Order Type definition for Process orders (transaction CORN) only has a field for a status profile at the header level.  Iu2019ve searched through Configuration and the Recipe, and the Production Version, and the Control Key, but can find no where to set the default status profile for a Process Order Operation..
    As a final desperate act, I manually edited a T003O record for a Process Order Type in our test system, but even this failed to set a default Operation Status Profile for subsequently created Process Orders.
    If you have any knowledge about this, then please help.

    As of this date, we have still not implemented a fix, but I did get some information from someone else who has.
    I'll post his information here for all to see.  Hope you find it helpful.
    From: Joe
    Yes we managed to do it.
    After several false starts and CMOD/projects which suffered because only the default keys (for order number, aufpl etc) were in place and not the actual, we coded up the IN_UPDATE method in the WORKORDER_UPDATE badi. This gives us the final format after the DB save (but before the commit). The update of the STATUS using the SAP std function module was actioned successfully but the status profile was not actually passed through. We assumed that this was because of the update task - so we introduced an INSERT into JSTO instead (a bit naughty I know, but desperate needs etc). If you require anything more let me know.
    Best Regards
    Joe

  • BAPI_PROCORD_CHANGE for process order operation level change

    Hi,
    Can any buddy tell me how to change operation dates in process order with following requirement:
    Process order scheduling type is 'Forward',
    1st step, read operation start dates 'Earliest Dates' and 'Latest Dates',
    2nd step, change operation 'Earliest Dates' and 'Latest Dates' directly, this step can't be done in foreground,
    Can use BAPI_PROCORD_CHANGE to update operation dates directly?
    Best Regards
    Amy

    Hi Amy
    BAPI_PROCORD_CHANGE cannot be used to change operations.
    According to note 1694267 you can use the remote-enabled function module CO_SE_PRODORD_CHANGE that is released by the customer to change the order header, sequences, operations and production resource/tool. See the detailed documentation for the function module.
    BR
    Caetano

  • Change material code in process order or delete process order

    Hi experts,
    While creating a process order in COR1 transaction code, wrong material code was entered.
    Can we change the material code in process order.  If not, what is the complete procedure to cancel or delete the process order.
    Request you to revert.
    Thanks in Advance.
    Regards,
    Farha.

    Dear ,
    One the Process Order has been created with any material either it is wrong code or correct code , it can not be deleted .If it wrong code , then do not  perfom goods Issue -MIGO-261 or through Backflash  and also operation confirmation etc .
    If Goods Issue , Confirmation happend then you need to reverse those txn once again .
    In that case the best oiption will be goto COR2-Enter the Process Order -Select Process Order from Header -Restrict Processing -Choose Technically Complete .
    Now , once you did TECO , then there will not be any farther txanationl posting like Goods Issue , confirmation will not be possible .Likewise , you can also Lock or make set CLOSE  from COR2 in case there is no WIP , Variance .
    Hope this is clear
    Regards
    JH

  • Table to find the phase number in process order operation

    Hello All,
    Is there a way to find the table for phase details which are assigned to operation in a process order.
    Regards,
    Rohit

    Hi Rohit samant,
    Go to Process order Change or Display mode ie Tcode : COR2 or COR3.
    Enter the process order no , click on "Operation Overview (F6)", Click on the Phase field on any one operation, Click "F1", the Performance Assistance Screen will be displayed, Click Technical Details, you can get all details, like programe Name, Status, Table Name, Fieldname & all Technical details.
    I hope the above information is as per your request, Hence Reward Points,
    Regards,
    Nayeem Ahamed

  • Process order operation

    Hi
    In Process order we are using Operation & Phases in master recipe.
    Standard values are giving to phases only.
    Individual Confirmation (COR6) are performing using Phases only..
    Process instructions are also giving to phases only.
    For  creating phases operation is required( superior operation)
    Just i want to know  where these operations will be used in a process order  other than this.
    I want  to know the difference between Primary & Secondary resource and their application in Process order..as these terms are not there in REM/Discrete Mfg..
    Regards,
    srihari.

    Hello Shrihari,
    What you have observed is right.
    In process order processing we need to use the phases instead of operations in production order eg. when you want to do the partial confirmation, you need to do it for the phases and not the operations.the GI of components( if attached to the Phase )will then take place at that time.
    About primary and secondary resources I can give you a practical example.
    If you consider a washing machine as a resource then it has two parts the Wash tub and the drying tub. You can consider the washing machine as the primary resource and the washing tubs and drying tubs as secondary resources of the washing machine.
    Hope this helps you.
    Award points if benefitted.
    Hemant

  • Editing of scheduled dates in Process Order Operations

    Hello,
    I have a requirement, in which the client would like to change the Scheduled dates in the operation details of a process order.
    In the header screen of a process order, if we change the basic start / finish dates (depending on forward or backward scheduling), and reschedule the process order, the process order is rescheduled, with the new dates.
    The client's requirement is, they should be able to change the Scheduled dates in the tab "Operation - Dates", of the "Operation overview" screen, in a process order. Normally the field is not editable, and the system calculates the dates, based on the start / finish dates, entered in the process order header.
    I would like to know, what is the way out, to meet this requirement.
    Thanks.

    Hi,
    As every body else is explaining it is not possible for standard SAP ,  as of normal business or any business scenario why would a client want to change the operation dates from Production order ( still not understood.....)
    There are two options to do that:
    1) Copy the whole transaction ( programmes ) into some Z - transaction and in the programme you can change the object ( CO_VG_OPR_*) from being grayed out.
    This will alllow you to change the dates.
    2) you can go for enhancement with the following FM
        BAPI_ALM_ORDER_MAINTAIN
    I suggest you to clear these things with client.These things require more of ABAP work.
    And as said changing the standard behaviour of the system can cause performance issues.
    Please close the thread if satisfied.
    prakash

  • Resource in a process order

    Assume that process order no is 100. The master recipe grp is 50000000. There are 5 operations in the recipe (10 to 50) & the last operation is milestone operation. All the operations & the phases in the recipe are based on the same resorce for ex---machine1.
    Suppose after confirmation (operation-50 which is milestone operation), (conf no--1000001),  how can I get back the resource used for the order 100 from the order no????
    <b>which tables will give me the resource no????</b>
    This is required to me for report development. Can anybody guide me on this front.???
    Regards,
    Manish

    Thanks for the quickest reply.
    Exactly the same is required by me. I skipped off from my mind that the object id is the tech name for resource which can be seen admin data tab page in basic data of resource.
    But ur timely help is  definately benefial. Thanks once again for the same & hoping similar responses from you in future too.
    Thanks & Regards,
    Manish

  • Changing BOM-items in Process Order not allowed

    that Hello,
    Mi client is asking me if it is posible, once created a Process Order, upon modifying the order (COR2), that the user can not change any of the cuantities and batches of the material list (BOM) updated in the Process Order.
    Is there any way one can protect the material list from being modified once created, or once liberated the order?
    Is it posible, moreover to just protect the BOM ítems updated in the Process order but let the option open to add exta BOM ítems manually.
    Is there a userexit or a Badi one can use to acomplish this?
    Thanks for any reply.
    Aart

    Hi Aart,
    Yes, you can use BADI to protect the BOM items from not to change the BOM items in Process order.
    In one of our project we have taken the help from the ABAPer, has has done the same thing.
    Then we have acheived the same requirement.
    You check with the ABAPer, he will help you for the requirement.
    Thanks

  • Fm for processing time in processing order operation

    Hi
    I need to obtain processing time from processing order's operations. ASAIK there are some formulas to calculate this but i cannot find it. Could you give me some tips about that? Is there a fm or bapi to obtaint this?
    regards
    Wojciech.

    Hi,
    Please let me know what is a processing order to which module it belongs so that I can help you out
    Thanks & Regards,
    Chandralekha.