Hi PP Experts,
Please someone help me on my problem regarding changing UoM on routing operation. I have to change or convert the labor time and machine time from CTS (cents of second) to S(second). How can i change that and i have to consider the impact on report such as routing check, standard time checking report and finacial cost.
Thanks for your help.
Edited by: yatch0325 on Oct 13, 2010 7:58 AM

Hi,
1. In the routing change the UOM for standard value to S and eneter the calculated machine time in S.
2.Change the Base qty and the operation unit.
3.Activity type and the cost needs to be checked.
Thanks,
nandha
Edited by: S.Nandakumar on Oct 13, 2010 8:25 AM

Similar Messages

  • Changing UOM and activity in routing

    Dear All,
    we have defined an activity compressed air with uom FT3 in routing. Compressor are runned on electricity. The power bill is being received for kwh. Now the management wants to change the uom to kwh and subsequently the quantity also.
    Now the problem is there are approx. 5000 FG materials where the change is required to be done.
    Please give suggestions how to achieve this.
    I understand that in CUNI we can develop the conversion factor from FT3 to KWH. Any other workaround available.
    Regards,
    Divraj

    Hi,
    Try with CEWB (Engineering Workbench) where you need to select Working Area SAP_OPERATION     Focus: Operation where you will get Operations Overview screen in mass.
    Hope this helps.
    Regards,
    Tejas

  • Track Changes made in Routing Operation Detail

    Hi gurus,
    I need your help with Routings.
    We have a process where if a change is made into the Routing, we have the Change Master process and a Change number is assigned to this Routing.
    For example, if a change is made into the Description of the "Operation" into the Routing, I can see this change with transaction CA60 and CA61.
    But, if a change is made into the "Operation Details" i.e.:  change the labour data or the overlapping data (where before it was Required overlapping and now is No overlapping); this kind of change into my Routing is not showed in transactions CA60 or CA61.
    I checked that a changed was made because the "Changed on" field was updated and "Changed by" field.
    Then, I checked the tables CHDHR and CDPOS and I can see that a document was created with the changed that I did, but, it does not show the detail of my change (i.e. old value was: Required overlapping, new value is: No overlapping).
    Do you know where I can see that my change was made? Or, is it possible to track these kinds of changes into SAP? where and how?
    Many thanks for your time and your feedback will be very well appreciated!
    Regards,
    Sandra

    Hi,
    Look for the change history in change header and change positions.
    The tables are CDHDR and CDPOS.
    Regards,
    Renjith Michael.

  • Change of activity type of operation overview through object dependency

    Hi,
    I am working on variant configuration project and I am using the global object dependencies (procedures) to change the BOM item quantities, Operation standatd values and activity types in super bom and super routings. When I use these dependencies BOM quantities and routing standard values are changed but activity types are not updated.
    If anybody have any idea about this, how to use the dependency to update the activity type? or any prgram error / any OSS note for this?
    We are working on ECC6.0.
    Advanced thanks...
    B Venkat

    Hi Venkat,
    As you may be having idea of usage of reference characteristics usage in changing the fields because you are already told that you are able to change the Qty field, same like this you need to have the reference char relevant to this field and table .
    Now the activity type comes from the work center. so you need to change actvity type in work center or you have to change the workcenter ( expected workcenter should have your required activity type) by the object dependency. It's looking a bit thoghtful one. Just think in your functionality it will work.
    Thanks
    Ankaiah

  • HKONG: ROUTING 이 없으면 하위 품목에 대해 OPERATION PULL 지정이 불가능할 때 처리방법

    PURPOSE
    ROUTING 이 없으면 하위 품목에 대해 OPERATION PULL 지정이 불가능할 때 처리방법
    Problem Description
    ROUTING 이 없으면 하위 품목에 대해 OPERATION PULL 지정이 불가능함
    Workaround
    N/A
    Solution Description
    원인>
    Bills form does not allow 'operation pull' when there is no routing for the assembly.
    This cause done as a fix for Bug 4247916
    해결책>
    The patch#4689976 will do the following:
    1. Revert the changes that are made in Bug 4247916.
    만약, BOMFMBM1.pld의 version이 " 115.75.115100.5" 보다 낮을 경우, 다음과 같이 patch를 TEST환경에
    적용하여, Test하여 주시기 바랍니다.
    -- To implement the solution, please execute the following steps::
    1. Please download and review the readme and pre-requisites for Patch 4689976 .
    2. Please apply Patch 4689976 in a test environment.
    3. Please confirm the following file versions:
    BOMFDBOM.fmb - 115.245.115100.17
    BOMFMBM1.pld - 115.75.115100.5
    4. Please retest the issue.
    5. If the issue is resolved, please migrate the solution as appropriate to other environments.
    Reference Documents
    -------------------

  • PM: change all Orders from sub-operation to operation level

    Hi Folks,
    I've a requirement to change all PM-Orders from Operation-SubOperation to only Operation Level.
    Example:
    Op SubOp --> New Op   (no subOp)
    10__10__-->____10
    10__11__-->____11
    10__12__-->____12
    10__13__-->____13
    10__14__-->____14
    20__10__-->____20
    20__11__-->____21
    Does someone here know, how I can make do this in an easy and save way?
    The only way I see is to make an own report with calling BAPI BAPI_ALM_ORDER_MAINTAIN.
    Have someone another solution
    - SAP-Standard-Report?
    - LSMW?
    Regards

    Hi Raghu,
    Many Thanks for your quick reply.
    Okay ... no LSMW.
    And also no Standard-Reports?
    Do you think, making my own program is the best way?
    Regards,
    Daniel

  • When I use the shortcut to open a new window in safari (command N), I get a 404 error message from Google. How do I change where 'Command N' routes to?

    When I use the shortcut to open a new window in safari (command N) on my Macbook Pro, I get a 404 error message from Google. How do I change where 'Command N' routes to? 

    It's not necessary to change the Command N keystroke..
    From your Safari menu bar click Safari > Preferences then select the Privacy tab.
    Click:   Remove All Website Data
    Then delete the cache.
    Open a Finder window. From the Finder menu bar click Go > Go to Folder
    Type or copy paste the following
    ~/Library/Caches/com.apple.Safari/Cache.db
    Click Go then move the Cache.db file to the Trash.
    Quit and relaunch Safari to test.
    If that didn't help, troubleshoot Safari extensions.
    From the Safari menu bar click Safari > Preferences then select the Extensions tab. Turn that OFF, quit and relaunch Safari to test.
    If that helped, turn one extension on then quit and relaunch Safari to test until you find the incompatible extension then click uninstall.

  • Change UOM in PR but PO exist for PR

    Hi Experts,
    We created a PR with a customized account assignment cat. and material text (no material code) with UOM L , we created PO in UOM L but purchasers cant do GRN because they received material in UOM LG ( which they mentioned in PO/PR Texts area). Now, the issue is with changing the UOM from L to LG in PR/PO.  I could though of only option to delete PO and PR line item and create a new but that we can't do because the same PO number is been shared between concerned parties/departments/contractors.
    Please tell me what are the other ways to change UOM. (as I am not using material code so additional data field doesnt come in picture)
    Thanks.
    Saurabh

    Thanks Jurgen.
    Even if I delete PO line item and create a new one then UOM should come from PR itself but after PO deletion also PR UOM is in display mode. Is there any program required to run to make it editable?
    I found one info. in PO about 'Order price unit' which says:
    Order Price Unit (Purchasing)
    Indicates the unit of measurement to which the purchase order price relates.
    Example
    A material or commodity (for example, oil) can be ordered by the liter, but the vendor's invoice shows a price of 2 dollars per kilogram.
    You enter 10 l as the order quantity and order unit, but specify 2 dollars per kg as purchase order price and purchase order price unit.
    In addition, you enter the conversion factor "order unit -> purchase order price unit" (for example 2 l per 1 kg) in the "details" data of the purchase order item.
    In GRN it says:
    Definition: purchase order price unit
    Purchasing (MM-PUR)
    An alternative unit of measure that can be used for ordering purposes.
    The purchase order price unit enables you to express the purchase order price in a unit that differs from the order unit.
    Example
    Ordered: 100 m2;    Price: $24.20 for 10 kg.
    The order unit is m2. The purchase order price unit is kg.
    Return ->
    Definition: purchase order price unit 
    I was just wondering if I could use this method to change/show a change in UOM. But if no relation exists then... it wont work I think.
    Kindly suggest.
    Thanks

  • I lost my connection when I was using internet and when I want to reconnect to airport it give me connection timeout error, I changed my password on router but still doesn't work. How can i fix my problem?

    Hi,
    I lost my airport connection when I was using internet and when I wanted to re-reconnect to airport it gave me connection timeout error, I changed my password on router but still doesn't work. How can i fix my problem?

    Hello there hastibahreini,
    It sounds like you were using your Wi-Fi network from your Airport base station and the connection cut out. You have reset the password on the device but the issue persists. I would try the 3 resets outlined in the following article in order to help resolve the issue. If it persists, is the Wi-Fi connection issue happening on more than one device or computer?
    Resetting an AirPort base station FAQ
    http://support.apple.com/kb/ht3728
    Thank you for using Apple Support Communities.
    Cheers,
    Sterling

  • Changes in poduction order,routing not updating in product cost estimate

    Dear SAP Gurus,
    i had done mto thru sale order and done some changes in production order,routing,and not updated the standard costestimate  of newly updated can anybody tell me the procedure of updating the routings and production  orders after production order released .
    pls help me the standard cost estimate how to get updated while changing the routing,production order.
    regards,
    muralidhar putta

    Hi Muralidhar,
    Could you please share with us how your problem was resolved. It may help others too.
    Thanks,
    Manjula.S

  • Changing UoM of Item which has a transaction

    we are going to change UoM of one Item in inventory, But this Item has transaction in system , and also some onhand. how we can do this task by consider the cost and quantity?
    thanks

    Dear Farhadn,
    It is not possible to change the items UoM once there are transactions linked to the item. This is the current system definition of SAP Business One.
    However, you can use factors (in the item master data) and Base units in marketing documents as workaround.
    Please, find instructions in the attached document.
    There is also a webex session available on the SAP service market place. Please find below the path to the webex:
    https://websmp207.sap-ag.de/~sapidb/011000358700000050892007E
    Go to Logistics - Inventory and core logistics -> 11.12.2006 - Items per purchase Unit in the Item Master Data
    Regards,
    Varun
    SAP Business One Forum Team

  • [SOLVED]How Can I change language on Google in Opera?

    Hello, I have a problem with Opera. I try to change de language of google to another language, but it has no effect:
    As you can see, I tried to change the language of google (it's for now in spanish) but it never changes. In konqueror and Firefox it changes correctly.
    Cookies on Opera are activated.
    What must I do to solve this problem? Maybe a bug?
    Greetings
    Last edited by Davigetto (2007-11-16 15:14:17)

    Well, cookies were activated, I have made all I could..., but nothing work.
    I have solved the problem at "brutal mode", I have erased all .opera folder xDDD, now google can change Language
    Strange...
    Thank You for all your help
    Last edited by Davigetto (2007-11-16 15:13:44)

  • Change UoM in Master Data

    Dear All,
    I am going to change UoM in material master data but the system prompts an error "Independent requirements are already assigned to the Material".  However, I already deleted the independent requirements and still the system does not allow.  There are no existing PO or stocks for the material.
    Where else should i look into to resolve my error?
    Thanks and regards
    Ching

    Hello Ching,
    If it is the base unit of measure that you want to chnage and you have made some use of the material already then the way you will change the base unit of measure is to create a new material copying the existing one but changing the base unit of measure of course before saving and deleting the existing material afterwards.
    Regards, Richard

  • Change UOM in Material master

    Hi friends,
    I have a material X in Plant ABC and Plant XYZ.
    I have no open PR's and PO's for those materials.
    I have received 10 Ea in Plant ABC on 10/20/09 ( Current stock is 10 ea in ABC)
                       and 20 Ea in Plant XYZ on 11/12/2009.( Current stock is 20 ea in XYZ)
    Now I wanted to change the UOM from EA to LB.
    I did issue (GM 201) 10 Ea from ABC and 20 Ea from XYZ. So, in MMBE no stock was showing.
    Still, when i try to change UOM, it was erroring that "Stock exist in Plant ABC and Plant XYZ" ????
    Any Idea, why so.
    Appreciate your valuable feed back.
    Note: I could change the UOM once I canceled the previous material documents to make sure Zero stock.
    But, Why I could not be able to change when I issue (GM 201) and made zero stock????
    Regards,
    Dev.

    Hi,
    According to your explanation the condition has gone through as below scenarios:
    You have received 10 Ea in Plant ABC on 10/20/09 ( Current stock is 10 ea in ABC)
    and 20 Ea in Plant XYZ on 11/12/2009.( Current stock is 20 ea in XYZ)
    You've issued 10ea in plant ABC on 11/23/09 (GM 201)
    and you've I issued 20 ea in plant XYZ on 11/23/09 (GM201)
    From the above, I conclude your current period is 11/2009 (November) and for solving the case on:
    Plant ABC. --> cancel your GI (mvt 202) for 10ea with the same current date 11/23/09 then follow by
                            GI with the previous posting period 10/30/09
    Plant XYZ --> display material stock with MM03 under storage location stock tab for previous period stock info.
                           then you should GI for relevant qty that you've seen onto previous period posting date.
    Hope it may helps you...
    Cheers,
    Girang
    Edited by: girang irawan on Nov 25, 2009 9:48 AM

  • Need to select all equipments (PRT) for a plan (routing) operation (PLPO)

    hi,
    I need to select all assigned equipments (PRT) for a plan (routing) operation (PLPO).
    Can anybody tell me the database table relation or is there a function module or a BAPI or something like this !?
    Thanks
    Olaf
    Edited by: Olaf Krüger on Feb 20, 2008 12:03 PM:  BADI to BAPI

    I suppose you have every PLPO needed (else look at function module WOSTS_TASKLIST_READ_FROM_DB)
    Then read
    PLMZ Allocation of bill of material items to operations
    STPO BOM item
    SELECT * FROM plmz INTO TABLE t_plmz
        FOR ALL ENTRIES IN t_plpo
        WHERE plnty = t_plpo-plnty
          AND plnnr = t_plpo-plnnr
          AND plnkn = t_plpo-plnkn.
      SELECT * FROM stpo INTO TABLE t_stpo
        FOR ALL ENTRIES IN t_plmz
        WHERE stlty = t_plmz-stlty
          AND stlnr = t_plmz-stlnr
          AND stlkn = t_plmz-stlkn.
    Regards

Maybe you are looking for

  • "Unable to Open" PDF attachment using BlackBerry PlayBook when message is received from Exchange 03

    Hello, Recently I have found that some users are having an issue with opening PDF attachments on the BlackBerry PlayBook using their Exchange 2003 accounts. I have isolated the issued to only users on Exchange 2003 using activesync. To resolve/workar

  • Premiere Pro CC 2014.2 Crashing on Startup

    Hi guys, My Premier Pro keeps crashing when it starts up. It only started happening a couple of days ago. I've pulled the below out of the event viewer. I have already tried the following; 1) Disabled intel graphics to leave just my AMD Radeon Graphi

  • ROWTYPE to get better query ?

    Hello, I have two identical tables: PHOTOS_TEMP AND IMAGES_TEST (ID PK number , content blob, filename varchar2 (200), mimetype varchar2 (200), filesize varchar2 (200), res_id FK number, watermarked varchar2 (1))I have CODE 1, I want to make it more

  • 11g grid infrastructure pre requisite errors

    Hi All, I am installing 11g grid infrastructure in a Solaris 10 SPARC 64 Bit During the pre requisite check, the installer gave failure for umask Error : PRVF-7612: User file creation mask check cannot be performed for user"oracle" on node We have th

  • Advertisements on lock screen?, Advertisements on lock screen?

    I am now seeing a small advertising bar on the bottom of my lock screen after updating to IOS 7.1. Has any one else noticed this? The ad is under the unlock swipe bar. how do i make this go away?