Changing operation date in co02

Hello everyone,
We have quite lengthy production operations and we need to change individual operation date, of planned or production orders (especially production order, in fact, before they are relased in fact).
The problem is that when I access Co02, and go to the operation list view, I cannot change the date. I can enter an operation or delete one but I can't change the start date of each operation.
It is absolutely needed in our case, as we have a lot of waiting time in the shop floor and need to review the schedule to match free slot. There is not a lot of orders , so the most convenient way is to do it from the Operation list, in Co02.
Please could you tell me how it is possible.
Many thanks,
Pierre Mikael

Dear ,
I am not sure whether you have Capacity Requirement Planning is in place  for PP cycle .Basically , operation dates and production order schedule dates can be changes based on the available capacity of Work Centre wehre the respective operations are happing in shop floor.There two kind of production scheduling happend in any production order .One is operation level scheduling and another order level scheduling .Order level scheuling should havppned based on the total details scheduling of operation based on the work centre load ( available , over load , requirement hrs at work centre ) .
Any operation in a scheuled production order , can have changes in date wheile deispathing the operation for work centre once the CRP in place .Here , we have Scheduling margine ( FBP, FAP, Opening periods ) contributes to Basic Start Dates in Production order .It is possible though Capacity Leveling -CM21/CM22/CM31/CM23  after cheking the Capacity Load in CM05/CM07 for a particular work centre level.
The simplest way to adop CRP and explore the same .please find belwo the detaiuls of  the same :
Setting Required :*
1. Settings for Available Capacity
2. Setting for Capacity requirements
3. Settings for Capacity evaluation and leveling
4.Materials Master define the Production scheduler and production scheduling profile
5.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view. 6.Routing - enter the values for the standard values. Use control key with scheduling.
7.In transaction OPU5 and OPU3Z - define the scheduling parameters for planned order and productiion orders and activate the checkbox Capacity requirement and Scheduling.
8.Capacity Setup :
1.Define time profile in OPD2.
2.Define the strategy profile in OPDB
3.Define the Overall profiles in OPD0.
4.In the order control OPJK  maintained check capacity with SAPSFCG013 profile.
5.Define Scheduling parameters for Production orders-OPKP-Maintain Capacity Checked /Finite Scheduling Cheked /Scheduing Type -BW/FW .
Hope this will help u in analysis
Regards
JH

Similar Messages

  • FM or BAPI to change Operation data

    Hi,
    Is there any BAPI to change operation data? BAPI_ALM_ORDER_MAINTAIN is not useful in my case. I want to use   IBAPI_ORDER_OPERATION_CHANGE but not able to get proper documentation for same.Can anyone give me a sample code about how to use IBAPI_ORDER_OPERATION_CHANGE?
    My requirement is to tick check box 'Required Splitting' in operation if some conditions are met. I am planning to do this using cuatomer exit. Everything is working fine only i need to know how to use above BAPI. If this doesn't work then as a last option i will go with BDC.
    Regards,
    Kamal

    Hi Kamal,
    Unfortunately I can not see any BAPI which changes operation data of a production order.
    BAPI_PRODORD_CHANGE is available only for changing header details.
    BAPI_ALM_ORDER_MAINTAIN and IBAPI_ORDER_OPERATION_CHANGE are used for changing maintenance or service orders, and not production orders, most probablty this won't work or cause issues.
    I'm afraid BDC is the only option in this case.
    Regards,
    Marcelo Pacheco

  • How to change operation dates in Production Order /Capacity Leveling

    Dear Experts ,
    We are using ECC 5.0 .In production order , scheduling happing as Backward  based on the Sales Order Delivery Date .I am doing the following :
    1.Demand as Sales Order with Delievery date : 20.03.2010
    2.Running MRP with Lead Time Scheduling -2  in md02 and converting the Planned Order to Production Order .
    4.Production Order have following dates :
             Basic Finsish Date : 21.03.2010
             Basic Start : the day Pl.Or--Pr.Ord
             Schedule Start : 15.03.2010
             Schedule Finsish : 17.03.2010
            Schedule Release : 13.03.2010
    5.In schedueling margin key :  Float Before Production : 3    , FAP : 3 , Release Period : 2
    6.In material master : Work Scheduling View : Setup : 3 days , Processing : 4 ,Interoperation : 2 for one Base Qty 1
    7.In operation : Op1  : Start Date  : 15.03.2010    Finish Date: 15.03.2010
                             Op2 : Start Date : 16.03.2010      Finish Date : 17.03.2010
                             Op2 : Start Date : 17.03.2010      FD : 17.03.2010
    Question :
    1.How to change the Operation dates  in Production Order Operation over view screen ? Today,  operation over view screen , Start date and Finsih Date  of individual operation are not changable with in Production Basic Start /BF date  or beyond .It is only changing based on the Standard Value : Labor
    2.How to change/re-schedule operation dates d in CM21 (Graphical view -Work Center Capacity load as per   Production Order and Operation combination ) based on capacity availale in advance dates? I am using  Time Profile : SAPSFCZ002 -SFC Graph midterm-3 motnhs and Planning  ,
    How to solve this above issue in scheduling operation and capacity distribution .
    Regards
    JH

    Closing the thread

  • Function Or BAPI to Change BP Data

    Hi All
    We need to change the value of a field Classification of the BP after we create a Quotation, but we are not able to find the function to do it.
    Best Regards.

    Hi Kamal,
    Unfortunately I can not see any BAPI which changes operation data of a production order.
    BAPI_PRODORD_CHANGE is available only for changing header details.
    BAPI_ALM_ORDER_MAINTAIN and IBAPI_ORDER_OPERATION_CHANGE are used for changing maintenance or service orders, and not production orders, most probablty this won't work or cause issues.
    I'm afraid BDC is the only option in this case.
    Regards,
    Marcelo Pacheco

  • I am trying to organize thousands of images in aperture.  The dates on the old scanned images is all 2008, when I started importing them.  When I change the date in aperture some of them hold the modified date and some revert to 2008.  Any ideas?

    I am trying to organize thousands of old images in aperture.  Aperture dates them all in 2008, when I started this project.  When I change the date in aperture some of them hold the modified date and some revert to 2008.  Any ideas?

      I just tried a test library, re-imported fresh images from a hard drive, and the date changes still revert.
    So neither your external drive nor your Aperture library are to blame.
    What do you mean test in a different user acct?  Would it be a good idea to uninstall and re-download aperture 3?
    Appreciate all your help.
    I meant the trouble shooting procedure described here:  Isolating an issue by using another user account
    To test, if some settings in your user account are faulty or preferences files corrupted, it helps to create a new user account from the "Users&Groups" System preferences. With a brand new user account you can see, if something in your current account is causing this.
    Should you see, that Aperture is not even working from a new and clean account, I'd reinstall Aperture, and if need be the Operating system.  Are you using any plug-ins?

  • Crashes when changing editing data model

    Reports 6i crashes (My windows (Unix) disappears) often when I am changing the data model (i.e removing and adding columns). I did figure out one thing and that is you when you delete a column that has a data link without removing the data link first it will not remove the column and the report will crash when you attempt to make an additional changes to that query that was changed. Any additional reasons?

    Kathy,
    Suggest you log a TAR with Oracle Support on this issue. The builder should not be crashing and I did not find any bugs logged. They will need to reproduce the problem and log a bug if necessary. You will need to supply them with the specific version of Reports and the operating system.
    Regards,
    The Oracle Reports Team jls

  • CO11N  I need than operation date is equal to goods movements date

    I am notifying with the CO11N, and need that the date of the movements of goods is equal to the  finish operation date .
    For default it takes the release date of the order.
    Is it possible this?
    Thank you.

    Hi
    Defaults will be like that only.
    If you want you can change the date of posting as requited.
    Can you explain your sceanrio in detail.
    Regards
    YMREDDY

  • New SAP update: Operation date in FI docs

    Hi gurus,
    In order to manage dates according to the law in several countries, e.g, Norm 340 in Spain where it says that operation date have to be in every financial posting relating to a billable service, we have heard that SAP is applying some changes to manage a new date in the FI docs. This date would be so called "Operation Date".
    Have you heard anything of this? Do you know where to find additional info about it?
    Thanks,
    VL

    Hi Eli,
    Thanks for your answer, but I still have a doubt to create a substitution, where you say to define the precondition document numbers, what document number are you refering? FI document? CO document?
    Can I change the substitution on tcode GGB1?
    Thanks again,
    Rgds
    Antónia

  • Operational Data Source for SAP OPInt

    Hello Experts,
    If I am configuring a business scenario which executes in a non-SAP system which does not generate events or change logs, I understand I need to configure a Operational Data Source in my business scenario.
    But, from where do I get access to the data store tables? Do I need to configure a connection to them separately? If yes, how do I do it?
    Thanks,
    Diptee

    Hello Diptee,
    for Operational Data Source to work, you need to grant select and execute authorizations on the schema where your operational data exists.
    Please refer to page 62 of the Developers Guide regarding "Grant select, execute on schema <schema_name> to <user_name or role_name>"
    Regards,
    Hee Tatt.

  • Problem in changing end date of PA-Infotype using HR_INFOTYPE_OPERATIONS .

    Hi All,
    I am trying to change the end date of an active record in an infotype using HR_INFOTYPE_OPERATIONS FM. But am getting an error, 'Infotype does not exist'.
    I am using operation as 'MOD' and passing appropriate parameters as required.
    it would be great if someone can help me out to understand, why could that error be coming?

    Hi Santosh,
    With this FM you cannot change the enddate as enddate is a key field and used to determine the exact record in the database.
    Why don't you use PA30 to change end date of an infotype record?
    Or else delete the row first w. HR_INFOTYPE_OPERATION DEL and insert it again with INS operation and new end date.
    Regards,
    Dilek
    Edited by: Dilek Ersoz Adak on Jan 8, 2010 7:54 AM

  • Can't change the date and time

    On a recent trip abroad, my N96 automatically switched to the local time on arrival, but it failed to switch back to UK time when I returned. Now my phone is stuck 3 hours ahead, and it won't let me change the date or time manually. When I select Settings | General | Date and time, and click Open, 'Change' flashes up briefly, but even if I'm fast enough to click it, nothing happens.
    I've tried reverting to the Factory Settings, but that did not resolve the problem. I've also checked for Firmware updates, but there aren't any. Any suggestions for fixing this would be very welcome...

    Your operator doesn't seem to support time autoupdate while the operator you connected to while abroad does.
    Go into the clock settings and set auto time update to "off". Then set the time zone to "GMT 0:00 London". This should bring the clock's time back to what it should be. If it doesn't, at least you can do so manually now (having auto time update set to "on" removes your ability to set the date and time manually).
    Was this post helpful? If so, please click on the white "Kudos!" star below. Thank you!

  • User Exit that triggers for Change operation

    Hi All..
    I want a user exit which triggers when I enter into an infotype(2001) from tcode PA30.
    My actual requirement is to show the field REFNR in display mode.
    By using the exit PBAS0001 exit0001 I can make the field REFNR in displaymode for create operation.
    But in change operation of the infotype the exit is not getting triggered.
    Regards,
    Anji.

    chk these
    Transaction Code - PA30                     Maintain HR Master Data
    Enhancement/ Business Add-in            Description
    Enhancement
    PBASRP01                                PA: User exit distributed reporting
    PBAS0002                                PA: Enhancements for Personnel Administration - Menu
    PBAS0001                                PA: Pers.Admin./Recruitment: Default values and checks
    PARA0002                                Enhancement for Calculating Annual Salary; IT0008,14,15
    PARA0001                                Enhancement for Determining the Number of Periods
    HRRPAI01                                User exit for FB HR_ENTRY_DATE and HR_LEAVING_DATE
    HRPC0001                                HR: PC download authorization
    HRPBAS01                                User Exit for HR Master Data
      Business Add-in
    HRPAD00_PREM                            Definition of User Exit for Collective Search Help PREM
    HRPADUS_PBAS_0001                       Customer Exit for Message handling
    HRPAD_SUBTY_CHECK
    HR_F4_GET_SUBTYPE                       HR: Entry help for subtypes
    HR_FAST_ACTION_CHECK                    Check fields on the fast entry screen
    HR_INDVAL                               HR: Indirect wage type valuation
    HR_SET_PKGAB
    HRPAD00_RECOG_SCREEN                    Employee - Recognition Screen
    HRPAYXX_DELETE_PERNR                    BAdI for Reports Deleting Personnel Numbers
    HRPAD00_PAPM                            Definition of User Exit for Collective Search Help PAPM
    HRPAD00_GET_AF_0008                     Additional Fields for Basic Pay Infotype (0008)
    HRPAD00_ENTRY_LEAVE                     HR_ENTRY_DATE and HR_LEAVING_DATE
    HRPAD00_ADRS                            HR: Address formatting
    HRPAD00MGEACTIVATION                    Activation Action BAdI for Global Employees
    HRPAD00INFTY                            Update / Infotype maintenance
    HRPAD00AUTH_TIME                        Time Logic in the PA Authorization Check
    HRPAD00AUTH_RECORD                      Spanish Data Privacy Law: Exit for Recording
    HRPAD00AUTH_CHECK                       HR: Authorization Check
    HRIV_REDUCE_AMOUNT                      Reduction within Indirect Valuation

  • Using Aobe Photoshop Elements 6:  1.  How to download photos in the same order as on the smart card from which I downloaded them?  2.  Changing the date on each photo

    Using Adobe Photoshop Elements 6:
    1.  How can I get the 2000 photos I downloaded in the same order as on the smart card from which I downloaded them?  (This will help me label them correctly)
    2.  How can I change the date on each photo? (I want to sort by date the picture was taken, not the date it was downloaded.
    Thank you!
    Linda Berteau
    [email protected]

    You indicated that the images "seemed" to be in the right order.  It might be a good idea to rename the images on export using a custom name/sequence.  If you have done that and the images are still not in order, it's possible that your operating system browsing window is using a different sort order.  I sometimes change windows explorer to sort by file type, and then files are sometimes in what seems be a strange order.

  • Please Help Urgently to refresh the report on the change in data

    We want to refresh report at runtime for the Drill Down report if any user changes the Data. We changes the data from the form which is called from the report and we want to this effect on the report on the prompt.
    Is there any method to close the report while it is in the queue of Background Engine? Can we refresh the report ? Please help urgently.
    Thanks in Advance.

    Pritesh,
    Reports goes out to the database and fetches the data (not a snapshot) and returns the information, formats it and displays it. The only way to refresh, is to rerun the report.
    If your are running from the server, you need to make sure you are not fetching from cache (you determine this from destype and set the life of the cache in the servername.ora file).
    I am unaware of any way to programatically close the report once displayed. The user must take action to close the report (unless you call the operating system to kill the display). When you rerun the report from Oracle Forms, you will get fresh data.
    Regards,
    The Oracle Reports Team jls

  • How does one change the date format for PlayMemories Home folders?

    I am using PlayMemories Home Version 2.0.00.11271 and have many folders within it which contain only photographs imported from my Sony DSC-H9.  Unfortunately, PlayMemories Home insists upon dating all folders in a month/day/year manner; and this makes little sense if one wishes to have the folders listed in logical chronological order.  How can I change the date format to year/month/day?  Changing the name of each folder, one by one, will take a very long time!  Your helpful advice in this matter will be greatly appreciated.  Thank you. System information:
    Operating system: Microsoft Windows XP Professional
    Service pack : Service Pack 3
    Memory: 1.5 GB
    Processor:         Intel(R) Pentium(R) M processor 1.86GHz
    Max. clock speed: 1.86
    Manufacturer: IBM
    Model: 1847W76
    System language setting: English (United States)
    User language setting: English (United States) 

    I too thought that the folder naming format was obviously wrong and couldn't find a way to change it. I do agree that placing photos in folders according to when they were taken is a great idea. I had been considering writing some software to do just that. After discovering that PlayMemories does it, I had it re-import all my photos. Then I wrote a small Perl script to rename all of the folders into year-month-day format. Included here is the Perl script. It only acts on a single folder - use it on the root folder where all the PlayMemories folders are. It will rename all folders currently in a month-day-year format. I used it without problems but of course there is no guarentee that it is error free. This should work with any common version of Perl. Tom # There should be one command line argument: the directory to act upon
    if ( scalar(@ARGV) == 0 ){
     print "Usage: RenameDirs <dir>\n";
     print " Where dir is the directory containing the directories to rename.\n";
     exit;
    $mydir = $ARGV[0];
    chdir $mydir or die "Couldn't chdir to $mydir: $!";
    opendir(ROOTPHOTODIR, ".") or die "Failed to open the pictures directory $mydir: $!";
    @allphotodirs = readdir ROOTPHOTODIR;
    closedir ROOTPHOTODIR;
    foreach $dir (@allphotodirs) {
     if ( -d $dir ) {
      print "$dir is a directory";
      if ( $dir =~ /^(\d{1,2})-(\d{1,2})-(\d{4})$/ ) {
       print " and has the proper format: month $1 day $2 year $3 and will be renamed to ";
       $newname = sprintf "%4u-%02u-%02u", $3, $1, $2;
       print "$newname\n";
       rename $dir, $newname or die "failed to rename $dir to $newname: $!";
      else {
       print " but is not of the proper format\n"
     elsif ( -f $dir ) {
      print "$dir is a file\n";
     else {
      print "$dir is neither a directory nor a file\n";
    }

Maybe you are looking for

  • Cleanup of DB13 Plannings + Job error

    Hi all, when i have gone through ST04, JOBS->DBA LOG, i am getting the following job  error 16.01.2008     14:00:46     16.01.2008     14:00:46     00:00:00     Collection of DB Performance History     OK 16.01.2008     14:00:44     16.01.2008     14

  • Help needed with flash and web service call

    Hi all, I need some help with web services and flash. I'm very new to flash, so please have that in the back of your mind when reading this :-) I've got a .swf file, and I would like to display a number received from a web service (using adobe flash

  • Dreamweaver CS5.5 Crashing multiple times per day

    Hi All, Can someone please help me with this. Dreamweaver has been crashing about 1 or 2 times a day and I can't pinpoint why. This debilitating my working day. I've never has problems like this with the CS5 version. I am runing Dreamweaver CS5.5 as

  • CORBA  BAD_PARAM/201

    Hi I'm having difficulty passing info from my server to my client; primitive data types are no problem, but am not successful in implementing arrays. A video file is read into an array in the Server, and upon request from the Client, the Server attem

  • Phone power on/off