Hi Gurus,
Iam doing characteristic planning for a KMAT material in a new development project, is there any way to enter historical data for characteristic values so that they will be forecast.
does historical data for characteristic values will remains in the SAP system for make to order process in future?
i will try to give detail information if my question is not understandable. please suggest me.

Hello ,
I delete all characters in RSKC transaction and write " ALL_CAPITAL".
Then I try to upload data from ODS to infocube.Result is the same.I can not update infocube because of invalid character error message.
ODS is extracting data from generic datasource.And uploading data to ODS is succesfull.I have no error messages such as invalid characters.But I can not load data to infocube from the ODS.
I looked at the record in RSA3 Tcode in R3 system.The value is '5950514174#'.I can not this value to infocube.It is a description field in R3.
But as you will see in my first post I defined space(''), (#) and ('  #)  characters in RSKC before.And this time I define ALL_CAPITAL in RSKC.But nothing changed in both cases.
I have still the same error.
PS :I created a char characteristic, size 60,in BW  to upload this description field.
Waiting for your responses.
Thanks..

Similar Messages

  • How to set a characteristic dependent on value of a keyfigure

    Hi folks,
    I'm facing the following problem:
    I need to create a solution that enables a user to set a characteristic to a values (Y or N).
    Because of the circumstances no direct access to RSA1 is possible.
    This is why I thought about BI  IP.
    The idea is now to plan a keyfigure with 0 and 1. Next step would be to use a planfunction in order to create the corresponding characteristic values:
    so like
    keyfigure
                       month Jan Feb
    customer A              1     0
    customer B              1    1
    char
    leads to                   Jan Feb
    customer A              N    Y
    customer B              N    N
    Any comment whether I'm on the right path?
    My Fox Formular looks like:
    DATA  FYEAR TYPE 0FISCYEAR.
    DATA FKNO_Y TYPE YKNOKUN.
    DATA FKNO_N TYPE YKNOKUN.
    DATA FREMSPER_Y TYPE YREMSPER.
    DATA FREMSPER_N TYPE YREMSPER.
    FKNO_Y = Y.
    FKNO_N = N .
    FREMSPER_Y = Y.
    FREMSPER_N = N.
    FYEAR = VARV(YMM0005E).
    FOREACH FYEAR.
       IF {YKNORESP, FYEAR, FKNO_Y, # } = 1.
          {YKNORESP, FYEAR, FKNO_N, Y} = 1.
      ELSE.
             {YKNORESP, FYEAR, FKNO_N, N} = 0.
      ENDIF.
    ENDFOR.

    Create 2 reports
    Report 1 having Month equal to @{Pv_Type}{Dummy}
    Report 2 having Year equal to @{Pv_Type}{Dummy} . Assuming Year in in CHAR datatype . If it is not then convert it to char.
    Now for your Year section use Report 1 in condition (row count greater than 0) and for your Month section use Report 2 in condition (row count greater than 0).
    Thanks

  • TPM: planning view - value distribution

    Hi Gurus,
    I have a requirement where the entered advert contribution as a trade spend must be distributed evenly among the assigned products.
    We will do the planning either at product or product group level. We use the standard planning profile 4TPM0002 in our trade promotions. When the planning view is displayed we don't have an agregated total line so we have to manually distribute the cost among the assigned products. No automatically distribution takes place. So my question is:
    Do I have to set up value distribution in the IMG (SPRO->SAP Reference IMG-> Customer Relationship management->Marketing->Marketing planning and campaign management->Key figure planning->*Maintain value distribution)
    Is the above configuration also applicable for TPM or do we have to set up distribution from aggregate level in BPS?
    I have the same issue with the uplift to APO.
    Regards
    Anne

    Hello Anne,
    Mentioned path is for campaigns only.that is beacause Distribution to target objects is only provided for campaigns and campaign elements.
    To answer your Question, you have to set up distribution from aggregate level in BPS.
    Thanks
    Raja Pamireddy
    CRM Marketing Forum Moderator.

  • Forecasting: all historical values are zero

    Hello,
    I would like to execute forecast for a specific material.
    Then I'm in MM02 in forecasting view, I filled all necessary parameters and I press "execute forecasts".
    I received different pop ups, and one is "Between 11.2006 and 10.2011 all historical values are zero".
    If I go out of this, and press on "Consumption vals", I have no data for unplanned consumption but if I click on "Total consumption", I got all values for each period of my historical periods.
    So why do I have this message that historical values are zero? Then I have no chance to execute forecast with that behavior.
    Same with several other materials.
    Thanks for help.

    Dear Olivia,
    In MM of forecasting view there is filed Hist. periods which you could have probably maintain more than 12 months say 60. So starting from current months it will go backward & search value for last 60 months. In your case it is not finding any past values. Have you maintain it in Additional data of material master Consumption tab ? Maintain some values for months & then try
    Regards
    Abhijit Gautam

  • FM for Planned Total values of a WBS

    Hi All,
    Looking for an FM which can give me Planned Total values of a WBS element (that means, of that particular WBS element and all the objects below that WBS, including WBS, activities, etc.) just like this figure is calculated in CJ40 "Planned Total" column.
    Reply asap as this is urgent requirement.
    Thanks.

    Hi Aditya,
    see if the below FMs help you in any way
    CK_F_COST_ROLLUP
    KBPP_EXTERN_UPDATE_CO
    KBPR_READ_DATA
    Cheers
    Sammar

  • Forecasting and User Settings For Displaying Historical Values

    Hello,
    I am attempting to perform a forecast model.  After entering the selection criteria I get the message "Forecast includes only historical values as from P 01/2011 --> F1" .
    when I expand on the message I see
    Forecast includes only historical values as from P 01/2011 --> F1
         Message no. MA 559
    Diagnosis
         You want to carry out the forecast for the historical values from 04/2010 to 08/2011.  However, historical values prior to P
         01/2011 are zero.  The system response to this situation depends on the user.  The following responses are possible:
         1.  The entire historical period is included nonetheless.
         2.  Historical values before P 01/2011 are not included.
         The user setting that has been made for you corresponds to variant 2.
    Procedure
       You can change the historical values in the period from 04/2010 to 08/2011 manually, regardless of the user setting.  If
       variant 2 applies and zero values before P 01/2011 are then corrected, the historical period used by the forecast is extended
       to include this date or period.
    Questions
       1.  Where does the "user setting that has been make for you corresponds to variant 2" reside in SAP?  How can I see this? 
            What other variant values are available to me?  How would I change this value if I wanted to?  This seems to indicate that
            this is a user profile setting since it's dependent on the user????
       2.  I am ?assuming? that variant 2 means that "2.  Historical values before P 01/2011 are not included" is the choice, above,
            that is being made.  I ?assume? that variant 2 means that the forecast extends back as far in the selected period as there 
            is a value that is found that is not zero.  Is that correct?
    Any insight/help would be appreciated.
    Thanks!

    Hi Tilak,
    Plz find the below threads for your reference...
    Change in Decimal Points with comma
    Decimal Notation
    Regarding Decimal Notation
    Defualt Value of Requisitioner
    Again back to u all :)
    can not put decimal quantity in BOM quantity
    Also find the below search link...
    https://www.sdn.sap.com/irj/sdn/advancedsearch?cat=sdn_all&query=defaultsettingsinSU01decimal+notation&adv=false&sortby=cm_rnd_rankvalue
    Assign points if this helps u...
    Regards,
    KK.

  • Mass Upload for Historical Value in Forecast

    Hi Guru,
    Is there any way by which I can do mass upload of historical values (Total Consumption) in Forecasting Tab of Material Masters?
    Regards,
    Pradeep

    Dear,
    Please use report RMDATIND, MVER_DI or BAPI_MATERIAL_MAINTAINDATA_RT
    For more details please refer the OSS  Note 200547 - Program: Direct input for consumption values
    Regards,
    R.Brahmankar

  • Planned depreciation value for each period

    Hi,
    Where can I get the planned depreciation value for each period? I need the fields for customised report.
    Thank you

    Hi,
    You can get the dep planned values for the each period by using SAP standard report S_ALR_87012936.
    In the selection screen of that report, click on All selections button on application tool bar. Then you will be able to see the all the available fields for selection.
    Choose evaluation period as Month.
    Now execute it. After getting output, you need to go for change layout and adopt fileds like Dep 01-2010, Dep 02-2010, Dep 03-2010....Etc till Dep 12-2010.
    This will fix your requirement.
    Thanks,
    Srinu

  • PP Demand Planning Historical Forecast

    Hi,
    I am trying to run a forecast in the past to allow me to see the outcome of different forecast models as compared to the actual results (e.g.. Historical period current -2 and forecast period current -1).  The job appears to work without an error (Ex Post forecast), but no forecast is generated.  Does SAP only allow the generation of forecast data for future periods?
    Thanks
    Mark

    Strictly speaking yes, forecast is meant to, as the name suggests forecast future values. However, when there is sufficient data the system performs what is called an EX-post forecast.  The point of the ex-post forecast is to apply the selected model (for future values) to historical values so that the validity of the selected model can be made (I believe this is what you want to do)
    Below is a small example. For a given material I performed the forecast for period 06.2007 onwards, but as you can see that system has also done an ex-post forecast (==> applied the forecats model to past values). I have included a picture to highlight what I mean <a href="http://www.renet-web.net/sdn/forecast.jpg">here</a>. The value circled is the forecasted value for a past period.
    hope this helps.

  • FM of Original Historical Value of Material

    Hi All,
    I would like to know is there any function module available for finding Original Historical Value of Material?
    Above value can be found in Forecasting view of material. MM02/MM03->Forecasting(view)->Forecast Values 
    System will display a popup box and in the first column it shows Original Forecasting Value.
    I have to display this value in my report but I am not able to find function module. Can somebody please help me?
    Regards,
    Sanjay

    Actually it comes up with three boxes.....first I have to press Enter....second Execute Forecast(F7)....the again Execute Forcast(F7) on different pop up window and finally it shows data on a new-pop up here we have to press Enter key again to see the result of function module. I used MATERIAL_FORECAST_DIALOG in my program hoping it won't show above pop-ups but it does shows and after doing above 4 steps only it shows me result. I am not sure how to avoide these po-ups.
    thanks
    sanjay

  • SAP Planned Depreciation Values

    Hi,
    Can anybody suggest how can I bring the total planned depreciation values (month wise).
    I would like to know the structure, table or function module.
    We have tried with function module ANEP_AFARECHNEN but notfetching the results.
    I know ANLC table shows the values but only for the years that are roll-forwarded by the system.
    But, I want the planned depreciation values for complete life of the asset.
    Any help would be appreciated.
    Regards,
    Ravi

    Hi Ravi,
    For depreciation planned value by month, it should be calculated using the total value from table ANLC by double checking program AW01N perhaps storing in work area within the program.
    As for depreciaiont posted monthly from acquisition up until now, table ANLP shall gives the details monthly.
    Hope the above helps.
    Kind regards,
    John Chin

  • Forecasting using historical values

    I am doing forecasting for a material. I have created the forecasting view for the material and entered the consulption values. I want the forecasting output to create a forecast where the current month' s forecast = the same month's historical sales last year. When I try to execute the forecast the 'forecast execution' tab has the 'historical' as greyed out. Is there a way I can copy historical values as forecast.
    thanks

    Hi John,
                As per my understanding you want that that the sales for month jan-2008 = forecast for jan-2009.
    If that is the requirement then you can maintain the following setting.
    Model = D constant
    Period indicator = M
    histroy period = 12
    Forecast period = 12
    Maintain the Consumption for the whole year 2007.
    Regrads
    Kaushik

  • In Classificaiton datsource - Error "Characteristic has multiple values"

    Hello All,
    I have created classification data source 1CL_OMAT001 for material ATTR.. When adding the "PRODLINE" as one of characteristic I am facing this error "Characteristic has multiple values". I want to extract the Prod line to BW after this extraction.
    Adding info, This PRODLINE is under a class "BUSINESS LINE". It is a only component of this class type, If i add characteristic of any other type say engineeering class.
    Please help. If any information u want from me let me know.
    Regards, Karthik

    Hello Karthik,
    classification allows to assign multiple values for one charateristics to the same classified object, if the characteristic is defined accordingly (see please transaction CT04). Because only one value per characteristic and object can be extracted, CTBW checks the definitions of the characteristics you are assigning to a datasource. It refuses to assign characteristics, which allow multiple values, to a datasource. That's what you have observed.
    In some cases characteristics allow multiple values for technical reasons, but actually only one value is assigned when objects are classified. For such cases you may turn the observed error to a warning (see please SAP note 350296). The first found value will be extracted. Further values would be ignored.
    If you need to extract multiple values, you may use a solution like described in SAP note 1002105.
    Regards,
    Rolf

  • Difference in planned depreciation value because of wrong positing of unpla

    Hi All,
    1.     Unplanned depreciation has been posted in last fiscal year.
    2.     Amount posted in IGAAP was higher than IFRS value.
    3.     Now planned value of depreciation in being calculated by system is not equal for both books (IFRS / IGAAP) because of difference in unplanned depreciation posted in last year.
    Example "
    IFRS -01 AREA- 765431.89
    IGGAP-02 AREA- 765431.78       = 0.11 difference in 01 and 02 areas.
    T.codeABCO i posted unplanned depreciation in 01 area after posting 01 and 01 unplanned depreciation amount are same but Planned depreciation values show 0.11 difference.
    Please suggest what steps needs t be followed to settle this difference of depreciation in both books.
    Thanks in advance

    Hi Kishore,
    please check if area 03 = - 01 + 02 and you have special settings in OADB for area 03.
    In this case the system  makes roundigs to fulfill this settings.
    regards Bernhard

  • How to Load Historical values from Material Prices

    Hi
    I have to load historical values from Material Prices.
    I'm using extractors 0CO_PC_ACT_02 and 0CO_PC_ACT_05.
    Do you know how I can do this in a easy way?
    Help is appreciated.
    thanks in advance.
    best regards

    Hi Joao,
    This extractor0CO_PC_ACT_05 takes the data from table MBEW. ( data for the current period, previous period and last period of the previous year )
    If material ledger is active, then it takes the information from table ckmlhd for those materials.
    It does not look like fetching from MBEWH.
    Please validate my above comments with sample extraction for a material and plant.
    If that is the case, I would suggest you have to create a custom extractor based on MBEWH to get the historic price data and with 0CO_PC_ACT_05 you can get the prices for the previous period as they get completed .
    0CO_PC_ACT_02 gets you the inventory value and not the price in the same way.
    You might have to think about 0CO_PC_ACT_06 and 0CO_PC_ACT_07, if you have project stock and sales order stock in your business scenario.
    Please let me know, how this goes.
    Thanks,
    Krishnan.

Maybe you are looking for

  • Executing amadmin command in Unix box.  --*** Urgent*****

    I tried to execute following command on Unix machine: ./amadmin -u uid=amAdmin,ou=People,o=ievesp.net -v -w "password" -s /etc/opt/SUNWam/config/xml/amUser.xml I am getting following error message: Info 112: Entering ldapAuthenticate method! Success

  • Why is the google app not rated 17+ and why is msecure and 1password pro rated 17+

    The google app on iphone and ipad is basically a web browser and should be rated 17+. On the other hand why is msecure and 1password pro rated 17+?

  • JSP Compile Woes

    Hi All;           I am using WLS 5.1 sp9/10 on a RH6.2 Box. I have a WAR application, and I           get strangeness. When sp9 is in use, one of my JSPs fails to load and I           don't know why. The JSP works fine in DEV, but in PRD I get the st

  • Backward Navigation in development components

    Hi folks According to my scenario, i have 3 DC's named A, B, C. A is master DC and is using B as used DC's in metadata . where B is using DC C. So there is linear dependency between them. Now my requirement is to navigate from A to C through B.and vi

  • Creative cloud for mac apps not appearing

    No apps are appearing in my apps menu, thus I cant dowload any of them