Changing Production order quantity and invoicing again

Production order was completed for less than full quanity and invoice was generated. . Now can we cancel the invoice and change the quanity in Production oredr to full quantity and then regenrate the invoice? Are there any other steps?
Thanks

Hi,
SAP Confirmation for Orders is to caputre the actual activity used and goods issue (if backflushing is activated). MRP cannot sense the confirmed Qty.
If you want the MRP to Plan the difference qty, you have to do GR for the 95, remaining 5 will be generated as planned order in next MRP run.
You can also assign automatic GR for the last operation in your routing. So after confirming the last operation, GR will happen for the Qty. then you can run MRP, then it will generate planned order for qty 5.
Thanks,
JK

Similar Messages

  • Functional module to change production order

    Hi,
    I tried with FM CO2H_PROD_ORDER_CHANGE
    to change production order quantity field GAMNG value, but it did not work.
    Please suggest me any FM or BAPI to change Production order quantity.
    Thanks
    Hema

    Hi Ferry,
    Thanks for your fast reply.
    I tested with the function modules
    KK_F_AFKO_AFPO_UPDATE
    RK_AUFTRAG_SICHERN
    First FM does not have GAMNG(total order qty) field.
    With 2nd FM, it is directly updating table AUFK and AFPO with order qty and order qty. It will not update operation quantity, that is alsor required.
    If we do manually in CO02 transaction, operation quantity also will update once we change the order quantity.
    Thanks
    Hema

  • Activity is calculated on Production Order Quantity based .

    Hi Experts,
    My requirement is Planned Activity cost should be calculated based on Production order Quantity. and not on timing mentioned in Routing.
    For Example-   My PO Quantity is 10 - and activity assigned rate is 1 then = 10 RS is my planned activity Price
                                IF PO quantity is 1  then planned Activity Price is 1 RS
    pour some light on this
    Regards,
    Girish

    Hi
    Create an Activity Type and assign in work center / Routing... Keep the Activty Qty same as Base Qty in Routing....
    if you create Prod Order for 10, system would automatically propose Qty as 10.... Assign a fully variable formula in the work center to this activity
    Then maintain a price for this n KP26
    br, Ajay M

  • Changing of production order quantity not allowed

    Dear Gurus
    My client is converting production order from planned order .These  planned orders have been generated from sales orders during mrp run. What my; client wants is that the production order quantity generated from the planned orders nobody can change that in either co02 or in co01. How can this be possible?
    Regards
    Sandip Sarkar

    Dear Sandeep,
    u can do this Via SHD0
    Plz find the below link & make the required field as output only
    [https://www.sdn.sap.com/irj/scn/wiki?path=/display/snippets/transactionVariant-AStepbyStepGuidefor+Creation]
    Regards
    kumar

  • IDoc Configuration for Production Order Creation and Change

    Hi All,
    Please Help me out for IDoc Configuration for Production Order Creation and Change
    I have found the IDoc for Production Order
    Messgae Type : LOIPRO and IDoc type : LOIPRO01
    Actually my requirment is to send the (LOIPRO01 )IDoc from SAP R/3 to XI system ,when ever the Production Order Created and Changed,
    I have done following Configurations:
    1. RFC Destination created for XI system
    2. PORT was created for XI
    3. Partner profile created WE20 and LOIPRO01 IDoc is added in OutBound Perameter.
    I need to know how to do the followning.
    1. How do i configure the outbound Production order idocs when Production Order is created or changed.
    2. in NACE (Output control) which is the Application for Production Order.
    3. How can I set IDoc as output Type for Production Order Creation.
    Thanks in advance
    Dhanabal T

    Hi Michal,
    I know that it is the old thread but still want to get clarified from you out of curiosity.
    Unlike other IDOC, i actiavated change pointers for LOIPRO
    1.message and idoc type is linked
    2.function module , message type , idoc type is linked
    function module used is CLOI_MASTERIDOC_CREATE_LOIPRO
    3.BD64, distribution model is created and distributed
    4. port and partner profile is in place.
    5. IDOC is not getting generated after creating the process order.
    do we need to activate the change documents for the message type in BD52,
    if yes can you please provide the object types for the same.
    or i am missing something else. please guide me in this regards.
    Thanks in advance for your time.
    S.Janagar

  • Sales order, Delivery and Invoice changes history tables

    Dear All,
    I want to know how to find out the changes done in Sales Order, Delivery and Invoice.
    As far as sales order is concerned, I know CDHDR and CDPOS are tables can be used to find out the changes.
    But I am not sure about the "Object ID". Where we need to find out this Object ID?
    In the Data element "VBELN_VA" "Change Document" option has been checked under "Further Characteristics" tab.
    Please confirm about the "Object ID".
    Similarly give inputs for Delivery and Invoice change history also.
    Regards,
    Mullairaja

    Hi,
    Could you please explain, how to use these programs?
    Regards,
    Mullairaja

  • Which enhancement to use change purchase order quantity ?

    Hi all,
    can u tell me
    1) what is the enhancement to use to change the purchase order quantity with reference to the change in production order   quantity?
    Regards,
    Naveen
    Moderator Message: SEARCH!
    Edited by: kishan P on Nov 29, 2010 11:09 AM

    Hello,
    In this case you should use the message PORDCH and BAPI method BAPI_PO_CHANGE but only exist as of release 4.7.
    Function module    BAPI_IDOC_INPUT1
    Idoc Type              PORDCH01
    Message Type      PORDCH
    So check carefully the following OSS notes:
      [Notes 589066 - BAPI_PO_CHANGE: Incorrect account assignment to network |https://service.sap.com/sap/support/notes/589066] (not be fooled by the description)
    [ Notes 197958 - BAPIs for purchase orders - Missing Functions|https://service.sap.com/sap/support/notes/197958]
    Regards,
    Andrea
    Edited by: Andrea Olivieri on Sep 3, 2009 10:17 AM

  • Production order quantity

    hi,
    I get a mistake when I confirm a production order. I saw it intransaction COGI. This mistake is 'Production order quantity is exceed by ...' How can I solve it?
    Thanks and regards,

    Hi Hilal,
    Goto C013, give the production order Number and reverse the each confirmation supposse u have done operation lvel cofirmation & ensure the goods movement.
    And confirm again with correct order qty,
    Regards
    Pradeep

  • Regarding production order closing and demand closing

    Hi Gurus,
    I am new to pp module..
    I have the requirement on production order closing and demand order closing.
    The requirement needs plant,reuirement plan no ,basic finish date and percentage in selection screen.
    In the output display plant,requirement plan no,PIR No,order,order finish dat ,***.order qty,***.delivered qty,qty difference,percentage%,order status as in alv grid display.
    And in the output it has 2 buttons named technically complete and demend close .whener user click on first button system should take all the orders which r selected to the program with the same reuirement plan as for the selected order and then technically close all the orders with the same reuirement plan number.
    when user clicks on demand close button,system should take the respetcive requirement plan number,order finish date and material and it has to take the pir no which match the above and deactivate the pir and save.
    I need the help about this.
    Thankx in advance.

    Dear Chandu,
    First settle the production order using the T Code CO88,and then close the production order.
    Prerequisites
    Prerequisites for setting the CLSD status are:
    The order must have the status Released (REL) or Technically completed (TECO)
    The order balance must be 0
    There can be no open purchase requisitions, purchase orders or commitments
    There can be no future change records from confirmation processes
    Regards
    Mangalraj.S

  • Order Quantity and Target Quantity, both as editable in Sales Order

    Hi All,
    We have a requirement in which order quantity and target quantity, both should be allowed as editable fields in overview screen while creating a sales order or contract. Currently, only one quantity field is editable (order quantity in sales order and target quantity in contract).
    First question, is this possible?
    Second, If possible, then please tell the configurations need to maintain?
    Note: The material is relevant for delivery (so schedule lines allowed).
    Thanks & Regards,
    Vishal

    Hi Lakshmi,
    Thanks for the reply. I think I did not clarify the actual requirements. Let me explain it again:
    I understand that generally, Target qty is in contract and Order Qty is in sales order. But actually, here query is,
    When I create Sales Order (VA01), then while entering Material, user should see both quantity columns (Order Qty and Target Qty) in editable mode.
    So is this possible? If yes, then please guide.
    Please revert back if any further clarifications is required.
    Thanks & Regards,
    Vishal

  • Unable to change the order quantity value during save of sales order

    Hi Experts,
    There is a need to change the order quantity value, based on some conditions, when pressed 'ENTER' or during 'SAVE' of the sales order (VA01, VA02).
    We are trying to change the order quantity value (KWMENG) in table XVBAP in the subroutines userexit_field_modification, userexit_save_document and userexit_save_document_prepare of the user exit 'MV45AFZZ'. But the change is not replicated to field on GUI.
    The order quantity value can be changed in subroutine 'userexit_move_field_to_vbap', but the subroutine is not getting triggered when user changes only the order quantity on screen.
    Please help us in resolving this issue.
    Regards,
    Santosh

    Thanks for your time guys. The issue is resolved.
    SAP is not triggering the vbap user exit as the order quantity on screen is in structure RV45A.
    There are two ways of resolving the issue.
    1. Implement the SAP note #513342 - Quantity change and USEREXIT_MOVE_FIELD_TO_VBAP. But, it is SAP modification note.
    2. Write the code in VBEP exit of MV45AFZZ. This user exit is called whenever the order quantity is changed. But, it is called multiple times in some cases. Hence, need to write code to limit our code execution only once e.g. maintain a global table with our quantity & uom. Check when the quantity and uom in our table is same as quantity on screen. If not, exit from user-exit.
    Edited by: Santosh Kacham on Nov 11, 2011 6:37 AM

  • Purchase Order Price and Invoice verification price

    Hi All,
    In which report we can get purchase order price and Invoice verification price in SAP standard.
    Thank in Advance........
    Regards,
    Sanjay

    Hello,
    Check ME80FN transaction and select change view on the output screen and select Purchase order history.
    Regards,
    Shailesh

  • How to get Production Order Quantity

    I have material number and plant. From this information how to get production order quantity that is displayed in the transaction MD04.
    Thanks,
    Vinay.

    Hi Vinay,
    Have you looked FM <b>MD_STOCK_REQUIREMENTS_LIST_API</b>?
    Hope this will help.
    Regards,
    Ferry ianto

  • GR quantity more than production order quantity triggering cost difference

    Hi Gurus,
    We have observed a scenario where the cost(price) dfference account getting hit whenever the GR quantity is greater than the production order total quantity. The dollars posted to this acount are directly propotional to the difference between the GR quantity and the production order quantity.
    The total quantity specified in production order is 1 M2U and GR quantity is 1,000 M2U.Material price is $195.65.
    Accounting Document;
    Inventory account           - 195.65
    Offset account                - 200.00
    Cost difference account  -    4.35
    If we do GR for less than or same quantity as in the production order, this account is not getting triggered.
    Any idea what is causing this scenario? I really appreciate if you can share with any SAP note related to this.
    Thanks,
    Mano.

    Hello Gurus,
    One  more observation is,
    The palnned costs and actual costs are always different when dealing huge quantities. But the cost difference account is only getting triggered if the actual quantity is  more than the palnned quantity.
    And,
    when the difference between atual quantity and palnned quantity is huge then
    Planned costs are booked to the inventory account
    Actual costs are booked to the prodcution cost account.
    Significant cost variance is booked to the cost variance account.
    When the difference between actual quantity is less than/equal to planned quantity is not so huge then
    Actual costs are booked to the inventory account
    Actual costs are booked to the prodcution cost account.
    Is this a standard behaviour?
    Thanks,
    Mano.

  • Any function module or bapi to get sales order number and invoice number?

    hi all,
    with delivery order number provided, do we have any function module or bapi to get sales order number
    and invoice number?
    thanks.

    Hi,
    Check
    BAPI_SALESORDER_CREATEFROMDAT1
    BAPI_REMUREQSLISTA_CREATEMULT  Agency Business: BAPI Create Invoice Lists from Vendor Billing Documents
    BAPI_REMUREQSLISTB_CREATEMULT  Agency Business: BAPI Create Invoice Lists from Payment Documents
    BAPI_REMUREQSLISTC_CREATEMULT  Agency Business: BAPI Create Invoice Lists from Posting Lists
    BAPI_REMUREQSLIST_CHANGEMULT   Agency Business: Change Invoice List Documents BAPI
    BAPI_REMUREQSLIST_GETLIST      Agency Business: BAPI Determine Detailed Data for Invoice List Documents
    BAPI_REMUREQSLIST_RELEASE      Agency Business: BAPI Release Invoice List Documents to FI
    Edited by: Neenu Jose on Nov 26, 2008 8:53 AM

Maybe you are looking for

  • My iWeb's main blog page has photos of entries all mixed up

    My site is egsilberman.com and all but the main blog page is functioning.  The index.html looks perfect, the page listing all the blog pages using the index.html in the browser looks as it should. But after uploading the site to my FTP - using iWeb S

  • Lots of XYZ Points

    Hello, I have about 100,000 "XYZ" points I'd like to load into a simple Java3D application. Here's some sample data: LONGITUDE, LATITUDE,HEIGHT 382656.74, 3097890.30, 6.72 382656.76, 3097890.22, 6.70 382656.79, 3097890.13, 6.70 I'm new to Jave3D and

  • Cannot open repository in online mode

    I cannot open repository in ONLINE mode I'm using Oracle BI Administration tool version 11.1.1.3 and Oracle Enterprise Manager 11g version 11.1.1.3. My procedure is: - Enterprise Manage: open repository, apply changes, restart services - Administrati

  • Clearing single call numbers

    3g 4.2 - Telephone "recent call" list is full, how do I clear individual numbers leaving others?

  • Tcode for the List of customers

    Hi All can any body tell me the tcode for the list of customers in the system