I am reporting on Infocubes (Not Aggregates), May I get updated data in reports without running change run?

Hi Mannev,
   The changerun is meant for updating the master data. if there is any change in the master data structure, then this by doing change run if there are aggregates to a cube it will update to aggregtes. if there are no aggregates there is no use of change run. the query will get updated data from the cube it self.
Please assign full points if helpful,
with regards,
  sreekanth.

Similar Messages

  • Effect of Full Attribute Extract on Aggregate Attribute Change Run

    Because we extract data that does not trigger the change pointer on 0CUST_SALES we do a FULL extract of this data daily instead of a DELTA.  We recently created an aggregate which contains navigational attributes of 0CUST_SALES (namely Sales Office & Sales Group).
    My question is does the system look to see if any information has changed between the new and old values or does it assume since there is a new version for every entry that 100% of the values have changed?
    The reason I'm asking is BW appears to be rebuilding this aggregate from scratch each day instead of changing the aggregate for the few entries that actually changed.

    I did a FULL extract for 0CUST_SALES in our QA system.  It transferred 28617 records.  When I look into the monitor > processing > data package 1 > update I see the following:
    3 data records in table /BI0/XCUST_SALES marked for deletion
    3 data records inserted in table /BI0/XCUST_SALES
    3 data records n table /BI0/PCUST_SALES marked for deletion
    3 data records inserted in table /BI0/PCUST_SALES
    Different database operations were executed
    When I run the attribute change I see the following messages:
    The Change Run is executing                                                                               
    Attribute 0CUST_SALES__ZZROUTE for basic characteristic 0CUST_SALES: 2 changes   
    Attribute 0CUST_SALES__0BILLTOPRTY for basic characteristic 0CUST_SALES: 2 changes
    Attribute 0CUST_SALES__0PAYER for basic characteristic 0CUST_SALES: 2 changes    
    Attribute 0CUST_SALES__ZZACGRP for basic characteristic 0CUST_SALES: 2 changes   
    0001 ZSD_C02    100016     Aggregates Will Be Adjusted by:Reconstruction
    0002 ZSD_C02    100019     Aggregates Will Be Adjusted by:Reconstruction
    After seeing this i revisited the documentation for threshold value in RSCUSTV8.  Ours is BLANK!  So according to the documents when it is blank the aggregate is reconstructed generally.  Not what we want!!
    I will change the setting to the suggested 20% to start and we'll work from there.
    Thanks for your help Oliver.

  • Attribute Change run taking too long time to complete.

    Hi all,
    Attribute change run has been taking too long time to complete.It has to realign 50 odd aggreagates, some by delta , some by reconstruction. But inspite of all the aggregates it used to finish in quick time earlier. But since last 4-5 days it is taking indefinite time to finish.
    Can anyone please suggest what all reasons may be causing this? and what possibly can be the solution to the problem? It is becoming a big issue. So kindly help with ur advises.
    Promise to reward your answer liberally.
    Regards,
    Pradyut.

    Hi,
    Check with your functional owners in R/3 if there are mass changes/realignments or classification changes are going on regarding master data. e.g. reasigning materials to other material groups. This causes a major realignment in BW for all the aggregates. Otherwise check for parameterchanges / patches or missing db stats with your sap basis team.
    Kind regards, Patrick Rieken.

  • ERROR while running attribute change run.

    hi sap xperts,
    I got an error while running the attribute change run in a process chain.
    At first i got an error "The action is locked by a change run"
    SO I DID THE FOLLOWING STEPS.
    1.RUN ATTRIB CHANGE RUN MANUALLY  IT RUN SUCCESSFULLY,but the process chain is still red.
    Q1.Is there any way to link the manually run attrib chnage to process chain so that the process chain becomes Green?
    2.SM12 - realease the locks and right click the pc and repeat.It didn't work
    Q1.While removing the locks what should we remove,bcoz i removed all the locks?
    3.I again removed the lock and repeat the process but still i didn't work.Now its chowing "SQL ERROR OCCURED WHILE ACCESSING"
    So the Process chain got stuck,Can any body help me to run the attrib chnage run.
    If possible can anybody send the Process chain monitoring documents to my email id:
      <email ID removed>
    please.thanks in advance,i know how to say thanks in sdn.

    At any point in time only one attribute change run can run in the system. The other ACR's will fail due to locks. In your case, to set the process chain to green, try the following steps.
    Open the messages of a failed step by right clicking on it and selecting 'display messages'.
    In the opened popup click on the tab 'Chain'.
    In a parallel session goto transaction se16 for table rspcprocesslog and display the entries with the following selections:
    1. copy the variant from the popup to the variante of table rspcprocesslog
    2. copy the instance from the popup to the instance of table rspcprocesslog
    3. copy the start date from the popup to the batchdate of table rspcprocesslog
    Press F8 to display the entries of table rspcprocesslog.
    Now open another session and goto transaction se37. Enter RSPC_PROCESS_FINISH as the name of the function module and run the fm in test mode.
    Now copy the entries of table rspcprocesslog to the input parameters of the function module like described as follows:
    1. rspcprocesslog-log_id -> i_logid
    2. rspcprocesslog-type -> i_type
    3. rspcprocesslog-variante -> i_variant
    4. rspcprocesslog-instance -> i_instance
    5. enter 'G' for parameter i_state (sets the status to green).
    Now press F8 to run the fm.
    The above steps will help you continue with the rest of the process chain (thus avoiding manual runs) but the failed step might still remain red. Hope this helps.

  • Error while realigning aggregates through master data attr. change run

    Hi all,
    We are using Sales Overview cube (SD_C03) on which we have built aggregates. now during the master data attribute change run it tries to realign the aggregate once the master data is loaded via Process chain. In this step we are facing an error:
    "Error while procesing aggregate <aggregate technical name>"
    From ST22 we can find
    Database error text........: "ORA-14400: inserted partition key does not map to any partition"
    Internal call code.........: "[RSQL/INSR//BIC/F200009 ]".
    Whereas from SM21 we can find out:
    Database error 14400 at INS access to table /BIC/F200009.
    /BIC/F200009 is the fact table of one of the aggreates we have. really looking forward to your valuable suggestion.
    Thnaks,
    Abhishek.

    Hi Jogeswara Rao Kavala,
    When I am pressing back or NO option  it is showing error like this
    What is this OK- Code means?
    how can I resume this process, even it was not going to back screen also and only one option is available for exit from this is by going into MENU-SYSTEM-SERVICES-BATCH INPUT-CANCEL.
    Sunil Boya

  • Issue with Attrbute Change Run in BI 7.0

    Hi All,
    I have loaded a few master data objects as well as some custom master data objects and have found that they do not always show up in the list when you go to apply the attribute change run to something you have just loaded. 
    For instance I have just loaded a custom object from a DSO and if I click on manage on the attribute the load is there but I am not seeing any data in the object, then if I go to apply the attribute change run in the tools menu.  The infoobject does not show up in the list???
    Has anyone else run into this issue.  I have done a search but could not find anything that answered my question.
    Thank you!
    Caroline

    Hi Caroline,
    If the hierarchies and attributes of characteristics that belong to an InfoCube have been changed, you have to make structural changes to the aggregates to modify the data accordingly.
    In this task, you can perform the attribute change run ad hoc.
    http://help.sap.com/saphelp_nw70/helpdata/en/80/1a67ece07211d2acb80000e829fbfe/content.htm
    After each full load of master data, if you want to run attribute change run for an object eventhough the object does not show up in the list.  Go to se38 Execute the program RSDDS_AGGREGATES_MAINTAIN. In selection, Info object list - enter the infoobject name then execute it. Will give a pop-up message Hierarchy/attribute change successfully carried out.
    Edited by: Priya.D on Mar 11, 2010 6:16 AM

  • Attribute change run problem - infoobject is not listed in the list

    Hi folks,
    When I load master data for 0customer, the infoobject 0customer doesnt come in the infoobject list for attribute change run. Also, when I try to activate master data manually it says 'Master Data already active'. and the reality is M version of Data is not active.
    Can you guide me.

    Try running the program RSDMD_CHECKPRG_ALL for this infoobject. You can select all the options when running this program.
    Try running this program multiple times, coz my experience showed that initial run may not always fix this issue.
    Good luck!

  • Hi i have 50 infoobjects as part of my aggregates and in that 10 infoobjects have received changes in masterdata.so in my process chain the Attribute change run in running for a long time.can i kill the job and repeat the same.

    Hi i have 50 infoobjects as part of my aggregates and in that 10 infoobjects have received changes in masterdata.so in my process chain the Attribute change run in running for a long time.can i kill the job and repeat the same.

    Hi,
    I believe this would be your Prod system, so don't just cancel it but look at the job log. If it is still processing then don't kill it and wait for the change run to complete but if you can see that nothing is happening and it is stuck for a long time then you can go ahead and cancel it.
    But please be sure, as these kind of jobs can create problems if you cancel them in the middle of a job.
    Regards,
    Arminder Singh

  • Getting no attributes changes after change run monitor program is executed

    Hi ,
    We have a z-program where we are calling function module RSDDS_CHANGE_MONITOR . The structure of this function module is changes after upgrade from  BI 3.5 to 7.0. Accordingly i have adjusted the z-program . But the result is No Attribute Change Run Found .
    The function module called  is as follows
    CALL FUNCTION 'RSDDS_CHANGERUN_MONITOR'
    EXPORTING
      I_WITH_DETAILS           = RS_C_TRUE
      I_T_CHABASNM             =
      I_T_HIEID                =
       IMPORTING
         E_TS_STATE_CR            = l_cr_state
         E_TS_CHANM_IN_AGGR       = l_t_chanm
         E_TS_HIER_CR             = l_t_hieid
       E_TS_CHABASNM_CR         =
         E_T_AGGREGATE_CR         = l_t_aggrstate
       E_TS_TREXAGGR_CR         =
         E_TSX_MSG_CR             = l_t_msg
       EXCEPTIONS
         ERROR                    = 1
         OTHERS                   = 2
      IF SY-SUBRC <> 0.
    MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
            WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
      ENDIF.
    The l_cr_state has the details of the status in BI 7.0
    But after upgrade , its empty.
    Pls help on the issue.
    Regards,
    Sarang

    go through this link:
    http://help.sap.com/saphelp_nw04/helpdata/en/64/32a5682e6a4e0cbb3f8a33970d11a8/frameset.htm

  • ABAP program to add in the process chain before the attribute change run

    Hi
    I need a ABAP program to add in the process chain before the attribute change run(process) to avoid the locks, can any one send me the program
    Regards,
    Satish

    I am not sure of any standard program .... but you can write your own... should be a small one..
    you can check if the table RSDMDENQ has entry for your InfoObject... if yes, then its locked.. if not.. its not locked

  • Problem with hierarchy change run in aggregates

    Hi,
    I have made changes in Cost center hierarchy (infact I have included 2 cost centers in a seperate node). After it I loaded hierarchy into BW through Process chain. Process chain uses Attribute/hierarchy change run process. Consequently Cost center hierarchy is loaded into BW successfully.
    In Cost center master data, hierarchy table, i can see two new records for these added costcenters in Active status. It means hierarchy change has worked properly.
    I have also read that hierarchy change run automatically reflects the changes in Aggregates, that are using Cost center info objects.
    But my problem is I did not find new added cost centers in any aggregate using cost center info object. Though it should be taken care by Attribute/hierarchy change run.
    Please suggest, if I make any change in source system hierarchy, then how and when it will impact aggregates ? How can I test that hierarchy change has impacted aggregates ?
    Thanks and Regards
    Saurabh

    Hi Fede
    Did you manage to solve your problem?
    I have a similar situation where the technical ID of the hierarchy is set as default value for the hierarchy variable in the variable input screen.
    I have noticed that if I un-check the option "Suppress 'Unassigned' Node" in the Hierarchy Attributes Settings in RSH1, then the default value is gone, but I would like to have it checked in order not to display the unassigned nodes for the end users.
    Any help or comments on what you have done to overcome this problem would be jhighly appriciated.
    Thanks.
    Regards
    Peter

  • Problem in Activating Hierarchy Attribute change run through process chain.

    Hi All,
    I have the problem in Hierarchy change run processw running through process chain..and also process chain completes successfully without any error..
    Even hierarchy change run  completes successfully the hierarchy objects are not activating,
    so daily when i have to activate hierarchy objects manually..
    and what i did was in one attributechange run process i have included 10 hierarchy object is it correct or else i have to separatly create 10 attribute change hierachy proceess in the process chain.. pls through some lights on this issue
    With regards,
    Hari

    Hi venkat,
    Yes.. i already include the save hierarchies process in process chain...
    my main problem is hierarchy infobject are not activating  using process chain and also even process chain is not giving error message.. and in which log table the hierarchy objects are maintained (such as run time, date , status etc..).
    IS there is any other settings to be made in process chain..
    with regards,
    hari

  • Issue: attributes change run triggers the rebuilt of 0IC_C03 aggregates

    Hello Guru,
    I am facing to a problem that I don't understand.
    Here is below the detail of the messages of a '3-infoobjects attributes change run' step of a Master Data process chain.
    22:06:14     Job started
    22:06:14     Step 001 started (program RSPROCESS, variant &0000000231235, user ID RFC_BW)
    22:06:16     Starting process type ATTRIBCHAN with 3 objects...
    22:06:16     Program RSBATCH_EXECUTE_PROZESS successfully scheduled as job BICHNG_D8FC4Q04UD7NGLDMZ0QUBLX4K with ID 22061600
    22:06:16     Editing of aggregate 100139; background job BICHNG_D8FC4Q04UD7NGLDMZ0QUBLX4K; start time 22:06:16/07.07.2010
    22:06:18     Program RSBATCH_EXECUTE_PROZESS successfully scheduled as job BICHNG_D8FC4Q04UD7NGLDMZ0QUBLX4K with ID 22061601
    22:06:18     Editing of aggregate 100143; background job BICHNG_D8FC4Q04UD7NGLDMZ0QUBLX4K; start time 22:06:18/07.07.2010
    23:02:29     Program RSBATCH_EXECUTE_PROZESS successfully scheduled as job BICHNG_D8FC4Q04UD7NGLDMZ0QUBLX4K with ID 23022900
    23:02:29     Editing of aggregate 100140; background job BICHNG_D8FC4Q04UD7NGLDMZ0QUBLX4K; start time 23:02:29/07.07.2010
    23:52:38     Starting process type MDHIERACT with 2 objects...
    23:52:39     Program RSBATCH_EXECUTE_PROZESS successfully scheduled as job BIACTI_D8FCR9Y1NWOP2T4F76FYE0HDG with ID 23523900
    23:52:39     Program RSBATCH_EXECUTE_PROZESS successfully scheduled as job BIACTI_D8FCR9Y1NWOP2T4F76FYE0HDG with ID 23523901
    23:53:10     Aggregate 100139: Repair indexes
    23:57:14     Aggregate 100140: Repair indexes
    00:17:23     Aggregate 100143: Repair indexes
    00:50:09     3 aggregates are condensed
    00:50:09     Starting process type CONDAGGR with 3 objects...
    00:50:10     Program RSBATCH_EXECUTE_PROZESS successfully scheduled as job BICOND_D8FD3GTNF0KF92R34346SW6PG with ID 00501000
    00:50:10     Editing of aggregate 100143; background job BICOND_D8FD3GTNF0KF92R34346SW6PG; start time 00:50:10/08.07.2010
    00:50:10     Program RSBATCH_EXECUTE_PROZESS successfully scheduled as job BICOND_D8FD3GTNF0KF92R34346SW6PG with ID 00501001
    00:50:10     Editing of aggregate 100140; background job BICOND_D8FD3GTNF0KF92R34346SW6PG; start time 00:50:10/08.07.2010
    00:50:16     Program RSBATCH_EXECUTE_PROZESS successfully scheduled as job BICOND_D8FD3GTNF0KF92R34346SW6PG with ID 00501600
    00:50:16     Editing of aggregate 100139; background job BICOND_D8FD3GTNF0KF92R34346SW6PG; start time 00:50:16/08.07.2010
    00:50:22     Hierarchy/attribute change successfully carried out
    00:50:23     Event RSPROCESS with parameter D59BE8XWZMHY0IFP2VLEFP671 successfully triggered
    00:50:23     Job finished
    As you can observe, the step takes almost 3 hours !!!!!!! After anlyses BICHNG_* concerns
    22:06:16 Job started
    22:06:16 Step 001 started (program RSBATCH_EXECUTE_PROZESS, variant &0000000891873, user ID RFC_BW)
    22:06:18 Aggregate 100139( 0IC_C03) is being adapted / rebuilt
    22:06:18 Statistic UID of the aggregate process: 'D8FC4Q9KSAMRDWQ1RDPPKMF3O' (RSDDSTATAGGR)
    22:06:27 Aggregate 100139: Read (1) from table /BI0/E0ICC03_ (max 500000 records)22:06:27 SQL: 07.07.2010 22:06:27 RFC_BW
    I don't understand what is the link between the '3-infoobjects attributes change run' (BBATCH, 0MAT_SALES, 0MAT_PLANT) and the rebuilt of 3 0IC_C03 (Material Stocks/Movements) aggregates (why does the 'attribute chan run' trigger the rebuit of aggregates???).
    The rebuilt of the 3 aggregates takes 1 416, 3 366, 3 009 secondes...
    Does anyone understand my problematic? If not I can give you more details.
    Thanks in advance for your help.
    Samuel

    1/ Exactly Fred
    Here is the definitions of the aggregate:
    100139:
    0PLANT
    0STOR_LOC
    0MAT_PLANT__0VAL_CLASS
    0STOCKCAT
    0STOCKTYPE
    BMODIFIC
    BMVTSTOCK
    0MATL_TYPE
    0CALxxx
    2/ For my information in the aggregate 100140 , does the presence of BBATCH (one of the 3 IO) trigger the rebuilt or is it only 0MAT_PLANT__0VAL_CLASS ?
    100140:
    0PLANT
    0STOR_LOC
    0MATERIAL
    0MAT_PLANT__0VAL_CLASS
    BBATCH
    0STOCKCAT
    0STOCKTYPE
    BMODIFIC
    BMVTSTOCK
    0MATL_TYPE
    0CALxxx
    3/ In the same process chain, I have another Attributes Change Run: 0MATERIAL. Several active aggregates using 0MATERIAL__0MATL_TYPE are built on a CO-PA cube.
    Why did the '0MATERIAL Attributes Change Run' rebuild no aggregate? (see below)
    22:06:04     Job started
    22:06:04     Step 001 started (program RSPROCESS, variant &0000000231238, user ID RFC_BW)
    22:06:06     Activation of master data for 0MATERIAL
    22:06:07     154 Data records deleted
    22:06:11     154 Data records deleted
    22:06:12     154 Data records updated
    22:06:13     154 Data records updated
    22:06:13     0 aggregates are condensed
    22:06:14     Hierarchy/attribute change successfully carried out
    22:06:14     Event RSPROCESS with parameter D59BEEE069HKRCRU0ZPYFUPB1 successfully triggered
    22:06:14     Job finished
    Samuel

  • BIA Master Data Index Not Updated After Change Run

    In BIA it shows master data 0VERSION table /BI0/SVERSION has 360 records which matches with the number of entries in SE16 /BI0/SVERSION.  One record was added to 0VERSION so now SE16 /BI0/SVERSION shows 361 records.  I did a change run for this infoobject 0VERSION but the BIA index for /BI0/SVERSION still only show 360 records. I expect it to show 361 records after the change run.  Is this a bug?  Thanks.

    Hi Thao,
    I see one of 3 possible scenarios:
    1) You load 0VERSION as a part of master data load (from flat file or another system). You see your 11th record in version "M" after load and then you run change run that makes "A" version of the record. ---> BIA index should be automatically updated. If not - open OSS message to SAP.
    2) You load transactional data in an InfoCube, and it has new value for characteristic 0VERSION. ---> In this case you need to run roll-up of this new load request in the InfoCube to let BIA index be in-sync.
    3) You are modifying 0VERSION manually (e.g. SQL INSERT statement), so system is not aware of new record at all. ---> You need to run the mentioned single-table-index program to update BIA index.
    Is it any of these 3 scenarios, or you have the 4th one?
    Regards,
    -Vitaliy
    Edited by: Vitaliy on Aug 19, 2008 1:59 PM

  • Attr changes runs for  all Infoobject in a process chain

    Hi,
    I have a process chain for the master data ( ATTR, TEXT and HIER),I want a Hierarchy/attribute change run like a last process in my chain and actives all the InfoObject and Hierarchy.
    How can I carry out the structural changes for all InfoObject in a process chain?
    Thanks!

    yes but it requests me a variant. then a layout "execute infopackage", then the attr change doesn´t have Object.
    I don´t know what I do?
    This process actives all my ATTR and HIER in my chain???
    Message was edited by: Victoria León

  • Regarding attribute change runs in process chains

    Hi All,
    While creating process chain for master data objects. I am trying to incorporate attribute change run process type for an info object. But the system asks for the DTP of the attribute and when i choose the DTP then both DTP and then Attribute are being incorporated. This is not exactly a problem but i need to understand why it is happening as i am already using that DTP to load data. Will this affect the data in master data object?. Thanks in advance.
    regards
    satish

    Hi Bhagyarekha,
    The reason behind that error could be:
    An attempt is made to activate a characteristic whose compounding was replaced and whose navigation attributes were simultaneously deleted. The replacement of the compounding temporarily deletes the M view of the characteristic during internal activation. The process of deleting navigation attributes involves converting the attribute SID tables. However, the M-view of the characteristic, which has just been deleted, is needed for this conversion.
    Check this SAP Note:
    Note 684405 - Replacing the compounding and deleting navigation attr.
    Hope it helps.
    Veerendra.