Change/restart start of cycle for strategy maintenance plan MPLA- STADT

Dear experts,
is it possible to change the start of cycle date in strategy maintenance plan (MPLA- STADT).
The start of cycle was entered incorrectly into the strategy maintenance plan (IP42)
Maint. plan was already started
...and called: Service orders are already created
The existing maint. plan should be used with a new cycle start date.
By using u201Crestartu201D in IP10, a new start of cycle date is entered and the orders are called correctly.
But the cycle start date is not updated in the data base: MPLA- STADT
Why?
Regards,
Philipp

Dear all,
I opened a OSS message. SAP replied that this is not covered by SAP standard. so system works as designed.
SAP:
The described behaviour is the SAP/R3 standard and works as designed.
IP16 only shows this field if it's updated in MPLA-STADT.
The 'Cycle start' resulting of scheduling (IP10) is kept in the table
MHIS (field STADT).
Transaction IP16 takes data from MPLA and does not read the entries
in MHIS. The only value that can therefore be shown as 'cycle start'
is the original value as recorded in MPLA.
Well, this explains why system behaves like it does.
But in my eyes this is not the correct system behavior.
If a maint. plan is restarted, future calls will be calculated based on
the new cycle date - what is ok.
But IP16 indicates the old cycle date!
In my eyes this is not correct because the list will show an incorrect
cycle date.
I was told to take a look at note 11:
Sehr geehrte Kundin, sehr geehrter Kunde,
die von Ihnen benötigte Funktionalität ist leider nicht im SAP-Standardsystem enthalten.
Wenn Sie mit SAP an zukünftiger Produktfunktionalität arbeiten möchten, empfehlen wir Ihnen, dies entweder über die Mitarbeit in einer SAP Anwendergruppe oder über die Mitarbeit in einer der SAP Communities of Innovation zu tun. Eine Liste aller SAP Anwendergruppen finden Sie unter http://www.sapusergroups.org.
Eine Beschreibung der SAP Communities of Innovation können Sie unter http://www.sap.com/ecosystem/communities/index.epx einsehen.
Alternativ können Sie spezielle, von Ihnen gewünschte Funktionalität von SAP Custom Development entwickeln lassen (http://www.sap.com/services/bysubject/customdev).
Weiterführende Informationen finden Sie unter http://service.sap.com/rollin.
Mit freundlichen Grüßen
Ihr SAP Active Global Support
How can I trigger such an improvement?
Regards,
Philipp

Similar Messages

  • Change start of cycle date in maintenance plan

    Dear Experts,
    We would like to change start of cycle date in maintenance plan. Iwe have rescheduled the plan but the start of cycle date remains the same.
    could you please confirm, whether it can be changed. The requirement is because of some Mt plan created with future start date in production (Year-2020) and we want to correct the same.
    Thanks

    Don,
    To determine the next maintenance call date you need to tell the system when the last maintenance call occured
    Example:
    You want the next call date on the 1 June based on a six month cycle. Therefore the last maintenance date would have been 1 January (assuming key date scheduling).
    In your case you need to RESTART your single-cycle plan on the 1 January and the system then calculates the next maintenance calls.
    PeteA

  • How to look for New start Called call for a Maintenance plan

    Hi,
    I need to find out all calls for a maintenance plan of scheduling type- 'New Start' and Status- 'Called'. How to find this using tables.
    For 'New Start' scheduling type probably table field and value is MHIS-TERMA = 'N'. There are different statuse in this table but I am not able to identify the status 'called'. Also what is the field MHIS-ZAEHL(Maintenance package number) for?
    Thanks,
    Vimal

    Taken from the standard IP10 program:
    * possible status combinations
    * TSABR - Scheduling status: planned date called
    * TSVBT - Scheduling status: call outstanding
    * TSENQ - Scheduling status: call horizon not reached
    * TSENM - Scheduling status: stopped manually
    * TSTAT - Sceduling status
    * TSABR   TSVBT   TSENQ   TSENM   TSTAT
    *   X       -       -       -       A     called with order
    *   X       -       -       -       -     called without order
    *   -       X       X       -       -     on hold (TSENQ), due (TSVBT)
    *   -       X       X       -       F     on hold, due and fixed
    *   X       -       -       -       X     skipped
    *   -       X       X       X       -     blocked
    *   -       X       X       X       F     blocked
    *   X       -       -       -       -     LRMDT <> 0, completed

  • Strategy - Maintenance Plan - IP42

    Hello All,
    I have a query regarding "strategy" in Maintenance Plan IP42.
    1) Need to understand the strategy field in transaction IP42 and whats its impact.
    2) Also need to know how we can configure new strategies.
    Best Regards
    Himanshu

    Hi Himanshu,
                         You can have single cycle plan as well as the Strategy Plan.
    in the single cycle plan you can have only one cycle for all the operations which are defined in the task list, where as in the startegy plan you can have different cycles for all the operations in the Task list but make sure the startegy should be same in the task list and in the Strategy Plan(IP42).
    Example you have a Strategy define in the unit of days in the T-Code IP11 and you have define different cycles like 7days, 15 days, 30 days, 60 days Etc.
    now you are using the same Strategy in the General Task list IA05, and you have operations as 10,20,30,40,50,60........and so on.
    In this condition when you are in the header of the Task list, you can find the staretgy field where you give in the same startegy defined in IP11.
    then in the operations screen you can see an Icon at the bottom named as "MntPack", this is for maintenance package, if you will click here you can understand that all your operations can be assigned to 1 or more packages, for which they will be called in the Maintenance orders.
    Now time to create the Strategy Maintenance Plan, now u use the T-code IP42and give in the same startegy as defined earlier and go ahead with the different entries, here if you will choose the correct Task list the system will accept and if suppose the Strategy of the task list does not matches with the startegy of the maintenance plan, the system will throw an error
    Hope you can get a better idea.
    regards,
    yawar Khan

  • I have recently changed jobs and previously registered for a CC plan using my previous email address - now inaccessible. I also no longer have my laptop. I am paying fees each month ut can't access my membership to change my email address. Help!

    I have recently changed jobs and previously registered for a CC plan using my previous email address - now inaccessible.
    I also no longer have my laptop.
    I am paying fees each month but can't access my membership to change my email address. Help!
    I am paying my CC subscription monthly but cannot stop payments or preferably, change my email address so I can access my plan and use it on another computer.
    I can't contactAdobe to sort this - there seems to be no way of making contact and no reference to this problem in the forums that I can find
    Help!

    This is an open forum, not Adobe support... You need Adobe support to cancel a subscription
    -start here https://forums.adobe.com/thread/1703848
    -or by telephone http://helpx.adobe.com/x-productkb/global/phone-support-orders.html
    --and two links which may provide more details, if the above links don't help you
    -http://helpx.adobe.com/x-productkb/policy-pricing/return-cancel-or-change-order.html
    -http://helpx.adobe.com/x-productkb/policy-pricing/cancel-membership-subscription.html

  • Any FM to calculate planned costs for a Maintenance plan

    Hi all,
    Is there any FM to calculate planned costs for an Maintenance plan.
    I can use report RISTRA30(IP31). but i need to use for multiple multiple Mplans and different time frames. using SUBMIT to this report and getting data will lead to performance in my actual report.
    Please do provide any FM's or any other pointers for the same.
    warm regards,
    Sumanth

    Dear,
    In maintenance plan you can speciefy - order type,task list type,task list group & counter.
    when system automatically create service/maintenance order then system will determine plan cost, but for this you have to maintain planned price by t-code KP26.
    And then you can see report by IP31
    REGARDS,
    Kapil
    Edited by: Kapildev Farakte on Nov 17, 2009 10:38 AM

  • FM to find out schedule calls and their statuses for a Maintenance plan

    Hi,
    Please let me know if there is any FM to find out all schedule calls and their statuses for a Maintenance plan.
    Regards,
    Vimal

    Hi Vimal
    Below function module will serve your purpose.
    ZPM_GET_SCHEDULING_STATUS
    Regards
    Anil Kumar

  • Start cycle date in maintenance plan

    Hello Every one,
    In my project i have uploaded all the plans in production server with start cycle date. Now when i am going in change mode i cant see the start cycle date even thoug i can see the scheduling overview in plan as correct date but i m not able to see the start cycle date. Kindly help me in this.
    Regards
    Abhishek Sinha

    Hi,
    In Maintenance Plan, once you have mentioned the start of the cycle. Again it wont appear in Change Maintenance Plan, you will have to restart or reschedule the Plan.
    Regards,

  • To retreive the Maintenance Cycle for a Maintenance Package

    Hi All,
    I am trying to retrieve the 'Maintenance cycle' for a Package in the Maintenace package of the Maintenance strategy.
    I tried table T351P, but except 'Maintenance Cycle' i can see all other fields.
    In IP11 and in IP03 transactions i can see the Maintenace cycle field in the grid where maintenance packages are listed.
    But could not find a way to retrieve the maintenance cycle.
    Appreciate if you guys could help me out in getting the Maintenance Cylce.
    Cheers,
    Jaffer Ali.S

    Hi,
    Check the table MMPX Maintenance cycle short texts .
    Regards,
    Ankur Parab

  • Change or Add Cycles in a Maintenance Plan (IP02)

    good afternoon all,
    we have an issue with a number of maintenance plans that were setup as 1 year cycles, and now we want to run them as monthly. Is there a way to either change the yearly cycle to monthly, or add a new monthly cycle?
    SAP ECC6
    Release 731 sp level 0007.
    Thanks.

    Greetings Santosh,
    You are correct, the key word here is "approximately", as the Cycle Modification Factor has only two decimals of precision, you will need to input 0,08 to reflect the appropriate factor of 1/12=0,08(3) - so that will mean your cycle is 360*0,08=28,8 and not 30 days, which is why I did not propose this route. But if it's not an issue, then yes, that's another way to do this
    EDIT: Which reminds me, after switching the cycle to monthly, consider if you require Time or Key Date scheduling on the Maintenance Plan scheduling parameters, as for SAP 1 Month = 30 Days with the former, but with the latter the scheduling is always for the same day of each month.

  • How do I change the start/stop time for multiple songs not just one song at a time?

    How do I chnage the start/stop time for multiple songs not just one song at a time?

    I don't think you can in iTunes.
    Multiple editing in Get Info does not offer an option to change start/stop times.

  • How do I change the start up page for new tabs?

    I've tried looking through options but I can't seem to find anything related to it. Please help.

    New tabs are blank by default, there's no setting for changing that in Firefox. If you have something other than a blank page now appearing, an add-on you have installed changed the default action.
    You can use this add-on to specify which page you want to open in a new tab. <br />
    https://addons.mozilla.org/en-US/firefox/addon/newtaburl/

  • Change of Basic Finish Date for a Maintenance Order

    Hi Experts,
    I have a requirement where I need to change the Basic Finish Date of an order. Currently in config for order type and plant combination, scheduling parameters are set as:
    Adjust to Basic Finish Dates
    Automatic Scheduling.
    If in an order, I remove the tick for Automatic Scheduling, I am able to change that but I am not supposed to do that.
    Can you suggest me how thisissue can be resolved. Remember, changing the Config is not an option.
    Regards...

    hi
    Since you have done the adjust basic dates ,kindly change the operation dates ,which will automatically change the dates specified in the operation dates
    regards
    thyagarajan

  • MRP for Scheduled Maintenance Plan

    Hello here!
    Please help me.
    I customised MRP type VB (Manual Reorder Point Planning).
    Then I created monthly Task List with some components from materials.
    In next step i assigned my Task List to my Maintanance Plan.
    I Scheduled and Started my Maintanance Plan (from 30.07.2011).
    If I run MRP(01.08.2011) and Work Order was created (30.07.2011) - everything work great. MRP will create Purchase Requisition.
    But i need to customise MRP for posibility of creating Purchase Requisition for future Work Order's(30.08.2011, 30.09.2011 etc)
    It is posible?
    Thanks you and sorry for my english.

    Work Order (Maintenance Order) will be created based on scheduling. In case of any stock items, Maintenance order will create the reservation.
    If you run the MRP for that material, based on stock availability, MRP run will create PR.
    As you are using Reorder Point Planning, system will consider that material only when the available stock comes below the Reorder point.
    So you can keep safety stock by considering future orders as well, so that MRP will create PRs for future work orders.

  • How to set start of cycle/next planned date at the Maintenance Item level??

    Hi All,
    We are uploading a bulk of Strategy Maintenance Plans into the system. Each plan has multiple maintenance items and each maintenance item in a plan having different next due dates. Now if we set the Start of cycle at the Maintenance Plan level, then the next due dates of the maintenance items in that plan would be calculated on the basis on Start of Cycle (Common for all) and frequency as set in MPackages in an item Task list. Since each Maintenance item may have different Frequency and next due date, generating a call object while scheduling the plan correctly to satisfy at the Maintenance item level is not seeming possible.
    Can someone please suggest as to how do I set the Start of cycle or say Next Planned Date or Last Scheduled date at the Maintenance Item level either through configuration or programmatically.We are working on an SAP 4.6C version.It is urgent!!!

    hi
    i think specifying start of the cycle for each maintenance level is not possible ,since start of the cycle refers to maintenance plan only .
    for SAP standard kindly refer the following [link|http://help.sap.com/saphelp_46c/helpdata/en/94/43a968abc011d395bd00a0c93029cf/content.htm]
    it is better to create one maintenance item per maintenance plan,if you want to control each maintenance item independently
    regards
    thyagarajan

Maybe you are looking for

  • 500 Internal Server Error while saving variant in web

    Hi, I am facing "500 Internal Server Error" when I try to save a variant through web analyzer or wed application designer.It works fine for analyzer.Below are details shown with this error.Please help me to solve this issue. "The initial exception th

  • Big lcd screen in conjunction with my laptop

    I have been running LR on my laptop with a 15.4 screen. Although it isn't state of the art dual core pc, it runs ok and I am happy with it. I was thinking of getting a bigger laptop with a 17 inch screen, but now I'm thinking of getting a big 20 inch

  • In FBL1N report  - Unable to see Username

    Hi SAP Gurus I am have selected "User name" in FBL1N report layout.It is showing blank. I have checked it in BKPF( BKPF-USNAM) table and it is available. Any idea as to why is it blank. I would also like to have this 'User name" in selection screen i

  • POJO-based BO enterprise reporting OR Not?

    We are considering using Pojo for creating ETL On-Demand reports as opposed to encapsulating business logic in Stored Procedures embedded in a separate reporting database that talks to the Enterprise APP database (Oracle -in this case). Please commen

  • Error for Acrobat Pro Trial

    I have tried different browsers, different download managers, different computers... I am getting this message when I try to install the Acrobat Pro 30day trial... PLEASE HELP!!