ChaRM and CTS+ integration

Hello Experts,
Is it possible to integrate ChaRM with CTS+ ? i.e. Java transports can also be controled from ChaRM same as ABAP. Can anyone list steps needed to perform to achieve this. a Step-by-step guide will be appreciated.
Thanks in advance.
Regards,
Swapnil

Hi Swapnil,
According to SAP this is possible.  Please have a look at the document in service.sap.com -> Media Library -> Technical Papers -> "How to Set up and Use eCTS/ChaRM Solution Manager 7.0 SP12"
Would be interested to hear how you get on.
Regards, Chris.

Similar Messages

  • ChaRm and CTS+ configuration

    Hello Experts,
    Can anyone forward ChaRm and CTS+ configuration document to me, I have received Business requirments and trying to configure the same. I would appreciate step by step configuration guide for both.
    Thanks in advance.
    Regards,
    Swapnil Lakhe
    lakhess<at>gmail

    Hi,
    Please find the below steps for Charm confirguration :
    1.SAP Solution Manager Implementation Guide  SAP Solution Manager  Basic Settings  SAP Solution Manager System  Activate Integration with Change Request Management
    Click on the Execute icon with the text Activate Integration with Change Request Management
    Double click the Activate Change Request Management and set up client
    It will show the following window type your Change Request Management Client Number
    Click on the Integration Solution Manager
    If you have different system for Change Request Management gives the RFC destination for that System.
    Click back button
    Double click on the Integration Change Request Management
    You have to maintain the following data here
    Column 1: Application: CHARM
    Column 2: + : W
    Column 3: RFC Destination:  NONE
    Column 4: + : CUST620
    Column 5: + : 1.0
    2.SAP Solution Manager Implementation Guide  SAP Solution Manager  Scenario-Specific Settings Change Request Management  Standard Configuration 
    General activities
    Click on the Execute button with the text u201CActivate BC Sets u201C
    It will take us to SCPR20 Transaction which is used to Activate the BC sets
    Select the BC set SOLMAN40_CHARM_BASICFUNC_001 ,  it is for solution manager version 4.0
    Click on the Activate Button
    Create a Request for Activating the BC Set
    Click Save button to assign with a TP .Other wise Create a new Transport Request (TP).
    In Overwrite Data Box, select the Overwrite data, and in Activation Mode box select Expert Mode Option , Click on OK Button to activate this BC set.
    3.SAP Solution Manager Implementation Guide  SAP Solution Manager  Scenario-Specific Settings Change Request Management  Standard Configuration 
    Transport Management System.
    In Order to do all the Settings under the Transport Management System do follow the steps.
    All the below settings has to be done in satellite system not solution manager
    1.     Define Transport Routes for System Landscape
    Go to Transaction STMS
    Choose Overview -> Systems.
      Double-click each system.
    The Display TMS Configuration: System <system ID> screen appears.
    Select the Transport Tool tab page.
    If the entry CTC does not appear in the Parameters column, enter it there, and then in the Value column, enter 1.
    Save your entries.
    Configure Transport Strategy
    Go to Stms Transaction
    Go to Menu Overview  Transport Route
    Doubt click on Each System . In the Transport strategy group box, select Single transports
    (since only Import Single and Import Project All are used).
    In the Quality assurance group box, deselect Delivery after confirmation
    1.     Choose Continue.
    Activate TMS Trusted Services
    Choose Overview -> Systems.
    Choose Goto -> Transport domain.
    In Management Tab
    In Security Options group box
    Click on Trusted Services Active
    Go to QA Approval Procedure
    You should not assign any QA approval system there
    Save your Entries
    Call Transaction STMS.
    Choose Overview  Systems. The system overview appears.
    Choose SAP System  Create  Domain link.
    The dialog box Request for Linking 2 Domains appears.
    Enter the system name, host name and system number of the domain controller you want to link to, and then confirm your entries.
    Your SAP System performs the following actions automatically:
    o     Generates the required RFC destinations.
    o     Sends the address data of the controller to the controller in the other domain.
    You can now see that you have requested the domain link to the other domain in the system overview.
    Click the Distribute and Activate TMS Configuration ICON on the Application Toolbar
    After that Go to SAP System  Check   Connection Test, transport directory and transport tool
    Check all once whether it is having inconsistency.
    4.Check Configuration of Transport Domain
    Log on to every domain controller that is connected to your transport landscape.
    Call transaction STMS
    Apart from the information "You are logged onto the domain controller", you should not be able to see other messages or warnings.
    Generate RFC Destinations to Client 000
    Call Transaction SMSY.
    Go To Landscape Components
    Go to your Satellite System
    Click on the Domain Controller System
    In the Right side Tab strip, Click on the Clients, Select 000 client Click on RFC generate Button
    Give the User name for Read Access and Change Manager
    Click the OK Button to Continue
    Add Import Authorization to Operator/Administrator
    Make sure that the operator and administrator users in client 000 of the target systems have the same name as their user in the Solution Manager   system.
    Assign import authorization to the operator and administrator users in client 000 of the target systems (SAP_CHANGEMAN_OPERATOR and SAP_CHANGEMAN_ADMIN roles).
    5.Set Project Assignment of Requests as Mandatory
    If you want to enable your change request project is mandatory while creating a request for workbench or customization object, follow the steps
    Go to Transaction
    /N/TMWFLOW/CMSCONF
    Select the Change Request Management System
    Double click on the Project Assignment column
    A new windows opened as follows
    In the Attribute Required for Requests Box , Select Mandatory on the Default for all clients List
    In the Client u2013Specific Setting Activate the tick mark of the Right side of the Table Control
    6.Change Transport Request Option
    Requirements
    u2022     Repository changes are permitted in the system where you want to change the transport request option. (If they are not, proceed as described in SAP Note 327351.)
    u2022     You do NOT use template projects.
    Go to Transaction SE38
    Enter the following Program   SAPLSCMA
    Click on the Display Button
    Click the Find icon and type the following keyword,
    G_ACTIVATE_CORRECTION_SYSTEM
    Click on the OK Button to search
    Using Modification, Edit the Program in Change Mode
    Delete the following lines ,
      message id sy-msgid type sy-msgty number sy-msgno
                    with sy-msgv1 sy-msgv2 sy-msgv3 sy-msgv4.
    And Insert the following lines ,
      no_automatic_recording = 'X'.
    Call Transaction SCC4
    Select the Change Request Management Client and Click the Display ICON.
    Go to Transaction SE 11
    Enter the table SCMATREED
    Choose Display
    In Menu Click on Goto -> Indexes,
    Choose Yes in the dialog box, and enter the index name 001, and the following short description: Index for Node in SCMATREE.
    Maintain Number Ranges
    Go to Transaction SNRO
    Enter Object Name  /tmwflow/M
    Click on Number Range Button on the Application Toolbar
    Click on the Change Intervals Button
    For the new interval, enter 01, and use the F4 Help function to select a value for the From Number field.
    The system returns 000000001 to 999999999.
    Save the Entries
    Come to the SNRO First Screen again; follow the same procedure for the following objects
    /tmwflow/d and /tmwflow/v.
    SAP Solution Manager Implementation Guide  SAP Solution Manager  Scenario-Specific Settings Change Request Management  Extended Configuration  Schedule Manager
    ( Note in HLL  We have using the Standard SAP Variants )
    Create Customer-Specific Variant for Task Lists
    Click on the Execute button
    To Create a New Entries, Click on the Create New Entries Button
    Type the Variant Name in the Variant Column Starts with the name space of u2018Zu2019, and in the Description Column you can maintain the description
    Define Additional Tasks for Task Lists
    Create Customer-Specific Header and Footer Tasks
    Install Template Report
    For all the above Refer IMG Node, follow the Steps
    SAP Solution Manager Implementation Guide  SAP Solution Manager  Scenario-Specific Settings Change Request Management  Change Transaction
    Check Installation Activities
    Make sure that you have performed the iBase IMG acitivities before you proceed with the Change Transaction IMG activities: SAP Solution Manager -> Basic Settings -> SAP Solution Manager System -> Service Desk -> iBase.
    Check the all the following settings has been done .
    Initially Create and Assign the Component Systems as iBase Components
    Manually Create and Assign the Component Systems as iBase Components
    Assign Business Partners to iBase Components
    In the following Link all the Settings comes with BC Set.
    SAP Solution Manager Implementation Guide  SAP Solution Manager  Scenario-Specific Settings Change Request Management  Change Transaction
    USER Authorization
    Administrator
    SAP_CM_SMAN_ADMINISTRATOR
    Change Manager
    SAP_CM_SMAN_CHANGE_MANAGER
    IT Operator
    SAP_CM_SMAN_OPERATOR
    Developer
    SAP_SOCM_DEVELOPER
    Regards
    Sreedhar Reddy.A

  • ChaRM and CTS+ for EP 7.0 in SolMan

    Hi,
    I've been trying to get CHaRM working for EP 7.0 in our SolMan systems for a while, but have not been able to get it working. I've read through and followed all the documentation on the resources page here, the Solution Manager documentation on help.sap.com and service.sap.com and all the notes I can find. We are running SolMan 7.0 SPS 17, and the Portal is on NW7.0 SPS 15.
    I have configured SMSY, populated from SLD and assigned to a system (I've tried NETWEAVER 7.0 - Enterprise Portal main instance, and ERP 6.0 - SAP XSS main instance) and assigned the dev and prod systems to a locical component.
    I have configured STMS, a single client independant consolidation route from dev to prod. The dev system is defined as a Non-ABAP "source system" in TMS, and I've set the communication system to be the solman system/client.
    The CTS+ config all seems to work, I can create/release transports and add objects to transports from the EP dev system.
    When I try to implement ChaRM, I create a new maintenance project. I add the portal landscape component to it, and activate change management. This works. When I try to create the task list, it fails trying to create the project IMG for the system. It gives me the error -
    IMG project creation error -> see long text
    Message no. /TMWFLOW/TASKLIST164
    Diagnosis
    You want to create a new maintenance cycle. An error has occurred.
    When you create a maintenance cycle for a maintenance project in the Solution Manager (SMI project), a project is created in the Central Transport System (CTS project), per logical development system. This CTS project is required as an attribute for the transport requests.
    A CTS project is always assigned to an implementation project (IMG project) in the physical system. There must be an IMG project in all physical systems in an SMI project, in which a system change (development/maintenance) can be made.
    If there is no IMG project in a system, one is created automatically. The generated IMG project has the same name TEST as the SMI project, but there cannot be an SMI project and an IMG project with the same name in one system, for system-internal reasons.
    In SMI project TEST there is a development system in the same physical system SMU as the Solution Manager.
    System Response
    If one of the development systems is in the same physical system as the Solution Manager, the IMG project cannot be created automatically.
    Procedure
    Create an IMG project manually in system SMU. In the path: SAP Menu -> Tools -> Solution Manager -> Project Administration.
    Choose the SMI project TEST, go to the 'System Landscape' tab, and then the 'IMG Projects' tab.
    Select an entry for the system SMU and try to create the IMG project. The system tells you that a system of the same name already exists, and asks you whether you want to choose another project name. Answer 'Yes', and change the project name.
    You should then be able to create the task plan.
    SMU (solution Manager) is not in the system landscape of this project, I expect that it is trying to create the IMG in this system since this is the communication system for portal dev. However, since it's not in the landscape, it isn't in the IMG tab to be able to create manually as described.
    If I try to create the IMG project for the Portal Dev system directly in the project, I get the error -
    Error getting RFC destination for logical system EPU
    Message no. SMSY_PPMS_API044
    Diagnosis
    No RFC destination was found for the logical system 'EPU' .
    System Response
    The RFC connection to the system 'EPU' cannot be created.
    Procedure
    Create the required RFC connection in the Solution Manger System Landscape Maintenance.
    Any advise would be appreciated.
    Thanks,
    James Blair

    Hi James (and others),
    I trust you have resolved your issues with ChaRM and CTS+.
    If you are running a partuicularly extensive landscape you may want to consider a third party alternative to ChaRM.
    Particularly one that integrates with CTS+ (to include non ABAP such as Portal, NWDI Java and so on).
    There are several available, the one I am most falimiar with (Note: I do work with Revelation Software Concepts) is Rev-Trac and you can read user reviews at http://www.sdn.sap.com/irj/ecohub/solutions/revtrac
    If you run an EcoHub search on Change and Request Management or similar the other alternatives should be returned.
    Regards, Rick

  • Integration of Charm and test work bench or customizing

    Hello,
    Solution Manager allows one to define the business processes. One can then define test cases for these business processes. Then one can use the test workbench to do the testing.
    Is there any way to link the test workbench with Charm?
    Are there any such plans for such integration?
    Customizing can also be done from the business process definitions in a project. Are there any way that charm can be integrated to make changes in this way?
    Regards,
    Avrohom Weissman

    This is very far from the type of integration I expect to see. Proper incident management means when a problem occurs and incident is logged into the sap service desk. If this incident requires a change it should be forwarded to the CHange Reqest Management (CHaRM). From there it should have a business impact analysis, then a system or architecture review, only then if it is approved should development be started, after the development, it goes into QA for testing. Since the business process is defined in the solman and there are test cases for this business process. It makes sense that one can use the test workbench to verify the business process, and document the testing. If there is a problem with the testing and it needs to go back to development, it should be connected to the same incident logged initially. There should not be a second problem logged. It is still part of the same incident and should be managed as such.
    This question exists also for a maintenance project. Once I have an operational system and all the business process defined in the project and a change arrives into ChaRM, why canu2019t the change be done in the project like and implementation?
    How can one find out the direction of this product? Does SAP have any plans to develop solman into an integrated tool or will it remain a bunch of simple tools that co-exist on the same server?

  • CMS and CTS+

    Hi all,
    I want to know the difference between CTS+ and CMS. Is there any additional advantage provided by CTS+ over CMS? Also what is the difference in the procedure to transport IR and ID objects in CMS and CTS+.
    Any links to documents related to transporting IR , ID objects via CMS and CTS+ will be very helpful.
    Regards,
    Santosh

    Hi,
    What is CTS+ and why is is introduced:
    The Change and Transport System (CTS) is a tool that helps you to organize development projects in the ABAP Workbench and in Customizing, and then transport the changes between the SAP Systems in your system landscape.
    The XI use case for CTS+ introduces a new transport handling mechanism that offers tighter integration for the transport of ABAP, Java, and Integration Builder objects (Integration Repository and Integration Directory) using the Change and Transport System (BC-CTS) functionality.
    As your XI system requires both the ABAP and the Java stack of the SAP NetWeaver Application Server, the following transport tools are available after installation:
    u2022
    The ABAP transport environment (BC-CTS)
    u2022
    The file export and import mechanisms or CMS integration to transport Repository or Directory objects in your transport landscape
    In addition, you might also have to transport Java development objects by using the SAP NetWeaver Development Infrastructure itself.
    The enhancements to CTS in combination with the SAP Solution Manager Change Request Management (ChaRM) address the following issues:
    u2022
    Synchronized transports for mixed systems (ABAP & Java)
    u2022
    A unified application for mixed system landscapes
    u2022
    Tracking of non-ABAP transports including Change Request Management
    For your XI landscapes there will be one central transport environment with CTS+ where you can manage all XI-relevant transport objects from a single entry point.
    This how-to guide describes the configuration settings you must make in the CTS+ system and XI systems. The functionality must be set up according to the release version of the integrated XI system. The two configurations will be described separately:
    u2022
    Configuration setup for releases prior to SAP NetWeaver 7.0 SPS12 (also for SAP NetWeaver 2004 SPS14 and higher).
    u2022
    Configuration setup for release SAP NetWeaver 7.0 SPS12 and higher.
    Refer the link for CTS+ step by step method of transport:
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/80bbbd55-5004-2a10-f181-8bb096923cb6
    http://help.sap.com/saphelp_nw04/helpdata/en/03/dcb6b6048711d3b42a00609419f767/frameset.htm
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/90d3b550-b6fb-2910-0fa5-ece5d61fb9c3
    CMS is generally used to transport Java development objects. The XI Integration Server uses CMS to transport Integration Server content. When the Integration Server uses CMS to transport XI Content, no Component Build Service (CBS) or Design Time Repository (DTR) is used and can therefore be switched off. If you want to transport Integration Server content and Java developments (Java proxies or adapter modules), the CBS and DTR must be running.
    If you transport Java developments, you should keep in mind that deployment of Java code can destabilize the runtime environment. Therefore, it is beneficial to install CMS on a separate server, as described in SAP Note 737368 for NWDI.
    In this How-to Guide, CMS is installed together with an Integration Server system in the development environment. The advantage of this approach is that you have fewer steps in user management and CMS cannot influence the runtime of a productive environment.
    With the enhancements of the SAP NetWeaver Change and Transport System (CTS for short, or CTS+ respectively, if specifically the enhanced capabilities are meant), available with SPS12 of SAP NetWeaver 7.0, the CTS has been enhanced to handle any type of object that can be transported in an SAP system landscape. Therefore, an administrator of your ABAP system can now also manage the transports for the non-ABAP parts of your system landscape.
    You can now use CTS to transport (almost) arbitrary objects in an SAP system landscape with transport orders of the Transport Organizer:
    u2022
    Enterprise Portal archives (EPAs)
    u2022
    Exchange Infrastructure objects (TPZs)
    u2022
    Software component archives (SCAs)
    u2022
    Software delivery archives (SDAs)
    u2022
    Enterprise Application Archives (EARs)
    u2022
    ABAP objects
    Development objects will be deployed according to their application type. Objects in a single transport order can be a mixture of all types u2013 however that only makes sense, if both are intended for the same system because transport paths are defined in the transport domain controller system.
    CTS+ and usage type PI (SAP NetWeaver Exchange Infrastructure, XI)
    o
    If you are not using the Change Management Service CMS of the NWDI, you should seriously consider using CTS+ for your XI transports (CTS+ & SAP NetWeaver usage type PI).
    o
    If you are already using the CMS, you should postpone any planned migration to use CTS+ up to availability of SAP NetWeaver 7.0 SPS 13 , where integration will be enhanced futher.
    o
    In any case you should evaluate the enhanced CTS options of SAP NetWeaver 7.0 comming with SPS 12 and extensions planned with SPS 13/14 for XI transports u2013 in the mid and long term CTS+ is the best practice recommended by SAP for XI tranports.
    CMS for SAP Exchange Infrastructure
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/b8d8f7b2-0701-0010-b09a-cda4cca2c98e
    Configuration of CMS in Central NWDI & SLD to transport XI objects
    Configuration of CMS in Central NWDI & SLD to transport XI objects
    How to Use CMS in XI 3.0.pdf
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/43f5d790-0201-0010-2984-ff72d822b109
    CMS based transport in XI
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/b8d8f7b2-0701-0010-b09a-cda4cca2c98e
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/9e76e511-0d01-0010-5c9d-9f768d644808
    Regards,
    Phani

  • CTS+ integration with NWDI in NW 7.01

    Hi, all.
    I read in the release note that in NW 7.01, you can package NWDI activity and transport it using CTS+. For most of the afternoon, I was searching in vain for the procedure on help.sap.com, SDN and service.sap.com. The doc on help.sap.com in particular is a joke. The EHP2 doc is still referencing the same 7.0 CTS/NWDI integration procedure. The closest thing I found is a document called "Enhanced change and Transport System" by Karin Sudrow.
    I would really appreciate if you are aware of any useful doc for the NWDI/CTS+ integration.
    Thanks,
    Jonathan.

    Actually I just found an excellent procedure "News in Enhancement Package 1 for SAP
    NetWeaver 7.0 around CTS+ and NWDI" by Marion Schlotte if you are interested.
    Thanks,
    Jonathan.

  • ChaRM: usage of ChaRM and none-Charm transport strategy

    Hi ChaRM-TMS Gurus!
    We have the following [SAP system landscape |http://www.file-upload.net/view-1086963/SDN_TMS_Ist_Soll.jpg.html] and would like to use ChaRM approach simultaneously.
    What are the minimal requirements concerning transport layers/routes, which settings should be changed?
    How much and which transport layer/routes does ChaRM need?
    a) 1 any new transport layer/route
    b) standard transport layer, transport layer "SAP" and others
    Should all the standard transport layer/routes from virtual systems to real QAS and PRD systems or can I start as follows:
    1) Leave the current TMS settings unchanged
    2) Activate the extended transport control
    Result: the current setting will be client specific and all the old transport requests will be moved to client specific transport routes
    3) change the transport strategy (from mass transport to single transport)
    3) Define new transport layer
    4) Define  new transport route for SAP objects from DEV to QAS
    and assign the transport layer from 3) (client specific)
    5) Define  new transport route ZXXX from DEV to QAS
    and assign the transport layer from 3) (client specific)
    6) Define the delivery transport route from QAS to PRD (client specific)
    7) activate and distribute the settings
    Thank you very much indeed!
    Thom

    Hi Martin,
    Solmaniacs' assumptions are correct. You can have as many source clients as you want.
    As long as
    - STMS configuration (transport routes, and domain links) are consistent
    - SMSY configuration (logical components are declared properly with assigning the right role types to systems/clients)
    - Project declaration are done correctly (so that from Solman solar_project_admin you can read the STMS as confiured in the distant STMS domain)
    - IMPORTANT: those configuration GO ALONG with each other !! (SMSY should nt contradict STMS for example...)
    The tasklist that is generated for each Solman project will be as follow
    - Node 1: Header Tasks (commun to all systems)
    - Node x: Corresponding to track x declared in Project (each Source System will have his own node with the corresponding track under)
    - Node x+1
    - Node ...
    - Last Node : Tasks for Tasklist closure - checks on scma consistancy and CTS projects closure
    So you'll always have n+2 nodes in your tasklist; n beeing the number of declared source (=dev) systems in project
    For each action launched from change docuemnts like creation of TR, release of TR or Retrofit (as Solmaniac said) you'll have an additional pop-up that will appears letting you choose the system you want to use for the action
    Hope its helpful
    Regards
    Khalil

  • Oracle Portal and Discoverer Integration

    Portal Version: 9.0.2.0.1
    RDBMS Versjion: 9.0.1.3
    OS/Vers. Where Portal is Installed:: Suse 7 SLES
    Error Number(s)::
    Oracle Portal and Discoverer Integration
    We're trying to integrate Discoverer with Portal unsuccessfully.
    We made many things in accordance with oracle's documentation until add discoverer portlets (worksheet and list of workbooks) in a test page.
    In view mode, the worksheet portlet shows the error:
    "The portlet has not been defined. The publisher must define the portlet by clicking on Edit Defaults for the portlet on the edit mode of this page. Please contact the publisher of this page."
    We think we have to edit properties before. Is this? Anyway edit worksheet portlet crashes between step 1 and 2. The error is: "The listener returned the following Message: 500 Internal Server Error".
    We have a public conection created in EM and a discoverer application which can be viewed using plus or viewer.
    Furthermore, it's not possible delete the added portlets neither the page that contain it. The error at delete is:
    Error: An unexpected error occurred: User-Defined Exception (WWC-44082)
    (WWC-00000)
    An unexpected error has occurred in portlet instances: User-Defined Exception (WWC-
    44846)
    An unexpected error occurred: User-Defined Exception (WWC-43000)
    The following error occurred during the call to Web provider:
    oracle.portal.provider.v2.PortletNotFoundException
    at oracle.portal.utils.v2.ContainerException.fillInStackTrace(Unknown Source)
    at java.lang.Throwable.<init>(Throwable.java:78)
    at java.lang.Exception.<init>(Exception.java:29)
    at oracle.portal.utils.v2.ContainerException.<init>(Unknown Source)
    at oracle.portal.provider.v2.PortletException.<init>(Unknown Source)
    at oracle.portal.provider.v2.PortletNotFoundException.<init>(Unknown Source)
    at oracle.disco.portlet.provider.DiscoPortletPersonalizationMgr.destroy
    (DiscoPortletPersonalizationMgr.java:65)
    at oracle.portal.provider.v2.DefaultPortletInstance.deregister(Unknown Source)
    at oracle.webdb.provider.v2.adapter.soapV1.ProviderAdapter.deregisterPortlet
    (Unknown Source)
    at java.lang.reflect.Method.invoke(Native Method)
    at oracle.webdb.provider.v2.utils.soap.SOAPProcessor.doMethodCall(Unknown Source)
    at oracle.webdb.provider.v2.utils.soap.SOAPProcessor.processInternal(Unknown Source)
    at oracle.webdb.provider.v2.utils.soap.SOAPProcessor.process(Unknown Source)
    at oracle.webdb.provider.v2.adapter.SOAPServlet.doSOAPCall(Unknown Source)
    at oracle.webdb.provider.v2.adapter.SOAPServlet.service(Unknown Source)
    at javax.servlet.http.HttpServlet.service(HttpServlet.java:336)
    at com.evermind.server.http.ResourceFilterChain.doFilter
    (ResourceFilterChain.java:59)
    at oracle.security.jazn.oc4j.JAZNFilter.doFilter(JAZNFilter.java:283)
    at com.evermind.server.http.ServletRequestDispatcher.invoke
    (ServletRequestDispatcher.java:523)
    at com.evermind.server.http.ServletRequestDispatcher.forwardInternal
    (ServletRequestDispatcher.java:269)
    at com.evermind.server.http.HttpRequestHandler.processRequest
    (HttpRequestHandler.java:735)
    at com.evermind.server.http.AJPRequestHandler.run(AJPRequestHandler.java:151)
    at com.evermind.util.ThreadPoolThread.run(ThreadPoolThread.java:64)
    (WWC-43147)
    Edit properties for portlet List of Workbook works but in view mode we have the error in the portlet area:
    "Failed to refresh portlet. Please verify that the information used to create the
    portlet instance or customization is still valid. Otherwise, please contact your
    iAS administrator. oracle.discoiv.controller.FatalControllerException:
    DiscoNetworkException - Nested exception: org.omg.CORBA.OBJECT_NOT_EXIST: minor
    code: 0 completed: No null"
    Any ideas?
    Thanks

    Hi there,
    Have you applied any patches to 9ias since it was first installed? We had the same problem and had to apply a couple of patches to get the portlets working.
    1. Apply the 9.0.2.53.16 one-off patch for Oracle 9iAS Discoverer which takes Discoverer up to 9.0.2.53.16. This patch appears to be password protected and you need to get someone at Oracle support to give you a password.
    2. Apply the Discoverer Portlet Provider: 9.0.2.53.00c patch (patch no. 2595444) which gives you a new discportal.xsl file that actually works. It's this second step that solves your problem but you need to do step 1 before this. This is password protected as well.
    3. As you've upgraded Disco on the server to 9.0.2.53, you'll need to upgrade Disco Admin & Desktop within your 9iDS installation using patch no. 2555265. This is because Disco 9.0.2.53 uses an upgraded EUL that Disco Admin & Desktop need to be patched to use.
    This was the course of action Oracle support advised us about nine months ago. Of course they may have released a further patch to Disco that does 1 & 2 in one go, but we regularly carry out steps 1 and 2 on servers we use and we can use the Disco portlets successfully.
    Hope this helps
    Mark Rittman
    [email protected]

  • Unit testing and system integration testing for crystal report

    Hi gurus,
           I am creating crystal report by oracle procedure, will you please tell me how to do unit testing and system integration testing? appreciate very much.

    The focus of this forum is report design. The actual testing of reports would be subject to your own internal policies and procedures.
    Jason

  • Question regarding MM and FI integration

    Hi Experts
    I have a question regarding MM and FI integration
    Is the transaction Key in OMJJ is same as OBYC transaction key?
    If yes, then why canu2019t I see transaction Key BSX in Movement type 101?
    Thanks

    No, they are not the same.  The movement type transaction (OMJJ) links the account key and account modifier to a specific movement types.  Transaction code (OBYC) contains the account assignments for all material document postings, whether they are movement type dependent or not.  Account key BSX is not movement type dependent.  Instead, BSX is dependent on the valuation class of the material, so it won't show in OMJJ.
    thanks,

  • Jabber and O365 integration

    Hello,
    Do we need any additional licenses from Cisco or Microsoft to make a full possible integration between O365 and Jabber ?
    For example features like :
    Single Inbox Unified Messaging with SpeechView transcriptions,  Microsoft Word Click to Call, SharePoint Presence & Click to Call,  Jabber video calling and desktop sharing, and WebEx on desktop and iPad,
    Thank you for your help
    Best Regards,
    Tomasz

    Tomek,
    There is no direct integration between Jabber and Office 365, except for Exchange Gateway integration on IMP server side which is not supported with Office 365. All other Jabber integrations do not go to Office 365, calendar client integrations are done with Outlook, and UM integration is between Office 365 and Unity Connection, which does not affect Jabber.
    HTH,
    Chris (Krzysiek) :-)

  • REPORT WITH SALES AND PRODUCTIN INTEGRATION?

    HI,
       HERE I NEED TO DISPLAY THE SALES AND PRODUCTION INTEGRATED (FOR MAKE TO STOCK) LIST BY DAY WISE ,I AM NOT ABLE TO FIND THE TABLES FOR THAT.
    HERE LIST HEADER IS FOLOWING.
    MATERIAL CODE, MATERIAL DISCRIPTION, PRODUCTION QTY, PROD. VALUE, SALES(BILLING QTY, SALES(BILLING) VALUE.
    AND THAT LIST TOTAL PRODUCTION VALUE SHOULD EQUAL TO THAT PARTICULAR DAY TOTAL PRODUCTION VALUE,
    AND THAT LIST TOTAL SALES(BLIING) VALUE SHOULD EQUAL TO THAT PARTICULSR DAY TOTAL SALES(BILLING) VALUE.
    PLZ HELP OUT FROM THIS,
    REWARDS IN ADVANCE....
    REGARDS,
    NAVEEN

    Have you tried the txn code MC-Q or the report program RMCV0500.

  • Facebook and Twitter integration not working

    I'm have trouble using Facebook and Twitter integration in Mountain Lion. When I click 'Click to Tweet', or 'Click to Post', nothing happens; I don't get the notecard looking thig, and it's like I never clicked the button. Same thing with sharing from an app, except for Twitter. I receive notifications from both just fine, but I'm unable to post. I can tweet something from the sharing menu (link to a webpage with Safari, for example), but I cannot send a tweet using the 'Click to Tweet' button in Notification Center. Also, I cannot post to Facebook by neither sharing nor the 'Click to Post' button. So far I have tried sharing with Safari, Finder, and Preview, all with the same results. (Facebook sharing with iPhoto does work, but I don't believe that is integrated with OS X.)
    I have also tried the following, with no luck:
    Checked my settings on the Facebook and Twitter sites.
    Removed my acounts and re-added them.
    Obviously, my internet connection is working.
    Added my Facebook account to the 'Guest User' account, and another administrator account.
    Had a friend add his Facebook account to his own (limited) account on my computer--he could not post to Facebook either.
    I believe the last two things I tried indicate that this is a system-wide problem. A couple more things to note: 1) there is no kind of error message; it just sits there, like nothing happend, no 'spinning wheel' or anything. 2) It DID work before. Twitter worked when I first upgraded to Mountain Lion, and Facebook worked when I installed the 10.8.2 update. I don't use either often enough to know when exactly they stopped.
    Here is a video illistrating my problem.
    It's been driving myself crazy with this over the past few days, and can't seem to find an answer anywhere. I also seem to be the only one with this problem.

    First, I would eject whatever it is that you downloaded. Go to Finder and eject it that way or depending how you have your system set up, do the two finger tap and Eject it. Download the link above. Once it downloads, double click it to install it. It should work. If it doesn't you need to use your Disk Utility to check for errors. Click your Finder again and then Applications. Scroll down to Utilities and then Disk Utility. Click on your hard drive and you will get a menu of items on the right side. Towards the bottom, you will see a button to Verify Disk Permissions. Click that and let it run. It may take a few minutes to finish. Once it's finished there may be a list of things wrong with your system. Click the Repair Permissions and let the computer do it's thing. Use Disk Utility at least once a month to make sure everything is in order on your system. If this doesn't fix it, I don't have any other suggestions. I'd hate to say do a fresh install but that might be the next step if this doesn't work.
    Something else to consider is that is if you use Time Machine and the system did work at one point, you could go back to the last known good point and reinstall that back-up. You would lose anything you have saved since that point (obviously). If you take steps to back up your information, that should not be an issue. (For me), Time Machine works as advertised. If you are not backing system up regularly, shame on you. You need to start ASAP backing up. It's an easy process and it's times like you are having now, that make the small preventive maintenance, worth extra time and effort.
    Good luck.

  • PS and PP integration

    Dear Experts,
    Good Morning....
    Please suggest me PS and PP integration customization steps.
    Regards
    Lallan

    PP is not a major player in PS as far as integration is concerned. It is through Material Management that Production Planning is informed of Production Orders using special settings in the Material Master.
    One another area, the PP and PM modules share Work Centers with Project System.
    The Work Center is needed for Capacity Planning and Planning costs. If we integrate this Work Center with HR module, we will be able to select only the people who have been assigned to the Work Center. We can specify the amount of work the individual will contribute. This forms the basis for capacity planning.
    Hope u must have understand.
    PS - Process
    After creating the project next step is u want to do cost, Revenue & Budget Planning for the project
    in the t-codes CJ42, CJ30 & CJ40 respectively. Next step is creating the Sale order in va01 T-code.
    But I have internal project scenario, example: Overhauling of DG set. Assigned work enter & Workforce & also material to network. So shall I do costing? As explained! Is it necessary to create of Sales Order?
    CMP2 - Assign workforce to activities
    CAT2 - Transfer actual time to CATS. In CAT2 we have record the actual timing correct for an activity, on day basis & with personal number.
    MD51 - Run Project MRP to create Planned orders.
    MD04, ME21N, MIGO - Convert planned orders to purchase requisitions and P.O, and goods receipt.
    MB1A - once the goods are brought is project stock; the same needs to be consumed by mb1a -281 Q on the project.
    CJ20n - Attach milestones as per the payment terms.
    VA02 - Copy billing plan to sales order.
    VF01 - Billing
    CJ20n - Project tech complete and closure.
    Hope this will help you,
    Regards,
    ANSAR

  • SAP  R/3 and BW integration Landscape

    Hello Gurus,
    Could you'll suggest a site or link where I could get a better insight into the SAP  R/3 and BW integration Landscape, i.e. how Data gets transferred from SAP R/3 to BW.
    Thanks,
    Sebastian

    Hi,
    YOU can check the following for BW extraction
    http://help.sap.com/bp_biv235/BI_EN/html/bw.htm
    business content
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/biw/g-i/how%20to%20co-pa%20extraction%203.0x
    https://websmp203.sap-ag.de/co
    http://help.sap.com/saphelp_nw04/helpdata/en/37/5fb13cd0500255e10000000a114084/frameset.htm
    PLease also have a look at BW data modelling guide,
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/5586d290-0201-0010-b19e-a8b8b91207b8
    http://www.thespot4sap.com/Articles/SAP_BW_Metadata_Modelling.asp
    Please reward points.

Maybe you are looking for

  • Pending  GR / IR Balances report  for a given period

    Hi,           How can you  check  pending  GR / IR doc's  for a given  period ?  In  MB5S there is no date field in selection sreen as well as output  layout.  Please  give  suggetions . Thanks &  Regards,        Aruna.

  • How do I get a popup window to stay open with a validation failure?

    Environment: APEX 3.1.1.00.09 on AIX 5.3 Oracle 10.2.0.2 EE on AIX 5.3 Sample app on apex.oracle.com: Workspace: galway User: gwicke Pass: gwicke Steps: 1- run Page 3 2- select J & B Marketing from drop down 3- select only contract from drop down 4-

  • Unable to Boot from OSX -- Get Strange Schematic

    Hello - A friend forgot her password on her iBook. Using this forum, we found out that she can access and change the password by booting from the OSX disk (Tiger) and opening the "Utilities" on the installer. So we inserted the disk and restarted the

  • Want to construct insert statement from all_tab_columns

    I am using Oracle 10GR2 and a new user for plsql I want to write a plsql block or SQL in order to insert some dummy data. I want to use the column list from all_tab_columns and want to construct insert statement EX: I am trying to construct SQL as be

  • Bunch of blank spaces before my contacts--can't delete

    After I added all of my contacts the first time they disappeared for some reason... then I resynched with google but somehow the blank spaces are all still there...and I have to scroll through them all before I can get to my contacts.  I can't delete